Y1DA--558-21-106 | Correct Atrium Fire Protection Issues Federal contract opportunity
Solicitation number
36C24624B0007_1
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6

About this file

This invitation for bid outlines a federal construction contract opportunity for corrective fire protection work at a Department of Veterans Affairs medical center. The contractor will install a new smoke exhaust system, supply system, and roof replacement to meet design requirements for the atrium area. Additional scope includes new ducting, electrical upgrades, and coordination with the VA to complete roof work on weekends to minimize disruptions. The contractor is responsible for all supervision, materials, labor, equipment, transportation, testing and storage. Bids are due by March 12, 2024 with award anticipated for a 360-day period of performance. The opportunity is set aside for certified service-disabled veteran-owned small businesses.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--558-21-106 | Correct Atrium Fire Protection Issues, newest first.
File Type Posted
36C24624B0007 0004.pdf PDF
36C24624B0007 0003.pdf PDF
36C24624B0007 0002.docx DOCX document
Attachment A - Base Bid Cost Breakdown Worksheet.xlsx XLSX spreadsheet
558-21-106 IFC Specs 23AUG23.pdf PDF
36C24624B0007 0001.docx DOCX document
IFC 04AUG2023 Specs Revision 2.pdf PDF
IFC 04AUG2023 Drawings Revision 2.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES NO

a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

1of 70

36C24624B0007 X

02-06-2024

TBD

558-21-106

Vangie T. Miller Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

ATTN: Vangie T. Miller Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

Vangie Miller 757-315-3999

INVITATION FOR BID: Project # 558-21-106 ~ Correct Atrium Fire Protection Magnitude of Construction: $2,000,000 and $5,000,000.

See Statement of Work, Master Specifications, and Drawings for details This is a Total SDVOSB Set-Aside NAICS: 236220| Size Standard: $45 Million

Site Visit: February 13, 2024 at 1:00 - 3:00PM Eastern Standard Time (EST) Location: 508 Fulton St, Durham, NC 27705 (Building 1)

Questions Due Date: February 22, 2024 10:00AM EST | Submit all questions to Vangie.Miller@va.gov Sealed Bids Due Date: March 12, 2024 2:00PM EST (Bids may be hand-carried or mailed to the address listed in block 8) Bid opening: March 12, 2024 2:00PM EST (Building 27)

The contractor shall install a new smoke exhaust system, new supply system, and roof replacement to meet the design requirements. New ducting, electrical, and fire alarm system upgrades will need to be done for the new system.

The contractor will have to coordinate the installation schedule with Durham VA, it is anticipated that all roof replacement will have to be done on weekends. The contractor is responsible for providing all supervision, materials, labor, equipment, transportation, testing, and storage for this project.

15 360

X X 52.211-10

X 15

(one) 1 14:00 EDT

03-12-2024

X

14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

PHONE: FAX:

28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code)

(Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

(Type or print)

(4 copies unless otherwise specified)

(Type or print) (Type or print)

(Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror)

(To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

Financial Services Center

PO BOX 149971

Austin TX 78714-9971 512-460-5049 512-460-5221

Table of Contents

PART I - THE SCHEDULE

SECTION A - SOLICITATION/CONTRACT FORM

A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)

A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,

ALTERATION, OR REPAIR)– BACK

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO

BIDDERS/OFFERORS

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND

BONDS

1.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB

1998)

1.2 52.216-1 TYPE OF CONTRACT (APR 1984)

1.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE

OF THE WORK (MAY 2014)

1.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION

MATERIALS (MAY 2014)

1.5 52.233-2 SERVICE OF PROTEST (SEP 2006)

1.6 VAAR 852.209-70 ORGANIZATIONAL CONFLICTS OF INTEREST (OCT 2020).. 22

1.7 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION

(OCT 2018)

1.8 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)

1.9 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY

ACCESSIBILITY NOTICE (FEB 2023)

1.10 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED

BY REFERENCE (JAN 2008)

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023) .. 25

3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS

AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)

3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)

3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—

CERTIFICATION (NOV 2021)

