014529-Testing_Laboratory.pdf

PDF 116 KB Posted

Attached to
Z1DA--528A4-18-203 GROUND WATER MITIGATION BUILDING 30
Solicitation number
36C24222B0037
Issued by

About this file

This document outlines testing laboratory services requirements for the Z1DA--528A4-18-203 GROUND WATER MITIGATION BUILDING 30 federal contract opportunity. The testing laboratory will be responsible for conducting various materials testing and inspections during construction, including compaction testing of fill and backfill materials, concrete cylinder compressive strength testing, reinforcement inspections, and floor flatness and levelness measurements. The laboratory must be accredited and meet requirements for personnel qualifications, sample handling and curing, testing procedures, and report submittals. Minimum required testing includes soil and aggregate gradation, compaction, concrete slump and air content, reinforcement splices, and masonry prism strength. The opportunity is available through the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2.

View the file

Other files

File Type Posted
36C24222B0037 0005.docx DOCX document
333000 - Sanitary Sewer Utilities.pdf PDF
079200-Joint_Sealant.pdf PDF
12. CG101 Erosion and Sedimentation Control Plan A.pdf PDF
260519-Low-Voltage_EPower_Cond_and_Cables.pdf PDF
040100-Maintenance_of_Masonry.pdf PDF
15. CS501 Construction Details.pdf PDF
220523-General_Duty_Valves_for_Plumbing_Piping.pdf PDF
022113-Site_Survey.pdf PDF
13. CG102 Erosion and Sedimentation Control Plan B.pdf PDF
015719-Temporary_Enviromental_Controls.pdf PDF
3. GI003 Contractor Submittal List.pdf PDF
23. EP101 Power Basement New Work Plan.pdf PDF
101400-Signage.pdf PDF
312011-Earthwork_Short_Form.pdf PDF
018113-Sustanabile_Construction_Requirements.pdf PDF
36C24222B0037 0004.pdf PDF
220511-Common_Work_Results_for_Plumbing.pdf PDF
010000-General_Requirements.pdf PDF
329000-Planting.pdf PDF
4. CD100 Overall Existing Features Plan.pdf PDF
16. CS502 Construction Details.pdf PDF
260526-Grounding_and_Bonding_for_Electrical_Systems.pdf PDF
024100-Demolition.pdf PDF
055000-Metal_Fabrication.pdf PDF
6. CD102 Existing Features and Demolition Plan B.pdf PDF
000115-List_of_Drawings.pdf PDF
260541-Underground_Electrical_Construction.pdf PDF
262911-Motor_Controllers.pdf PDF
Drawings Amendment 2.pdf PDF
1. GI001 Title Sheet.pdf PDF
321723-Pavement_Markings.pdf PDF
18. PP101 Plumbing Piping Plan.pdf PDF
320523-Cement_and_Conc_for_Ext_Imp.pdf PDF
040513-Masonry_Mortaring.pdf PDF
11. CU103 Groundwater Force Main Plan & Profile C.pdf PDF
321216-Asphalt_Paving.pdf PDF
2. GI002 General Notes Sheet.pdf PDF
17. CS503 Construction Details.pdf PDF
220512-General_Motor_Requirements_for_Plumbing_Equipment.pdf PDF
334000-Storm_Sewer_Utilities.pdf PDF
20. ED101 Electrical Systems Demolition Plan.pdf PDF
312319-Dewatering.pdf PDF
14. CG103 Erosion and Sedimentation Control Plan C.pdf PDF
014219-Reference_Standards.pdf PDF
10. CU102 Groundwater Force Main Plan & Profile B.pdf PDF
_CoverBatavia.pdf PDF
033053-Concrete_Short_Form.pdf PDF
323113-Chain_Link_Fences_and_Gates.pdf PDF
21. ES101 Electrical Systems New Work Plan.pdf PDF
Show 40 more

Latest 50 of 76 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Batavia VAMC Contract #36C24219C0228

Improve Ground Water, Building 30 Project #528A4-18-203

11-01-18

01 45 29 - 1

SECTION 01 45 29

TESTING LABORATORY SERVICES

PART 1 - GENERAL

1.1 DESCRIPTION:

This section specifies materials testing activities and inspection services required during project construction to be provided by a

Testing Laboratory retained by the General Contractor.

1.2 APPLICABLE PUBLICATIONS:

A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

B. American Association of State Highway and Transportation Officials

(AASHTO):

T27-11..................Standard Method of Test for Sieve Analysis of

Fine and Coarse Aggregates

T96-02 (R2006)..........Standard Method of Test for Resistance to

Degradation of Small-Size Coarse Aggregate by

Abrasion and Impact in the Los Angeles Machine

T99-10..................Standard Method of Test for Moisture-Density

Relations of Soils Using a 2.5 Kg (5.5 lb.)

