This solicitation package includes a quality control plan specification and details for a federal construction contract opportunity. The quality control plan specification outlines requirements for contractor quality control, including developing a CQC plan and conducting preparatory, initial, and follow-up phases of control. It also specifies personnel requirements and documentation.

The related federal contract opportunity is to provide construction services for a two-story, 15,000 square foot cancer center addition to a VA medical center in Richmond, Virginia. The work must be completed within 630 calendar days of receiving the notice to proceed and in accordance with provided drawings and specifications. The estimated cost is between $5-10 million. The NAICS code is 236220 and it is a 100% SDVOSB set-aside. Questions must be emailed to the contracting officer by the response date listed in the forthcoming solicitation.

36C24619B0040 0003 014500 (03-2019) Quality Control.pdf

View the file

Other files

File Type Posted
36C24619B0040-0003007.pdf PDF
36C24619B0040-0003001.pdf PDF
36C24619B0040-0003004.pdf PDF
36C24619B0040-0003006.pdf PDF
36C24619B0040-0003003.pdf PDF
36C24619B0040-0003005.pdf PDF
36C24619B0040-0003000.docx DOCX document
36C24619B0040-0003002.pdf PDF
36C24619B0040-0003000.docx DOCX document
36C24619B0040-0003004.pdf PDF
36C24619B0040-0003001.pdf PDF
36C24619B0040-0003007.pdf PDF
36C24619B0040-0003002.pdf PDF
36C24619B0040-0003006.pdf PDF
36C24619B0040-0003005.pdf PDF
36C24619B0040-0002000.docx DOCX document
36C24619B0040-0002000.docx DOCX document
36C24619B0040-0001000.docx DOCX document
36C24619B0040-0001000.docx DOCX document
36C24619B0040-008.pdf PDF
36C24619B0040-003.pdf PDF
36C24619B0040-004.pdf PDF
36C24619B0040-010.pdf PDF
36C24619B0040-001.docx DOCX document
36C24619B0040-013.pdf PDF
36C24619B0040-005.pdf PDF
36C24619B0040-007.pdf PDF
36C24619B0040-011.pdf PDF
36C24619B0040-006.pdf PDF
36C24619B0040-012.pdf PDF
36C24619B0040-009.pdf PDF
36C24619B0040-002.docx DOCX document
36C24619B0040-003.pdf PDF
36C24619B0040-009.pdf PDF
36C24619B0040-008.pdf PDF
36C24619B0040-011.pdf PDF
36C24619B0040-013.pdf PDF
36C24619B0040-002.docx DOCX document
36C24619B0040-007.pdf PDF
36C24619B0040-004.pdf PDF
36C24619B0040-012.pdf PDF
36C24619B0040-001.docx DOCX document
36C24619B0040-010.pdf PDF
36C24619B0040-006.pdf PDF
36C24619B0040-005.pdf PDF
36C24619B0040-000.docx DOCX document
36C24619B0040-000.docx DOCX document
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Medical Center - Richmond, VA Project No. 652-3 18 Construct Cancer Center Bid Documents: 09/09/19

01 45 00 - 1

SECTION 01 45 00

QUALITY CONTROL

PART 1 - GENERAL

1.1 DESCRIPTION

This section specifies requirements for Contractor Quality Control

(CQC) for Design-Bid-Build (DBB) construction proje cts.

1.2 APPLICABLE PUBLICATIONS

A. The publication listed below form a part of this sp ecification to the extent referenced. The publications are referred to within the text by the basic designation only.

B. ASTM International (ASTM)

1. D3740 - (2012a) Minimum Requirements for Agencies E ngaged in the

Testing and/or Inspection of Soil and Rock as Used in Engineering

Design and Construction

2. E329 - (2014a) Standard Specification for Agencies Engaged in the

Testing and/or Inspection of Materials Used in Cons truction

1.3 SUBMITTALS

Government approval is required for all submittals . CQC inspection reports shall be submitted under this Specification section and follow the [Applicable CQC Control Phase (Preparatory, Ini tial, or Follow-

Up)]: [Applicable Specification section] naming con vention.

