This document contains responses to contractor questions regarding a federal solicitation for renovation of a boiler plant project. The solicitation seeks offers to renovate Boiler Plant Number 595-13-101 for the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 4. Key project details include replacing two existing boilers with new gas-fired boilers, installing a new 350kW emergency generator, upgrading electrical infrastructure, and demolishing existing equipment. The response date was extended to March 22, 2023. Project completion is required within 365 calendar days of the notice to proceed, though extensions may be considered for supply chain delays. The VA will provide fuel for testing and operation of temporary equipment.

View the file

Other files

File Type Posted
2021-03-26 Bid Documents - Drawing PDFs 01_Civil_.pdf PDF
2021-03-26 Bid Documents - Drawing PDFs 02_Structural_.pdf PDF
Lebanon Boiler_Bid Specs_Vol I.pdf PDF
Lebanon Boiler_Bid Specs_Vol II.pdf PDF
Asbestos Report - Building 10.pdf PDF
2021-03-26 Bid Documents - Drawing PDFs 03_Plumbing_.pdf PDF
2021-03-26 Bid Documents - Drawing PDFs 05_Electrical_.pdf PDF
2021-03-26 Bid Documents - Drawing PDFs 04_Mechanical_.pdf PDF
2021-03-26 Bid Documents - Drawing PDFs 03a_Life Safety_.pdf PDF
2021-03-26 Bid Documents - Drawing PDFs 00_General Information_.pdf PDF
2021-03-26 Bid Documents - Drawing PDFs 02a_Fire Protection_.pdf PDF
36C24423R0002 0001.pdf PDF
2021-03-26 Bid Documents - Drawing PDFs 03_Plumbing.pdf PDF
EXHIBIT B - subcontractor information and consent form.docx DOCX document
2021-03-26 Bid Documents - Drawing PDFs 04_Mechanical.pdf PDF
2021-03-26 Bid Documents - Drawing PDFs 02_Structural.pdf PDF
2021-03-26 Bid Documents - Drawing PDFs 02a_Fire Protection.pdf PDF
2020-09-02 Vol II Specifications - Bid Submission.pdf PDF
EXHIBIT A - Past Performance Relevancy Questionnaire.docx DOCX document
36C24423R0002.docx DOCX document
EXHIBIT E - past performance questionnaire.docx DOCX document
EXHIBIT D - sample transmittal letter.docx DOCX document
EXHIBIT C - calculation of self-performed work.docx DOCX document
2021-03-26 Bid Documents - Drawing PDFs 05_Electrical.pdf PDF
2020-09-02 Vol I Specifications - Bid Submission.pdf PDF
Locks - J and A_Posted.pdf PDF
2021-03-26 Bid Documents - Drawing PDFs 01_Civil.pdf PDF
Wage Determination PA20230093.pdf PDF
2021-03-26 Bid Documents - Drawing PDFs 00_General Information.pdf PDF
Brand Name or Equal Items.pdf PDF
2021-03-26 Bid Documents - Drawing PDFs 03a_Life Safety.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 9

0002 2/16/2023

595-13-101

00244

Department of Veterans Affairs Network Contracting Office 4

00244

Department of Veterans Affairs Network Contracting Office 4

To all Offerors/Bidders

36C24423R0002

01-19-2023

X

X X

See Box 14.

X 1

Boiler Plant Renovation Project # 595-13-101

This amendment is issued for the Technical Question Responses.

NOTE: REVISED DESIGN & SPECIFICATIONS ARE INCLUDED

Proposal due date is extended to: March 22, 2023 @ 1300

All other Terms and Conditions Remain unchanged.

Melvin Moore Contracting Officer

Boiler Plant Renovation Project # 595-13-101

1. Volume 1 Subfactor 1, Experience asks for five projects with a time period spanning the past five years. Would the VA consider expanding this time period from five years to seven years to allow for a deeper pool of projects from which offerors can choose?

