36C24518B0233-001.docx
DOCX document 113 KB Posted
- Attached to
- CONST DOM CLINIC & CLC ADMIN PROJ 613-121 Federal contract opportunity
- Solicitation number
- 36C24518B0233
About this file
36C24518B0233 36C24518B0233.docx
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24518C0215-000.docx | DOCX document | |
| 36C24518B0233-0001001.pdf | ||
| 36C24518B0233-0001000.docx | DOCX document | |
| 36C24518B0233-010.pdf | ||
| 36C24518B0233-003.pdf | ||
| 36C24518B0233-013.pdf | ||
| 36C24518B0233-012.pdf | ||
| 36C24518B0233-011.pdf | ||
| 36C24518B0233-005.pdf | ||
| 36C24518B0233-004.pdf | ||
| 36C24518B0233-006.pdf | ||
| 36C24518B0233-007.pdf | ||
| 36C24518B0233-002.pdf | ||
| 36C24518B0233-009.pdf | ||
| 36C24518B0233-008.pdf | ||
| 36C24518B0233-000.docx | DOCX document |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24518B0233
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24518B0233 X 08-02-2018 613-121 Department of Veterans Affairs
VAMC (613)
VISN 5 Contract Satellite Office 510 Butler Avenue, Building 306A Martinsburg
WV
25405 Department of Veterans Affairs
VAMC 613
NCO 5 Contract Satellite Office 510 Butler Ave, Bldg 306A Martinsburg, WV 25405
LAURA TAWZER
304-263-0811 X3170 BID ITEM NO. 1, BASE BID: Furnish all labor, tools, material, equipment, and supervision necessary to:
Item I - Construct Dom Clinic Addition (Building 502F), work includes general construction, abatement, minor alterations at wall shared with existing building, walks, grading, drainage, plumbing, mechanical and electrical work, utility systems and structural work necessary for addition.
Item II - Construct CLC Admin Addition (Building 501D, work includes general construction, abatement, minor alterations at wall shared with existing building, roads, walks, grading, drainage, plumbing, mechanical and electrical work, utility systems and structural work, including necessary demo of existing smoking structure necessary for addition.
This include Office/Exam space as well as the connecting corridor, support spaces and entry.
CONSTRUCTION COMPLETION TIME: 630 calendar days from NTP.
ADDITIONAL BID ITEMS 2 THROUGH BID ITEMS 7 ON PAGE 13.
NAICS: 236220 SIZE STANDARD: $36.5 MILLION COST RANGE: BETWEEN $5 MILLION TO $10 MILLION
A single award will be made on Item No. 1. In the event the offer exceeds the funds available, a single award will be made on Bid Item No. 2, 3, 4, 5, 6, or 7, in that order, based on available funding. Offerors should quote a price on each item listed.
A single award will be made to that offeror who submits an acceptable proposal and has lowest price for satisfactory completion of all contract requirements.
Notice: Clause 52.222-37 Employment Reports on Disabled Veterans and Veterans is incorporated by reference in this solicitation. Public Law (P.L. 105-339), Section 1354 provides that no agency may enter into a contract with a contractor who has not filed a VETS 4212 report for the preceding fiscal year under Title 38 Section 4212(d). Offerors are strongly encouraged to complete this to possibly avoid delays @ https://dol.gov/vets/vets4212.
This is a 100% Service Disabled Veteran Owned Small Business Set-Aside. Contractor must be verified in VetBiz to be eligible for award.
PRE-PROPOSAL SITE VISIT IS SCHEDULED FOR THURSDAY, AUGUST 16, 2018 @ 1:00 PM LOCAL TIME AT THE VAMC MARTINSBURG, 510 BUTLER AVE, MARTINSBURG, WV 25405, 308B CONFERENCE ROOM. SITE VISIT ATTENDANCE IS HIGHLY ENCOURAGED AND RECOMMENDED.
ALL RFIs SHALL BE SUBMITTED IN WRITING NLT AUGUST 30, 2018 @ 1:00 PM LOCAL TIME.
AWARD IS SUBJECT TO AVAILABILITY OF FUNDS IAW FAR 52.232-18 AVAILABILITY OF FUNDS.