GENERAL CONDITIONS

4.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

4.2 52.204-27 PROHIBITION ON A BYTEDANCE COVERED APPLICATION (JUN

2023)

4.3 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN

2020)

4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(APR 1984)

4.5 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)

4.6 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION

(SEP 2023)

4.7 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT

FOR EPA-DESIGNATED ITEMS (MAY 2008) ALTERNATE I (MAY 2008)

4.8 52.223-20 AEROSOLS (JUN 2016)

4.9 52.223-21 FOAMS (JUN 2016)

4.10 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)

4.11 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)

4.12 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)

4.13 SUPPLEMENTAL INSURANCE REQUIREMENTS

4.14 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)54

4.15 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

4.16 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)

4.17 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED

SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023)

(DEVIATION)

4.18 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—

CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)

(DEVIATION)

4.19 VAAR 852.223-71 SAFETY AND HEALTH (SEP 2019)

4.20 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)

4.21 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND

VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)

4.22 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION

CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)

4.23 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV

2018)

4.24 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION

(APR 2019)

4.25 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR

2019) ALTERNATE I (APR 2019)

4.26 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)

4.27 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)

ALTERNATE I (APR 2019)

4.28 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT

ADMINISTRATION (OCT 2020)

4.29 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) .. 69

4.30 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT

(SEP 2019)

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM

NUMBER

DESCRIPTION OF

SUPPLIES/SERVICES QUANTITY UNIT

UNIT

PRICE AMOUNT

0001 Correct Atrium Fire Protection

1.00 JB GRAND

TOTAL

PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction

PRODUCT/SERVICE CODE: Y1DA - Construction of Hospitals and Infirmaries

PERIOD OF PERFORMANCE: 360 Calendar days from Notice to Proceed (NTP)

Correct Atrium Fire Protection

Project Number 558-21-106

STATEMENT OF WORK

Description of Work - Summary:

The atrium of the Durham VA Health Care Center, 508 Fulton St, Durham, NC needs improvement to meet current fire codes by having a smoke exhaust system installed with supporting ducting, electrical, and fire protection utilities, new fire-rated windows, and atrium roof replacement. The Durham VA atrium is the main dining area of the hospital, scheduling of work will be an important aspect of construction schedule.

General:

The contractor shall install a new smoke exhaust system, new supply system, and roof replacement to meet the design requirements. New ducting, electrical, and fire alarm system upgrades will need to be done for the new system. The contractor will have to coordinate the installation schedule with Durham VA, it is anticipated that all roof replacement will have to be done on weekends. The contractor is responsible for providing all supervision, materials, labor, equipment, transportation, testing, and storage for this project.

Shutting down of the entire dining area during normal weekday hours for construction will not be allowed.

Specific Requirements:

The construction for this project will cover the following but not limited to:

• The addition of mechanical/electrical equipment on the roof of the atrium.

• The atrium roof is mostly comprised of structural steel trusses made from hollow steel sections. The new equipment will be supported with new structural steel roof framing beams that will be welded to existing structural steel trusses.

• New vertical ductwork will be exposed and supported by metal fabrications attached to existing building structure.

• New electrical work and connection to existing system

• New fire alarm installation and connection to existing system

• New fire-rated window replacement inside the atrium at multiple levels, this will impact administrative office spaces, not patient rooms. Appropriate ICRA barriers and coordination must occur for this portion of scope to be done.

• Demolition of single office space and replacement with new corridor

• Updating of fire sprinkler system in kitchen storage

• Replace existing roofing system.

o Option 1: provide price of partial re-roofing.

All material and installation will be in accordance with all state and federal codes, NFPA, ANSI standards.

Installation Requirements: Competent, experienced, licensed, or certified workers shall perform crafts requiring specialized skills. All work shall be performed in full accordance with applicable local and Federal regulations. All equipment and installation shall conform to the VA master specifications. All equipment and installation shall conform to the recommendations of the National Fire Protection Association (NFPA), including the National Electrical Code (NEC).

