This file contains specifications for a fiberglass insulated translucent sandwich panel wall system with enhanced protection for a federal construction project, as well as details for a related federal contract opportunity to construct a chiller plant at the Erie VA Medical Center.

The specifications cover flat prefabricated structural insulated translucent sandwich panels with a minimum 4-inch thickness and thermally broken aluminum frame. Performance requirements include missile impact resistance per ASTM E1996, a maximum air leakage of 0.01 cfm/ft2, and maintaining a visible clarity of bullet-resistant materials for 10 years. The contractor shall provide all labor, materials, equipment and testing to install the wall system in accordance with the specifications, shop drawings and federal, state and local codes.

The related federal contract opportunity is a 100% SDVOSB set-aside to construct a chiller plant for the Erie VAMC with an estimated value between $5-10 million. The period of performance is 365 calendar days from notice to proceed. The NAICS code is 236220 for commercial and institutional building construction.

View the file

Other files

File Type Posted
36C24420R0052 0009.docx DOCX document
General Decision Number- PA20200088 08-21-2020.docx DOCX document
36C24420R0052 0008.docx DOCX document
SCHEDULE 01-Add Alternates -2.docx DOCX document
Erie Chiller Amendment 08 200917.pdf PDF
MD102.pdf PDF
AE201.pdf PDF
AE101.pdf PDF
Memo Chiller Plant Questions_HDG Responses.pdf PDF
36C24420R0052 0007.docx DOCX document
AD101.pdf PDF
AE301.pdf PDF
AD200.pdf PDF
GI001.pdf PDF
AD102.pdf PDF
AE102.pdf PDF
SCHEDULE 01-Add Alternate.docx DOCX document
36C24420R0052 0006.docx DOCX document
Erie Chiller - Amendment 06.zip ZIP file
36C24420R0052 0005.docx DOCX document
36C24420R0052 0004.docx DOCX document
S02 36C24420R0052 0003.docx DOCX document
Drawing-GS001.pdf PDF
36C24420R0052 0002.docx DOCX document
Sign-in sheet Pre-Proposal meeting held 6-30-2020.pdf PDF
S06 36C24420R0052 0001.docx DOCX document
S02 Erie Chiller CD 8 Final Documents Submission Drawings 190808-3-61-80.pdf PDF
EXHIBIT B - Subcontractor Information and Consent Form 36C24420R0052.docx DOCX document
Erie Chiller CD 8 Final Documents Submission Specifications 190808.pdf PDF
S02 Erie Chiller CD 8 Final Documents Submission Drawings 190808-2 Pages 41-60.pdf PDF
S02 36C24420R0052-Posted 6-22-2020.docx DOCX document
S02 Erie Chiller CD 8 Final Documents Submission Drawings 190808-1 Pages 1-40.pdf PDF
EXHIBIT A - Past Performance Relevancy Questionnaire 36C24420R0052.docx DOCX document
EXHIBIT C - Calculation of Self-Performed Work 36C24420R0052 3-16-20.docx DOCX document
EXHIBIT D - Sample Transmittal Letter for Past Performance Evaluation Questionnaire 36C24420R0052.docx DOCX document
S02 Erie Chiller CD 8 Final Documents Submission Drawings 190808-4-81-135.pdf PDF
EXHIBIT E - Past Performance Questionnaire 36C24420R0052.docx DOCX document
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

10-01-15

SECTION 08 80 00

insulated translucent fiberglass Sandwich panel wall system with enhanced protection: Add ALTERNATE 1

PART 1 - GENERAL

1.1 DESCRIPTION:

A. Section includes the insulated translucent sandwich panel system and accessories as shown and specified. Work includes providing and installing:

1. Flat factory prefabricated structural insulated translucent sandwich panels.

2.Aluminum installation system.
3.Aluminum sill flashing.

B. The basis of design for this specification is for products manufactured by Kalwall Corporation. Model is 4” Insulated Translucent Fiberglass Sandwich Panel Wall System for Windborne Debris Resistance (Enhanced Protection) in Thermally Broken Frame.

