This document is a draft schedule for planned electrical outages and maintenance activities at the Martinsburg Veterans Affairs Medical Center. It details a series of outages and testing to be conducted on the facility's electrical infrastructure, including 12 kV vacuum switchgear breakers, automatic transfer switches, 480V switchgear, transformers, and other components. The outages are scheduled to occur over the course of several months, with the work being performed in the evenings and on weekends to minimize disruptions to the medical center's operations. The document provides a comprehensive overview of the specific equipment involved, the work to be done, the duration of the outages, and the planned test dates.
The related federal contract opportunity is a solicitation for contractor services to provide inspection, testing, and maintenance services for the electrical systems at the Martinsburg VA Medical Center. The solicitation number is 36C24524Q0607, and the services are required to be performed at the Martinsburg, WV facility. The Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 5 is the contracting agency.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Oil Samples 2014.pdf | ||
| 36C24524Q0607 0002_1.docx | DOCX document | |
| Maintenance Report 2014.pdf | ||
| Pre-Bid RFIs Test Facility Electrical Sysstem 2024 07 08 -.xlsx | XLSX spreadsheet | |
| Draft Schedule 2024-07-01.pdf | ||
| 4.2 - Breaker Settings.xls | XLS spreadsheet | |
| Master Site Electrical Dist System_30x42.pdf | ||
| Master Site Plan.pdf | ||
| Appendix G - One-lines - MRTN 100.pdf | ||
| 36C24524Q0607 0002 AMENDMENT.pdf | ||
| 36C24524Q0607 0001_1.docx | DOCX document | |
| 36C24524Q0607 0001 EXTENDING RFQ DATE.pdf | ||
| VHA Directive 1028_D_2020-02-24.pdf | ||
| 36C24524Q0607_1.docx | DOCX document | |
| 36C24524Q0607 --RFQ.pdf | ||
| WAGE DETERMINATION BERKELEY COUNTY WV.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Location Room/Pnl Device Type Device Number
Device Description Clearance Point (FD) Clearance Point (Back FD) Alt Feed Voltage Impacts Work Done Outage Desc.
Outage Duration
Ops Limits Outage Type Planned Test Date
Bldg 505 Elect Substation East
Station Air Switch #1 (B.5.a) Charlestown thru Bardane Feeder Disconn
Utility 34.5 kV Bldg 522A - ATS 1 Stby Gens Bldg 522 or auto tie in Bldg 503A
12470 Transient sensitive Equipment All Bldgs on A feed
Maintain and Test Station Air Switch
Parallel Standby Generators for
ATS 2
Transparent
Weekday in afternoon after surgery.
Needs Utility clearance
Utility Afternoon after Surgery
Flexible, when pepco available
Bldg 505 Elect Substation West
Station Air Switch #2 (B.5.b) Martinsburg Feeder Disconn Utility 34.5 kV Bldg 522A - ATS 2 Stby Gens Bldg 522 or auto tie in Bldg 503A
12470 Transient sensitive Equipment All Bldgs on B feed
Maintain and Test Station Air Switch
Parallel Stanby Generators for ATS
Transparent
Weekday in afternoon after surgery.
Needs Utility clearance
Utility Afternoon after Surgery
Flexible, when pepco available
Bldg 503A Station Vacuum Ckt Bkr A.1.a Auto Tie Breaker N/A, is racked out N/A, is racked out N/A, is racked out 12470 N/A, is racked out Maintain and Test breaker
N/A, is racked out N/A, is racked out
Reduced Redundancy
N/A, is racked out
When Test Company Available prior to Base Date +1
Bldg 503A Station Vacuum Ckt Bkr A.4.a Ckt 1 Out Buildings Loop N/A, is racked out N/A, is racked out N/A, is racked out 12470 N/A, is racked out Maintain and Test breaker
N/A, is racked out N/A, is racked out
Reduced Redundancy
N/A, is racked out
When Test Company Available prior to Base Date +1
Bldg 503A Station Vacuum Ckt Bkr A.2.a Ckt 1 Chiller Plant Loop N/A, is racked out N/A, is racked out N/A, is racked out 12470 N/A, is racked out Maintain and Test breaker
N/A, is racked out N/A, is racked out
Reduced Redundancy
N/A, is racked out
When Test Company Available prior to Base Date +1
Bldg 503A Station Vacuum Ckt Bkr Bus
A.1.a Bus between Ckt 1 and Ckt 2 Buses
Clean Bus, Along with put Campus on Ckt 2 and re-install tie breaker previously tested and maintianed.
