542-19-113 - Bid Form - Reno Building 58- Updated.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
Amendment 2 | Z1DA--542-19-13 | Renovate Building 58 1st and 2nd Floors Domiciliary 100% Set-Aside for SDVOSB Contractors
Solicitation number
36C24423R0083
Issued by

About this file

This file contains a bid form and information on a related federal contract opportunity. The bid form is for contractors to submit pricing details for renovating the 1st and 2nd floors of Building 58 at a VA medical center. The project involves work in multiple construction divisions. The form requires contractors to provide material, labor, equipment, and total costs for each division and the overall base bid. It also includes spaces for bid deducts and calculations for overhead and profit.

The associated federal contract opportunity is a special notice for Amendment 2 to solicitation number 36C24423R0083. The renovation of Building 58 at the VA medical center is being conducted as a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses. The contracting agency is the VA Veterans Health Administration VISN 4. The amendment provides additional unspecified information on the opportunity.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Form (auto calc)

Contractor Bid FormProject Name:Renovate Building 58 1st and 2nd Floors
Project Number:542-19-113
Contract Number:
Contractor Name:
Date:
To be filled out by the Contractor
DescriptionQtyUnitMatrl SubtotalLabor SubtotalEquipment SubtotalTotal
Divisions
NoGeneral Conditions
1Division 1
2Division 2
3Division 3
4Division 4
5Division 5
6Division 6
7Division 7
8Division 8
9Division 9
10Division 10
11Division 12
12Division 21
13Division 22
14Division 23
15Division 26
16Division 27
17Division 28
Base Bid Subtotal
Bid Deducts
Deduct 1
Deduct 2
Deduct 3
Deduct 4
Deduct 5
Bid Deducts Subtotal

Subtotal (Direct Costs)

Direct Overhead (first $20,000)10.0%
Direct Overhead (next $30,000)7.5%
Direct Overhead (over $50,000)5.0%
Direct Overhead Total

Subtotal (Direct + Overhead

Profit (first $20,000)10.0%
Profit (next $30,000)7.5%
Profit (over $50,000)5.0%
Profit Total

Insurance and Taxes %

Taxes on Material and Equipment %

Total Prime Contractor Cost