C. Kalwall Corporation, Tel: (800) 258-9777 – Fax: (603) 627-7905 – Email: info@kalwall.com

1.2 RELATED WORK:

A. Section 07 92 00, Joint Sealants.

B. Section 07 60 00, Flashing and Sheet Metal.

C. Section 07 84 00, Firestopping.

1.3 LABELS:

A.Temporary labels:
1.Provide temporary label on each light of plastic material identifying manufacturer or brand and glass type, quality and nominal thickness.
2.Label in accordance with NFRC label requirements.
3.Temporary labels are to remain intact until plastic material is approved by Contracting Officer Representative (COR).
B.Permanent labels:
1.Locate in corner for each pane.
2.Bullet resistance plastic assemblies:
a.Bullet resistance glass or plastic assemblies in accordance with UL 752 requirements for power rating specified.
b.Identify each security glazing permanently with glazing manufacturer's name, date of manufacture, product number, and DOS Code number inconspicuously located in lower corner on protective side and visible after glazing is framed.
c.The "attack (threat) side" is to be identified in bold lettering on each side of glazing with removable label.

1.4 PERFORMANCE REQUIREMENTS:

A.General: Design glazing system consistent with guidance and practices presented in the GANA Glazing Manual, GANA Laminated Glazing Manual, and GANA Sealant Manual, as applicable to project. Installed glazing is to withstand applied loads, thermal stresses, thermal movements, building movements, permitted tolerances, and combinations of these conditions without failure, including loss or glass breakage attributable to defective manufacture, fabrication, or installation; failure of sealants or gaskets to remain watertight and airtight; deterioration of glazing materials; unsafe engagement of the framing system; deflections beyond specified limits; or other defects in construction.
B.Glazing Unit Design: Design glass, including engineering analysis meeting requirements of authorities having jurisdiction. Thicknesses listed are minimum. Coordinate thicknesses with framing system manufacturers.
1.Design glass in accordance with ASTM E1300, and for conditions beyond the scope of ASTM E1300, by a properly substantiated structural analysis.
2.Design Wind Pressures: In accordance with ASCE 7-10 and in accordance with applicable code.
3.Wind Design Data: As indicated on construction documents.
4.Maximum Lateral Deflection: For glass supported on all four edges, limit center-of-glass deflection at design wind pressure to not more than the structural capacity of the glazing unit, the threshold at which frame engagement is no longer safely assured, 1/100 times the short-side length, or 19 mm (0.75 inch), whichever is less.
C.Ballistic- and Blast- resistant glass or plastic glazing assemblies:
1.For blast-resistant and ballistic-resistant units comply with requirements in UFC 4-010-01, Physical Security Design Manual for VA Facilities, and project-specific criteria provided by VA.
2.Spall Resistance: Laminated glazing is not permitted to produce spall to interior (protected side) when impacted with scheduled ballistics.
3.Tolerances:
a.Outside dimensions: Overall outside dimensions (height and width) of laminated security glazing is to maintain tolerance of 3 mm (+ 0.12 inch).
b.Warpage: Out-of-flat (warpage or bowing) condition of laminates is not to exceed 2.5 mm per lineal meter (0.10 inch per 3.3 lineal foot). The condition, if present, is to be localized to extent not greater than 0.75 mm (0.03 inch) for any 0.3 meter (0.98 feet) section.
E.Building Enclosure Vapor Retarder and Air Barrier:
1.Utilize the inner pane of multiple pane sealed units for the continuity of the air barrier and vapor retarder seal.
2.Maintain a continuous air barrier and vapor retarder throughout the glazed assembly from glass pane to heel bead of glazing sealant.

1.5 SUBMITTALS:

A. In accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

B. Submit manufacturer’s product data. Include construction details, material descriptions, profiles and finishes of components.

C.Submit shop drawings. Include elevations and details
D.Submit manufacturer's color charts showing the full range of colors available for factory-finished aluminum.
1.When requested, submit samples for each exposed finish required, in same thickness and material indicated for the work and in size indicated below. If finishes involve normal color variations, include sample sets consisting of two or more units showing the full range of variations expected.
a.Sandwich panels: 14” x 28” units
b.Factory finished aluminum: 5” long sections

E. Submit Installer Certificate, signed by installer, certifying compliance with project qualification requirements.

F. Submit product reports from a qualified independent testing agency indicating each type and class of panel system complies with the project performance requirements, based on comprehensive testing of current products. Previously completed reports will be acceptable if for current manufacturer and indicative of products used on this project.