Yes, the VA will consider projects completed with a time period of 7 years.

2. Volume 1 Subfactor 2, Personnel and Organization asks for Exhibit B Information and Consent Forms for each featured subcontractor, in order for them to be considered. We respectfully request that the VA remove this as a requirement, as it can be challenging asking subcontractors to complete and submit this form in time for proposal submission.

No, submit Exhibit B information and consent forms as directed.

3. Volume 1 Subfactor 4, Schedule asks for a physical schedule but does not stipulate a ball-park Notice to Proceed date. What NTP date should offerors use in their schedules?

The NTP date is arbitrary as there is no guarantee when the NTP will occur. Please use 31 May 2023 for purposes of your schedule estimates.

4. Volume 1 Factor 2, Past Performance Information asks for the submission of Past Performance Questionnaires (PPQs) directly back to the VA. In lieu of the submission of PPQs, we respectfully request that the VA allow for the submission of CPARS evaluations in the proposal submissions. We have had a few project representatives mention to us that they will not complete new PPQs if CPARS evaluations exist. Additionally, a few of our project representatives are no longer able to provide new PPQs because they have either moved on to other agencies, or have retired.

No. PPQs shall be submitted as directed. As noted in the solicitation, we will be reviewing CPARS as well.

5. Confirm that the steel erector and steel fabricator must be AISC certified per specification.

The VA standard specification requires this certification.

6. SECTION 23 09 23 was not included with the specification (i.e., Trane). The unit heaters and exhaust fans all require control interlock. The louver will also require a damper actuator interlocked with the generator operation. Please provide SECTION 23 09 23.

Specification 23 09 23 is not required and therefore not included.

7. Please confirm this is a “two-hat” project. SECTION 01 35 26 1.7-C requires a full-time on-site SSHO separate from the Prime's Superintendent and/or Quality Control Manager. Please confirm the Prime shall provide a full-time on-site Superintendent/Quality Control Manager AND SSHO.

The SSHO has to be a separate qualified individual from the Prime Contractor’s Superintendent and/or Quality Control Manager, however, they do not need to be on site full time. Competent

CONTRACTOR PRE-BID RFI’S

persons must be on site at all times and the Superintendent must have OSHA 30 training.

8. Please confirm an Infection Control Manager is not required for this project.

Infection control duties can be collateral duties to the Superintendent

9. Please confirm opacity monitors are not required for the new boilers.

Boiler stack opacity monitoring is required.

10. Confirm fuel for the new tank will be supplied by the Government.

Yes, the VA facility will provide the fuel oil for the new tank.

11. Confirm fuel oil for testing will be supplied by the Government.

Yes, the VA facility will provide the fuel oil for testing.

12. The solicitation indicates the project shall be complete within (365) calendar days from NTP. Due to boiler and balance of plant equipment lead time at nearly half a year (after approved submittals) and the new 2500 KVA transformer having a lead time of nearly a year, we request the contract duration be extended.

The plan is to adhere to the 365 calendar schedule, however in the event that supply chain issues delay certain equipment, the VA will require manufacturers proof of lead time, for a NO COST

EXTENSION.

13. Per the drawings, the 2500 KVA transformer shall be installed prior to starting the temporary boilers, we request that Government/Engineer re-review load requirements to see if the existing 2000 KVA transformer will be sufficient. The transformer has approximately a one-year lead time, which would really impact project schedule.

The phasing notes on E-601 are intended to provide a general framework on the installation sequence. This is a recommended phasing sequence and can be modified as required to suit constructability issues so that the work can proceed in an orderly manner. The main requirement for the new service transformer is that it must be installed prior to the new boiler systems in the building being started up. The existing transformer has the capacity to run the temporary boilers and the chiller plant. Contractor shall ensure that the VA is alerted 4 weeks in advance of any service outage to the chiller/boiler plant.