1. Preconstruction Submittals

a. Interim CQC Plan

b. CQC Plan

c. Additional Requirements for Design Quality Control (DQC) Plan

2. Design Data

a. Discipline-Specific Checklists

b. Design Quality Control

3. Test Reports

a. Verification Statement

01 45 00 - 2

PART 2 PRODUCTS – NOT USED

PART 3 - EXECUTION

3.1 GENERAL REQUIREMENTS

Establish and maintain an effective quality contro l (QC) system that complies with the FAR Clause 52.246.12 titled “Insp ection of

Construction”. QC consists of plans, procedures, an d organization necessary to produce an end product which complies with the Contract requirements. The QC system covers all design and c onstruction operations, both onsite and offsite, and be keyed t o the proposed design and construction sequence. The project super intendent will be held responsible for the quality of work and is sub ject to removal by the Contracting Office or Authorized designee for n on-compliance with the quality requirements specified in the Contract. In this context the highest level manager responsible for the overall c onstruction activities at the site, including quality and produ ction is the project superintendent. The project superintendent maintain s a physical presence at the site at all times and is responsibl e for all construction and related activities at the site, ex cept as otherwise acceptable to the Contracting Officer.

3.2 CQC PLAN:

A. Submit no later than 30 days after receipt of Notic e to Proceed (NTP) the CQC Plan proposed to implement the requirements of the FAR Clause

52.246.12 titled “Inspection of Construction”. The Government will consider an Interim CQC Plan for the first 30 days of operation, which must be accepted within 10 business days of NTP. De sign and/or construction will be permitted to begin only after acceptance of the CQC

Plan or acceptance of an Interim plan applicable to the particular feature of work to be started. Work outside of the accepted Interim CQC

Plan will not be permitted to begin until acceptanc e of a CQC Plan or another Interim CQC Plan containing the additional work scope is accepted.

B. Content of the CQC Plan: Include, as a minimum, the following to cover all design and construction operations, both onsite and offsite, including work by subcontractors, designers of reco rd consultants, architects/engineers (A/E), fabricators, suppliers, and purchasing agents:

01 45 00 - 3

1. A description of the QC organization, including a c hart showing lines of authority and acknowledgement that the CQC staff will implement the three phase control system for all as pects of the work specified. Include a CQC System Manager that report s to the project superintendent.

2. The name, qualifications (in resume format) duties, responsibilities, and authorities of each person as signed a CQC function.

3. A copy of the letter to the CQC System Manager sign ed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including auth ority to stop work which is not in compliance with the Contract. Letters of direction to all other various quality control repr esentatives outlining duties, authorities, and responsibilities will to the

Contracting Officer or Authorized designee. be issu ed by the CQC

System Manager. Furnish copies of these letters

4. Procedures for scheduling, reviewing, certifying, a nd managing submittals including those of subcontractors, desig ners of record, consultants, A/E’s offsite fabricators, suppliers a nd purchasing agents. These procedures must be in accordance with Section 01 33 23

Shop Drawings, Product Data, and Samples.

5. Control, verification, and acceptance of testing pr ocedures for each specific test to include the test name, specificati on paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facil ities approved by the Contracting Officer or Authorized designee are required to be used)

6. Procedures for tracking Preparatory, Initial, and F ollow-Up control phases and control, verification, and acceptance te sts including documentation.

7. Procedures for tracking design and construction def iciencies from identification through acceptable corrective action . Establish verification procedures that identified deficiencie s have been corrected.

8. Reporting procedures, including proposed reporting formats.

9. A list of the definable features of work. A definab le feature of work is a task which is separate and distinct from other tasks has

01 45 00 - 4 separate control requirements, and is identified by different trades or disciplines, or it is work by the same trade in a different environment. Although each section of specification s can generally be considered as a definable feature of work, there are frequently more than one definable feature under a particular section. This list will be agreed upon during the Coordination me eting.