1. Reports required are:

a.International Building Code Evaluation Report
b.Flame Spread and Smoke Developed (UL 723) – Submit UL Card
c.Burn Extent (ASTM D 635)
d.Color Difference (ASTM D 2244)
e.Impact Strength (UL 972)
f.Bond Tensile Strength (ASTM C 297 after aging by ASTM D 1037)
g.Bond Shear Strength (ASTM D 1002)
h.Beam Bending Strength (ASTM E 72)
i.Insulation U-Factor (NFRC 100)
j.NFRC System U-Factor Certification (NFRC 700)
k.Solar Heat Gain Coefficient (NFRC or Calculations)
l.Condensation Resistance Factor (AAMA 1503)
m.Air Leakage (ASTM E 283)
n.Structural Performance (ASTM E 330)
o.Water Penetration (ASTM E 331)
p.1200°F Fire Resistance (SWRI)
q.ASTM E1886/1996 or TAS 201, 202 and 203

1.6 DELIVERY, STORAGE AND HANDLING:

A.Delivery: Schedule delivery to coincide with glazing schedules so minimum handling of crates is required. Do not open crates except as required for inspection for shipping damage.
B.Storage: Store cases according to printed instructions on case, in areas least subject to traffic or falling objects. Keep storage area clean and dry. Store panels on the long edge; several inches above the ground, blocked and under cover in accordance with manufacturer's storage and handling instructions.
C.Handling: Unpack cases following printed instructions on case. Stack individual windows on edge leaned slightly against upright supports with separators between each.
D.Protect laminated security glazing units against face and edge damage during entire sequence of fabrication, handling, and delivery to installation location. Provide protective covering on exposed faces of glazing plastics, and mark inside as "INTERIOR FACE" or "PROTECTED FACE":
1.Treat security glazing as fragile merchandise, and packaged and shipped in export wood cases with width end in upright position and blocked together in a mass. Storage and handling to comply with manufacturer's directions and as required to prevent edge damage or other damage to glazing resulting from effects of moisture, condensation, temperature changes, direct exposure to sun, other environmental conditions, and contact with chemical solvents.
2.Protect sealed-air-space insulating glazing units from exposure to abnormal pressure changes, as could result from substantial changes in altitude during delivery by air freight. Provide temporary breather tubes which do not nullify applicable warranties on hermetic seals.
3.Temporary protections: The glass front and polycarbonate back of glazing are to be temporarily protected with compatible, peelable, heat-resistant film which will be peeled for inspections and reapplied and finally removed after doors and windows are installed at destination. Since many adhesives will attack polycarbonate, the film used on exposed polycarbonate surfaces is to be approved and applied by manufacturer.
4.Edge protection: To cushion and protect glass clad, and polycarbonate edges from contamination or foreign matter, the four (4) edges are to be sealed the depth of glazing with continuous standardthickness thermoplastic rubber tape. Alternatively, continuous channel shaped extrusion of thermoplastic rubber are to be used, with flanges extending into face sides of glazing.
5.Protect "Constant Temperature" units including every unit where glass sheet is directly laminated to or directly sealed with metaltube type spacer bar to polycarbonate sheet, from exposures to ambient temperatures outside the range of 16 to 24 degrees C (60 to 75 degrees F), during the fabricating, handling, shipping, storing, installation, and subsequent protection of glazing.

1.7 PROJECT CONDITIONS:

Field Measurements: Field measure openings before ordering tempered glass products to assure for proper fit of field measured products.

1.8 warranty:

A. Construction Warranty: Comply with the FAR clause 52.24621 “Warranty of Construction”.

B. Manufacturer Warranty: Manufacturer shall warranty their glazing from the date of installation and final acceptance by the Government as follows. Submit manufacturer warranty.

1.Bullet resistive plastic material to remain visibly clear without discoloration for 10 years.
2.Polycarbonate to remain clear and ultraviolet light stabilized for five (5) years.
3.Insulating plastic to not have more than 6 percent decrease in light transmission and be ultraviolet light stabilized for ten (10) years.

1.9 APPLICABLE PUBLICATIONS:

A. Publications listed below form a part of this specification to extent referenced. Publications are referenced in text by basic designation only.