The Supplier shall use good safety practices while working. All hardware should be installed in such a manner to minimize damage and maximize patient and employee safety. All equipment and procedures shall conform to OSHA, NEMA, and ANSI Standards and conform to the Standard Building Code and the Standard Mechanical Code. All installations for the Durham VAMC shall conform to VAR and FAR standards.

Normal working hours shall be 7:30 AM to 4:00 PM, Monday through Friday – Federal Holidays or any other Holiday designated by the President of the United States excluded. Some work may be outside normal working hours. For working outside the “normal working hours” as defined in this contract, the vendor shall give 7-day notice to the Contracting Officer so that arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section. No photography of VA premises is allowed without written permission of the Contracting Officer.

Any dust creating activity from the work that will impact the dining area of the canteen (the ground floor area outside the service line area) will have to be done when dining area is closed. This means after 4:00pm Monday thru Friday, or weekends. That will be at least: activities where drilling thru the bricks occur (electrical conduit, duct work, etc.), roofing activities (cutting holes thru the roof), steel reinforcing activities, storefront/window replacement, setting of equipment on roof (by any means), or other demolition inside the atrium.

Execute work to interfere as little as possible with normal functioning of Medical Center, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied jointly by patients or medical personnel, and Contractor’s personnel, except as permitted by COR where required by limited working space.

No utility service such as water, gas, steam sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the Medical Center Director’s prior knowledge and written approval. The vendor shall submit a request to interrupt any such services to COR, in writing, 20 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

VA reserves the right to close or shut down the project site and order the vendor’s employees off the premises in the event of a national emergency. The vendor may return to the site only with the written approval of the Contracting Officer.

Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.

Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads.

Minimize disruptions and coordinate with COR.

Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B. Coordinate with COR. Obtain permits from facility Safety Manager at least 24 hours in advance.

The contractor shall maintain neat and orderly work areas and shall clean area of debris and rubbish daily and dispose of waste materials offsite per hospital policies. The contractor shall provide a dumpster if it is determined to be necessary and shall work with the COR in advance for a spot-on site to establish the dumpster. Space on campus is limited and a dumpster location is not guaranteed.

The contractor will clean up any debris created by their activities at the end of their work shift. The hospital staff will still do a final cleaning prior to use by patients/customers.

Place of Performance: Tasks will be performed at the VA Medical Center Durham, VA. Work will be around an occupied healthcare facility in operation 24 hours a day. This work will require appropriate personal protective equipment and proper infection control measures. Work will be phased to minimize disruption to clinic and medical center operations.

Period of Performance: Period of performance shall be 360 days. This includes allotted lead time and construction performance time.

See attached document: IFC 04AUG2023 Specs Revision 2.

See attached document: IFC 04AUG2023 Drawings Revision 2.

"General Decision Number: NC20240003 01/05/2024

Superseded General Decision Number: NC20230003

State: North Carolina

Construction Type: Building

County: Durham County in North Carolina.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).

|If the contract is entered |� Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |� The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.20 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2024. | |If the contract was awarded on|� Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |� The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $12.90 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours performing on that | | | contract in 2024. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/05/2024

ELEC0553-001 12/01/2022

Rates Fringes

ELECTRICIAN......................$ 28.96 12.45

IRON0848-003 07/01/2023

Rates Fringes

IRONWORKER.......................$ 28.00 17.10

PLUM0421-006 07/01/2023

Rates Fringes

PIPEFITTER.......................$ 33.96 13.48

SUNC2018-003 08/08/2023

Rates Fringes

BRICKLAYER.......................$ 19.37 0.00

CARPENTER........................$ 19.74 3.63

CEMENT MASON/CONCRETE FINISHER...$ 17.86 0.00

LABORER: Common or General......$ 11.72 ** 0.00

LABORER: Mason Tender - Brick...$ 13.52 ** 0.00

LABORER: Mason Tender - Cement/Concrete..................$ 15.26 ** 0.00

LABORER: Pipelayer..............$ 15.00 ** 0.00

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 19.45 0.00

OPERATOR: Bulldozer.............$ 17.77 3.01

OPERATOR: Forklift..............$ 16.00 ** 0.00

OPERATOR: Grader/Blade..........$ 22.68 3.27

OPERATOR: Roller................$ 15.31 ** 1.46

PAINTER..........................$ 15.55 ** 1.05

PLUMBER..........................$ 23.66 6.60

ROOFER...........................$ 18.26 4.38

SHEET METAL WORKER...............$ 19.67 13.27

TRUCK DRIVER: Dump Truck........$ 16.56 ** 3.09

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.20) or 13658 ($12.90). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