X X 52.211-10 X
1:00 PM EDT
09-20-2018 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
BID ITEM NO. 1 (BASE BID): $________________________________
BID ITEM NO. 2, DEDUCT ALTERNATE 1: $_______________________
BID ITEM NO. 3, DEDUCT ALTERNATE 2: $_______________________
BID ITEM NO. 4, DEDUCT ALTERNATE 3: $_______________________
BID ITEM NO. 5, DEDUCT ALTERNATE 4: $_______________________
BID ITEM NO. 6, DEDUCT ALTERNATE 5: $_______________________
BID ITEM NO. 7, DEDUCT ALTERNATE 6: $_______________________
Department of Veterans Affairs
VAMC (613)
VISN 5 Contract Satellite Office 510 Butler Avenue, Building 308B Martinsburg
WV
25405
PAYMENT WILL BE MADE BY
FSC e-Invoice Payment Invoice must be submitted electronically http://www.fsc.va.gov/einvoice.asp http://www.fsc.va.gov/einvoice.asp
LAURA TAWZER
CONTRACTING OFFICER
TABLE OF CONTENTS
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| SPECIFICATION LISTING | 4 |
| DRAWINGS LISTING | 8 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 21 |
| STATEMENT OF WORK | 22 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 25 |
| REPRESENTATIONS AND CERTIFICATIONS | 27 |
| GENERAL CONDITIONS | 42 |
| GENERAL WAGE DETERMINATION | 75 |
| SPECIFICATIONS ATTACHMENT | 79 |
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
| DIVISION 00 SPECIAL SECTIONS |
| DATE |
| 00 01 15 |
| List of Drawing Sheets |
| 07-15 |
DIVISION 01 GENERAL REQUIREMENTS
| 01 00 00 |
| General Requirements |
| 11-15 |
| 01 08 14 |
| Risk of TB to Contracted Construction Workers |
| xx-15 |
| 01 32 16.15 |
| Project Schedules (Small Projects – Design/Bid/Build |
| 04-13 |
| 01 33 23 |
| Shop Drawings, Product Data, and Samples |
| 02-17 |
| 01 35 26.1 |
| Safety Requirements |
| 02-17 |
| 01 35 26.2 |
| Safety Requirements Attachment |
| 12-14 |
| 01 42 19 |
| Reference Standards |
| 05-16 |
| 01 45 29 |
| Testing Laboratory Services |
| 06-16 |
| 01 57 19 |
| Temporary Environmental Controls |
| 01-11 |
| 01 58 16 |
| Temporary Interior Signage |
| 07-15 |
| 01 74 19 |
| Construction Waste Management |
| 09-13 |
| 01 81 13 |
| Sustainable Construction Requirements |
| 09-15 |
| 01 91 00 |
| General Commissioning Requirements |
| 10-15 |
DIVISION 02 – EXISTING CONDITIONS
| 02 82 11 |
| Traditional Asbestos Abatement |
| 09-15 |
DIVISION 03 – CONCRETE
| 03 30 00 |
| Cast-in-Place Concrete |
| 12-15 |
DIVISION 04 – MASONRY
| 04 05 13 |
| Masonry Mortaring |
| 02-16 |
| 04 20 00 |
| Unit Masonry |
| 02-16 |
DIVISION 05 – METALS
| 05 12 00 |
| Structural Steel Framing |
| 02-16 |
| 05 21 00 |
| Steel Joist Framing |
| 03-10 |
| 05 31 00 |
| Steel Decking |
| 02-16 |
| 05 40 00 |
| Cold-Formed Metal Framing |
| 05-16 |
| 05 50 00 |
| Metal Fabrications |
| 07-14 |
DIVISION 06 – WOOD,PLASTICS AND COMPOSITES
| 06 10 00 |
| Rough Carpentry |
| 10-15 |
DIVISION 07 THERMAL AND MOISTURE PROTECTION
| 07 08 00 |
| Facility Exterior Closure Commissioning |
| 11-16 |
| 07 11 13 |
| Bituminous Dampproofing |
| 02-16 |
| 07 21 13 |
| Thermal Insulation |
| 02-16 |
| 07 22 00 |
| Roof and Deck Insulation |
| 02-16 |
| 07 24 00 |
| Exterior Insulation and Finish Systems |
| 02-16 |
| 07 27 26 |
| Fluid-Applied Membrane Air Barrier, Vapor Permeable |
| 02-16 |
| 07 31 13 |
| Asphalt Shingles |
| 02-16 |
| 07 54 23 |
| Thermoplastic Polyolefin (TPO) Roofing |
| 08-16 |
| 07 60 00 |
| Flashing and Sheet Metal |
| 07-14 |
| 07 72 00 |
| Roof Accessories |
| 10-15 |
| 07 84 00 |
| Firestopping |
| 02-16 |
| 07 92 00 |
| Joint Sealants |
| 10-15 |
| 07 95 13 |
| Expansion Joint Cover Assemblies |
| 02-16 |
DIVISION 08 OPENINGS
| 08 11 13 |
| Hollow Metal Doors and Frames |
| 08-16 |
| 08 14 00 |
| Interior Wood Doors |
| 02-16 |
| 08 31 13 |
| Access Doors and Frames |
| 02-16 |
