This is a Questions and Answers (Q&A) document addressing clarifications for a federal construction contract involving roof replacement and related work. The document contains 61 numbered questions with corresponding answers from the contracting office and final VA answers, addressing technical specifications, material requirements, and contract administration details.
The project requires replacement of approximately 1,300 square feet of EPDM roofing, including all gutters, downspouts, and facia as necessary. Key material specifications include 90 mil white EPDM roofing with a 25-year manufacturer warranty (any equivalent or better product acceptable), 5-inch Type K seamless aluminum gutters, 4-inch aluminum downspouts, R-30 mineral wool insulation with continuous vapor barrier, and a 3/8-inch dens deck cover board. The contractor must remove the membrane and cover to deck, inspect and repair damaged decking (limited to a 200 square foot deduct, with change orders for additional repairs), and install new coverboard and membrane per drawings. Insulation is only removed if wet or damaged, unless the manufacturer requires full replacement to maintain warranty. The roof features four-way slope with no tapered insulation or snow guards required. The contract period of performance is 120 calendar days after notice to proceed, with a government estimate between $250,000 and $500,000. Performance and payment bonds are required; a bid bond is not. The site superintendent must be directly employed by the prime contractor and present on-site at all times, and an OSHA-defined Competent Person must be on-site during all work. The superintendent and Site Safety Health Officer may be dual-hatted positions if the individual is qualified for both roles. The contractor is responsible for field verification of existing conditions, providing portable restrooms, and submitting as-built documentation through internal systems (Autodesk Construction Cloud is no longer available). No asbestos-containing material is known to exist, though suspected ACM encountered during work must be immediately reported to the Contracting Officer's Representative.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
# Question AE Answer VA Final Answer 1 Drawing A102. Please provide the model number for basis of design for the new downspout to UG pipe connector?
This is unknown and the responsibility of the contractor to provide their proposed solution via submittal once awarded.
2 Drawing A102. Please provide the model number for basis of design for the new downspout to Cleanout/UG pipe connector?
This is unknown and the responsibility of the contractor to provide their proposed solution via submittal once awarded.
3 Specification Section 01 00 00, Paragraph 1.6J and Drawing G003: Are temporary construction fence panels acceptable in lieu of drive-in fence posts?
Yes, temporary construction fence panels are acceptable.
4 Are 6-ft-tall temporary construction fence panels acceptable in lieu of the 7-ft height specified in the specifications?
Yes, temporary 6’-0” construction fence panels are acceptable.
5 Windscreen typically cannot be used with temporary fence panels that utilize weights or sandbags due to wind load. Is it acceptable to omit the windscreen if temporary fence panels are used?
Yes
6 Specification Section 01 00 00, Paragraph 1.3.A (Statement of Bid Items): Is a new lightning protection system required for the new roof?
Lightning protection is not within the scope of this project.
7 Specification Section 07 53 23 (EPDM Roofing), Paragraph 2.3.A (Products- General): Are there other manufacturers of equivalent thickness that would be acceptable for the EPDM roofing? (e.g., Carlisle or Versico).
Any equivalent or better product is acceptable.
8 Is the entire existing roof system to be torn down to deck, deck inspected and new insulation, and EPDM system to be installed?
The membrane and any cover is required to be removed to deck, the deck inspected and repaired if necessary, and new coverboard/membrane installed per the detail on sheet A103, detail 1.
9 Or is only the membrane to be removed the insulation to be replaced only if wet or damaged?
Insulation is only to be removed if wet or damaged. Please refer to RFI question #33 as well.
10 There is no spec for a cover board to be installed. In the drawings below it appears that the plan is to keep current insulation and install 3/8 inch dens deck cover board. Are we correct in this assumption?
Yes
11 Is the gypsum board to be mechanically fastened?
Yes
12 Is the EPDM system to be adhered? Yes 13 25-year warranty is called out in the specifications are we able to utilize another manufacturer if we can meet the 90 mil EPDM and 25-year warranty requirement.
Any equivalent or better product is acceptable.
14 What size gutter is to be installed? 5” Type ‘K’ Seamless Aluminum, 4” aluminum downspouts 15 What type of roof deck on the building? Current roof decking is suspected to be 3/4” pressure-treated plywood, but it is the contractors responsibility to field verify and replace in kind. See drawing sheet A103, detail 1.
16 What is the thickness of the existing insulation?
Current insulation is R-30 mineral wool w/ cont. vapor barrier stapled to joists. ASTM E 84 moisture resistant, flame resistant and mold resistant.
17 Is the roof deck sloped or is tapered insulation required?
Please refer to drawings. This is a low slope (1/2" in 12”) EPDM roof.
18 What is the thickness of new insulation? Current insulation is R-30 mineral wool w/ cont. vapor barrier stapled to joists. ASTM E 84 moisture resistant, flame resistant and mold resistant.
19 Does the new roof require a cover board or vapor barrier?
See drawing sheet A103, detail 1. Current insulation is R-30 mineral wool w/ cont. vapor barrier stapled to joists. ASTM E 84 moisture resistant, flame resistant and mold resistant.
20 Please confirm that the new metal is to be aluminum.
Yes, aluminum gutters, downspouts and any facia.
21 Please confirm that gutters and downspouts are to be removed for reinstallation.
No, provide new gutters and downspouts per drawings.
22 Please confirm is this work is just for the replacement of 1300 SF of roofing and anything else has to be perform?, since the government estimate is between $250K - $500K When is the expected day to start?
The contractor is required to replace roughly 1,300SF of roofing, all gutters, downspouts, facia as necessary, repair/replace water damaged roof decking/insulation, and provide new cover board.
23 confirm if the deck replacement is limited to 200 SF?
Please provide this as a deduct. If not required, it will be deducted from the contract. If more is required a change order is appropriate.
24 do you need any carpentry to be replace, as rafters, beams, struts, etc?
No, this is not expected and not within scope.
25 Is Procore Photo Tools (Map, Timeline, Albums) acceptable for photo documentation?
Yes
26 Can the Site Superintendent and SSHO dual hat ?
Yes
27 Where is the laydown area? Refer to sheet G003 of the drawing package, labeled “staging area” 28 Can the dumpster be placed next to the building during tear off?
Yes, this is acceptable
29 How close can a boom truck be placed next to the building for placing materials?
Or should we plan to use a crane for longer lift?
A boom truck or other machinery is permitted as close to the building as terrain allows.
30 Please confirm requirement for Portable restrooms.
The VA will not provide restrooms to contractor; thus alternative arrangements must be made by the contractor.
31 Specification Section 01 00 00, 1.3.a calls for Alternate 1 but it is not indicated on the Price Schedule, is it required?
Yes, ALTERNATE NO. 1 is required.
32 If Alternate 1 is required, please specify roof decking material and thickness required so we may provide accurate pricing.
Current roof decking is suspected to be 3/4” pressure-treated plywood, but it is the contractors responsibility to field verify and replace in kind.
33 Drawing A102 notes ‘Ex. Insulation replace any Damaged in Kind’. This is difficult to quantify especially if the roof is currently leaking. Manufacturer will likely require all insulation be replaced to maintain a warranty. Please clarify this requirement for fair and equitable bidding.
If replacement of all insulation is required by the manufacturer to maintain warranty, then this must be included, however, it is up to the contractor’s discretion on how this is to be handle/bid.
34 Drawing A101 doesn’t indicate any roof penetrations. Since we weren’t able to get on the roof please provide quantity, type and size of roof penetrations and/or photos.
35 Has hazardous testing been completed on the roofing existing materials?
1. ASBESTOS CONTAINING MATERIAL (ACM) MAY EXIST IN NORMALLY INACCESSIBLE
LOCATIONS SUCH AS WITHIN WALLS, CEILINGS, CRAWL SPACES, PIPE CHASES, SHAFTS,
TRENCHES, OR OTHER LOCATIONS. THERE IS NO KNOWN ACM FOR THIS PROJECT.
2. IF SUSPECT MATERIAL IS ENCOUNTERED DURING THE COURSE OF THIS PROJECT, WORK IN
THIS AREA SHALL STOP AND THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE COR.
3. MATERIALS WHICH ARE COMPLETELY NACCESSIBLE UNDER NORMAL CIRCUMSTANCES AND
WHICH ARE IN RELATIVELY INTACT CONDITION ARE UNLIKELY TO POSE A SIGNIFICANT
HEALTH HAZARD TO BUILDING OCCUPANTS, AND IF UNDISTURBED, CAN REMAIN IN PLACE.
4. ANY SUSPECTED ACM WHICH IS ENCOUNTERED DURING MAINTENANCE, RENOVATION OR
DEMOLITION WORK SHOULD BE ASSUMED TO BE ASBESTOS-CONTAINING AND BE TREATED
ACCORDINGLY.
36 Will the government accept CPARs in lieu of PPQs?
CPARs may be submitted, but please make every effort to procure PPQ’s and document as such.
37 I was interested in clarification of this paragraph in Appendix 1 below Bond requirements? Disclosure of the magnitude of construction: between $250,000 and $500,000.
Performance and payment bonds are required a bid bond is not.
38 Does the Superintendent need to be directly employed by the Prime Contractor?
Yes Yes
39 Must the Superintendent be on site at all times while work is commencing?
Yes Yes
40 Does the SSHO (Site Safety Health Officer) need to be directly employed by the Prime Contractor?
No, but a memo or other document giving the SSHO full authority to act on behalf of the contractor must be provided.
41 Must the SSHO be on site at all times while work is commencing?
Yes, this person may also be the Competent Person
42 Can the Superintendent & SSHO be a dual-hatted individual assuming that individual is qualified for both roles?
Yes
43 Are there any other mandatory on-site roles required in this contract?
Yes, the contractor is required to have an OSHA-defined “Competent Person” (i.e. supervisor) on site at all times work is being performed.
44 When does the VA expect the project to start following the award?
The project period of performance is 120 calendar days after notice to proceed. It is up to the contractor’s discretion when to perform the work during those 120 days.
45 Are there any concerns for Asbestos Containing Material or Lead in the areas being worked in?
1. ASBESTOS CONTAINING MATERIAL (ACM) MAY EXIST IN NORMALLY INACCESSIBLE
LOCATIONS SUCH AS WITHIN WALLS, CEILINGS, CRAWL SPACES, PIPE CHASES, SHAFTS,
TRENCHES, OR OTHER LOCATIONS. THERE IS NO KNOWN ACM FOR THIS PROJECT.
2. IF SUSPECT MATERIAL IS ENCOUNTERED DURING THE COURSE OF THIS PROJECT, WORK IN
THIS AREA SHALL STOP AND THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE COR.
3. MATERIALS WHICH ARE COMPLETELY NACCESSIBLE UNDER NORMAL CIRCUMSTANCES AND
WHICH ARE IN RELATIVELY INTACT CONDITION ARE UNLIKELY TO POSE A SIGNIFICANT
HEALTH HAZARD TO BUILDING OCCUPANTS, AND IF
UNDISTURBED, CAN REMAIN IN PLACE.
4. ANY SUSPECTED ACM WHICH IS ENCOUNTERED DURING MAINTENANCE, RENOVATION OR
DEMOLITION WORK SHOULD BE ASSUMED TO BE ASBESTOS-CONTAINING AND BE TREATED
ACCORDINGLY.
46 Are there any ICRA requirements for this project?
No, this building is not subject to infection control.
47 Are there any ICRA requirements for this project?
No, this building is not subject to infection control.
48 Is this contract Tax Exempt? Yes Yes 49 Will the site visit sign in sheet be posted? Yes Yes 50 • Can the VA please confirm that
Autodesk Construction Cloud will still be the required project management and documentation platform for this contract?
• If Autodesk Construction Cloud will not be utilized, please clarify which platform (if any) will replace it and whether licenses will be provided to the contractor. Additionally, if no platform is provided, please confirm whether the contractor will be required to use their own internal documentation and as-built drawing management system (or 3rd part services) in compliance with the submittal requirements.
• If other systems / services are used, will the as-builts need to be stamped by a licensed architect?
• Autodesk Construction Cloud is no longer available, and no substitute platforms are currently replacing the software. Please provide internal documentation and as-built drawing management system (or 3rd party services) in compliance with the submittal requirements.
• As-builts will be verified by the COR to be complete and accurate. No professional stamp is required.
51 • Has the VA conducted any roof core sampling, testing, or investigative reports that can be shared with offerors?
• If not, does the VA intend to perform core sampling prior to award and publicly release the findings for bidding consistency? This information would
No core samplings have been or will be performed/provided. It is assumed that deck repairs are limited to the deduct of 200SF or less. If more repairs are required, a change order would be appropriate at that time.
significantly impact material quantities, deck repair assumptions, and labor estimating.
52 • Can the VA clarify how deck repairs beyond the identified allowance will be handled (e.g., unit price modification, change order, or contingency)?
It is assumed that deck repairs are limited to the deduct of 200SF or less. If more repairs are required, a change order would be appropriate at that time.
53 • Please confirm the minimum required EPDM roofing warranty for this project (e.g., 20-year, 25-year NDL, manufacturer system warranty, etc.) and whether manufacturer inspections or certifications will be required.
Per spec section 07 53 23 sub section 1.10.B the manufacturer must warrant the roofing system against material and manufacturing defects and agree to repair any leak caused by a defect in the roofing system materials or workmanship of the installer for a minimum of 25 years. The VA does not require any inspections so long as the warranty requirements are met.
54 The specs mention to remove or cut off wet insulation areas. Is the insulation expected to remain or is this a full tear off?
Insulation is expected to remain except where wet/damaged. Please also see RFI question #33.
55 The specs mention a fully adhered .090 White EPDM for a 25 Year Warranty – is this correct?
The specifications govern the project and supersede the drawings if/when any conflict exists.
56 The specs also only mention Elevate as the manufacturer, is this the only manufacturer that can be utilized?
Elevate is the BOD. Any equivalent or better product may be utilized.
57 Is there a minimum or average R-value for the insulation?
Current insulation is R-30 mineral wool w/ cont. vapor barrier stapled to joists. ASTM E 84 moisture resistant, flame resistant and mold resistant. Any replacement must meet or exceed existing.
58 For the gutters and downspouts, is there a specific gutter size, downspout size, and metal type?
5” Type ‘K’ Seamless Aluminum, 4” aluminum downspouts
59 The documents reference snow guards, however, manufacturer, model, spacing, and performance requirements are not
There are no snow guards required.
specified. Please confirm the required system and installation criteria.
60 The membrane listed in the spec, 90mil white EPDM from Elevate, is not produced anymore. If you want 90mil white EPDM, it will have to be from another manufacturer. Elevate makes black EPDM as well as white TPO.
Elevate is the BOD. Any product that meets the specification is acceptable.
61 Is the roof deck sloped 4 ways, or do we need tapered insulation?
The roof is sloped four ways. Please see drawings.