14. SECTION 23 50 11 (2.9) has specifications for a chemical feed system. Drawing MD-101 note 9 states to remove the boiler chemical feed system in its entirety, including all associated pumps, piping valves, and inline devices, hangers and supports. MP101 does not show the new chemical feed system nor do the electrical drawings. Please advise if we shall reuse the existing or if a new chemical feed system is required. Drawings will need to be updated.

The steam generation chemical feed system will be provided by the VA’s contractor. Drawing MP101 was revised on April 6, 2022 and does show the location for the chemical storage tanks.

15. Confirm Government will provide and maintain chemicals for the temporary boilers.

Yes, however the general contractor shall coordinate with the facility’s chemical treatment contractor Coastline Limited.

Hendrik Amelink Contact: hendrik.amelink@coastlineltd.com 202-330-8733 – Cell 1-888-466-0200 – Office P.O. Box 1247 Alexandria, VA 22313 www.Coastlineltd.com

16. Please provide asbestos surveys.

Will be provided with Solicitation Amendment.

17. Please provide specification section for Division 21.

Specifications 21 08 00 and 21 13 13 were provided in the contract documents.

18. Per Drawing S-506, General Sheet Note 4 delegates the design of the helical piles for the new fuel tank foundation to the contractor. Please provide information required for such design, including:

a. Depth to the top of rock at the fuel tank location.

Depth of rock is unknown but assumed to be below normal bearing depths.

b. Type of rock.

Type of rock is unknown but assumed to be below normal bearing depths.

c. Other similar helical pile designs used at this facility.

Other helical pile designs on this site are unknown. The helical pile delegate design is for uplift to prevent fuel tank overturning for blast loads.

19. Please confirm delegated seismic design and calculations are required for this project.

Seismic bracing delegated design is required. Specification section 13 05 41 outlines seismic bracing delegated design requirements.

20. Please confirm delegated hanger design system drawings and calculations are required for this project (SECTION 23 21 11).

Piping hanger design including drawings and calculations are required.

21. Please confirm coordinated layout drawings in 3D format are required for this project.

Yes, 3D Revit coordination drawings are required.

22. Is it the intent of the specification for the insulation of the proposed DA Tank to supply and install Calcium Silicate utilizing chamfered mailto:hendrik.amelink@coastlineltd.com http://www.coastlineltd.com/ blocks to fit curvature of the vessel followed by aluminum jacketing?

Yes

23. Will the Government handle/submit and coordinate any air-permitting modifications as it relates to the new boilers and temporary boilers/generator?

The VA will address the air permits for the new boilers only. It is the contractor’s responsibility to handle all air permitting required for the temporary boilers.

24. Generators: DIV 26: E-601: Please verify the intention of the 200KW Generator. This will be used during the swap out of the 2500KVA transformer, but is the plan to keep this on site as an emergency back up during the renovation? We would need to know a duration for rental.

The generator will remain on site for the duration of the project as backup power for the temporary boiler system and construction trailer. When the new boiler system is fully operational and the temporary boilers are removed, the 200kW generator will be removed.

25. Generators: DIV 26: E-601: Please verify the intention of the temporary 25KW Generator. Will this be needed to feed LPA 24hrs a day during the Renovation? If so /could we propose an alternate to eliminate the 25KW generator and feed LPA from a Temporary 120/208V panel fed from the MCC?

The intent of the 25kW generator is to power Panel LPA while the electrical infrastructure within the boiler plant is upgraded. Panel LPA is located on the chiller plant side of the building and cannot be shut down for an extended period of time. Alternatives will be considered provided the downtime on Panel LPA is limited to a cutover only. The motor control center on the boiler plant side is scheduled for demolition and is not a viable alternative source of power. The existing motor control center on the chiller plant side is a consideration, however this is a 480-volt MCC and would require a transformer.

26. Temporary Feeders: DIV 26: E-601: Is the temporary feed to the NEMA 3R manual transfer switch to be (4) 350AWG with a #4 ground installed in 3" rigid conduit in its entirety from the transformer? Will any of this conduit and/or conductors remain after the project or will it all need to be removed?