No Normal Power
Bldg 501 MV Air Switch (Selector & Disconnect)
No Normal Power
Bldg 502 MV Air Switch (Selector & Disconnect)
No Normal Power
Bldg 503 MV Air Switch (Selector) No Normal Power
Bldg 500 GE-103 MV Air Switch XFMR A Feed No Normal Power
Bldg 500 GE-103 MV Air Switch XFMR B Feed No Normal Power Bldg 500 GE-103 MV Air Switch XFMR Feed Cross tie No Normal Power
Bldg 522A
ATS SWGR
Station ATS ATS-1 Station ATS=1 Station Air Switch #1 & Standby Gen/Bkr ATS-1 Control Power?
Bldg 503A - Ckt 1 Main ATS-2 and auto tie in Bldg 503A
12470 Reduced Redundancy
Maintain and Test
ATS-1
On Alt Feed B Train N/A No Surgery Any time (Clearance on weekend)
Base Date +1
Bldg 503A Station Vacuum Ckt Bkr A.6.a Main Breaker, Ckt 1 Bldg 522A ATS-1 Norm & Emerg Fd Bldg 503A Control Power?
Ckt 1 Main Hospital Loop LB, Ckt 1 Out Buildings Loop LB, and Auto Tie Breaker
Bldg 503A Main Breaker Ckt 2, Bldg 508 LB, Bldg 501 XFR SW, Bldg 502 XFR SW B, Bldg 500 XFMR BKR B & Bldg 500 Cross Tie Bkr
12470 Reduced Redundancy
Maintain and Test Main Breaker (Ckt
1) and maintain Ckt 1 Bus
On Alt Feed B Train N/A No Surgery, ??
Any time (Clearance on weekend)
Base Date +1
Maintain and Test selector and disconnect switches & leave on Ckt 2
Maintain and Test Main Feed and cross tie switches & leave on Ckt 2
Bldg 503A Main Breaker Ckt 1 (or ATS -1 or Station Air Switch 1 and
Standby Generator lockout) & Bldg 503A Main Breaker Ckt 2 (or ATS -2 or Station Air Switch and
Standby Generator lockout)
N/A None Available 12470 All Normal Power to Campus 4 Hours
Base Date Weekend
Fri PM
Only Have Emergency Power
Weekend
Number
Device Description Clearance Point (FD) Clearance Point (Back FD) Alt Feed Voltage Impacts Work Done Outage Desc.
Outage Duration
Ops Limits Outage Type Planned Test Date
Bldg 503A Station Vacuum Ckt Bkr A.5.a Ckt 1 Main Hospital Loop Bldg 503A Main Breaker, Ckt 1 & Bldg 503A Auto Tie Breaker
Main Hospital Loop Break Bldg 508
Bldg 503A Main Breaker Ckt 2, Bldg 508 LB, Bldg 501 XFR SW, Bldg 502 XFR SW B, Bldg 500 XFMR BKR B & Bldg 500 Cross Tie Bkr
12470 Reduced Redundancy
Maintain and Test Main Hospital Loop Breaker and Maintain Bus
On Alt Feed B Train N/A Reduced redundancy
Any time (Clearance on weekend)
Base Date +1
Bldg 503A Station Vacuum Ckt Bkr A.2.a Ckt 1 Chiller Plant Loop Bldg 503A Main Breaker, Ckt 1 & Bldg 503A Auto Tie Breaker
N/A
Bldg 503A Main Breaker Ckt 2, Bldg 508 LB, Bldg 501 XFR SW, Bldg 502 XFR SW B, Bldg 500 XFMR BKR B & Bldg 500 Cross Tie Bkr
12470 Reduced Redundancy
Clean Bus connections and re-rack previously tested breaker
Re-Rack before lift clearance N/A Reduced Redundancy
Any time (Clearance on weekend)
Base Date +1
Bldg 503A Station Vacuum Ckt Bkr A.4.a Ckt 1 Out Buildings Loop Bldg 503A Main Breaker, Ckt 1
Loop Break Outbuildings ?XFMR N Bldg 117 Chapel?
Bldg 503A Main Breaker Ckt 2, Bldg 508 LB, Bldg 501 XFR SW, Bldg 502 XFR SW B, Bldg 500 XFMR BKR B & Bldg 500 Cross Tie Bkr
12470 Reduced Redundancy
Clean Bus connections and re-rack previously tested breaker
On Alt Feed B Train N/A Reduced Redundancy
Evening Base Date +3
N/A N/A N/A 12470 All Normal Power to Campus
Move Alt Feed from B Train (Ckt 2) to A Train (Ckt 1)
No Normal Power 20 minutes Only Have Emergency Power
Evening Base Date +3
Bldg 522A
ATS SWGR
Station ATS ATS-2 Station ATS-2 Station Air Switch #2 & Standby Gen/Bkr ATS-2 Control Power?