10. Coordinate schedule work with Special Inspections r equired by

Section 01 45 35 Special Inspections, the Statement of Special

Inspections and Schedule of Special Inspections. Wh ere the applicable Code issue by the International Code Cou ncil (ICC) calls for inspections by the Building Official, the Contr actor must include the inspections in the CQC Plan and must pe rform the inspections required by the applicable ICC. The Con tractor must perform these inspections using independent qualifi ed inspectors.

Include the Special Inspection Plan requirements in the CQC Plan.

C. Additional Requirements for Design Quality Control (DQC) Plan: The following additional requirements apply to the DQC Plan for DB projects only:

1. Submit and maintain a DQC Plan as an effective QC p rogram which assures that all services required by this contract are performed and provided in a manner that meets professional ar chitectural and engineering quality standards. As a minimum, all do cuments must be technically reviewed by competent, independent revi ewers identified in the DQC Plan. The same element that produced the product may not perform the independent technical review (ITR). Cor rect errors and deficiencies in the design documents prior to submi tting them to the

Government.

2. Include the design schedule in the master project s chedule, showing the sequence of events involved in carrying out the project design tasks within the specific Contract period. This sho uld be at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of wor k. Include review and correction periods associated with each item. T his should be a forward planning as well as a project monitoring to ol. The schedule reflects calendar days and not dates for each activ ity. If the schedule is changed, submit a revised schedule refl ecting the change within 7 calendar days. Include in the DQC Plan the discipline-specific checklists to be used during the design an d quality control

01 45 00 - 5 of each submittal. Submit at each design phase as p art of the project documentation these completed discipline-sp ecific checklists.

3. Implement the DQC Plan by a DQC Manager who has the responsibility of being cognizant of and assuring that all documen ts on the project have been coordinated. This individual must be a pe rson who has verifiable engineering or architectural design expe rience and is a

Professional Engineer or Registered Architect withi n the state of

Construction location. Notify the Contracting Offic er or Authorized designee, in writing, of the name of the individual , and the name of an alternate person assigned to the position.

D. Acceptance of Plan: Acceptance of the Contractor’s plan is required prior to the start of design and construction. Acce ptance is conditional and will be predicated on satisfactory performance during the design and construction. The Government reserve s the right to require the Contractor to make changes in the CQC P lan and operations including removal of personnel as necessary, to obt ain the quality specified.

E. Notification of Changes: After acceptance of the CQ C Plan, notify the

Contracting Officer or Authorized designee in writi ng of any proposed change. Proposed changes are subject to acceptance by the Government prior to implementation by the Contractor.

3.3 COORDINATION MEETING:

After the Preconstruction Conference Post-award Co nference before start of design or construction, and prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer or Authorized designee to discuss the Contractor’s quality control system. Submit the CQC Plan a minimum of 5 business days prior to the Coordinat ion Meeting. During the meeting, a mutual understanding of the system d etails must be developed, including the forms for recording the CC operations, design activities (if applicable), control activities, tes ting, administration of the system for both onsite and offsite work, and the interrelationship of Contractor’s Management and co ntrol with the

Government’s Quality Assurance. Minutes of the mee ting will be prepared by the Government, signed by both the Cont ractor and

Contracting Officer or Authorized designee and will become a part of the contract file. There can be occasions when subs equent conferences will be called by either party to reconfirm mutual understandings or

01 45 00 - 6 address deficiencies in the CQC system or procedure s which can require corrective action by the Contractor.

3.4 QUALITY CONTROL ORGANIZATION:

A. Personnel Requirements: The requirements for the CQ C organization are a

Safety and Health Manager, CQC System Manager, a De sign Quality Manager

(if applicable), and sufficient number of additiona l qualified personnel to ensure safety and Contract compliance. The Safety and

Health Manager shall satisfy the requirements of Sp ecification 01 35 26

Safety Requirements and reports directly to a senio r project (or corporate) official independent from the CQC System Manager. The Safety and Health Manager will also serve as a member of t he CQC Staff.

