This document is a Table of Contents for VHA Master Specifications for construction project 630A-22-413, an Upgrade Station Chilled Water project at the James J. Peters VA Medical Center in Brooklyn, NY. The specifications represent 100% Construction Documents dated January 10, 2025, with a base date of March 1, 2024.
The specifications encompass 29 divisions of construction work organized according to the Construction Specifications Institute (CSI) MasterFormat. Key divisions include General Requirements (Division 01), Existing Conditions (Division 02), Concrete (Division 03), Metals (Division 05), Thermal and Moisture Protection (Division 07), Openings (Division 08), Finishes (Division 09), Fire Suppression (Division 21), Plumbing (Division 22), HVAC (Division 23), Electrical (Division 26), and Electronic Safety and Security (Division 28). Relevant to the chilled water upgrade, Division 23 includes critical sections for hydronic piping, hydronic pumps, packaged water chillers, HVAC water treatment, and commissioning of HVAC systems, all updated to March 2024. The specifications also address supporting work including structural steel framing, waterproofing, firestopping, plumbing fixtures and distribution, electrical installations, and fire detection systems. All sections reference current VA standards with effective dates ranging from June 2015 to March 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24226B0010 0004_.docx | DOCX document | |
| VFD SPECIFICATION SECTION -262911-MOTOR CONTROL UPDATED.pdf | ||
| 36C24226B0010 0004.docx | DOCX document | |
| 211313-WET-PIPE SPRINKLER SYSTEMS.pdf | ||
| 36C24226B0010 0003.docx | DOCX document | |
| 630A4-22-413 Pre-bid site walk.jpg | JPG image | |
| VFD SPECIFICATION SECTION -262911-MOTOR CONTROL.pdf | ||
| QUESTIONS - Upgrade Station Chilled Water for PID.pdf | ||
| 000110 TOC.pdf | ||
| 36C24226B0010 002.docx | DOCX document | |
| 36C24226B0010 0001_1.docx | DOCX document | |
| 36C24226B0010 0002.docx | DOCX document | |
| 36C24226B0010.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
630A-22-413 Upgrade Station Chilled Water Date:01/10/2025
James J. Peters VA Medical Center 100% Construction Documents
800 Poly Place, Brooklyn NY 11209 03-01-24
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 01-24
01 33 23 Shop Drawings, Product Data, and Samples 11-23
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 06-21
01 57 19 Temporary Environmental Controls 01-21
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 04-22
01 81 13 Sustainable Construction Requirements 10-17
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 11 Traditional Asbestos Abatement 01-21
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 01-21
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 13 00 Sheet Waterproofing 01-21
07 81 00 Applied Fireproofing 07-23
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 31 13 Access Doors and Frames 04-22
08 71 00 Door Hardware 03-24
08 90 00 Louvers and Vents 01-21
800 Poly Place, Brooklyn NY 11209 03-01-24
00 01 10-2
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 06 00 Schedule for Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 30 13 Ceramic/Porcelain Tiling 01-21
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 01-21
09 67 23.20 Resinous Epoxy Base (RES 1) 12-21
09 91 00 Painting 01-21
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 07 11 Plumbing Insulation 09-19
22 11 00 Facility Water Distribution 05-21
22 13 00 Facility Sanitary and Vent Piping 09-20
22 40 00 Plumbing Fixtures 12-22
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 03-23
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
03-23
23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23
23 08 00 Commissioning of HVAC Systems 03-23
23 09 23 Direct-Digital Control System for HVAC 03-23
23 21 13 Hydronic Piping 03-23
23 21 23 Hydronic Pumps 03-23
23 22 13 Steam and Condensate Heating Piping 03-24 23 25 00 HVAC Water Treatment 03-23
23 31 00 HVAC Ducts and Casings 03-23
23 34 00 HVAC Fans 03-23
23 37 00 Air Outlets and Inlets 03-23
23 64 00 Packaged Water Chillers 03-24
23 73 00 Indoor Central-Station Air-Handling Units 03-23
23 82 16 Air Coils 03-24
23 84 00 Humidity Control Equipment 03-24
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22
26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22
26 05 26 Grounding and Bonding for Electrical Systems 11-22
26 05 33 Raceway and Boxes for Electrical Systems 11-22
800 Poly Place, Brooklyn NY 11209 03-01-24
00 01 10-3
SECTION NO DIVISION AND SECTION TITLES DATE
26 05 73 Overcurrent Protective Device Coordination Study 11-22
26 09 23 Lighting Controls 11-22
26 24 16 Panelboards 11-22
26 27 26 Wiring Devices 11-22
26 29 11 Motor Controllers 11-22
26 29 21 Enclosed Switches and Circuit Breakers 11-22
26 43 13 Surge Protective Devices 11-22
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 31 00 Fire Detection and Alarm 10-11