23. EP101 Power Basement New Work Plan.pdf

PDF 492 KB Posted

Attached to
Z1DA--528A4-18-203 GROUND WATER MITIGATION BUILDING 30
Solicitation number
36C24222B0037
Issued by

About this file

This document includes an electrical plan and specifications for upgrades to the basement power and pump control systems at the Batavia VA Medical Center in Batavia, New York. The project involves removing circuits for pumps P5 and P6 from one electrical panel and extending the conductors and conduits to a second panel, installing a new control panel for pumps P1 and P2, adding NEMA 3R disconnects, and ensuring the new control panel includes visual alarms and maintains emergency power connections. The related federal contract opportunity is solicitation number 36C24222B0037 for ground water mitigation work at Building 30 of the Batavia VA Medical Center. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2 is the contracting agency.

View the file

Other files

File Type Posted
36C24222B0037 0005.docx DOCX document
014529-Testing_Laboratory.pdf PDF
333000 - Sanitary Sewer Utilities.pdf PDF
079200-Joint_Sealant.pdf PDF
12. CG101 Erosion and Sedimentation Control Plan A.pdf PDF
260519-Low-Voltage_EPower_Cond_and_Cables.pdf PDF
040100-Maintenance_of_Masonry.pdf PDF
15. CS501 Construction Details.pdf PDF
220523-General_Duty_Valves_for_Plumbing_Piping.pdf PDF
022113-Site_Survey.pdf PDF
13. CG102 Erosion and Sedimentation Control Plan B.pdf PDF
015719-Temporary_Enviromental_Controls.pdf PDF
3. GI003 Contractor Submittal List.pdf PDF
101400-Signage.pdf PDF
312011-Earthwork_Short_Form.pdf PDF
018113-Sustanabile_Construction_Requirements.pdf PDF
36C24222B0037 0004.pdf PDF
220511-Common_Work_Results_for_Plumbing.pdf PDF
010000-General_Requirements.pdf PDF
329000-Planting.pdf PDF
4. CD100 Overall Existing Features Plan.pdf PDF
16. CS502 Construction Details.pdf PDF
260526-Grounding_and_Bonding_for_Electrical_Systems.pdf PDF
024100-Demolition.pdf PDF
055000-Metal_Fabrication.pdf PDF
6. CD102 Existing Features and Demolition Plan B.pdf PDF
000115-List_of_Drawings.pdf PDF
260541-Underground_Electrical_Construction.pdf PDF
262911-Motor_Controllers.pdf PDF
Drawings Amendment 2.pdf PDF
1. GI001 Title Sheet.pdf PDF
321723-Pavement_Markings.pdf PDF
18. PP101 Plumbing Piping Plan.pdf PDF
320523-Cement_and_Conc_for_Ext_Imp.pdf PDF
040513-Masonry_Mortaring.pdf PDF
11. CU103 Groundwater Force Main Plan & Profile C.pdf PDF
321216-Asphalt_Paving.pdf PDF
2. GI002 General Notes Sheet.pdf PDF
17. CS503 Construction Details.pdf PDF
220512-General_Motor_Requirements_for_Plumbing_Equipment.pdf PDF
334000-Storm_Sewer_Utilities.pdf PDF
20. ED101 Electrical Systems Demolition Plan.pdf PDF
312319-Dewatering.pdf PDF
14. CG103 Erosion and Sedimentation Control Plan C.pdf PDF
014219-Reference_Standards.pdf PDF
10. CU102 Groundwater Force Main Plan & Profile B.pdf PDF
_CoverBatavia.pdf PDF
033053-Concrete_Short_Form.pdf PDF
323113-Chain_Link_Fences_and_Gates.pdf PDF
21. ES101 Electrical Systems New Work Plan.pdf PDF
Show 40 more

Latest 50 of 76 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P3 P4 P5 P6

P2

PUMP-2

P1

PUMP-1

1 1

EX. PANEL

BPCL1 EX. PANEL

BLSL1

NEW CONTROL PANEL

FOR P1 AND P2

NEW NEMA 3R

240V/60A/3PH

DISCONNECTS

NEW WORK GENERAL NOTES

1. REFER TO THE PLANS FOR EQUIPMENT LAYOUT. CLOSELY COORDINATE THE EXACT

LOCATION OF ALL OUTLETS AND DEVICES WITH ELEVATIONS. ADJUST LOCATIONS AND

MOUNTING HEIGHTS WHERE NECESSARY TO PREVENT INTERFERENCE WITH

FURNITURE, FIXED CASEWORK, EQUIPMENT, ETC. VERIFY ALL CHANGES PRIOR TO

ROUGH-IN.