The feeder shall be in rigid conduit from the transformer to the manual transfer switch. This is a temporary feeder and shall be removed at the conclusion of the project when the temporary boilers are no longer needed.

27. Temporary Transfer Switch: DIV 26: GC-101 & E-601: Drawing GC- 101 Construction Phasing note 4.b. mentions a NEMA 3R Automatic Transfer Switch but on drawing E-601 it mentions a NEMA 3R Manual transfer switch. Please clarify.

Provide an automatic transfer switch per the requirements of Drawing GC101, construction phasing note 4. b.

28. Temporary Generators: DIV 26: GC-101 & E-601: Who will be responsible for refueling and fuel costs related to the Generators?

The VA facility will provide fuel oil for the emergency generators.

29. Generators: DIV 26: E-601: Please verify whether the new permanent 350KW generator is to be exterior or interior. Drawing E- 601 mentions an exterior generator in the phasing notes and the one line mentions "exterior sound attenuated enclosure" typical of an exterior installed generator. EP-101 shows the generator in the electric room.

New 350kW generator shall be interior as shown on Drawing EP101. Contractor will not provide a sound attenuated enclosure.

30. Drawing ED101 shows the EC to demolish the generator day tank.

Please clarify that this should be by the Mechanical Contractor.

General contractor is responsible for demolition of the equipment. It is the responsibility of the general contractor to provide direction to their subcontractors regarding demolition scope of work.

31. Drawing ED101 shows the EC to demolish the air handling unit on the mezzanine. Please clarify that the EC will only disconnect/make safe the AHU with removal by the Mechanical Contractor.

General contractor is responsible for demolition of the equipment. It is the responsibility of the general contractor to provide direction to their subcontractors regarding demolition scope of work.

32. Drawing ED101 shows the EC to demolish the generator radiator.

Please clarify that this should be by the Mechanical Contractor.

General contractor is responsible for demolition of the equipment. It is the responsibility of the general contractor to provide direction to their subcontractors regarding demolition scope of work.

33. Drawing ED101 shows the EC to relocate/remove compressors.

Please clarify that the EC will only disconnect/make safe the compressors for relocation/removal by the Mechanical Contractor.

General contractor is responsible for demolition of the equipment. It is the responsibility of the general contractor to provide direction to their subcontractors regarding demolition scope of work.

34. Drawing ED101 shows the EC to demolish the boiler control lineup.

Please clarify that the EC will only disconnect/make safe the boiler control line up with removal by the Mechanical Contractor.

General contractor is responsible for demolition of the equipment. It is the responsibility of the general contractor to provide direction to their subcontractors regarding demolition scope of work.

35. Drawing ED101 shows the EC to demolish the boilers. Please clarify that the EC will only disconnect/make safe the boilers with removal by the Mechanical Contractor.

General contractor is responsible for demolition of the equipment. It is the responsibility of the general contractor to provide direction to their subcontractors regarding demolition scope of work.

36. Drawing ED101 shows the EC to demolish existing pumps. Please clarify that the EC will only disconnect/make safe the pumps with removal by the Mechanical Contractor.

General contractor is responsible for demolition of the equipment. It is the responsibility of the general contractor to provide direction to their subcontractors regarding demolition scope of work.

37. Drawing ED101 shows the EC to demolishing opacity & O2 monitors, unit heaters, fuel pumps, scada system panel. Please clarify that the EC will only disconnect/make safe this equipment with removal by the Mechanical Contractor.

General contractor is responsible for demolition of the equipment. It is the responsibility of the general contractor to provide direction to their subcontractors regarding demolition scope of work.

38. Drawing ED101 shows the EC to demolish the generator underground fuel tank. Please clarify that this should be by the Mechanical Contractor.

The underground fuel tank shall be abandoned in place. See General Sheet Note 3 on GC101 for further information.