Personnel identified in the technical provisions as requiring specialized skills to assure the required work is b eing performed properly will also be included as part of the CQC o rganization. The

Contractor’s CQC staff maintains a presence at the site at all times during progress of the work and have complete autho rity and responsibility to take any action necessary to ensu re Contract compliance. The CQC staff will be subject to accept ance by the

Contracting Officer or Authorized designee. Provide adequate office space, filing systems, and other resources as neces sary to maintain an effective and fully functional CQC organization. Pr omptly complete and furnish all letters, material submittals, shop draw ings submittals, schedules and all other project documentation to th e CQC organization.

The CQC organization is responsible to maintain the se documents and records at the site at all times, except as otherwi se acceptable to the

Government.

B. CQC System Manager: Identify as CQC System Manager an individual within the onsite work organization that is responsible fo r overall management of CQC and has the authority to act in all CQC matt ers for the

Contractor. The CQC system Manager is required to b e a graduate engineer, graduate architect, or a graduate of cons truction management, with a minimum of 10 years construction experience on construction similar to the scope of this Contract. This CQC Sys tem manager is on the site at all times during construction and is em ployed by the

General Contractor. Identify in the plan an alterna te to serve in the event of the CDQC System Manager’s absence. The req uirements for the alternate are the same as the CQC System Manager.

01 45 00 - 7

C. CQC Personnel: In addition to CQC personnel specifi ed elsewhere in the contract, provide as part of the CQC organization s pecialized personnel to assist in the CQC System Manager for the followi ng areas, as applicable: electrical, mechanical, civil, structur al, environmental, architectural, materials technician submittals cler k, Commissioning

Agent/LEED specialist, and low voltage systems. The se individuals or specified technical companies are directly employed by the General

Contractor and cannot be employed by a supplier or subcontractor on this project or are employees of the prime or subco ntractor; be responsible to the CQC System Manager; be physicall y present at the construction site during work on the specialized pe rsonnel’s areas of responsibility; have the necessary education or exp erience in accordance with the Experience Matrix listed herein . These individuals can perform other duties but need to be allowed suf ficient time to perform the specialized personnel’s assigned qualit y controls duties as described in the CQC Plan. A single person can cove r more than one area provided that the single person is qualified to per form QC activities in each designated and that workload allows.

EXPERIENCE MATRIX

Area Qualifications

Civil

Graduate Civil Engineer or Construction

Manager with 2 years experience in the type of work being performed on this project or technician with 5 years related experience.

Mechanical

Graduate Mechanical Engineer with 2 years experience or construction professional with 5 years of experience supervising mechanical features of work in the field with a construction company.

Electrical

Graduate Electrical Engineer with 2 years related experience or construction professional with 5 years of experience supervising electrical features of work in the field with a construction company.

01 45 00 - 8

Area Qualifications

Structural

Graduate Civil Engineer (with Structural

Track or Focus), Structural Engineer, or

Construction Manager with 2 years experience or construction professional with 5 years experience supervising structural features of work in the field with a construction company.

Architectural

Graduate Architect with 2 years experience or construction professional with 5 years of related experience.

Environmental Graduate Environmental Engineer with 3 years experience.

Submittals Submittal Clerk with 1 year experience.

Concrete, Pavement, and Soils Materials Technician with 2 years experience for the appropriate area.

Testing, Adjusting, and Balancing (TAB)

Specialist must be a member of AABC or an experienced technicaion of the firm certified by the NEBB.

Design Quality Control Manager Registered Architect or Professional

Engineer

SPEC WRITE NOTE:The CQM Training certificate expires after 5 years. If the CQC System Manager’s certificate has expired, retake the course to remain current.

D. Additional Requirements: In addition to the above e xperience and education requirements, the CQC System Manager and Alternate CQC System

Manager are required to have completed the Construc tion Quality

Management (CQM) for Construction course. If the C QC System Manager does not have a current specification, obtain the C QM for Contractors course identification within 90 days of award. This course is periodically offered by the Naval Facilities Engine ering Command and the Army Corps of Engineers. Contact the Contractin g Officer or

Authorized designee for information on the next sch eduled class.

E. Organizational Changes: Maintain the CQC staff at f ull strength at all times. When it is necessary to make changes to the CQC staff, revise the CQC Plan to reflect the changes and submit the changes to the

Contracting Officer or Authorized designee for acce ptance.