B. American Architectural Manufacturers Association (AAMA):

800Test Methods for Sealants
810.1-77Expanded Cellular Glazing Tape
C.American National Standards Institute (ANSI):
Z97.1-14Safety Glazing Material Used in Building Safety Performance Specifications and Methods of Test
D.American Society of Civil Engineers (ASCE):
7-10Wind Load Provisions
E.ASTM International (ASTM):
C542-05(R2011)Lock-Strip Gaskets
C716-06Installing Lock-Strip Gaskets and Infill Glazing Materials
C794-10Adhesion-in-Peel of Elastomeric Joint Sealants
C864-05(R2011)Dense Elastomeric Compression Seal Gaskets, Setting Blocks, and Spacers
C920-14aElastomeric Joint Sealants
C964-07(R2012)Standard Guide for Lock-Strip Gasket Glazing
C1349-10Standard Specification for Architectural Flat Glass Clad Polycarbonate
D635-10Rate of Burning and/or Extent and Time of Burning of Self-Supporting Plastic in a Horizontal Position
D4802-10Poly (Methyl Methacrylate) Acrylic Plastic Sheet
E84-14Surface Burning Characteristics of Building Materials
E119-14Standard Test Methods for Fire Test of Building Construction and Material
E1886-13aStandard Test Method for Performance of Exterior Windows, Curtain Walls, Doors, and Impact Protective Systems Impacted by Missile(s) and Exposed to Cyclic Pressure Differentials
E1996-14aStandard Specification for Performance of Exterior Windows, Curtain Walls, Doors, and Impact Protective Systems Impacted by Windborne Debris in Hurricanes
E2190-10Insulating Glass Unit
F1233-08Standard Test Method for Security Glazing Materials and Systems
F1642-12Test Method for Glazing and Glazing Systems Subject to Airblast Loadings
E.Code of Federal Regulations (CFR):
16 CFR 1201-10Safety Standard for Architectural Glazing Materials
F.Glass Association of North America (GANA):
2010 EditionGANA Glazing Manual
2008 EditionGANA Sealant Manual
2009 EditionGANA Laminated Glazing Reference Manual
2010 EditionGANA Protective Glazing Reference Manual
G.International Code Council (ICC):
IBCInternational Building Code

H. Insulating Glass Certification Council (IGCC) I. Insulating Glass Manufacturer Alliance (IGMA):

TB-3001-13Guidelines for Sloped Glazing
TM-3000North American Glazing Guidelines for Sealed Insulating Glass Units for Commercial and Residential Use

J. Intertek Testing Services – Warnock Hersey (ITS-WHI) K. National Fire Protection Association (NFPA):

80-16Fire Doors and Windows
252-12Fire Tests of Door Assemblies
257-12Standard on Fire Test for Window and Glass Block Assemblies
L.National Fenestration Rating Council (NFRC)
M.Safety Glazing Certification Council (SGCC) 2012:
Certified Products Directory (Issued Semi-Annually).
N.Underwriters Laboratories, Inc. (UL):
9-08(R2009)Fire Tests of Window Assemblies
263-14Fire Tests of Building Construction and Materials
752-11Bullet-Resisting Equipment.
O.Unified Facilities Criteria (UFC):
4-010-01-03(R2007)DOD Minimum Antiterrorism Standards for Buildings
P.U.S. Veterans Administration:
Physical Security Design Manual for VA Facilities (VAPSDG); Life Safety Protected
Physical Security Design Manual for VA Facilities (VAPSDG); Mission Critical Facilities
Architectural Design Manual for VA Facilities (VASDM)

Q. Environmental Protection Agency (EPA):

40 CFR 59(2014) National Volatile Organic Compound Emission Standards for Consumer and Commercial Products

1.10 quality assurance:

A.Manufacturer's Qualifications
1.Material and products shall be manufactured by a company continuously and regularly employed in the manufacture of specified materials for a period of at least ten consecutive years and which can show evidence of those materials being satisfactorily used on at least six projects of similar size, scope and location. At least three of the projects shall have been in successful use for ten years or longer.
2.Panel system must be listed by an ANSI accredited Evaluation Service, which requires quality control inspections and fire, structural and water infiltration testing of sandwich panel systems by an accredited agency.
3.Quality control inspections shall be conducted at least once each year and shall include manufacturing facilities, sandwich panel components and production sandwich panels for conformance with AC177 “Translucent Fiberglass Reinforced Plastic (FRP) Faced Panel Wall, Roof and Skylight Systems” as issued by the ICC-ES.

