Memo Chiller Plant Questions_HDG Responses.pdf

PDF 151 KB Posted

Attached to
Y1DZ--Chiller Plant construction-Erie VAMC Project Number 562-14-115
Solicitation number
36C24420R0052
Issued by

About this file

This document contains responses to bidder questions regarding a federal solicitation for the construction of a Chiller Plant for the Erie VA Medical Center. The scope of work involves providing all labor, materials, equipment, permits, testing and reports to construct a new Chiller Plant in accordance with plans and specifications. The estimated value of the project is between $5 million to $10 million, with a 365-day period of performance from notice to proceed. The solicitation will be set aside exclusively for Service-Disabled Veteran Owned Small Businesses. Responses address bidder inquiries about specifications, schedules, hazardous materials handling, utility shutdown coordination, and clarifications to drawings.

View the file

Other files

File Type Posted
36C24420R0052 0009.docx DOCX document
General Decision Number- PA20200088 08-21-2020.docx DOCX document
36C24420R0052 0008.docx DOCX document
SCHEDULE 01-Add Alternates -2.docx DOCX document
Erie Chiller Amendment 08 200917.pdf PDF
MD102.pdf PDF
AE201.pdf PDF
AE101.pdf PDF
36C24420R0052 0007.docx DOCX document
AD101.pdf PDF
AE301.pdf PDF
AD200.pdf PDF
GI001.pdf PDF
AD102.pdf PDF
088000 ADD ALTERNATE 1r1.docx DOCX document
AE102.pdf PDF
SCHEDULE 01-Add Alternate.docx DOCX document
36C24420R0052 0006.docx DOCX document
Erie Chiller - Amendment 06.zip ZIP file
36C24420R0052 0005.docx DOCX document
36C24420R0052 0004.docx DOCX document
S02 36C24420R0052 0003.docx DOCX document
Drawing-GS001.pdf PDF
36C24420R0052 0002.docx DOCX document
Sign-in sheet Pre-Proposal meeting held 6-30-2020.pdf PDF
S06 36C24420R0052 0001.docx DOCX document
S02 Erie Chiller CD 8 Final Documents Submission Drawings 190808-3-61-80.pdf PDF
EXHIBIT B - Subcontractor Information and Consent Form 36C24420R0052.docx DOCX document
Erie Chiller CD 8 Final Documents Submission Specifications 190808.pdf PDF
S02 Erie Chiller CD 8 Final Documents Submission Drawings 190808-2 Pages 41-60.pdf PDF
S02 36C24420R0052-Posted 6-22-2020.docx DOCX document
S02 Erie Chiller CD 8 Final Documents Submission Drawings 190808-1 Pages 1-40.pdf PDF
EXHIBIT A - Past Performance Relevancy Questionnaire 36C24420R0052.docx DOCX document
EXHIBIT C - Calculation of Self-Performed Work 36C24420R0052 3-16-20.docx DOCX document
EXHIBIT D - Sample Transmittal Letter for Past Performance Evaluation Questionnaire 36C24420R0052.docx DOCX document
S02 Erie Chiller CD 8 Final Documents Submission Drawings 190808-4-81-135.pdf PDF
EXHIBIT E - Past Performance Questionnaire 36C24420R0052.docx DOCX document
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Owner Bid Questions

VA Bid Questions:

1. The purpose of this memo is to respond to questions from the Bidders on the above mentioned Project.

VA Comment: HDG Response:

Question #1: Add VA comment – Add “Superintendent cannot be changed out without 30-days written notice and approval from the Government.”

Question #4: The Government’s current chemical supplier is MIS-America; however, the current contract has no provisions to include the Cooling Towers and will ultimately need to be re-solicited. Bidders are advised to use whichever Vendor they are comfortable with.

Question #6: Does this address their comment about condensation developing in the tri-layer system shown?

Question #19: Evaluation Factor #2: References to Patient Aligned Care Team (PACT) have been changed to utility plant.

Question #20: Glycol Tie-in Procedure: Question is confusing – there are no existing chilled water systems that we are connecting to. Contractor shall provide adequate glycol to system such that system is prevented from freezing down to -20°F.

Question #23: Do Details B1/ MP501 and B2/MP502 apply to the hallway? Should this be noted?

See Spec 230541 Noise and Vibration Control for HVAC Piping and Equipment. Piping in hallway shall be per detail B4/MP501.

Question #25: Evaluation Factor #2: No. CPARS evaluations cannot be submitted in lieu of Past Performance Evaluation Questionnaire.

Question #26: Yes, refer to attached Worksheet and Photos of Existing Conditions Sk0808 attached.

SK-0808 labeled SK-0810

Question #27: Yes, refer to the attached asbestos report dated 12/6/2010 for reference.

Question #28: Refer to the attached asbestos report dated 12/6/2010 for reference.