2. EC SHALL VERIFY ALL EQUIPMENT LOCATIONS, MOUNTING HEIGHTS, AND CONNECTION

REQUIREMENTS (RECEPTACLES, SWITCHES, DISCONNECTS, ETC.) WITH EQUIPMENT

VENDOR PRIOR TO ROUGH-IN.

3. A DEDICATED NEUTRAL SHALL BE PROVIDED FOR EACH AND EVERY 120V AND 277V

BRANCH CIRCUIT. MULTIWIRE BRANCH CIRCUITS WITH SHARED NEUTRALS ARE NOT

PERMITTED.

4. PROVIDE #10 SIZE CONDUCTORS FOR 20A-120V CIRCUITS WITH DISTANCE LENGTHS

THAT EXCEED 100 FT.

5. EC IS RESPONSIBLE FOR SUBMITTING CONDUIT ROUTING COORDINATION DRAWINGS

WITH ELECTRICAL EQUIPMENT SUBMITTAL FOR APPROVAL. ROUTING DRAWINGS

SHALL INCLUDE FIELD VERIFIED ROUTING, BENDS, PULLBOXES, CONDUIT BODIES,

PENETRATIONS, ETC. EC SHALL INCLUDE EXISTING CONDITIONS WHERE NECESSARY

TO CONVEY ROUTING INFORMATION. MAINTAIN NEC REUIRED ACCESSIBILITY TO ALL

EXISTING PULLBOXES, JUNCTION BOXES, ETC. TO REMAIN. ELECTRICAL EQUIPMENT

SUBMITTAL WILL NOT BE APPROVED WITHOUT CONDUIT ROUTING DRAWINGS.

NEW WORK KEY NOTES

REMOVE THE CIRCUIT FOR PUMP P5 AND P6 FROM PANEL BPCL1 #37, 39 ,41 BY INSTALLING

A JUNCTION BOX IN THE ELECTRICAL ROOM AND EXTEND THE CONDUCTORS AND

CONDUITS TO PANEL BSLS1. CONNECT THE CONDUCTORS TO CIRCUIT #25, 27, 29 ON PANEL

BLSL1. CONTRACTOR SHALL UPDATE THE PANEL SCHEDULE. PROVIDE (4) #12AWG, (1) #10

GR IN 3/4"C EMT THHN COPPER CONDUCTORS.

EC SHALL REUSE THE UNDERGROUND CONDUITS AND UNISTRUT FOR THE EXISTING PUMP

CONTROL PANEL. THE VISUAL ALARM SHALL BE INCLUDED IN THE FUNCTIONS OF THE NEW

PUMP CONTROL PANEL. THE AUDIO ALARM (SPEAKER) SHALL BE REMOVED. THE EXISTING

3-PHASE RECEPTACLE AND POWER CONNECTION FOR EMERGENCY ANCILLARY PUMP

SHALL REMAIN AND CONNECT TO THE NEW PUMP CONTROL PANEL EMERGENCY POWER

SOURCE (BLSL1-26,28,30). REFER TO DUAL POWER PUMP CONTROL PANEL DETAIL ON E001.

NEW PUMP CONTROL PANEL MANUFACTURER: R.C.WORST @208-664-2133, 208-667-8775

NEW PUMP CONTROL PANEL MODEL SHALL BE Q-28575-1 TR OR APPROVED EQUIVALENT.

REFER TO THE PUMP CONTROL PANEL WIRING DETAIL AND PANEL SCHEDULES ON

DRAWING E001 FOR THE POWER CONNECTIONS.

8/1/2022

Batavia VA Medical Center Batavia, NY

528A4-18-203

CHRIS GEARY PE# 099085

Schadler/Waldron Geary

Project Number

Building Number

Sheet Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORDSTAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date: Dwg. of

REVISED PER CONFERENCE CALL ON MARCH 9, 2021

REVISED PER 60% DESIGN REVIEW LETTERS

REVISED PER 90% DESIGN REVIEW LETTERS

REVISED PER FONT ISSUE/LINE ISSUE

5/11/2021 9/10/2021 2/4/2022 7/26/2022

EP101

23 23

Power Basement New Work Plan Bid Documents For Construction

Improve Ground Water, Building 30