This document contains an amendment to a federal solicitation for construction services. The amendment provides answers to questions from offerors and changes the bid opening date to August 31, 2022 at 2:15 PM Eastern Time, with bids due no later than 2:00 PM on that date. The questions and answers indicate that medium to large rocks should be anticipated throughout excavation areas and removed from the site as part of the work. The specifications and drawings provide requirements for trench excavation, backfilling, and topsoil that offerors should review and address in their bids. The solicitation is for project number 36C24222B0037 to perform ground water mitigation work at Building 30 for the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2.
View the file
Other files
Show 40 more
Latest 50 of 76 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
528-22-3-4192-0029
528A4-18-203
Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road Suite 3500 Cheektowaga NY 14227
Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road Suite 3500 Cheektowaga NY 14227 To all Offerors/Bidders
36C24222B0037
X
528-3620162-4192-854200 Non-Recurring Ma-3215 Improvements to Land - Ca-23NRNR000
This amendment is issued to provide Q & A and change the date of the bid opening. See page #2 for the Q&A. The bid opening date changed to Wednesday August 31, 2022, at 2:15 PM Eastern Time. Bids are due NLT 2:00 PM Eastern Time before or on August 31, 2022.
***END***
Tanya Baldwin Contracting Officer
1. The amendment states the previous specs were re-uploaded.
Was anything new added to the specifications? If not, has any item been changed in the specifications? The specifications have NOT changed from the original posting.
1. The amendment states that we should now anticipate medium to large boulders underground along the entire line of civil demolition and remove them from the site.
For bidding purposes, how many rocks should be anticipated to be removed?/how many truckloads should be priced into the bid for rock removal?
· The contractor shall calculate the total volume in (ft^3, yard^3 or m^3) of the areas to be excavated for the trench, manholes, etc. based on the scale of the drawings that depicts the length, depth and width of the trench and other areas that need to be excavated including the manholes and spreader area.
· Drawing CS502 detail 7 depicts the requirements for the trench composition and fill.
· ALL excavated area in the trench, manholes, spreader area, etc. shall be removed from the campus as per contract requirements on this project.
· The VA COR shall inspect the trench daily to assure that ALL requirements are being met before closing the trench.
· A note from previous excavation projects, the soil has more rock here than what you may find in other areas such as Buffalo. Many of the rocks are approximately 6” to 8” in diameter and it is NOT uncommon to find rock much larger that are 15” to 20” in diameter. The rock that will be encountered is granite, limestone, etc.
· Refer to the contract drawings and specifications with respect for requirements on backfilling and topsoil. The contractor shall provide a submittal on backfilling material and topsoil. Some key notes (NOT all inclusive, the contractor shall review the entire contract) are as follows:
· Refer to detail #7 on drawing CS502 for trench detail, all materials are imported. Provide submittal for approval.
· Unsuitable backfill is defined in specification section 31 20 11 (size of rocks, tec) in section 1.2.A.
· The contractor shall install suitable backfill above the outlined pipe as defined in the specifications and drawings.