“END OF GENERAL DECISION"

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO

BIDDERS/OFFERORS

THIS SECTION IS FOR SOLICITATION PURPOSES ONLY. A COMPLETE BID

SHALL CONSIST OF THE FOLLOWING

(a) GENERAL INSTRUCTIONS:

1. Award will be made to the responsible bidder whose bid is deemed responsive to the terms of this invitation for bid and is deemed most advantageous to the Government.

2. All Bid preparation cost will be the sole responsibility of the Offeror. The Government will not reimburse any interested party for their bid preparation expenses (costs) or any expenses (costs) associated with their Pre-Bid Site Visit or Bid Opening attendance.

(b) SUBMISSION OF BIDS:

1. In accordance with FAR 14.302, Bids shall be submitted so that they will be received in the office designated in the invitation for bids not later than the exact time set for opening of bids. Bids may be delivered in person, or they can be mailed to the following address:

ATTN: Vangie Miller

100 Emancipation Drive, Building 27

Hampton, VA 23667

2. In accordance with FAR 14.304, Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated by the exact time for the Bid Opening specified below. Any bid, modification, or withdrawal of a bid received at the Government office designated in the IFB after the exact time specified for receipt of bids is "late" and will not be considered. Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the bid wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.

(c) BID OPENING INFORMATION: A public bid opening has been scheduled for March 12, 2024, at 2:00 PM EST, at the following location:

Hampton VA Medical Center

Building 27 Averill Avenue

Hampton, VA 23667

(d) SPECIFIC INSTRUCTIONS –A COMPLETE BID SHALL CONSIST OF THE

FOLLOWING

1. TAB A: General Information

a. Cover page with Solicitation Number and Project Title

b. Table of Contents

c. Company information to include SAM Unique Entry ID, Cage Code, Tax ID Number, Principal points of contact with addresses, phone numbers and email addresses.

d. Base Bid Cost Breakdown Worksheet (Attachment A)

TAB B: Offer, Guarantee, and Certifications

a. Complete the SF 1442, Blocks 14, 15, 16, 17, 19, 20A, 20B, 20C. An official having the authority to bind your company contractually must sign and date the SF 1442 Block 20A-C. One copy of the SF 1442 must bear an original, authorized signature. In doing so, the Offeror accedes to the contract terms and conditions as written in the IFB. All sections of the IFB, excluding Instructions to Offerors and Evaluation Procedures Sections, constitute the model contract. SF1442 Block 19 Acknowledgement of Amendments (as applicable) – Interested Parties need to acknowledge all amendments that were posted to SAM.gov prior to Bid Closing.

b. Bid Bond/Offer/Guarantee IAW Provision 52.228-1

c. Proof of SDVOSB certification in the SBA certification database at https://veterans.certify.sba.gov .

https://veterans.certify.sba.gov/

d. Complete the following Clause’s and Provisions and certify when necessary. i. 52.204-8 Annual Representations and Certifications, paragraph (d) applies to this contract.

ii. 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021)

iii. 52.209-5 Certification Regarding Responsibility Matters (Aug 2020)

iv. 52.209-7 Information Regarding Responsibility Matters (OCT 2018)

v. 52.209-13 Violation of Arms Control Treaties or Agreements-Certification (Nov 2021)

vi. 52.219-28 – POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2021) Complete Sections (h)(1) through (h)(8) and certify by signing and dating “Contractor to sign and date and insert authorized signer's name and title.”

vii. 52.225-9 Buy American-Construction Materials (Nov 2021) complete sections (d) or mark as Not Applicable by annotating “N/A” within the chart.

viii. 852.219-75 VA Notice of Limitations on Subcontracting—Certificate of Compliance for Services and Construction.