01 45 00 - 9

3.5 SUBMITTALS AND DELIVERABLES: Submittals have to comply with the requirements in Section 01 33 23 Shop Drawings, Pro duct Data, and

Samples. The CQC organization is responsible for ce rtifying that all submittals and deliverables are in compliance with the contract requirements. When Section 01 91 00 General Commis sioning Requirements is included in the contract, the submittals require d by the section have to be coordinated with the Section 01 33 23 Sh op Drawings, Product

Data, and Samples to ensure adequate time is allowe d for each type of submittal required.

3.6 CONTROL:

A. CQC is the means by which the Contractor ensures th at the construction, to include that of subcontractors and suppliers, co mplies with the requirements of the contract. At least three phases of control are required to be conducted by the CQC System Manager for each definable feature of the construction work as follows:

1. Preparatory Phase: This phase is performed prior to beginning work on each definable feature of work after all require d plans/documents/materials are approved/accepted, an d after copies are at the work site. This phase includes:

a. A review of each paragraph of applicable specifi cations, references codes, and standards. Make available dur ing the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of t he work to be accomplished in the field. Maintain and make availa ble in the field for use by Government personnel until final a cceptance of the work.

b. Review of the Contract drawings.

c. Check to assure that all materials and equipment ha ve been tested, submitted, and approved.

d. Review of provisions that have been made to provide required control inspection and testing.

e. Review Special Inspections required by Section 01 4 5 35 Special

Inspections, that Statement of Special Inspections and the

Schedule of Specials Inspections.

f. Examination of the work area to assure that all req uired preliminary work has been completed and is in compl iance with the Contract.

01 45 00 - 10

g. Examination of required materials, equipment, and s ample work to assure that they are on hand conform to approved sh op drawings or submitted data, and are properly stored.

h. Review of the appropriate Activity Hazard Analysis (AHA) to assure safety requirements are met.

i. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document constru ction tolerances and workmanship standards – contract def ined or industry standard if not contract defined - for tha t feature of work.

j. Check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Offi cer.

k. Discussion of the initial control phase.

l. The Government needs to be notified at least 48 hou rs or 2 business days in advance of beginning the Preparato ry control phase. Include a meeting conducted by the CQC Syste m Manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the de finable feature. Document the results of the Preparatory ph ase actions by separate minutes prepared by the CQC System Mana ger and attach to the daily CQC report. Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.

B. Initial Phase: This phase is accomplished at the be ginning of a definable feature of work. Accomplish the following :

1. Check work to ensure that it is in full compliance with contract requirements. Review minutes of the Preparatory mee ting.

2. Verify adequacy of controls to ensure full contract compliance.

Verify the required control inspection and testing is in compliance with the contract.

3. Establish level of workmanship and verify that it m eets minimum acceptable workmanship standards. Compare with requ ired sample panels as appropriate.

4. Resolve all differences.

5. Check safety to include compliance with an upgradin g of the safety plan and activity hazard analysis. Review the activ ity analysis with each worker.

01 45 00 - 11

6. The Government needs to be notified at least 48 hou rs or 2 business days in advance of beginning the initial phase for definable features of work. Prepare separate minutes of this phase by the CQC

System Manager and attach to the daily CQC report. Indicate the exact location of initial phase for definable featu re of work for future reference and comparison with Follow-Up phas es.

7. The initial phase for each definable feature of wor k is repeated for each new crew to work onsite, or any time acceptabl e specified quality standards are not being met.

8. Coordinate scheduled work with Special Inspections required by

Section 01 45 35 Special Inspections, the Statement of Special

Inspections, and the Schedule of Special Inspection s.

C. Follow-Up Phase: Perform daily checks to assure con trol activities, including control testing, are providing continued compliance with contract requirements until the completion of the p articular feature of work. Record the checks in the CQC documentation. C onduct final Follow-

Up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the defic ient work. Do not build upon nor conceal non-conforming work. Coordin ate scheduled work with Special Inspections required by Section 01 45 35 Special

Inspections, the Statement of Special Inspections, and the Schedule of

Special Inspections

D. Additional Preparatory and Initial Phases on the sa me definable features of work if: the quality ongoing work is un acceptable; if there are changes in the applicable CQC staff, onsite pro duction supervision or work crew; if work on a definable feature is res umed after a substantial period of inactivity, or if other probl ems develop.