| 08 33 00 |
| Coiling Doors and Grilles |
| 02-16 |
| 08 41 13 |
| Aluminum-Framed Entrances and Storefronts |
| 08-16 |
| 08 56 53 |
| Blast Resistant Windows |
| 02-16 |
| 08 62 23 |
| Tubular Daylighting Devices |
| 08 63 00 |
| Metal-Framed Skylights |
| 10-15 |
| 08 71 00 |
| Door Hardware |
| 01-16 |
| 08 71 13 |
| Automatic Door Operators |
| 02-16 |
| 08 80 00 |
| Glazing |
| 10-15 |
| 08 90 00 |
| Louvers and Vents |
| 05-15 |
DIVISION 09 – FINISHES
| 09 05 16 |
| Subsurface Preparation for Floor Finishes |
| 02-15 |
| 09 22 16 |
| Non-Structural Metal Framing |
| 05-16 |
| 09 29 00 |
| Gypsum Board |
| 11-14 |
| 09 30 13 |
| Ceramic/Porcelain Tiling |
| 09-15 |
| 09 51 00 |
| Acoustical Ceilings |
| 12-16 |
| 09 65 13 |
| Resilient Base and Accessories |
| 02-16 |
| 09 65 19 |
| Resilient Tile Flooring |
| 12-15 |
| 09 67 23.20 |
| Resinous Epoxy Base With Vinyl Chip Broadcast (RES 2) |
| 07-14 |
| 09 91 00 |
| Painting |
| 01-16 |
DIVISION 10 – SPECIALTIES
| 10 14 00 |
| Signage |
| 10-15 |
| 10 26 00 |
| Wall and Door Protection |
| 10-15 |
| 10 28 00 |
| Toilet, Bath, and Laundry Accessories |
| 02-16 |
| 10 44 13 |
| Fire Extinguisher Cabinets |
| 08-14 |
DIVISION 12 – FURNISHINGS
| 12 24 00 |
| Window Shades |
| 09-15 |
| 12 32 00 |
| Manufactured Wood Casework |
| 09-15 |
| 12 36 00 |
| Countertops |
| 12-15 |
DIVISION 14– CONVEYING EQUIPMENT
| 14 42 00 |
| Wheelchair Lift |
DIVISION 21- FIRE SUPPRESSION
| 21 08 00 |
| Commissioning of Fire Suppression System |
| 11-16 |
| 21 13 13 |
| Wet-Pipe Sprinkler Systems |
| 06-15 |
DIVISION 22 – PLUMBING
| 22 05 11 |
| Common Work Results for Plumbing |
| 07-16 |
| 22 05 23 |
| General-Duty Valves for Plumbing Piping |
| 09-15 |
| 22 07 11 |
| Plumbing Insulation |
| 09-15 |
| 22 08 00 |
| Commissioning of Plumbing Systems |
| 11-16 |
| 22 11 00 |
| Facility Water Distribution |
| 09-15 |
| 22 13 00 |
| Facility Sanitary and Vent Piping |
| 09-15 |
| 22 14 00 |
| Facility Storm Drainage |
| 09-15 |
| 22 33 00 |
| Electric Domestic Water Heaters |
| 09-15 |
| 22 40 00 |
| Plumbing Fixtures |
| 09-15 |
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
| 23 05 11 |
| Common Work Results for HVAC |
| 02-15 |
| 23 05 12 |
| General Motor Requirements for HVAC and Steam Generation Equipment |
| 11-10 |
| 23 05 41 |
| Noise and Vibration Control for HVAC Piping and Equipment |
| 02-15 |
| 23 05 93 |
| Testing, Adjusting, and Balancing for HVAC |
| 02-15 |
| 23 07 11 |
| HVAC and Boiler Plant Insulation |
| 02-15 |
| 23 08 00 |
| Commissioning of HVAC Systems |
| 11-16 |
| 23 09 23 |
| Direct-Digital Control System for HVAC |
| 09-11 |
| 23 21 13 |
| Hydronic Piping |
| 09-12 |
| 23 21 23 |
| Hydronic Pumps |
| 02-15 |
| 23 23 00 |
| Refrigerant Piping |
| 02-15 |
| 23 31 00 |
| HVAC Ducts and Casings |
| 03-13 |
| 23 34 00 |
| HVAC Fans |
| 02-15 |
| 23 36 00 |
| Air Terminal Units |
| 02-15 |
| 23 37 00 |
| Air Outlets and Inlets |
| 02-15 |
| 23 40 00 |
| HVAC Air Cleaning Devices |
| 02-12 |
| 23 73 00 |
| Indoor Central-Station Air-Handling Units |
| 04-11 |
| 23 81 00 |
| Decentralized Unitary HVAC Equipment |
| 02-11 |
| 23 82 16 |
| Air Coils |
| 04-11 |
DIVISION 26 – ELECTRICAL
| 26 05 11 |
| Requirements for Electrical Installations |
| 01-16 |
| 26 05 19 |
| Low-Voltage Electrical Power Conductors and Cables |
| 01-17 |
| 26 05 26 |
| Grounding and Bonding for Electrical Systems |
| 01-17 |
| 26 05 33 |
| Raceway and Boxes for Electrical Systems |
| 05-14 |
| 26 05 73 |
| Overcurrent Protective Device Coordination Study |
| 12-15 |
| 26 08 00 |
| Commissioning of Electrical Systems |
| 11-16 |
| 26 09 23 |
| Lighting Controls |
| 05-14 |
| 26 22 00 |
| Low-Voltage Transformers |
| 12-15 |
| 26 24 16 |
| Panelboards |
| 05-14 |
| 26 27 26 |
| Wiring Devices |
| 01-16 |
| 26 29 11 |
| Motor Controllers |
| 08-14 |
| 26 41 00 |
| Facility Lightning Protection |
| 01-17 |
| 26 43 13 |
| Surge Protective Devices |
| 01-17 |
| 26 51 00 |
| Interior Lighting |
| 08-14 |
| 26 56 00 |
| Exterior Lighting |
| 05-14 |
DIVISION 27 – COMMUNICATIONS
| 27 05 11 |
| Requirements for Communications Installations |
| 06-15 |
| 27 05 26 |
| Grounding and Bonding for Communications Systems |
| 06-15 |
| 27 05 33 |
| Raceways and Boxes for Communications Systems |
| 06-15 |
| 27 08 00 |
| Commissioning of Communications Systems |
| 11-16 |
| 27 10 00 |
| Control, Communication and Signal Wiring |
| 06-15 |
| 27 11 00 |
| Communications Equipment Room Fittings |
| 06-15 |
| 27 15 00 |
| Communications Structured Cabling |
| 01-16 |
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
| 28 05 00 |
| Common Work Results for Electronic Safety and Security |
| 09-11 |
| 28 05 13 |
| Conductors and Cables for Electronic Safety and Security |
| 09-11 |
| 28 08 00 |
| Commissioning of Electronic Safety and Security Systems |
| 11-16 |
| 28 13 00 |
| Physical Access Control System |
| 10-11 |
| 28 31 00 |
| Fire Detection and Alarm |
| 10-11 |
DIVISION 31 – EARTHWORK
| 31 20 00 |
| Earthwork |
| 07-16 |
| 31 23 23.33 |
| Flowable Fill |
| 07-16 |
DIVISION 32 – EXTERIOR IMPROVEMENTS
| 32 05 23 |
| Cement and Concrete for Exterior Improvements |
| 08-16 |
| 32 12 16 |
| Asphalt Paving |
| 32 17 23 |
| Pavement Markings |
| 08-16 |
| 32 31 40 |
| Gates |
| 08-16 |
| 32 90 00 |
| Planting |
| 08-16 |
DIVISION 33 – UTILITIES
| 33 10 00 |
| Water Utilities |
| 03-17 |
| 33 30 00 |
| Sanitary Sewer Utilities |
| 06-13 |
| 33 40 00 |
| Storm Sewer Utilities |
| 10-11 |
| Appendix #1 |
| Geotechnical Exploration Report 1 |
| Appendix #2 |
| Geotechnical Exploration Report 2 |
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
| GENERAL | ||
| G001 | COVER SHEET | |
| G002 | GENERAL NOTES, DETAILS, ABBREVIATIONS AND LEGENDS | |
| G003 | FIRST FLOOR DEDUCTIVE ALTERNATE PLAN – ALTERNATE NO.5 (BID ITEM NO. 6) |
| CIVIL | ||
| C001 | SITE SYMBOLS | |
| C100 | EXISTING SITE FEATURES-BUILDINGS 501 & 502 | |
| CD100 | SITE DEMOLITION PLAN | |
| C110 | SITE MATERIALS - BUILDING 501D | |
| C111 | SITE MATERIALS - BUILDING 502F | |
| C120 | SITE STAKE OUT PLAN - BUILDING 501D | |
| C121 | SITE STAKE OUT PLAN - BUILDING 502F | |
| C130 | SITE GRADING PLAN - BUILDING 501D | |
| C131 | SITE GRADING PLAN - BUILDING 502F | |
| C140 | SITE UTILITY PLAN – BUILDING 501D | |
| C141 | SITE UTILITY PLAN – NORTH | |
| C150 | EROSION & SEDIMENTATION CONTROL (E&S) PLAN - BUILDING 501D | |
| C151 | EROSION & SEDIMENTATION CONTROL (E&S) PLAN - BUILDING 502F | |
| C510 | SITE DETAILS | |
| C511 | SITE DETAILS | |
| C540 | STORM WATER MANAGEMENT DETAILS | |
| C541 | SITE UTILITY DETAILS | |
| C550 | EROSION & SEDIMENTATION CONTROL (E&S) DETAILS | |
| C740 | UTILITY PROFILES | |
| C741 | UTILITY PROFILES |
| ARCHITECTURAL | |||
| HM101 | FIRST FLOOR HAZARDOUS MATERIAL ABATEMENT PLAN – | ||
| CLC ADMIN | |||
| HM102 | FIRST FLOOR HAZARDOUS MATERIAL ABATEMENT PLAN – | ||
| DOM CLINIC | |||
| AD101 | FIRST FLOOR DEMO PLAN – CLC ADMIN | ||
| AD102 | FIRST FLOOR DEMO PLAN – DOM CLINIC | ||
| LS101 | FIRST FLOOR LIFE SAFETY PLAN – CLC ADMIN | ||
| LS102 | FIRST FLOOR LIFE SAFETY PLAN – DOM CLINIC | ||
| A100 | AREA PLANS – CLC ADMIN AND DOM CLINIC | ||
| A101 | FIRST FLOOR ANNOTATION PLAN – CLC ADMIN | ||
| A101A | FIRST FLOOR DIMENSION PLAN – CLC ADMIN | ||
| A102 | FIRST FLOOR ANNOTATION PLAN – DOM CLINIC | ||
| A102A | FIRST FLOOR DIMENSION PLAN – DOM CLINIC | ||
| A111 | FIRST FLOOR REFLECTED CEILING PLAN – CLC ADMIN | ||
| A112 | FIRST FLOOR REFLECTED CEILING PLAN – DOM CLINIC | ||
| A121 | ROOF PLAN – CLC ADMIN | ||
| A122 | ROOF PLAN – DOM CLINIC | ||
| A131 | FIRST FLOOR PNEUMATIC TUBE SYSTEM PLAN – CLC ADMIN | ||
| A132 | FIRST FLOOR PNEUMATIC TUBE SYSTEM PLAN – DOM CLINIC | ||
| A201 | EXTERIOR ELEVATIONS – CLC ADMIN | ||
| A202 | EXTERIOR ELEVATIONS AND BUILDING SECTIONS – | DOM CLINIC | |
| A301 | BUILDING SECTIONS – CLC ADMIN | ||
| A351 | WALL SECTIONS – CLC ADMIN | ||
| A352 | WALL SECTIONS – CLC ADMIN | ||
| A353 | WALL SECTIONS – CLC ADMIN | ||
| A354 | WALL SECTIONS – CLC ADMIN | ||
| A355 | WALL SECTIONS – CLC ADMIN | ||
| A356 | WALL SECTIONS – CLC ADMIN | ||
| A357 | WALL SECTIONS – CLC ADMIN | ||
| A358 | WALL SECTIONS – CLC ADMIN | ||
| A361 | WALL SECTIONS – DOM CLINIC | ||
| A362 | WALL SECTIONS – DOM CLINIC | ||
| A401 | ENLARGED FLOOR PLANS | ||
| A451 | INTERIOR ELEVATIONS | ||
| A452 | INTERIOR ELEVATIONS | ||
| ARCHITECTURAL (CONT.) | |||
| A453 | INTERIOR ELEVATIONS | ||
| A501 | PARTITION TYPES & FRAMING ELEVATIONS | ||
| A502 | FRAMING DETAILS | ||
| A511 | PLAN DETAILS | ||
| A512 | PLAN DETAILS | ||
| A513 | PLAN DETAILS | ||
| A521 | SECTION DETAILS | ||
| A522 | SECTION DETAILS | ||
| A531 | ROOF DETAILS | ||
| A532 | ROOF DETAILS | ||
| A541 | EXTERIOR INSULATION FINISHING SYSTEM DETAILS | ||
| A601 | ROOM FINISH SCHEDULES AND EQUIPMENT SCHEDULE | ||
| A611 | DOOR AND FRAME TYPES, SCHEDULES AND DETAILS | ||
| A612 | WINDOW AND LOUVER TYPES AND DETAILS | ||
| A701 | SIGNAGE TYPES |
| STRUCTURAL | ||
| S001 | STRUCTURAL NOTES | |
| S002 | STRUCTURAL NOTES | |
| S003 | STRUCTURAL NOTES | |
| S101 | CLC ADMIN ADDITION FOUNDATION PLAN | |
| S102 | CLC ADMIN ADDITION LOW ROOF FRAMING PLAN | |
| S103 | CLC ADMIN ADDITION HIGH ROOF FRAMING PLAN | |
| S104 | DOMICILIARY CLINIC ADDITION FOUNDATION PLAN | |
| S105 | DOMICILIARY CLINIC ADDITION ROOF FRAMING PLAN | |
| S201 | BRACING ELEVATION CLC ADMIN ADDITION | |
| S202 | BRACING AND FRAMING ELEVATIONS CLC ADMIN ADDITION | |
| S203 | BRACING ELEVATIONS - DOMICILIARY ADDITION | |
| S301 | CONCRETE DETAILS | |
| S302 | CONCRETE DETAILS | |
| S303 | CONCRETE DETAILS | |
| S304 | CONCRETE DETAILS | |
| S305 | CONCRETE DETAILS | |
| S401 | MASONRY DETAILS | |
| S501 | STEEL DETAILS | |
| S502 | STEEL DETAILS | |
| S503 | STEEL DETAILS | |
| STRUCTURAL (CONT.) | ||
| S504 | STEEL DETAILS |
| FIRE PROTECTION | ||
| F001 | GENERAL NOTES AND DETAILS | |
| FP101 | FIRST FLOOR CLC ADMIN | |
| FP102 | FIRST FLOOR DOM CLINIC |
| PLUMBING | ||
| P001 | PLUMBING LEGEND, GENERAL NOTES, AND SCHEDULES | |
| PL101 | FOUNDATION WASTE, DRAIN, AND VENT PIPING PLAN – CLC ADMIN | |
| PL102 | FOUNDATION WASTE, DRAIN, AND VENT PIPING PLAN– DOM | CLINIC |
| PL103 | FIRST FLOOR PLUMBING PIPING PLAN – CLC ADMIN | |
| PL104 | FIRST FLOOR PLUMBING PIPING PLAN – DOM CLINIC | |
| PL105 | ROOF PLAN PLUMBING PIPING PLAN – CLC ADMIN | |
| PL106 | ROOF PLAN PLUMBING PIPING PLAN – DOM CLINIC | |
| PL107 | FOUNDATION WASTE, DRAIN, AND VENT PIPING PLAN – CLC ADMIN BID ALTERNATE 5 | |
| PL108 | FIRST FLOOR PLUMBING PIPING PLAN - CLC ADMIN BID ALTERNATE 5 | |
| PL201 | WASTE, DRAIN, AND VENT PIPING ISOMETRIC RISER DIAGRAMS | |
| PL301 | DOMESTIC WATER DISTRIBUTION ISOMETRIC RISER DIAGRAMS |
| MECHANICAL | ||
| M001 | MECHANICAL LEGEND AND GENERAL NOTES | |
| MD101 | FIRST FLOOR DEMO PLAN – CLC ADMIN | |
| MD102 | FIRST FLOOR DEMO PLAN – DOM CLINIC | |
| MH101 | FIRST FLOOR DUCTWORK PLAN – CLC ADMIN | |
| MH102 | FIRST FLOOR DUCTWORK PLAN – DOM CLINIC | |
| MH103 | ROOF PLAN – CLC ADMIN | |
| MH104 | ROOF PLAN – DOM CLINIC | |
| MH105 | FIRST FLOOR MECHANICAL PLAN – CLC ADMIN – ALTERNATE No.5 – (BID ITEM No.6) | |
| MH401 | ENLARGED PLANS | |
| MP101 | FIRST FLOOR PIPING PLAN – CLC ADMIN |
MECHANICAL (CONT.)
| MP102 | FIRST FLOOR PIPING PLAN – DOM CLINIC |
| M501 | DETAILS |
| M502 | DETAILS |
| M601 | SCHEDULES |
| M602 | SCHEDULES |
| M701 | CONTROLS |
| ELECTRICAL | |||
| E001 | ELECTRICAL LEGEND | ||
| ED101 | ELECTRICAL DEMOLITION PLAN – CLC ADMIN | ||
| EL101 | FIRST FLOOR LIGHTING PLAN – CLC ADMIN | ||
| EL102 | FIRST FLOOR LIGHTING PLAN – DOM CLINIC | ||
| EL601 | LIGHTING FIXTURE SCHEDULE AND DETAILS | ||
| EP101 | FIRST FLOOR POWER PLAN – CLC ADMIN | ||
| EP102 | FIRST FLOOR POWER PLAN – DOM CLINIC | ||
| EP103 | ROOF POWER, LIGHTNING PROTECTION, AND GROUNDING PLANS – CLC ADMIN AND COM CLINIC | ||
| EP104 | FIRST FLOOR ELECTRICAL PLAN – CLC ADMIN – ALTERNATE No.5 – (BID ITEM No.6) | ||
| EP501 | ELECTRICAL DETAILS | ||
| EP601 | ELECTRICAL SCHEDULES | ||
| EP602 | ELECTRICAL SCHEDULES | ||
| EP701 | POWER RISER DIAGRAMS AND MECHANICAL CONNECTION SCHEDULE | ||
| EY101 | FIRST FLOOR TELECOMMUNICATIONS PLAN – CLC ADMINISTRATION ADDITION | ||
| EY102 | FIRST FLOOR TELECOMMUNICATIONS PLAN – DOMICILIARY | CLINIC | |
| EY501 | TELECOMMUNICATIONS DETAILS | ||
| EY701 | TELECOMMUNICATIONS RISER DIAGRAM |
END
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
Bidding materials may be obtained at https://www.fbo.gov. Contractors are responsible for downloading required documents.
Subcontractors, material firms, and others interested in preparing subbids may view the interested parties list at https://www.fbo.gov to obtain a list of organizations, such as Builders Exchanges, Chambers of Commerce, Contractors and others, who have received bidding materials.
A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000.00. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.
If the contract will exceed $100,000.00 (see Far 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of the SF 25 and 25A may be obtained upon application to the issuing office.
VERIFICATION OF STATUS OF APPARENTLY SUCCESSFUL OFFEROR: In accordance with VAAR 804.1102 VENDOR INFORMATION PAGES (VIP) DATABASE, prior to January 1, 2012, all VOSBs and SDVOSBs must be listed in the VIP database, available at http://www.VetBiz.gov, and also must be registered in the Central Contractor Registration (CCR) (see 48 CFR subpart 4.11) to submit offers and receive contract awards under VA’s Veteran-owned Small Business prime contracting and subcontracting opportunities program set forth in Part 819. After December 31, 2011, all VOSBs, including SDVOSBs, must be listed as verified in the VIP database, and also must be registered in the CCR to be eligible to participate in order to receive new contract awards under this program. SDVOSB Firms that submit bids/offers on SDVOSB/VOSB set-asides that are not listed on VIP will be deemed nonresponsive (IFB) or technically unacceptable (RFP/RFQ).SAFETY OR ENVIRONMENTAL VIOLATIONS AND EXPERIENCE MODIFICATION RATE: All Bidders/Offerors shall submit the following information pertaining to their past Safety and Environmental record. The information shall contain, at a minimum, a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.
SAFETY OR ENVIRONMENTAL VIOLATIONS AND EXPERIENCE MODIFICATION RATE: All Bidders/Offerors shall submit the following information pertaining to their past Safety and Environmental record. The information shall contain, at a minimum, a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.
All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information shall be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead.
Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.
A Determination of Responsibility will be accomplished for the apparent awardee prior to processing the award. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines above or submit this information will result in a determination of “Non-Responsibility” for the bidder/offeror. NOTE: Any information received by the Government that would cause for a negative Determination of Responsibility will make the bidder/offeror ineligible for award.
This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.
DESCRIPTION OF WORK:
Furnish all labor, tools, material, equipment, and supervision necessary to:
A. BASE BID (BID ITEM NO. 1):
ITEM I, GENERAL CONSTRUCTION: Construct Dom Clinic Addition (Building 502F): Work includes general construction, abatement, minor alterations at wall shared with existing building, walks, grading, drainage, plumbing, mechanical and electrical work, utility systems and structural work necessary for addition.
ITEM II, GENERAL CONSTRUCTION: Construct CLC Admin Addition (Building 501D): Work includes general construction, abatement, minor alterations at wall shared with existing building, roads, walks, grading, drainage, plumbing, mechanical and electrical work, utility systems and structural work, including necessary removal of the existing smoking structure, necessary for addition. This includes Office/Exam space as well as the connecting corridor, support spaces and entry.
CONSTRUCTION COMPLETION TIME (Base Bid): 630 calendar days from NTP.
B. ALTERNATE NO.1 (BID ITEM NO. 2): Include work as described in Base Bid (Bid Item No. 1), except the following: (a) Deduct all work necessary for the Patient Wheelchair Lift at 501D, space – LANDING 501D-136. This includes equipment and hardware. Electrical service to stub into covered junction box in wall for future connection.
CONSTRUCTION COMPLETION TIME: 630 calendar days from NTP.
C. ALTERNATE NO.2 (BID ITEM NO.3): Include work as described in Base Bid (Bid Item No. 1) EXCEPT DEDUCT ALTERNATE NO.1 (BID ITEM NO. 2), and the following: (a) Deduct all work necessary for the nine (9) Solar Daylighting Tubes, at Building 501D. This includes equipment, deck openings, ceiling openings, hardware, curbs and structural support.
CONSTRUCTION COMPLETION TIME: 623 calendar days from NTP.
D. ALTERNATE NO.3 (BID ITEM NO. 4): Include work as described in Base Bid (Bid Item No. 1), EXCEPT DEDUCT ALTERNATE NO.1 (BID ITEM NO. 2) and ALTERNATE NO.2 (BID ITEM NO.3), and the following: (a) Deduct all work necessary for the two (2) skylights at Building 501D. This includes equipment, deck openings, ceiling openings, hardware, curbs and structural support.
CONSTRUCTION COMPLETION TIME: 623 calendar days from NTP.
E. ALTERNATE NO.4 (BID ITEM NO. 5): Include work as described in Base Bid (Bid Item No. 1), EXCEPT DEDUCT ALTERNATE NO.1 (BID ITEM NO. 2), ALTERNATE NO.2 (BID ITEM NO.3) and ALTERNATE NO.3 (BID ITEM NO.4), and the following: (a) Deduct all work necessary for the Pneumatic Tube System for CLC Admin – Building 501D. This includes the Tube Station at space COPY/WORKROOM 501D-120 as well as all necessary tubing, blowers, conduit, cabling and conductors back to the existing transfer station origin point. (b) Installation of the new Tube System from the existing transfer station origin point to the Dom Clinic - Building 502F to remain.
CONSTRUCTION COMPLETION TIME: 623 calendar days from NTP.
F. ALTERNATE NO.5 (BID ITEM NO. 6): Include work as described in Base Bid (Bid Item No. 1), EXCEPT DEDUCT ALTERNATE NO.1 - (BID ITEM NO. 2), ALTERNATE NO.2 (BID ITEM NO.3), ALTERNATE NO.3 (BID ITEM NO.4) and ALTERNATE NO.4 (BID ITEM NO. 5), and the following: (a) deduct all work necessary for constructing unoccupied in the CLC Admin office area of new Building 501D. This includes architectural and systems items as referenced in the associated drawings below. Buildout of the exterior surfaces, connecting corridor/ramp, support spaces (501D-101, 102, 103, 104) and entry (501D-100) to remain. Grading, site work and installation of underground utilities to remain. See drawings G003, PL107, PL108, MH105 & EP104 for details.
CONSTRUCTION COMPLETION TIME: 540 calendar days from NTP.
G. ALTERNATE NO.6 (BID ITEM NO. 7): Include all associated work as shown for Building 502F and as described in Base Bid (Bid Item No. 1), EXCEPT DEDUCT ALTERNATE NO.1 - (BID ITEM NO. 2), ALTERNATE NO.2 (BID ITEM NO.3), ALTERNATE NO.3 (BID ITEM NO.4) and ALTERNATE NO.4 (BID ITEM NO. 5), ALTERNATE NO. 5 (BID ITEM NO. 6) and deduct all remaining work associated with the construction of Building 501D in its entirety and deduct all work associated with constructing a new walkway. This includes abatement, demolition, removal of the Smoking structure, grading, site work, utilities, structure, systems, interior partitions and finishes. All shall remain undisturbed outside at Building 501C.
CONSTRUCTION COMPLETION TIME: 450 calendar days from NTP.
COST RANGE: $5,000,000.00 to $10,000,000.00 SIZE DETERMINATION: For the purpose of this procurement for construction, a concern is small if its average annual receipts for its preceding 3 fiscal years did not exceed $36.5 million. The NAICS code is 236220.
PARTIAL PAYMENTS will be made monthly as the work progresses.
RATES OF PAY: Contractor shall be responsible for correct wage titles and compliance with all applicable wage and hour laws and applicable General Decision Number WV34 dtd 6/8/18.
Normal work hours are Monday through Friday, 8:00 a.m.- 4:30 p.m. local time excluding weekends and National holidays (New Year’s Day, Martin Luther King Day, Presidents’ Day Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day and any other day specifically declared by the President of the United States).
GENDER: Whenever the masculine gender is used in the solicitation and contract documents it shall be considered to include both masculine and feminine.
INDEMNITY: The Contractor shall be liable for, and shall indemnify and hold harmless the Government against, all actions or claims for loss of or damage to property or the injury or death of persons, arising out of or resulting from the fault, negligence, or act or omission of the Contractor, its agents, or employees.
DOCUMENTS REQUIRED WITH BID PACKAGE:
Completed 1442 – pages 1 & 2 Offer Guarantee/Bid Bond Representations and Certifications Price Proposal with Complete Breakdown
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE II (JUN 2009)
(a) Definitions. "Bahrainian, Mexican, or Omani construction material," "commercially available off-the-shelf (COTS) item," "construction material," "designated country construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials Under Trade Agreements" (Federal Acquisition Regulation (FAR) clause 52.225-11).
(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material, except foreign construction material from a designated country other than Bahrain, Mexico, or Oman that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.4 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Hand-Carried Address:
Department of Veterans Affairs
VAMC (613)
Laura Tawzer 510 Butler Ave, Building 306A Martinsburg WV 25405 Mailing Address:
Department of Veterans Affairs
VAMC (613)
Laura Tawzer 510 Butler Ave, Bldg 306A Martinsburg WV 25405
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) ALTERNATE I (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute shall submit the request with its offer, including the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for— August 16, 2018 @ 1:00pm local time
(c) Participants will meet at— Bldg 308B Conference Room (End of Provision)
2.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT |
| OCT 2016 |
| 52.204-16 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING |
| JUL 2016 |
| 52.204-22 |
| ALTERNATIVE LINE ITEM PROPOSAL |
| JAN 2017 |
| 52.214-3 |
| AMENDMENTS TO INVITATIONS FOR BIDS |
| DEC 2016 |
| 52.214-4 |
| FALSE STATEMENTS IN BIDS |
| APR 1984 |
| 52.214-5 |
| SUBMISSION OF BIDS |
| DEC 2016 |
| 52.214-6 |
| EXPLANATION TO PROSPECTIVE BIDDERS |
| APR 1984 |
| 52.214-7 |
| LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS |
| NOV 1999 |
| 52.214-18 |
| PREPARATION OF BIDS—CONSTRUCTION |
| APR 1984 |
| 52.214-19 |
| CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION |
| AUG 1996 |
| 52.214-34 |
| SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE |
| APR 1991 |
| 52.214-35 |
| SUBMISSION OF OFFERS IN U.S. CURRENCY |
| APR 1991 |
| 52.222-23 |
| NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION |
| FEB 1999 |
| 52.223-1 |
| BIOBASED PRODUCT CERTIFICATION |
| MAY 2012 |
2.8 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (JAN 2008)
The supplies or equipment required by this invitation for bid or request for proposal must conform to the standards of the National Electric Code, National Plumbing Code and National Fire Protection Association and shall be in compliance with applicable standards and/or codes as required in performance of this work. The successful bidder or offeror will be required to submit proof that the item(s) he/she furnishes conforms to this requirement. This proof may be in the form of a label or seal affixed to the equipment or supplies, warranting that they have been tested in accordance with and conform to the specified standards. Proof may also be furnished in the form of a certificate from one of the above listed organizations certifying that the item(s) furnished have been tested in accordance with and conform to the specified standards.
(End of Provision)
2.9 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.
(End of Clause)
2.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (JAN 2008)
(a) Any protest filed by an interested party shall:
(1) Include the name, address, fax number, and telephone number of the protester;
(2) Identify the solicitation and/or contract number;
(3) Include an original signed by the protester or the protester's representative and at least one copy;
(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;
(5) Specifically request a ruling of the individual upon whom the protest is served;
(6) State the form of relief requested; and
(7) Provide all information establishing the timeliness of the protest.
(b) Failure to comply with the above may result in dismissal of the protest without further consideration.
(c) Bidders/offerors and contracting officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.
(End of Provision)
2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (JAN 1998)
As an alternative to filing a protest with the contracting officer, an interested party may file a protest with the Deputy Assistant Secretary for Acquisition and Materiel Management, Acquisition Administration Team, Department of Veterans Affairs, 810 Vermont Avenue, NW., Washington, DC 20420, or for solicitations issued by the Office of Construction and Facilities Management, the Director, Office of Construction and Facilities Management, 810 Vermont Avenue, NW., Washington, DC 20420. The protest will not be considered if the interested party has a protest on the same or similar issues pending with the contracting officer.
(End of Provision) PLEASE NOTE: The correct mailing information for filing alternate protests is as follows:
| Deputy Assistant Secretary for Acquisition and Logistics, |
| Risk Management Team, Department of Veterans Affairs |
| 810 Vermont Avenue, N.W. |
| Washington, DC 20420 |
Or for solicitations issued by the Office of Construction and Facilities Management:
| Director, Office of Construction and Facilities Management |
| 811 Vermont Avenue, N.W. |
| Washington, DC 20420 |
2.12 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)
The contracting officer reserves the right to designate representatives to act for him/her in furnishing technical guidance and advice or generally monitor the work to be performed under this contract. Such designation will be in writing and will define the scope and limitation of the designee's authority. A copy of the designation shall be furnished to the contractor.
(End of Provision)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2018)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $36.5 Million.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.
(vii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(ix) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xvi) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the…