INFORMATION REGARDING BIDDING MATERIAL, BID

GUARANTEE AND BONDS

If the bid/offer exceeds $150,000, a bid guarantee is required in an amount not less than twenty

(20) percent of the bid/offer price or $3M, whichever is less.

Bidders are reminded that an acceptable Bid Guarantee MUST be received with the bid/offer before the bid opening. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids/offers, will require rejection of the bid/offer in all cases except those listed in Federal Acquisition Regulation (FAR) 28.101-4, and may be cause for rejection even then. For guidance, Bidders/Offerors are referred to FAR provision 52.228-1, BID GUARANTEE (SEP 1996) in the solicitation, FAR Part 28.101 Bid Guarantees, and FAR Part 28.2 Sureties and Other Security for Bonds. Corporate sureties offered for bonds must appear on the list contained in the Department of Treasury Circular 570, Department of the Treasury's Listing of Companies Holding Certificates of Authority

If the contract will exceed $30,000 but will not exceed $150,000, the bidder/offeror to whom award is made will be required to furnish a Payment Bond, Standard Form 25A, or alternative payment protection.

If the contract will exceed $150,000, the bidder/offeror to whom award is made shall be required to furnish a Payment Bond, Standard Form 25A, and a Performance Bond, Standard Form 25. Copies of the Standard Forms 25A and 25 may be obtained upon application to the Issuing Office.

1.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY

REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/

(End of Provision)

FAR

Number

Title Date

52.204-7 SYSTEM FOR AWARD MANAGEMENT OCT 2018

52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE

REPORTING

AUG 2020

52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017

52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS DEC 2016

52.214-4 FALSE STATEMENTS IN BIDS APR 1984

52.214-5 SUBMISSION OF BIDS DEC 2016

52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS APR 1984

52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND

WITHDRAWALS OF BIDS

NOV 1999

52.214-18 PREPARATION OF BIDS—CONSTRUCTION APR 1984

52.214-19 CONTRACT AWARD—SEALED BIDDING—

CONSTRUCTION

AUG 1996

52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE APR 1991

52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY APR 1991

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION

TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR

CONSTRUCTION

FEB 1999

52.223-1 BIOBASED PRODUCT CERTIFICATION MAY 2012

52.223-4 RECOVERED MATERIAL CERTIFICATION MAY 2008

52.228-1 BID GUARANTEE SEP 1996

52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID

GUARANTEE)

FEB 2021

52.236-27 SITE VISIT (CONSTRUCTION) ALTERNATE I (FEB 1995) FEB 1995

1.2 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

1.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—

SECONDARY SITE OF THE WORK (MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

1.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—

CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

1.5 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Hand-Carried Address:

Contracting Office Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 Mailing Address:

Department of Veterans Affairs

Contracting Office Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

1.6 VAAR 852.209-70 ORGANIZATIONAL CONFLICTS OF INTEREST

(OCT 2020)

(a) It is in the best interest of the Government to avoid situations which might create an organizational conflict of interest or where the Offeror’s performance of work under the contract may provide the Contractor with an unfair competitive advantage. The term ‘‘organizational conflict of interest’’ means that because of other activities or relationships with other persons, a person is unable to render impartial assistance or advice to the Government, or the person’s objectivity in performing the contract work is or might be otherwise impaired, or the person has an unfair competitive advantage.

(b) The Offeror shall provide a statement with its offer which describes, in a concise manner, all relevant facts concerning any past, present, or currently planned interest (financial, contractual, organizational, or otherwise) or actual or potential organizational conflicts of interest relating to the services to be provided under this solicitation. The Offeror shall also provide statements with its offer containing the same information for any consultants and subcontractors identified in its proposal and which will provide services under the solicitation. The Offeror may also provide relevant facts that show how its organizational and/or management system or other actions would avoid or mitigate any actual or potential organizational conflicts of interest.