Bldg 503A - Ckt 2 Main ATS-1 and auto tie in Bldg 503A
12470 Transient sensitive Equipment All Bldgs on B feed
On Alt Feed A, Will need to keep Ckt 2 and out buildings loop energized ourage not needed if cable not repaired
N/A No Surgery Any time (Clearance on weekend)
Base Date +4
Bldg 503A Station Vacuum Ckt Bkr A.8.a Main Breaker, Ckt 2 Bsdg 522A ATS-2 Norm & Gen
Loop Break & Bldg 503A Auto Tie Breaker
Bldg 503A Main Breaker Ckt 1, Bldg 508 LB, Bldg 501 XFR SW, Bldg 502 XFR SW A, Bldg 500 XFMR BKR A & Bldg 500 Cross Tie Bkr
12470 Entire campus loop by loop
On Alt Feed A, Will need to keep Ckt 2 and out buildings loop energized ourage not needed if cable not repaired
N/A No Surgery, ?? Evening Base Date +4
Bldg 503A Station Vacuum Ckt Bkr A.7.a Ckt 2 Main Hospital Loop 12470 Reduced Redundancy until lift Alt Feed
On Alt Feed A, Will need to keep Ckt 2 and out buildings loop energized ourage not needed if cable not repaired
N/A Reduced Redundancy
Evening Base Date +4
Bldg 503A Station Vacuum Ckt Bkr A.3.a Ckt 2 Chiller Plant Loop 12470 Reduced Redundancy until lift Alt Feed
On Alt Feed A, Will need to keep Ckt 2 and out buildings loop energized ourage not needed if cable not repaired
N/A Reduced Redundancy
Evening Base Date +5
Bldg 503A Station Vacuum Ckt Bkr A.9.a Ckt 2 Out Buldings Loop 12470 Reduced Redundancy until lift Alt Feed
On Alt Feed A, Will need to keep energized ourage not needed if cable not repaired
N/A Reduced Redundancy
Evening Base Date +5
Bldg 503A and ????
RESTORE NORMAL LINEUP Entire Campus Remove Alt Feed and put back on dual feed.
20 Minutes No Surgery, ?? Weekend Base Date +5
Bldg 522 Standby Swgr Ckt Bkr Gen G2A 150A Breaker Gen Start (x3) Station ATS-1 & 2 300A Alt FD Breaker
Normal Power 12470 Standby Power Source Off Line
Maintain and Test Gen G2A Isolation Breaker
Reduced Redundancy N/A Avoid Surgery Evening Flexible Base Date +6
Bldg 522 Standby Swgr Ckt Bkr Gen G3A 150A Breaker Gen Start (x3) Station ATS-1 & 2 300A Alt FD Breaker
Normal Power 12470 Standby Power Source Off Line
Maintain and Test Gen G3A Isolation Breaker
Reduced Redundancy N/A Avoid Surgery Evening Flexible Base Date +6
Bldg 522 Standby Swgr Ckt Bkr Gen G4A 150A Breaker Gen Start (x3) Station ATS-1 & 2 300A Alt FD Breaker
Normal Power 12470 Standby Power Source Off Line
Maintain and Test Gen G4A Isolation Breaker
Reduced Redundancy N/A Avoid Surgery Evening Flexible Base Date +6
Number
Device Description Clearance Point (FD) Clearance Point (Back FD) Alt Feed Voltage Impacts Work Done Outage Desc.