3.7 TESTS

A. Testing Procedure: Perform specified or required te sts to verify that control measures are adequate to provide a product which conforms to contract requirements. Upon request, furnish to the Government duplicate samples of test specimens for possible te sting by the

Government. Testing includes operation and acceptan ce test when specified. Procure the services of a Department of Veteran Affairs approved testing laboratory or establish an approve d testing laboratory at the project site. Perform the following activiti es and record and provide the following data:

1. Verify that testing procedures comply with contract requirements.

01 45 00 - 12

2. Verify that facilities and testing equipment are av ailable and comply with testing standards.

3. Check test instrument calibration data against cert ified standards.

4. Verify that recording forms and test identification control number system, including all of the test documentation req uirements, have been prepared.

5. Record results of all tests taken, both passing and failing on the

CQC report for the date taken. Specification paragr aph reference, location where tests were taken, and the unique seq uential control number identifying the test. If approved by the Con tracting Officer or Authorized designee, actual test reports are sub mitted later with a reference to the test number and date taken. Prov ide an information copy of tests performed by an offsite o r commercial test facility directly to the Contracting Officer or Aut horized designee.

Failure to submit timely test reports as stated res ults in nonpayment for related work performed and disapprov al of the test facility for this Contract.

B. Testing Laboratories: All testing laboratories m ust be validated through the procedures contained in Specification s ection 01 45 29

Testing Laboratory Services.

1. Capability Check: The Government reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specificati ons and to check the laboratory technician’s testing procedures and techniques.

Laboratories utilized for testing soils, concrete, asphalt and steel is required to meet criteria detailed in ASTM D3740 and ASTM E329.

2. Capability Recheck: If the selected laboratory fail s the capability check, the Contractor will be assessed a charge equ al to value of recheck to reimburse the Government for each succee ding recheck of the laboratory or the checking of a subsequently se lected laboratory. Such costs will be deducted from the Co ntract amount due the Contractor.

C. Onsite Laboratory: The Government reserves the r ight to utilize the

Contractor’s control testing laboratory and equipme nt to make assurance tests, and to check the Contractor’s testing proced ures, techniques, and test results at no additional cost to the Gover nment.

01 45 00 - 13

3.8 COMPLETION INSPECTION

A. Punch-Out Inspection: Conduct an inspection of the work by the CQC system Manager near the end of the work, or any inc rement of the work established by a time stated FAR 52.211-10 – Commen cement, Prosecution, and Completion of Work, or by the specifications. P repare and include in the CQC documentation a punch list of items whic h do not conform to the approved drawings and specifications. Include w ithin the list of deficiencies the estimated date by which the defici encies will be corrected. Make a second inspection the CQC System Manager or staff to ascertain that all deficiencies have been corrected . Once this is accomplished, notify the Government that the facili ty is ready for the

Government Pre-Final Inspection.

52.211-10 -- Commencement, Prosecution, and Completion of Work.

As prescribed in 11.404(b), insert the following clause in solicitations and contracts when a fixed-price construction contract is contemplated. The clause may be changed to accommodate the issuance of orders under indefinite-delivery contracts for construction.

Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to:

(a) commence work under this contract within _________ // Contracting Officer insert number// calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than ______________.* The time stated for completion shall include final cleanup of the premises.

(End of Clause)

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

Alternate I (Apr 1984). If the completion date is expressed as a specific calendar date, computed on the basis of the contractor receiving the notice to proceed by a certain day, add the following paragraph to the basic clause:

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by_______________ // Contracting Officer insert date //. The completion date will be extended by the number of calendar days after the above date that the

Contractor receives the notice to proceed, except to the extent that the delay in issuance of

01 45 00 - 14 the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

B. Pre-Final Inspection: The Government will perform t he Pre-Final

Inspection to verify that the facility is complete and ready to be occupied. A Government Pre-Final Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final Acceptance

Inspection with the customer can be scheduled. Corr ect any items noted on the Pre-Final Inspection in a timely manner. The se inspections and any deficiency corrections required by this paragra ph need to be accomplished within the time slated for completion of the entire work or any particular increment of the work if the proj ect is divided into increments by separate construction completion date s.