Rammer and a 305 mm (12 in.) Drop

T104-99 (R2007).........Standard Method of Test for Soundness of

Aggregate by Use of Sodium Sulfate or Magnesium

Sulfate

T180-10.................Standard Method of Test for Moisture-Density

Relations of Soils using a 4.54 kg (10 lb.)

Rammer and a 457 mm (18 in.) Drop

T191-02(R2006)..........Standard Method of Test for Density of Soil In-

Place by the Sand-Cone Method

T310-13.................Standard Method of Test for In-place Density and Moisture Content of Soil and Soil-aggregate by Nuclear Methods (Shallow Depth)

C. American Concrete Institute (ACI):

506.4R-94 (R2004).......Guide for the Evaluation of Shotcrete

D. American Society for Testing and Materials (ASTM):

A370-12.................Standard Test Methods and Definitions for

Mechanical Testing of Steel Products

11-01-18

01 45 29 - 2

A416/A416M-10...........Standard Specification for Steel Strand, Uncoated Seven-Wire for Prestressed Concrete

C31/C31M-10.............Standard Practice for Making and Curing

Concrete Test Specimens in the Field

C33/C33M-11a............Standard Specification for Concrete Aggregates

C39/C39M-12.............Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens

C109/C109M-11b..........Standard Test Method for Compressive Strength of Hydraulic Cement Mortars

C136-06.................Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates

C138/C138M-10b..........Standard Test Method for Density (Unit Weight), Yield, and Air Content (Gravimetric) of

Concrete

C140-12.................Standard Test Methods for Sampling and Testing

Concrete Masonry Units and Related Units

C143/C143M-10a..........Standard Test Method for Slump of Hydraulic

Cement Concrete

C172/C172M-10...........Standard Practice for Sampling Freshly Mixed

Concrete

C173/C173M-10b..........Standard Test Method for Air Content of freshly

Mixed Concrete by the Volumetric Method

C330/C330M-09...........Standard Specification for Lightweight

Aggregates for Structural Concrete

C567/C567M-11...........Standard Test Method for Density Structural

Lightweight Concrete

C780-11.................Standard Test Method for Pre-construction and

Construction Evaluation of Mortars for Plain and Reinforced Unit Masonry

C1019-11................Standard Test Method for Sampling and Testing

Grout

C1064/C1064M-11.........Standard Test Method for Temperature of Freshly

Mixed Portland Cement Concrete

C1077-11c...............Standard Practice for Agencies Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing Agency Evaluation

C1314-11a...............Standard Test Method for Compressive Strength of Masonry Prisms

11-01-18

01 45 29 - 3

D422-63(2007)...........Standard Test Method for Particle-Size Analysis of Soils

D698-07e1...............Standard Test Methods for Laboratory Compaction

Characteristics of Soil Using Standard Effort

D1140-00(2006)..........Standard Test Methods for Amount of Material in

Soils Finer than No. 200 Sieve

D1143/D1143M-07e1.......Standard Test Methods for Deep Foundations

Under Static Axial Compressive Load

D1188-07e1..............Standard Test Method for Bulk Specific Gravity and Density of Compacted Bituminous Mixtures

Using Coated Samples

D1556-07................Standard Test Method for Density and Unit

Weight of Soil in Place by the Sand-Cone Method

D1557-09................Standard Test Methods for Laboratory Compaction

Characteristics of Soil Using Modified Effort

(56,000ft lbf/ft3 (2,700 KNm/m3))

D2166-06................Standard Test Method for Unconfined Compressive

Strength of Cohesive Soil

D2167-08)...............Standard Test Method for Density and Unit

Weight of Soil in Place by the Rubber Balloon

Method

D2216-10................Standard Test Methods for Laboratory

Determination of Water (Moisture) Content of

Soil and Rock by Mass

D2974-07a...............Standard Test Methods for Moisture, Ash, and

Organic Matter of Peat and Other Organic Soils

D3666-11................Standard Specification for Minimum Requirements for Agencies Testing and Inspecting Road and

Paving Materials

D3740-11................Standard Practice for Minimum Requirements for

Agencies Engaged in Testing and/or Inspection of Soil and Rock as used in Engineering Design and Construction

D6938-10................Standard Test Method for In-Place Density and

Water Content of Soil and Soil-Aggregate by

Nuclear Methods (Shallow Depth)

E94-04(2010)............Standard Guide for Radiographic Examination

11-01-18

01 45 29 - 4

E164-08.................Standard Practice for Contact Ultrasonic

Testing of Weldments

E329-11c................Standard Specification for Agencies Engaged in

Construction Inspection, Testing, or Special

Inspection

E543-09.................Standard Specification for Agencies Performing

Non-Destructive Testing

E605-93(R2011)..........Standard Test Methods for Thickness and Density of Sprayed Fire Resistive Material (SFRM)

Applied to Structural Members

E709-08.................Standard Guide for Magnetic Particle

Examination

E1155-96(R2008).........Determining FF Floor Flatness and FL Floor

Levelness Numbers

F3125/F3125M-15.........Standard Specification for High Strength

Structural Bolts, Steel and Alloy Steel, Heat

Treated, 120 ksi (830 MPa) and 150 ksi (1040

MPa) Minimum Tensile Strength, Inch and Metric

Dimensions

E. American Welding Society (AWS):

D1.D1.1M-10.............Structural Welding Code-Steel

1.3 REQUIREMENTS:

A. Accreditation Requirements: Construction materials testing laboratories must be accredited by a laboratory accreditation authority and will be required to submit a copy of the Certificate of Accreditation and Scope of Accreditation. The laboratory’s scope of accreditation must include the appropriate ASTM standards (i.e.; E329, C1077, D3666, D3740, A880, E543) listed in the technical sections of the specifications.

Laboratories engaged in Hazardous Materials Testing shall meet the requirements of OSHA and EPA. The policy applies to the specific laboratory performing the actual testing, not just the “Corporate

Office.”

B. Inspection and Testing: Testing laboratory shall inspect materials and workmanship and perform tests described herein and additional tests requested by Resident Engineer. When it appears materials furnished, or work performed by Contractor fail to meet construction contract requirements, Testing Laboratory shall direct attention of Resident

Engineer to such failure.

11-01-18

01 45 29 - 5

C. Written Reports or letters: Testing laboratory shall submit test reports to Resident Engineer, Contractor, unless other arrangements are agreed to in writing by the Resident Engineer. Submit reports of tests that fail to meet construction contract requirements on colored paper.

The written reports or letters shall be reviewed by the contractor’s retained professional geotechnical engineer licensed in New York and signed and sealed by the contractor’s professional geotechnical engineer registered in the state of New York.

D. Verbal Reports: Give verbal notification to Resident Engineer immediately of any irregularity.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 EARTHWORK:

A. Contractor: The Contractor shall provide a qualified professional geotechnical engineer licensed in New York, a technician under the direct supervision of a professional geotechnical engineer licensed in

New York, materials, equipment, and transportation as required to perform the service identified/required herein, within the agreed to schedule and/or time frame. The work to be performed shall be as identified herein and shall include but not be limited to the following:

1. Observe fill and subgrades during proof-rolling by a qualified licensed professional geotechnical engineer to evaluate suitability of surface material to receive fill or base course. Provide recommendations to the Resident Engineer regarding suitability or unsuitability of areas where proof-rolling was observed. Where unsuitable results are observed, witness excavation of unsuitable material and recommend to Resident Engineer extent of removal and replacement of unsuitable materials and observe proof-rolling of replaced areas until satisfactory results are obtained. A letter or report, meeting the requirements in section 1.3, shall be submitted to, and approved by the resident engineer prior to placement of any fill or base course.

B. Testing Laboratory: The Testing Laboratory shall provide qualified personnel, materials, equipment, and transportation as required to perform the services identified/required herein, within the agreed to schedule and/or time frame. The work to be performed shall be as

11-01-18

01 45 29 - 6 identified herein and shall include but not be limited to the following:

1. Compaction testing.

2. Fill and backfill material gradation.

3. Testing materials.

4. Testing landscaping per section 3.2.

5. Testing asphalt concrete paving per section 3.3

6. Testing concrete per section 3.4 and section 3.5.

7. Testing reinforcement per section 3.6.

C. Testing Compaction:

1. Determine maximum density and optimum moisture content for each type of fill, backfill and subgrade material used, in compliance with

ASTM D698 and/or ASTM D1557.

2. Make field density tests in accordance with the primary testing method following ASTM D6938 wherever possible. Field density tests utilizing ASTM D1556, or ASTM D2167 shall be utilized on a case by case basis only if there are problems with the validity of the results from the primary method due to specific site field conditions. Should the testing laboratory propose these alternative methods, they should provide satisfactory explanation to the

Resident Engineer before the tests are conducted.

a. Pavement Subgrade: One test for each 335 m2 (400 square yards), but in no case fewer than two tests.

b. Curb, Gutter, and Sidewalk: One test for each 90 m (300 feet), but in no case fewer than two tests.

c. Trenches: One test at maximum 30 m (100 foot) intervals per 1200 mm (4 foot) of vertical lift and at changes in required density, but in no case fewer than two tests.

C. Fill and Backfill Material Gradation: One test per 200 cubic yards stockpiled or in-place source material. Gradation of fill and backfill material shall be determined in accordance with ASTM C136.