Outage Duration
Ops Limits Outage Type Planned Test Date
Bldg 522 Standby Swgr Ckt Bkr Station ATS-1 300A Alt FD Breaker
Gen Start (x3) Bldg 522A ATS-1 & ATS-2 Normal Power 12470 Standby Power Source Off Line
Maintain and Test ATS-1 Standby feed breaker
Reduced Redundancy N/A Avoid Surgery Evening Flexible Base Date +6
Bldg 522 Standby Swgr Ckt Bkr Station ATS-2 300A Alt FD Breaker
Gen Start (x3) Bldg 522A ATS-1 & ATS-2 Normal Power 12470 Standby Power Source Off Line
Maintain and Test ATS-2 Standby feed breaker
Reduced Redundancy N/A Avoid Surgery Evening Flexible Base Date +6
Bldg 500 Transformer XFMR A Bldg 500 MV Air Switch XFMR A Feed
Bldg 500 SWGR A Main Bkr Da.2
12470/480 1 second x 2 Reduced redundancy
Evening Base Date +10
Bldg 500 GE-102 LV Air Bkr? MCCB Swgr A Main Bkr DA.2 MV Air Switch XFMR A Feed Bldg 500 SWGR Cross Tie 480 1 second x 2 Reduced redundancy
Evening Base Date +10
Bldg 500 Transformer XFMR B Bldg 500 SWGR B Main Bkr Da.1
12470 1 second x 2 Reduced redundancy
Evening Base Date +10
Bldg 500 GE-102 LV Air Bkr? MCCB Swgr B Main Bkr DA.1 480 1 second x 2 Reduced redundancy
Evening Base Date +10
Bldg 500 LV Air Bkr? MCCB SWGR X Tie DA.3, In Swgr B Reduced redundancy N/A Reduced redundancy
Evening Base Date +10
Bldg 500 GE-102, SWGR A MCCB F MCC-1A Swgr A Main Bkr DA.2 480 Limited area no normal power 1 Hr Evening Base Date +10 Bldg 500 GE-102, SWGR A MCCB FB Pnl NE1-R Swgr A Main Bkr DA.2 480 Limited area no normal power 1 Hr Evening Base Date +10 Bldg 500 GE-102, SWGR A MCCB FB Elev EDP Swgr A Main Bkr DA.2 480 N/A 1 Hr None Base Date +10 Bldg 500 GE-102, SWGR A MCCB FB Elev 2 via Elev ATS Swgr A Main Bkr DA.2 480 Limited area no normal power 1 Hr Evening Base Date +10 Bldg 500 GE-102, SWGR A MCCB FB Bus Duct Swgr A Main Bkr DA.2 480 Limited area no normal power 1 Hr Evening Base Date +10
Bldg 500 GE-102, SWGR A MCCB FB ATS Normal Swgr A Main Bkr DA.2 480 Switching x2 Seconds, then seconds
Run Generator Reduced Redundancy
Evening Base Date +10
Bldg 500 GE-102, SWGR A MCCB FB Pnls DP-NCB, NC1, Nc2 Swgr A Main Bkr DA.2 480 Limited area no normal power 1 Hr Evening Base Date +10 Bldg 500 GE-102, SWGR A MCCB FB Pnl DP-SA Swgr A Main Bkr DA.2 480 Limited area no normal power 1 Hr Evening Base Date +10 Bldg 500 GE-102, SWGR A MCCB FB Internet Café Swgr A Main Bkr DA.2 480 Limited area no normal power 1 Hr Evening Base Date +10 Bldg 500 GE-102, SWGR A MCCB FB MDP-1 Bldg 512 Swgr A Main Bkr DA.2 480 Limited area no normal power 1 Hr Evening Base Date +10 Bldg 500 GE-102, SWGR B MCCB FB Pnl DP-SE2 Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +10 Bldg 500 GE-102, SWGR B MCCB FB Pnl DP-OR Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr No Surgery Weekend Base Date +11 Bldg 500 GE-102, SWGR B MCCB FB Pnl DP-NW2 Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +11 Bldg 500 GE-102, SWGR B MCCB FB Pnl DP-SW2 Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +11 Bldg 500 GE-102, SWGR B MCCB FB Pnl DP-NE2 Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +11 Bldg 500 GE-102, SWGR B MCCB FB Pnl DP-NW1 Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +11 Bldg 500 GE-102, SWGR B MCCB FB Pnl LP-SE1A Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +11 Bldg 500 GE-102, SWGR B MCCB FD Pnl DP-NEB Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +11 Bldg 500 GE-102, SWGR B MCCB FD Pnl DP-KA Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +11 Bldg 500 GE-102, SWGR B MCCB FD Pnl DP-NWB Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +11 Bldg 500 GE-102, SWGR B MCCB FD Pnl DP-NE1 Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +11 Bldg 500 GE-102, SWGR B MCCB FD ATS Room DP Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Run Generator Evening Base Date +11 Bldg 500 GE-102, SWGR B MCCB FD Pnl DP-SE1 Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +11 Bldg 500 GE-102, SWGR B MCCB FD Pnl DP-SWB Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +11 Bldg 500 GE-102, SWGR B MCCB FD Pnl DP-SEB Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +11 Bldg 500 GE-102, SWGR B MCCB FD Pnl DP-SW1, SW1-CA Swgr B Main Bkr DA.1 480 Limited area no normal power 1 Hr Evening Base Date +11 Bldg 500 GA-137A ATSs and Bus ATS-1 through ATS-10 No Emergency Power 8 Hours Weekend Base Date +7 Bldg 500 GA-137A ATSs and Bus ATS-1 through ATS-10 No Emergency Power 8 Hours Weekend Base Date +8 Bldg 500 GA-137A MCCB ATS-1 Norm Feed Bkr N/A Switching 1 second x 2 Run Generator Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-2 Norm Feed Bkr N/A Switching 1 second x 2 Run Generator Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-3 Norm Feed Bkr N/A Switching 1 second x 2 Run Generator Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-4 Norm Feed Bkr N/A Switching 1 second x 2 Run Generator Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-5 Norm Feed Bkr N/A Switching 1 second x 2 Run Generator Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-6 Norm Feed Bkr N/A Switching 1 second x 2 Run Generator Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-7 Norm Feed Bkr N/A Switching 1 second x 2 Run Generator Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-8 Norm Feed Bkr N/A Switching 1 second x 2 Run Generator Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-9 Norm Feed Bkr N/A Switching 1 second x 2 Run Generator Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-10 Norm Feed Bkr N/A Switching 1 second x 2 Run Generator Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-1 Alt Feed Bkr N/A Red Redund 1Hr N/A Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-2 Alt Feed Bkr N/A Red Redund 1Hr N/A Evening Base Date +12
Number
Device Description Clearance Point (FD) Clearance Point (Back FD) Alt Feed Voltage Impacts Work Done Outage Desc.
Outage Duration
Ops Limits Outage Type Planned Test Date
Bldg 500 GA-137A MCCB ATS-3 Alt Feed Bkr N/A Red Redund 1Hr N/A Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-4 Alt Feed Bkr N/A Red Redund 1Hr N/A Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-5 Alt Feed Bkr N/A Red Redund 1Hr N/A Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-6 Alt Feed Bkr N/A Red Redund 1Hr N/A Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-7 Alt Feed Bkr N/A Red Redund 1Hr N/A Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-8 Alt Feed Bkr N/A Red Redund 1Hr N/A Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-9 Alt Feed Bkr N/A Red Redund 1Hr N/A Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-10 Alt Feed Bkr N/A Red Redund 1Hr N/A Evening Base Date +12 Bldg 500 GA-137A MCCB ATS-1 Norm Load Bkr N/A Switching x2 1 second x 2 Evening Base Date +7 Bldg 500 GA-137A MCCB ATS-2 Norm Load Bkr N/A Switching x2 1 second x 2 Evening Base Date +7 Bldg 500 GA-137A MCCB ATS-3 Norm Load Bkr N/A Switching x2 1 second x 2 Evening Base Date +7 Bldg 500 GA-137A MCCB ATS-4 Norm Load Bkr N/A Switching x2 1 second x 2 Evening Base Date +7 Bldg 500 GA-137A MCCB ATS-5 Norm Load Bkr N/A Switching x2 1 second x 2 Evening Base Date +7 Bldg 500 GA-137A MCCB ATS-6 Norm Load Bkr N/A Switching x2 1 second x 2 Evening Base Date +7 Bldg 500 GA-137A MCCB ATS-7 Norm Load Bkr N/A Switching x2 1 second x 2 Evening Base Date +7 Bldg 500 GA-137A MCCB ATS-8 Norm Load Bkr N/A Switching x2 1 second x 2 Evening Base Date +7 Bldg 500 GA-137A MCCB ATS-9 Norm Load Bkr N/A Switching x2 1 second x 2 Evening Base Date +7 Bldg 500 GA-137A MCCB ATS-10 Norm Load Bkr N/A Switching x2 1 second x 2 Evening Base Date +7 Bldg 500 GA-137A MCCB ATS-1 Alt Load Bkr N/A N/A Evening Base Date +8 Bldg 500 GA-137A MCCB ATS-2 Alt Load Bkr N/A N/A Evening Base Date +8 Bldg 500 GA-137A MCCB ATS-3 Alt Load Bkr N/A N/A Evening Base Date +8 Bldg 500 GA-137A MCCB ATS-4 Alt Load Bkr N/A N/A Evening Base Date +8 Bldg 500 GA-137A MCCB ATS-5 Alt Load Bkr N/A N/A Evening Base Date +8 Bldg 500 GA-137A MCCB ATS-6 Alt Load Bkr N/A N/A Evening Base Date +8 Bldg 500 GA-137A MCCB ATS-7 Alt Load Bkr N/A N/A Evening Base Date +8 Bldg 500 GA-137A MCCB ATS-8 Alt Load Bkr N/A N/A Evening Base Date +8 Bldg 500 GA-137A MCCB ATS-9 Alt Load Bkr N/A N/A Evening Base Date +8 Bldg 500 GA-137A MCCB ATS-10 Alt Load Bkr N/A N/A Evening Base Date +8 Bldg 500 GE-104 MCCB ATS-1 through 10 Emerg FD Evening Base Date +13 Bldg 500 GE-104 MCCB ???Elevator"""" Base Date +13 Bldg 500 GE-104 ATS Elevator ATS Evening Base Date +13 Bldg 500 GE-102 MTS OR Backup MTS Weekend Base Date +13 Bldg 500 4C MTS 4C Wing Norm vs OR MTS Weekend Base Date +13 Bldg 500 2C-156A ATS OR ATS Weekend Base Date +13
Bldg 501 LV Air Bkr Evening Base Date +13 Bldg 501 LV Air Bkr Evening Base Date +13 Bldg 501 ATS ATS-LS Evening Base Date +13 Bldg 501 ATS ATS-CS Evening Base Date +13
Base Date +13
Bldg 502 LV Air Bkr Evening Base Date +13 Bldg 502 LV Air Bkr Evening Base Date +13 Bldg 502 ATS ATS-LS Evening Base Date +13 Bldg 502 ATS ATS-CR Evening Base Date +13