(c) Based on this information and any other information solicited or obtained by the Contracting Officer, the Contracting Officer may determine that an organizational conflict of interest exists which would warrant disqualifying the Contractor for award of the contract unless the organizational conflict of interest can be mitigated to the Contracting Officer’s satisfaction by negotiating terms and conditions of the contract to that effect. If the conflict of interest cannot be mitigated and if the Contracting Officer finds that it is in the best interest of the United States to award the contract, the Contracting Officer shall request a waiver in accordance with FAR 9.503.

(d) Nondisclosure or misrepresentation of actual or potential organizational conflicts of interest at the time of the offer or arising as a result of a modification to the contract, may result in the termination of the contract at no expense to the Government.

(End of Provision)

1.7 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE

RESOLUTION (OCT 2018)

(a) Any protest filed by an interested party shall—

(1) Include the name, address, fax number, email and telephone number of the protester;

(2) Identify the solicitation and/or contract number;

(3) Include an original signed by the protester or the protester’s representative and at least one copy;

(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;

(5) Specifically request a ruling of the individual upon whom the protest is served;

(6) State the form of relief requested; and

(7) Provide all information establishing the timeliness of the protest.

(b) Failure to comply with the above may result in dismissal of the protest without further consideration.

(c) Bidders/offerors and Contracting Officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.

(End of Provision)

1.8 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT

2018)

(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.

(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.

PLEASE NOTE: The correct mailing information for filing alternate protests is as follows:

Deputy Assistant Secretary for Acquisition and Logistics, Risk Management Team, Department of Veterans Affairs 810 Vermont Avenue, N.W.

Washington, DC 20420 Or for solicitations issued by the Office of Construction and Facilities Management:

Director, Office of Construction and Facilities Management 811 Vermont Avenue, N.W.

Washington, DC 20420

1.9 VAAR 852.239-75 INFORMATION AND COMMUNICATION

TECHNOLOGY ACCESSIBILITY NOTICE (FEB 2023)

(a) Any offeror responding to this solicitation must comply with established VA Information and Communication Technology (ICT) (formerly Electronic and Information (EIT)) accessibility standards. Information about Section 508 is available at http://www.section508.va.gov/.

(b) The Section 508 accessibility standards applicable to this solicitation are stated in the clause at 852.239–75, Information and Communication Technology Accessibility. In order to facilitate the Government’s determination whether proposed ICT supplies meet applicable http://www.section508.va.gov/

Section 508 accessibility standards, offerors must submit appropriate VA Section 508 Checklists, in accordance with the checklist completion instructions. The purpose of the checklists is to assist VA acquisition and program officials in determining whether proposed ICT supplies, or information, documentation and services conform to applicable Section 508 accessibility standards. The checklists allow offerors or developers to self-evaluate their supplies and document—in detail—whether they conform to a specific Section 508 accessibility standard, and any underway remediation efforts addressing conformance issues.

(c) Respondents to this solicitation must identify any exception to Section 508 requirements. If an offeror claims its supplies or services meet applicable Section 508 accessibility standards, and it is later determined by the Government, i.e., after award of a contract or order, that supplies or services delivered do not conform to the described accessibility standards, remediation of the supplies or services to the level of conformance specified in the contract will be the responsibility of the Contractor at its expense.

(End of Provision)

1.10 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES

INCORPORATED BY REFERENCE (JAN 2008)

The following provisions or clauses incorporated by reference in this solicitation must be completed by the offeror or prospective contractor and submitted with the quotation or offer.

Copies of these provisions or clauses are available on the Internet at the Web sites provided in the provision at FAR 52.252-1, Solicitation Provisions Incorporated by Reference, or the clause at FAR 52.252-2, Clauses Incorporated by Reference. Copies may also be obtained from the contracting officer.

[Contracting officer shall list all FAR and 48 CFR Chapter 8 (VAAR) provisions and clauses incorporated by reference that must be completed by the offeror or prospective contractor and submitted with the quotation or offer.]

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS

(MAR 2023)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.

(2) The small business size standard is $45 Million.

(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition—

(i) Is set aside for small business and has a value above the simplified acquisition threshold;

(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or

(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .