S02 EXHIBIT C Past Performance Questionnaire 10.15.25.docx

DOCX document 541 KB Posted

Attached to
Z1DA--LOCAL minimum guarantee base Construction MATOC| Lebanon-Altoona Construction MATOC (VA-26-00000908)
Solicitation number
36C24425R0084
Issued by

About this file

This document is a Past Performance Questionnaire for the Lebanon and Altoona Multiple Award Task Order Contract (MATOC) issued by the Department of Veterans Affairs Network Contracting Office. The form is designed for reference contacts to evaluate a contractor's past performance across multiple dimensions including quality management, timeliness, business practices, compliance, safety, and overall customer satisfaction. Contractors are expected to have references complete the detailed questionnaire, which uses a 0-5 rating scale for seventeen specific performance criteria, with space for written remarks and an overall performance rating.

The questionnaire must be returned to the Contracting Officers Elijah McIntosh and Jeffery Pruett by 4:30 pm local time on 10-29-25, which is one day before the Request for Proposal (RFP) due date. Key evaluation areas include technical and administrative abilities, quality control, schedule adherence, problem-solving skills, regulatory compliance, safety protocols, and infection control processes. The form concludes with specific questions about whether the reference would award another contract to the contractor and requires certification of the information's accuracy by the reference contact.

View the file

Other files

File Type Posted
Contractor Pre-Award OSHA Evaluation Form.pdf PDF
S02-Seed Project - Drawings - Building 1 Entrance Enclosure.pdf PDF
36C24425R0084 0002.pdf PDF
36C24425R0084 0002_1.docx DOCX document
S02-P01-Seed Project - Narrative - Building 1 Entrance Enclosure redacted.pdf PDF
36C24425R0084 0001.pdf PDF
MATOC Sitewalk SignIn 9-24-25.pdf PDF
36C24425R0084 0001_1.docx DOCX document
S02-P01-Seed Project - Narrative - Building 1 Entrance Enclosure redacted.pdf PDF
S02-S02-EXHIBIT A - Statement of Prior Experience.docx DOCX document
S02-S02-EXHIBIT B Subcontractor Information and Consent Form 5.29.25.docx DOCX document
S02-Davis Bacon Act WD PA20250093 _01.pdf PDF
S02-P01-Seed Project - Narrative - Building 1 Entrance Enclosure.pdf PDF
S02-Seed Project - Drawings - Building 1 Entrance Enclosure.pdf PDF
S02-S02-EXHIBIT C Past Performance Questionnaire 5.29.25.docx DOCX document
S02-112713-010000-General Requirements -Lebanon.pdf PDF
S02-P11-MCR Altoona - Medical Center Requirements 8.15.25.pdf PDF
S02-P11-013526 Lebanon Safety Requirements Spec.docx DOCX document
S02-Seed Project Task Order Package 7.17.25f.docx DOCX document
S02-Hot Work Permit - Lebanon.doc DOC document
S02-S02-EXHIBIT D Sample Transmittal Letter for Past Performance Evaluation Questionnaire.docx DOCX document
36C24425R0084_2.docx DOCX document
36C24425R0084 9.22.25 R1.pdf PDF
36C24425R0084_3.docx DOCX document
36C24425R0084 9.22.25.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of Veterans Affairs

Network Contracting Office 4 1010 Delafield Road Pittsburgh, PA 15215

Past Performance Questionnaire for: Lebanon and Altoona MATOC

INSTRUCTIONS TO OFFEROR

Complete the CONTRACTOR INFORMATION section, below (type answers into light blue shaded boxes). Save the document. Send an electronic or hard copy print of the form to each of your reference contacts, asking them to please complete the form and submit it according to the instructions, below.

Company Name

Street Address

Point of Contact (POC)

City

POC Phone Number

State

Reference Project Title

Zip Code

Contract Period of Performance (start to finish):

Email

Contract Number

Contract Dollar Value

Description of Work

Role of Contractor on This Project (check appropriate box)
|_| Prime Contractor |_| Sub-contractor |_| Key Personnel

INSTRUCTIONS TO REFERENCE CONTACT

The contractor named above is submitting a proposal for a United States Department of Veterans Affairs contract, and has sent this form to you as a past performance reference contact. Please complete the following pages in full (all areas shaded in light yellow, below). Once completed, please send the form to the Contracting Officer via postal mail or email directly to:

Elijah.mcintosh@va.gov and Jeffery.pruett@va.gov

Please return the completed form ASAP, but no later than 4:30 pm local time, 10-29-25. (Due a day before the RFP) If you have any questions, please contact the Contracting Officer: John.Mignogna@va.gov

RESPONDENT INFORMATION [completed by Reference Contact]

Company Name

Street Address

POC Name

City

Phone Number

State

Email

Zip Code

PERFORMANCE INFORMATION: Choose the number on the scale of 0 (Neutral) to 5 (Exceptional) that most accurately describes the contractor’s performance or situation. PLEASE PROVIDE AN EXPLANATION FOR THE OVERALL RATING in the Remarks section, below.

0
1
2
3
4
5
NEUTRAL
UNACCEPTABLE
MARGINAL
ACCEPTABLE
VERY GOOD
OUTSTANDING
No record of past performance, or not applicable or the record is inconclusive.
Performance did not meet most contractual requirements. There were serious problems and the contractor’s corrective actions were ineffective.
Performance did not meet some contractual requirements. There were problems, some of a serious nature, for which corrective action was only marginally effective.
Performance met most contractual requirements. There were some minor problems and corrective actions taken by the contractor were satisfactory.
Performance met all contract requirements and exceeded some to the government’s benefit. There were a few minor problems, which the contractor resolved in a timely, effective manner.
Performance exceeded all contract requirements. There were no problems.
The Contractor …
0
1
2
3
4
5

QUALITY – MANAGEMENT & WORKMANSHIP

1.
Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements.
|_|
|_|
|_|
|_|
|_|
|_|
2.
Demonstrated ability to hire, maintain, and replace, if necessary, qualified construction personnel during the contract period.
|_|
|_|
|_|
|_|
|_|
|_|
3.
Provided and followed approved quality control plan and/or inspection procedures to meet contract requirements.
|_|
|_|
|_|
|_|
|_|
|_|
4.
Corrected deficiencies in timely manner and pursuant to their quality control procedures.
|_|
|_|
|_|
|_|
|_|
|_|
5.
Submittals clearly identified the proposed item IAW the specifications and drawings.
|_|
|_|
|_|
|_|
|_|
|_|
6.
Suggested alternative approaches to problems.
|_|
|_|
|_|
|_|
|_|
|_|

TIMELINESS AND ADHERENCE TO SCHEDULE

0
1
2
3
4
5
7.
Contractor provided timely notices of possible delays/schedule revisions.

REMARKS:

|_|
|_|
|_|
|_|
|_|
|_|
8.
Timeliness in submitting submittals and reports and responding to agency inquiries, RFP's, etc.
|_|
|_|
|_|
|_|
|_|
|_|
9.
Developed realistic and met approved progress schedules.
|_|
|_|
|_|
|_|
|_|
|_|

BUSINESS PRACTICES/CUSTOMER RELATIONSHIP AND ABILITY TO PERFORM

10.
Displayed initiative to solve problems.
|_|
|_|
|_|
|_|
|_|
|_|
11.
How well did the contractor work independent of Government guidance, oversight and assistance?
|_|
|_|
|_|
|_|
|_|
|_|
12.
Subcontractors / tradesmen were adequately managed and coordinated. Explain any subcontracting issues (positive or negative) that impacted the performance of your contract(s).
|_|
|_|
|_|
|_|
|_|
|_|
13.
For contract changes, contractor provided timely and realistic change order proposals.
|_|
|_|
|_|
|_|
|_|
|_|

COMPLIANCE & SAFETY

0
1
2
3
4
5
14.
Reports (i.e., daily, test, logs) / records were submitted completely and accurately satisfy the requirement.
|_|
|_|
|_|
|_|
|_|
|_|
15.
Applicable to Federal Contracts –Contractor complied with applicable Federal Laws and Regulations such as Construction Wage Rate Requirements – timely payrolls and compliance; Drug-Free Workplace; Environmental Regulations and Use of Recovered Materials; Executive Order 13101 Greening the Government.
|_|
|_|
|_|
|_|
|_|
|_|
16.
Contractor’s safety program was in compliance with federal regulations. Contractor implemented and followed their safety plan and ran a “safe jobsite”.
|_|
|_|
|_|
|_|
|_|
|_|

INFECTION CONTROL

17.
Contractor had an Infection Control Process in place and complied with agency Infection Control Requirements.
|_|
|_|
|_|
|_|
|_|
|_|

OVERALL CUSTOMER SATISFACTION

18.
Demonstrated reasonableness in modifications cost proposal.
|_|
|_|
|_|
|_|
|_|
|_|
19.
Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain outcome in “remarks.”
|_|
YES
|_|
NO
20.
Would you award another contract to this contractor? If not, please explain in “remarks.”
|_|
YES
|_|
NO
OVERALL PERFORMANCE RATING:
|_|
|_|
|_|
|_|
|_|
|_|

REMARKS (Please use as much space as is needed – the box will expand as you type).

I hereby certify that the information that I have reported above is accurate to the best of my knowledge.

Printed Name

E-mail address

Business Title

Signature

Date

1 | Page image1.png image10.png

File details come from the government source that posted it. Updated .