Bldg 503 MV Air Switch (Selector) Evening Base Date +13 Bldg 503 LV Air Bkr Main 480 Evening Base Date +13 Bldg 503 LV Air Bkr Chiller #1 480 Evening Base Date +14 Bldg 503 LV Air Bkr Chiller #2 480 Evening Base Date +14 Bldg 503 LV Air Bkr Chiller #3 480 Evening Base Date +14 Bldg 503 LV Air Bkr MCCI 480 Evening Base Date +14 Bldg 503 LV Air Bkr Water Pumps 480 Evening Base Date +14 Bldg 503 LV Air Bkr MDP 480 Evening Base Date +14 Bldg 503 ATS Evening Base Date +14
Bldg 508 LV Air Bkr ? Base Date +14 Bldg 508 MDP MCCB MDP Main Evening Base Date +14 Bldg 508 MDP MCCB FD Pnl LPC Evening Base Date +14 Bldg 508 MDP MCCB FD Pnl LPD Evening Base Date +14 Bldg 508 MDP MCCB FD Pnl LPA Evening Base Date +14 Bldg 508 MDP MCCB FD MCC Evening Base Date +14
Number
Device Description Clearance Point (FD) Clearance Point (Back FD) Alt Feed Voltage Impacts Work Done Outage Desc.
Outage Duration
Ops Limits Outage Type Planned Test Date
Bldg 508 MDP MCCB FD Pnl LPB Evening Base Date +14 Bldg 508 MDP MCCB FD Pnl LPB-A Evening Base Date +14
Bldg 513 Outside MV Air Switch XFMR T/Bldg 513 Evening Base Date +17 Bldg 513 ATS ATS CS Evening Base Date +17 Bldg 513 ATS ATS LS Evening Base Date +17 Bldg 513 ATS ATS Elev Evening Base Date +17 Bldg 513 Outside XFMR XFMR T Evening Base Date +17 Bldg 513 MDP MCCB MB-MDP Evening Base Date +17 Bldg 513 MDP MCCB FD Pnls 1NL1, 2NL1 Evening Base Date +17 Bldg 513 MDP MCCB FD Pnl 1KL1 Evening Base Date +17 Bldg 513 MDP MCCB FD Pnl 1NL2 Evening Base Date +17 Bldg 513 MDP MCCB FD Pnls 1NH1, 2NH1 Evening Base Date +17
Bldg 513 MDP MCCB FD Pnls 1EH-C1, 2EH-C1 via ATS-
CS
Evening Base Date +17
Bldg 513 MDP MCCB FD AHU-1 Evening Base Date +17 Bldg 513 MDP MCCB FD 1EH-ELEV via ATS-EL Evening Base Date +17 Bldg 513 MDP MCCB FD Pnl 1EH-LS1 via ATS-LS Evening Base Date +17 Bldg 513 GEN MDP MCCB MB Gen MDP Evening Base Date +17 Bldg 513 GEN MDP MCCB FB EDP Bldg 513 Evening Base Date +17 Bldg 513 GEN MDP MCCB FB EDP Bldg 516 Evening Base Date +17
Bldg 516 ATS ATS LS Evening Base Date +17 Bldg 516 ATS ATS CR Evening Base Date +18 Bldg 516 Outside MV Air Switch XFMR S/Bldg 516 Evening Base Date +18 Bldg 516 Outside XFMR XFMR S Evening Base Date +18 Bldg 516 MDP MCCB MB MDP Evening Base Date +18 Bldg 516 MDP MCCB FD T1 Evening Base Date +18 Bldg 516 MDP MCCB FD ATS-LS Evening Base Date +18 Bldg 516 MDP MCCB FD ATS-CR Evening Base Date +18 Bldg 516 MDP MCCB FD MTS Evening Base Date +18 Bldg 516 EDP MCCB MB EDP Evening Base Date +18 Bldg 516 EDP MCCB FD ATS-LS Evening Base Date +18 Bldg 516 EDP MCCB FD ATS-CR Evening Base Date +18
Bldg 518 Outside XFMR XFMR U Flexible Evening Base Date +18 Bldg 518 MDP MCCB MB MDP XFMR U Load Breaks Flexible Evening Base Date +18 Bldg 518 MDP MCCB FB Pnl SLH1 Flexible Evening Base Date +18 Bldg 518 MDP MCCB FB Pnl NH1 Flexible Evening Base Date +18 Bldg 518 MDP MCCB FB Pnl MN1 Flexible Evening Base Date +18 Bldg 518 MDP MCCB FB Pnl SCH1 Flexible Evening Base Date +18