B. Installer’s Qualifications: Installation shall be by an experienced installer, which has been in the business of installing specified panel systems for at least two consecutive years and can show evidence of satisfactory completion of projects of similar size, scope and type.

1.11 performance requirements:

A. The manufacturer shall be responsible for the configuration and fabrication of the complete panel system.

1.Include structural analysis data signed and sealed by the qualified professional engineer responsible for their preparation.
2.Standard panel system shall have less than 0.01 cfm/ft² air leakage by ASTM E 283 at 6.24 PSF (50 mph) and no water penetration by ASTM E 331 at 15 PSF; and structural testing by ASTM E 330.
3.Structural Loads; Provide system capable of handling the following loads:
a.Positive Wind Load: 120 PSF
b.Negative Wind Load: 120 PSF

B. Impact Resistance Performance

1.Translucent panels must be impact-resistant meeting the requirements of an approved impact-resisting standard: ASTM E 1996 and ASTM E 1886 or TAS 201, 202 and 203.
2.Panel System designed to meet Missile Impact Requirements for Enhanced Protection “D” per ASTM E 1996.

PART 2 - PRODUCT

2.1 panel components:

A.Face Sheets
1.Translucent faces: Manufactured from glass fiber reinforced thermoset resins, formulated specifically for architectural use.
a.Thermoplastic (e.g. polycarbonate, acrylic) faces are not acceptable.
b.Face sheets shall not deform, deflect or drip when subjected to fire or flame.
2.Interior face sheets:
a.Flame spread: Underwriters Laboratories (UL) listed, which requires periodic unannounced retesting, with flame spread rating no greater than 50 and smoke developed no greater than 250 when tested in accordance with UL 723.
b.Burn extent by ASTM D 635 shall be no greater than 1”.
3.Exterior face sheets:
a.Color stability: Full thickness of the exterior face sheet shall not change color more than 3 CIE Units DELTA E by ASTM D 2244 after 5 years outdoor South Florida weathering at 5° facing south, determined by the average of at least three white samples with and without a protective film or coating to ensure long-term color stability. Color stability shall be unaffected by abrasion or scratching.
b.Strength: Exterior face sheet shall be uniform in strength, with panel meeting ASTM E1996 and ASTM E1886 or TAS 201, 202 and 203.
4.Appearance:
a.Exterior face sheets: Smooth .052” thick and white in color.
b.Interior face sheets: Smooth .052” thick and white in color.
c.Face sheets shall not vary more than ± 10% in thickness and be uniform in color.
B.Grid Core
1.Thermally broken composite I-beam grid core shall be of 6005-T5 alloy and temper with provisions for mechanical interlocking of muntin-mullion and perimeter. Width of I-beam shall be no less than 7/16”.
2.I-beam Thermal break: Minimum 2”, thermoset fiberglass composite.

C. Laminate Adhesive:

1. Thermally broken composite I-beam grid core shall be of 6005-T5 alloy and temper with provisions for mechanical interlocking of muntin-mullion and perimeter. Width of I-beam shall be no less than 7/16”. I-beam Thermal break: Minimum 2”, thermoset fiberglass composite.

2.2 panel construction:

A.Provide sandwich panels of flat fiberglass reinforced translucent face sheets laminated to a grid core of mechanically interlocking I-beams. The adhesive bonding line shall be straight, cover the entire width of the I-beam and have a neat, sharp edge.
1.Thickness: 4”
2.Light transmission: Match Existing %.
3.Solar heat gain coefficient 0.21.
4.Panel U-factor by NFRC certified laboratory: 4” thermally broken grid 0.53.
5.Complete insulated panel system shall have NFRC certified U-factor of 0.53.
6.Grid pattern: Match Existing.

