This document contains responses to bidder questions regarding a federal solicitation for the construction of a Chiller Plant for the Erie VA Medical Center. The scope of work involves providing all labor, materials, equipment, permits, testing and reports to construct a new Chiller Plant in accordance with plans and specifications. The estimated value of the project is between $5 million to $10 million, with a 365-day period of performance from notice to proceed. The solicitation will be set aside exclusively for Service-Disabled Veteran Owned Small Businesses. Responses address bidder inquiries about specifications, schedules, hazardous materials handling, utility shutdown coordination, and clarifications to drawings.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Owner Bid Questions
VA Bid Questions:
1. The purpose of this memo is to respond to questions from the Bidders on the above mentioned Project.
VA Comment: HDG Response:
Question #1: Add VA comment – Add “Superintendent cannot be changed out without 30-days written notice and approval from the Government.”
Question #4: The Government’s current chemical supplier is MIS-America; however, the current contract has no provisions to include the Cooling Towers and will ultimately need to be re-solicited. Bidders are advised to use whichever Vendor they are comfortable with.
Question #6: Does this address their comment about condensation developing in the tri-layer system shown?
Question #19: Evaluation Factor #2: References to Patient Aligned Care Team (PACT) have been changed to utility plant.
Question #20: Glycol Tie-in Procedure: Question is confusing – there are no existing chilled water systems that we are connecting to. Contractor shall provide adequate glycol to system such that system is prevented from freezing down to -20°F.
Question #23: Do Details B1/ MP501 and B2/MP502 apply to the hallway? Should this be noted?
See Spec 230541 Noise and Vibration Control for HVAC Piping and Equipment. Piping in hallway shall be per detail B4/MP501.
Question #25: Evaluation Factor #2: No. CPARS evaluations cannot be submitted in lieu of Past Performance Evaluation Questionnaire.
Question #26: Yes, refer to attached Worksheet and Photos of Existing Conditions Sk0808 attached.
SK-0808 labeled SK-0810
Question #27: Yes, refer to the attached asbestos report dated 12/6/2010 for reference.
Question #28: Refer to the attached asbestos report dated 12/6/2010 for reference.
Owner: Erie VA Medical Center
Project Title: Construct New Chiller Plant
Owner Contract/Project No.: 562-14-115
HDG Project No.: 14016
Submission Title: Owner Bid Questions
Date Submitted: August 14, 2020
VA Comments Due:
Question #29: Hazardous Materials Report for Building #1: Provided for reference only.
Question #30: This doesn’t answer the question. 09 05
Question #62: It is up to the Contractor’s discretion as to who JCI is assigned to.
Question #63: The current access control system is Lenel by Stanley Access Technologies.
Questions #64, 68 & 69: The cabling shall be run from the access control, camera, data and voice devices to the data closet located in room 107B-7 (inside the Grounds Shop).
Question #65: Security camera shall be Vigilant Cameras.
Question #70: Contractors should assume that new rack space will be required enough to support all equipment and devices in this Project.
Question #121 & 122: The exact procedure is a “means & methods” item; however, Contractor’s shall provide enough lead time to coordinate with the Facility. Refer to attached Outage Request Form.
Question #123: No Contractor will be allowed to energize or de-energize any utility on VA property. All shutdowns will be required to be coordinated thru the COR.
Question #124: No regular total steam shutdowns occur;
however, on can be scheduled.
Question #125: Hot taps are not permitted for any utility for any reason within the VA. A total steam shut down is possible and if no alternative is found, can be scheduled with appropriate lead time and coordination. Again, refer to attached Outage Request Memo Template.
Hot taps have been removed from the following Drawings GI003/4. VA also responded.
Question #126: Shiftwork and weekend work are to be anticipated.
2. In addition to the questions that have been presented by the bidders, there are still a few things that are open on our end that affect the Chiller Project.
VA Comment: HDG Response:
Winter conditions are to be anticipated. Government will not consider a shutdown of the Project for the winter.
Please see added note on GI001 Cover Sheet, under heading “Contractor Notes.”
Add Onyx Workstation for Fire Alarm System at Room 7- 108 (Electrician’s Shop).
Please see added note 13 on AE101.
Refer to relocated control compressor sketch (SK-0810) dated 11 August, 2020.
Please see added note on GI001 Cover Sheet, under heading “Contractor Notes.”
The Project that will relocate the surge tank has been delayed and will likely not be bid until Chiller Project is underway. This Contractor will have to maintain tank and pumps as shown on the plans until the other Contract can be awarded. That Project will advise the Bidders that they will be required to coordinate all work with this Contractor.
Please see added note on GI001 Cover Sheet, under heading “Contractor Notes.”
a. Sheet AD101 – Please see modified notes 3, 5, and 8 on sheet AD101.
i. Keynote #3. This work will be performed by the Owner as part of a separate Project prior to the Chiller Plant Project.
ii. Keynote #5. Remove existing concrete pads complete.
iii. Keynote #8. The Air Dryer will be relocated prior to the Chiller Plant Project.
Sheet AD102 – Remove and replace western Kalwall System in Detail #1; HDG: Consider keeping some of the mezzanines to maintain access to the storage space above the offices as well as next to the Northern stair tower.
As discussed on 09/02/2020, the mezzanine needs to be removed to allow for the chillers and related piping.
Kalwall replacement is Alternate 1.
Detail D1/ Sheet AD200 – Add Keynote #2 to replace the existing Kalwall Window System.
Kalwall replacement is Alternate 1.
Sheet AE101 – Keynote #8: Refer to VA Sketch Sk-0810 dated 11 August, 2020 for revisions to controls compressors and supporting equipment.
Please see revision to Note 8 on Drawing AE101.
Sheet AE 102 – Replace existing Kalwall Window System.
Show the existing Gas Train.
Kalwall replacement is Alternate 1. Gas Train is now shown.
Sheet AE 105 – HDG: not crazy about Keynote #11. Can’t we keep part of the mezzanine so we can maintain access to this room?
As discussed on 09/02/2020, the mezzanine needs to be removed to allow for the chillers and related piping.
Sheet AE 201 – Where the generator exhaust stacks (note
13) and the remote radiators (note 11) removed? Also, what about the exhaust fans (note 12) associated with the former generators.
Removed non-relevant work from AE201. These stacks and radiators were deleted from scope.
Sheets PD101, PD103, PL102, PP101, MD101 & MP101 – Refer to VA Sketch Sk-0810 dated 11. August, 2020 for revisions to controls compressors and supporting equipment.
Added note to refer to new air compressor form sketch drawings.
Sheet MD-102. Abandoned Gas Meter shown has already been removed.
Demo back to pipe coming out of ground as shown.
HDG: We had reviewed an alternate pipe route at the one meeting, but it we have never seen sheets to reflect.
Is this other route still an option?
The current drawings reflect the best possible pipe routing, which was modified per the August 2019 site visit.