Bldg 306A ATS Norm Fd Bkr MDPF Gen Flexible Evening Base Date +19 Bldg 306 XFMR XFMR F Bldg 503A Ckt 1 Bkr, verify 513, 516 & 518 on ckt 2 - Flexible Evening Base Date +19 Bldg 306 MDP F (On XFMR) MCCB Bldg 302A old music room XFMR F - Flexible Evening Base Date +19 Bldg 306 MDP F (On XFMR) MCCB Blsg 302B Transportation XFMR F - Flexible Evening Base Date +19 Bldg 306 MDP F (On XFMR) MCCB Bldg 304 Grounds & Maint. XFMR F - Flexible Evening Base Date +19 Bldg 306 MDP F (On XFMR) MCCB Bldg 306A ATS Norm FD XFMR F - Flexible Evening Base Date +19 Bldg 306 MDP F (On XFMR) MCCB Bldg 308A & 310 XFMR F - Flexible Evening Base Date +19
Bldg 217 A ATS 217 IRM Computer Flexible Evening Base Date +19 Bldg 217B ATS Bldg 217A Flexible Evening Base Date +19 Bldg 217B MDP G XFMR XFMR G Flexible Evening Base Date +19 Bldg 217B MDP G MCCB ATS Bldg 217B Norm FD Flexible Evening Base Date +19 Bldg 217B MDP G MCCB 217 DOM Flexible Evening Base Date +19 Bldg 217B MDP G MCCB ATS Bldg 217A Norm FD Flexible Evening Base Date +19 Bldg 217B MDP G MCCB Bldg 217 Fitness Center Flexible Evening Base Date +19 Bldg 217B MDP G MCCB Bldg 217 Walk Ins Flexible Evening Base Date +19
Bldg 331 XFMR XFMR GH Bldg 331 XFMR Flexible Evening Base Date +20 Bldg 331 MCCB Evening Base Date +20
Bldg 407B XFMR XFMR H Bldgs 401 - 409 XFMR Flexible Evening Base Date +20
Number
Device Description Clearance Point (FD) Clearance Point (Back FD) Alt Feed Voltage Impacts Work Done Outage Desc.
Outage Duration
Ops Limits Outage Type Planned Test Date
Bldg 407B MDP H MCCB Bldg 401 120/240 xfmr Flexible Evening Base Date +20 Bldg 407B MDP H MCCB Bldg 401 Flexible Evening Base Date +20 Bldg 407B MDP H MCCB Bldg 409. 411, 413 & 415 Flexible Evening Base Date +20 Bldg 407B MDP H MCCB Bldg 407, 405, & 403 Flexible Evening Base Date +20 Bldg 407B MDP H MCCB DP-HA Bldgs 417 & 421 Flexible Evening Base Date +20
Bldg 317 Outside XFMR XFMR J Bldg 317 & Streek Lights Flexible Evening Base Date +20 Bldg 317 ATS Evening Base Date +20 Bldg 317 MDP J MCCB Bldg 317 Flexible Evening Base Date +20 Bldg 317 MDP J MCCB Streed Lights Flexible Evening Base Date +20
Bldg 307 ATS Bldg 307E Flexible Evening Base Date +20
Bldg 307B Outside XFMR XFMR L Bldg 305, 307, 309, 309, 311, &
Flexible Evening Base Date +20
Bldg 307B MDP L MCCB Bldgs 309, 311 & 313 FD Flexible Evening Base Date +20
Bldg 307B MDP L MCCB Bldgs 307, 307 & 307E Norm FD Flexible Evening Base Date +20
Bldg 213 Outside XFMR XFMR LM Bldg 213 Hope Center Flexible Evening Base Date +21 Bldg 213 MCCB Bldg 213 MCB Flexible Evening Base Date +21
Bldg 207 ATS Flexible Evening Base Date +21
Bldg 207C Outside XFMR XFMR M Bldgs 203, 205, 207, 209 & 211 Flexible Evening Base Date +21
Bldg 207C MDP M MCCB Bldgs 203, 205, 209 & 211 Flexible Evening Base Date +21 Bldg 207C MDP M MCCB A/C Flexible Evening Base Date +21 Bldg 207C MDP M MCCB Bldgs 203 & 207 Flexible Evening Base Date +21