B. Standard panels shall deflect no more than 1.0” at 30 PSF in 10’ 0” span without a supporting frame by ASTM E 72.

C. Standard panels shall withstand 1200° F fire for minimum one hour without collapse or exterior flaming.

D. Thermally broken panels: Minimum Condensation Resistance Factor of 85 by AAMA 1503 measured on the bond line.

2.3 battens and perimeter closure system:

A.Closure system: Thermally broken extruded aluminum 6063-T6 and 6063-T5 alloy and temper clamp-tite screw type closure system.
B.Sealing tape: Manufacturer's standard, pre-applied to closure system at the factory under controlled conditions.
C.Fasteners: 300 series stainless steel screws for aluminum closures, excluding final fasteners to the building.
D.Finish:
1.Manufacturer's factory applied finish, which meets the performance requirements of AAMA 2604. Color to be selected from manufacturer's standards.

PART 3 - EXECUTION

3.1 EXAMINATION:

A.Verification of Conditions:
1.Examine openings for glass and glazing units; determine they are proper size; plumb; square; and level before installation is started.
2.Verify that glazing openings conform with details, dimensions and tolerances indicated on manufacturer is approved shop drawings.
B.Review for conditions which may adversely affect glass and glazing unit installation, prior to commencement of installation. Do not proceed with installation until unsatisfactory conditions have been corrected.
C.Verify that wash down of adjacent masonry is completed prior to erection of glass and glazing units.

3.2 PREPARATION:

A.For sealant glazing, prepare glazing surfaces in accordance with GANA Sealant Manual.
B.Determine glazing unit size and edge clearances by measuring the actual unit to receive the glazing.
C.Shop fabricate and cut glass with smooth, straight edges of full size required by openings to provide GANA recommended edge clearances.
D.Verify that components used are compatible.
E.Clean and dry glazing surfaces.
F.Prime surfaces scheduled to receive sealants, as determined by preconstruction sealant-substrate testing.

G. Metal Protection:

1.Where aluminum will contact dissimilar metals, protect against galvanic action by painting contact surfaces with primer or by applying sealant or tape recommended by manufacturer for this purpose.
2.Where aluminum will contact concrete, masonry or pressure treated wood, protect against corrosion by painting contact surfaces with bituminous paint or method recommended by manufacturer.

3.3 INSTALLATION:

A.Install in accordance with GANA Glazing Manual, GANA Sealant Manual, IGMA TB-3001, and IGMA TM-3000 unless specified otherwise.
B.Glaze in accordance with recommendations of glazing and framing manufacturers, and as required to meet the Performance Test Requirements specified in other applicable sections of specifications.
C.Set glazing without bending, twisting, or forcing of units.
D.Do not allow glass to rest on or contact any framing member.
E.Plastic:
1.Use dry glazing method.
2.Use only neoprene or EPDM gaskets.
F.Bullet Resisting Material:
1.Glaze as recommended by manufacturer, using glazing material which will permit expansion and contraction of the bullet resistive material in the frame.
2.The polycarbonate surface is not to be cleaned by scraping, razor blade, squeegee, or use of highly alkaline cleaner.

3. At no time is polycarbonate material be exposed to chemical solvents (benzene, gasoline, acetone, paint thinners) or aromatic hydrocarbons (toluene or xylene), nor should any of these solvents or fumes by used or present in confined area such as a security guard booth.

4. Due care is to be exercised (paint formula, ventilation, protection of polycarbonate) when painting becomes necessary to interiors of rooms of hardline glazed units; exposure to chemical solvents could result in irreparable damage to security glazings (delaminations, distortions, cracks, severe stress crazing, air bubbles, etc.).

G. Install the panel system in accordance with the manufacturer's suggested installation recommendations and approved shop drawings.

1.Anchor component parts securely in place by permanent mechanical attachment system.
2.Accommodate thermal and mechanical movements.
3.Set perimeter framing in a full bed of sealant compound, or with joint fillers or gaskets to provide weather-tight construction.

H. Install joint sealants at perimeter joints and within the panel system in accordance with manufacturer's installation instructions.

3.4 REPLACEMENT AND CLEANING:

A.Clean new glass surfaces removing temporary labels, paint spots, and defacement after approval by COR.
B.Replace cracked, broken, and imperfect glass, or glass which has been installed improperly.
C.Leave glass, putty, and other setting material in clean, whole, and acceptable condition.

D. Clean the panel system interior and exterior, immediately after installation. Refer to manufacturer's written recommendations.

3.5 PROTECTION:

A. Protect finished surfaces from damage during erection, and after completion of work. Strippable plastic coatings on colored anodized finish are not acceptable.

- - - E N D - - - 08 80 00 - 1