C. Final Acceptance Inspection: The Contractor’s QC In spection personnel, plus the superintendent or other primary management person, and the

Contracting Officer’s Authorized designee is requir ed to be in attendance at the Final Acceptance Inspection. Add itional Government personnel can also be in attendance. The Final Acce ptance Inspection will be formally scheduled by the Contracting Offic er’s or Authorized designee based upon results of the Pre-Final Inspec tion. Notify the

Contracting Officer through the Resident Engineer o ffice at least 14 days prior to the Final Acceptance Inspection and i nclude the

Contractor’s assurance that all specific items prev iously identified to the Contractor as being unacceptable, along with al l remaining work performed under the contract, will be complete and acceptable by the date schedule for the Final Acceptance Inspection. Failure of the

Contractor to have all contract work acceptably com plete for this inspection will be cause for the Contracting Office r to bill the

Contractor for the Government’s additional inspecti on cost in accordance with FAR Clause 52.246-12 titled “Inspec tion of

Construction”.

3.9 DOCUMENTATION

A. Quality Control Activities: Maintain current record s providing factual evidence that required QC activities and tests have been performed.

Include in these records the work of subcontractors and suppliers on an acceptable form that includes, as a minimum, the fo llowing information:

01 45 00 - 15

1. The name and area of responsibility of the Contract or/Subcontractor

2. Operating plant/equipment with hours worked, idle, or down for repair.

3. Work performed each day, giving location, descripti on, and by whom.

When Network Analysis (NAS) is used, identify each phase of work performed each day by NAS activity number.

4. Test and control activities performed with results and references to specification/drawing requirements. Identify the Co ntrol Phase

(Preparatory, Initial, and/or Follow-Up). List defi ciencies noted, along with corrective action.

5. Quantity of materials received at the site with sta tement as to acceptability, storage, and reference to specificat ion/drawing requirements.

6. Submittals and deliverables reviewed, with Contract reference, by whom, and action taken.

7. Offsite surveillance activities, including actions taken.

8. Job safety evaluations stating what was checked, re sults, and instructions or corrective actions.

9. Instructions given/received and conflicts in plans and specifications.

10. Provide documentation of design quality control act ivities. For independent design reviews, provide, as a minimum, identification of the Independent Technical Reviewer (ITR) team, the ITR review comments, responses, and the record of resolution o f the comments.

B. Verification Statement: Indicate a description of t rades working on the project; the number of personnel working; weather c onditions encountered; and any delays encountered. Cover both conforming and deficient features and include a statement that equ ipment and materials incorporated in the work and workmanship comply wit h the Contract.

Furnish the original and one copy of these records in report form to the Government daily with 1 week after the date cov ered by the report, except that reports need not be submitted for days on which no work is performed. As a minimum, prepare and submit on repo rt for every 7 days of no work and on the last day of a no work period. All calendar days need to be accounted for throughout the life of the contract. The first report following a day of no work will be for that day only. Reports need to be signed and dated by the CQC System Manag er. Include copies

01 45 00 - 16 of test reports and copies of reports prepared by a ll subordinate QC personnel within the CQC System Manager Report.

3.10 SAMPLE FORMS

014500 Referenced Example Form Template.pdf

3.11 NOTIFICATION OF NONCOMPLIANCE: The Contracting Officer or Authorized designee will notify the Contractor of any detected noncompliance with the foregoing requirements. The Contractor should t ake immediate corrective action after receipt of such notice. Suc h notice, when delivered to the Contractor at the work site will b e deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer can issue an order stopping all or part of the work until satisfactory correcti ve action has been taken. No part of the time lost due to such stop or ders will be made the subject of claim for extension of time or for e xcess costs or damages by the Contractor.

--- End of Section ---