39. Please clarify what the EC is to do with the outdoor transformer being removed?

Contractor is responsible for removal disposal of demolished equipment.

40. Please clarify what the EC is to do with the existing generator being removed?

Contractor is responsible for removal disposal of demolished equipment.

41. Is a Field office trailer required? Electrical service and connection? 010000-1.17 Says the following: RESIDENT ENGINEER'S FIELD OFFICE the COR. Office and furniture shall be new.

Field office for the COR is not required.

42. Could the fire alarm specs be provided please.

Fire alarm scope is limited to wiring new gas monitor system and tamper and flow switches to existing fire alarm control panel. All fire alarm devices are existing to remain.

43. Who is the buildings fire alarm manufacture?

Existing fire alarm control panel in building is a GE (Edwards) type

EST 3.

44. Could the following be addressed please: Provide manufacture information on existing panels, and pictures to address E002-note 27 and to provide new breakers (E701). Existing panels L&M modified as part of this project. EC must test breakers and replace non-working CB's, provide blanks.

The only new circuit breaker shown in an existing panel is within Panel M. Panel M is an old Square D model. Contractor shall field verify existing conditions.

45. Does the owner want the removed generator and associated equipment-ED101-note #4?

No, the VA does not want the generator or associated equipment.

Drawing ED101 does not have a note 4. Keynote 3 requires the contractor to remove the generator.

46. Removal of pad oil filled transformer-Is this considered hazardous/PCB?

This is a standard oil filled transformer replacement. Oil shall be drained and properly disposed. There is no evidence of PCBs within the transformer and its age does not point to their presence.

47. Does the owner want the removed pad mount transformer?

yes, turn the transformer over to the VA when removed from pad.

48. Please provide a specification section for the permanent 350KW generators sound attenuated enclosure.

Specification 263213 Engine Generators is included in the package.

The generator is interior to the building and therefore does not require a sound attenuated enclosure.

49. Do the VA Standards established by the Office of Construction & Facilities Management MASTER CONSTRUCTION SPECIFICATIONS as to Contract Design & Specifications take precedence over specific Project.

No.

50. Drawing EP102 detail 1 for electrical power on the lower-level pump area shows two disconnects on the bottom right corner of the room for equipment 10-CP-1 & 10-CP-2. Drawing E-701 electrical connection schedule does not show this equipment on the schedule nor is this equipment shown on any of the equipment schedules.

Please clarify where this equipment is being fed from and what size conduit and wire is required.

The pump disconnects tags that are being questioned on drawing EP102 were previously revised. The disconnects shown are for the condensate transfer pumps 10-CTP-1 & 10-CTP-2.

51. The Mechanical Drawings that are posted on Sam.gov are scanned in as 8 ½” x 11”. Can these drawings be provided in Full Size as soon as possible so we can review before the RFI cutoff date.

A new set of drawings and specifications is attached for the project. Proceed using only the drawings and specifications provided in this amendment.

See attached document: Lebanon Boiler_Bid Specs_Vol I.

See attached document: Lebanon Boiler_Bid Specs_Vol II.

See attached document: 2021-03-26 Bid Documents - Drawing PDFs 00_General Information.

See attached document: 2021-03-26 Bid Documents - Drawing PDFs 01_Civil.

See attached document: 2021-03-26 Bid Documents - Drawing PDFs 02_Structural.

See attached document: 2021-03-26 Bid Documents - Drawing PDFs 02a_Fire Protection.

See attached document: 2021-03-26 Bid Documents - Drawing PDFs 03_Plumbing.

See attached document: 2021-03-26 Bid Documents - Drawing PDFs 03a_Life Safety.

See attached document: 2021-03-26 Bid Documents - Drawing PDFs 04_Mechanical.

See attached document: 2021-03-26 Bid Documents - Drawing PDFs 05_Electrical.

See attached document: Asbestos Report - Building 10.