Bldg 314 Outside XFMR XFMR B Bldg 314, 316, & 318 Xfmr Bldg 503A Ckt 2 Bkr, verify 513, 516 & 518 on ckt 1 8 Hours Flexible Evening Base Date +21 Bldg 318 ATS Flexible Evening Base Date +21 Bldg 314 MDP B MCCB Bldg 318 LS Norm Feed Flexible Evening Base Date +21 Bldg 314 MDP B MCCB Bldg 316 Water Softener Flexible Evening Base Date +21 Bldg 314 MDP B MCCB Bldg 314 Shops Flexible Evening Base Date +21 Bldg 314 MDP B MCCB Bkdg 314 Shope Flexible Evening Base Date +21 Bldg 314 MDP B MCCB Bldg 314 Shops Flexible Evening Base Date +21 Bldg 314 MDP B MCCB ? Flexible Evening Base Date +21
Bldg 314 Outside XFMR XFMR A Bldg 314 Xfmr 2 Hours Flexible Evening Base Date +21
Well 4 XFMR XFMR C Well 4 Transformer 2 Hours Flexible Evening Base Date +21
Bldg 320 ATS Flexible Evening Base Date +24 Bldg 320 XFMR XFMR D Flexible Evening Base Date +24 Bldg 320 MCCB Flexible Evening Base Date +24 Bldg 320 MCCB Flexible Evening Base Date +24
Bldg 519 Outside XFMR XFMR DE Bldg 519 Flexible Evening Base Date +24
Bldg 519 Outside XFMR XFMR E Bldgs 332, 330, 328, 324, 308B, Parking Lot, Well 3 & 519
Flexible Evening Base Date +24
Bldg 519 MDP MCCB Flexible Evening Base Date +24 Bldg 519 MDP MCCB Flexible Evening Base Date +24 Bldg 519 MDP MCCB Flexible Evening Base Date +24 Bldg 519 MDP MCCB Flexible Evening Base Date +24 Bldg 519 MDP MCCB Flexible Evening Base Date +24 Bldg 519 MDP MCCB Flexible Evening Base Date +24 Bldg 519 MDP MCCB Flexible Evening Base Date +24 Bldg 519 MDP MCCB Flexible Evening Base Date +24
Bldg 504 ATS XFMR R Generator Flexible Evening Base Date +24 Bldg 504 Outside XFMR R Bldg 503A Ckt 2 Bkr, verify 513, 516 & 518 on ckt 1 Flexible Evening Base Date +24 Bldg 504 MCCB Main Service Breaker XFMR R Generator Flexible Evening Base Date +25
Number
Device Description Clearance Point (FD) Clearance Point (Back FD) Alt Feed Voltage Impacts Work Done Outage Desc.
Outage Duration
Ops Limits Outage Type Planned Test Date
Bldg 504 MDP R MCCB MDP-R Main Flexible Evening Base Date +25
Bldg 504 MDP R MCCB T-3 FD Sewage Pump Sta Ctrl Pnl
Flexible Evening Base Date +25
Bldg 504 MDP R MCCB Wastewater Control Pnl Flexible Evening Base Date +25 Bldg 504 MDP R MCCB Spare (Do not Test) Flexible Evening Base Date +25 Bldg 504 MDP R MCCB Well #1 FD Flexible Evening Base Date +25 Bldg 504 MDP R MCCB Spare (Do not Test) Flexible Evening Base Date +25 Bldg 504 MDP R MCCB Spare (Do not Test) Flexible Evening Base Date +25 Bldg 504 MDP R MCCB T-2 New Pnl "AUX" Flexible Evening Base Date +25 Bldg 504 MDP R MCCB New Panel "HV" FD Flexible Evening Base Date +25 Bldg 504 MDP R MCCB MCC #2 Flexible Evening Base Date +25 Bldg 504 MDP R MCCB T-1 New Pnl "LV" Flexible Evening Base Date +25 Bldg 504 MDP R MCCB MCC #1 Flexible Evening Base Date +25
Bldg 334 XFMR Q Flexible Evening Base Date +25 Bldg 334 MCCB GAC Main Breaker Flexible Evening Base Date +25
Bldg 19 Outside XFMR P XFMR P Flexible Evening Base Date +25
Bldg 17 Outside XFMR O XFMR O Flexible Evening Base Date +26 Bldg 17 XFMR O MCCB Bldg 17 FD Flexible Evening Base Date +26 Bldg 17 XFMR O MCCB Lot O MDP Flexible Evening Base Date +26
Bldg 117 Outside XFMR N XFMR N Flexible Evening Base Date +26 Bldg 117 MCCB Main Breaker Flexible Evening Base Date +26