Owner: Erie VA Medical Center

Project Title: Construct New Chiller Plant

Owner Contract/Project No.: 562-14-115

HDG Project No.: 14016

Submission Title: Owner Bid Questions

Date Submitted: August 14, 2020

VA Comments Due:

Question #29: Hazardous Materials Report for Building #1: Provided for reference only.

Question #30: This doesn’t answer the question. 09 05

Question #62: It is up to the Contractor’s discretion as to who JCI is assigned to.

Question #63: The current access control system is Lenel by Stanley Access Technologies.

Questions #64, 68 & 69: The cabling shall be run from the access control, camera, data and voice devices to the data closet located in room 107B-7 (inside the Grounds Shop).

Question #65: Security camera shall be Vigilant Cameras.

Question #70: Contractors should assume that new rack space will be required enough to support all equipment and devices in this Project.

Question #121 & 122: The exact procedure is a “means & methods” item; however, Contractor’s shall provide enough lead time to coordinate with the Facility. Refer to attached Outage Request Form.

Question #123: No Contractor will be allowed to energize or de-energize any utility on VA property. All shutdowns will be required to be coordinated thru the COR.

Question #124: No regular total steam shutdowns occur;

however, on can be scheduled.

Question #125: Hot taps are not permitted for any utility for any reason within the VA. A total steam shut down is possible and if no alternative is found, can be scheduled with appropriate lead time and coordination. Again, refer to attached Outage Request Memo Template.

Hot taps have been removed from the following Drawings GI003/4. VA also responded.

Question #126: Shiftwork and weekend work are to be anticipated.

2. In addition to the questions that have been presented by the bidders, there are still a few things that are open on our end that affect the Chiller Project.

VA Comment: HDG Response:

Winter conditions are to be anticipated. Government will not consider a shutdown of the Project for the winter.

Please see added note on GI001 Cover Sheet, under heading “Contractor Notes.”

Add Onyx Workstation for Fire Alarm System at Room 7- 108 (Electrician’s Shop).

Please see added note 13 on AE101.

Refer to relocated control compressor sketch (SK-0810) dated 11 August, 2020.

Please see added note on GI001 Cover Sheet, under heading “Contractor Notes.”

The Project that will relocate the surge tank has been delayed and will likely not be bid until Chiller Project is underway. This Contractor will have to maintain tank and pumps as shown on the plans until the other Contract can be awarded. That Project will advise the Bidders that they will be required to coordinate all work with this Contractor.

Please see added note on GI001 Cover Sheet, under heading “Contractor Notes.”

a. Sheet AD101 – Please see modified notes 3, 5, and 8 on sheet AD101.

i. Keynote #3. This work will be performed by the Owner as part of a separate Project prior to the Chiller Plant Project.

ii. Keynote #5. Remove existing concrete pads complete.

iii. Keynote #8. The Air Dryer will be relocated prior to the Chiller Plant Project.

Sheet AD102 – Remove and replace western Kalwall System in Detail #1; HDG: Consider keeping some of the mezzanines to maintain access to the storage space above the offices as well as next to the Northern stair tower.

As discussed on 09/02/2020, the mezzanine needs to be removed to allow for the chillers and related piping.

Kalwall replacement is Alternate 1.

Detail D1/ Sheet AD200 – Add Keynote #2 to replace the existing Kalwall Window System.

Kalwall replacement is Alternate 1.

Sheet AE101 – Keynote #8: Refer to VA Sketch Sk-0810 dated 11 August, 2020 for revisions to controls compressors and supporting equipment.

Please see revision to Note 8 on Drawing AE101.

Sheet AE 102 – Replace existing Kalwall Window System.

Show the existing Gas Train.

Kalwall replacement is Alternate 1. Gas Train is now shown.

Sheet AE 105 – HDG: not crazy about Keynote #11. Can’t we keep part of the mezzanine so we can maintain access to this room?

As discussed on 09/02/2020, the mezzanine needs to be removed to allow for the chillers and related piping.

Sheet AE 201 – Where the generator exhaust stacks (note

13) and the remote radiators (note 11) removed? Also, what about the exhaust fans (note 12) associated with the former generators.

Removed non-relevant work from AE201. These stacks and radiators were deleted from scope.

Sheets PD101, PD103, PL102, PP101, MD101 & MP101 – Refer to VA Sketch Sk-0810 dated 11. August, 2020 for revisions to controls compressors and supporting equipment.

Added note to refer to new air compressor form sketch drawings.

Sheet MD-102. Abandoned Gas Meter shown has already been removed.

Demo back to pipe coming out of ground as shown.

HDG: We had reviewed an alternate pipe route at the one meeting, but it we have never seen sheets to reflect.

Is this other route still an option?

The current drawings reflect the best possible pipe routing, which was modified per the August 2019 site visit.

File details come from the government source that posted it. Updated .