This document contains a base bid cost breakdown worksheet template for a federal construction project to correct atrium fire protection issues. The worksheet requires offerors to provide labor and material costs by construction division to arrive at a total base offer cost. Divisions include general requirements, concrete, masonry, metals, finishes, fire suppression, plumbing, HVAC, electrical, communications, and exterior improvements. Offerors must also specify overhead, profit, and bond percentages to calculate additional subtotals. The related federal contract opportunity is solicitation number 36C24624B0007_1 from the Department of Veterans Affairs to install a new smoke exhaust and supply system, replace the roof, and complete necessary ducting, electrical, and fire alarm upgrades at a Durham VA medical center. The contractor will coordinate installation with the agency and perform all work, including on weekends for the roof replacement.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--558-21-106 | Correct Atrium Fire Protection Issues, newest first.
File Type Posted
36C24624B0007 0004.pdf PDF
36C24624B0007 0003.pdf PDF
36C24624B0007 0002.docx DOCX document
558-21-106 IFC Specs 23AUG23.pdf PDF
36C24624B0007 0001.docx DOCX document
36C24624B0007_1.pdf PDF
IFC 04AUG2023 Specs Revision 2.pdf PDF
IFC 04AUG2023 Drawings Revision 2.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base Offer

Base Offer Cost Breakdown

Project Number:

Edward L Roy: VA assigned project #

Date:
Project Title
Edward L Roy: VA assigned Project TitleProject Location
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Sum of Overhead, Profit and Bond %.

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0

File details come from the government source that posted it. Updated .