D. Testing Materials: Test suitability of on-site and off-site borrow as directed by Resident Engineer.

3.2 FOUNDATION PILES: (NOT USED)

3.3 FOUNDATION CAISSONS: (NOT USED)

3.4 LANDSCAPING:

A. Test topsoil for organic materials, pH, phosphate, potash content, and gradation of particles.

11-01-18

01 45 29 - 7

1. Test for organic material by using ASTM D2974.

2. Determine percent of silt, sand, clay, and foreign materials such as rock, roots, and vegetation.

B. Submit laboratory test report of topsoil to Resident Engineer.

3.5 ASPHALT CONCRETE PAVING:

A. Aggregate Base Course:

1. Determine maximum density and optimum moisture content for aggregate base material in accordance with ASTM D1557, Method D.

2. Make a minimum of three field density tests on each day's final compaction on each aggregate course in accordance with ASTM D1556.

3. Sample and test aggregate as necessary to insure compliance with specification requirements for gradation, wear, and soundness as specified in the applicable state highway standards and specifications.

B. Asphalt Concrete:

1. Aggregate: Sample and test aggregates in stock pile and hot-bins as necessary to insure compliance with specification requirements for gradation (AASHTO T27), wear (AASHTO T96), and soundness (AASHTO

T104).

2. Temperature: Check temperature of each load of asphalt concrete at mixing plant and at site of paving operation.

3. Density: Make a minimum of two field density tests in accordance with ASTM D1188 of asphalt base and surface course for each day's paving operation.

3.6 SITE WORK CONCRETE:

Test site work concrete including materials for concrete as required in

Article CONCRETE of this section.

3.7 POST-TENSIONING OF CONCRETE: (NOT USED)

3.8 CONCRETE:

A. Batch Plant Inspection and Materials Testing:

1. Perform continuous batch plant inspection until concrete quality is established to satisfaction of Resident Engineer with concurrence of

Contracting Officer and perform periodic inspections thereafter as determined by the COR.

2. Periodically inspect and test batch proportioning equipment for accuracy and report deficiencies to Resident Engineer.

3. Sample and test mix ingredients as necessary to insure compliance with specifications.

11-01-18

01 45 29 - 8

4. Sample and test aggregates daily and as necessary for moisture content. Test the dry rodded weight of the coarse aggregate whenever a sieve analysis is made, and when it appears there has been a change in the aggregate.

5. Certify, in duplicate, ingredients and proportions and amounts of ingredients in concrete conform to approved trial mixes. When concrete is batched or mixed off immediate building site, certify

(by signing, initialing or stamping thereon) on delivery slips

(duplicate) that ingredients in truck-load mixes conform to proportions of aggregate weight, cement factor, and water-cement ratio of approved trial mixes.

B. Field Inspection and Materials Testing:

1. Provide a technician at site of placement at all times to perform concrete sampling and testing.

2. Review the delivery tickets of the ready-mix concrete trucks arriving on-site. Notify the Contractor if the concrete cannot be placed within the specified time limits or if the type of concrete delivered is incorrect. Reject any loads that do not comply with the

Specification requirements. Rejected loads are to be removed from the site at the Contractor’s expense. Any rejected concrete that is placed will be subject to removal.

3. Take concrete samples at point of placement in accordance with ASTM

C172. Mold and cure compression test cylinders in accordance with

ASTM C31. Make at least three cylinders for each 40 m3 (50 cubic yards) or less of each concrete type, and at least three cylinders for any one day's pour for each concrete type. Label each cylinder with an identification number. Resident Engineer may require additional cylinders to be molded and cured under job conditions.

4. Perform slump tests in accordance with ASTM C143. Test the first truck each day, and every time test cylinders are made. Test pumped concrete at the hopper and at the discharge end of the hose at the beginning of each day’s pumping operations to determine change in slump.

5. Determine the air content of concrete per ASTM C173. For concrete required to be air-entrained, test the first truck and every 20 m3

(25 cubic yards) thereafter each day. For concrete not required to be air-entrained, test every 80 m3 (100 cubic yards) at random. For

11-01-18

01 45 29 - 9 pumped concrete, initially test concrete at both the hopper and the discharge end of the hose to determine change in air content.

6. If slump or air content fall outside specified limits, make another test immediately from another portion of same batch.

7. Perform unit weight tests in compliance with ASTM C138 for normal weight concrete and ASTM C567 for lightweight concrete. Test the first truck and each time cylinders are made.

8. Notify laboratory technician at batch plant of mix irregularities and request materials and proportioning check.

9. Verify that specified mixing has been accomplished.

10. Environmental Conditions: Determine the temperature per ASTM C1064 for each truckload of concrete during hot weather and cold weather concreting operations:

a. When ambient air temperature falls below 4.4 degrees C (40 degrees F), record maximum and minimum air temperatures in each

24 hour period; record air temperature inside protective enclosure; record minimum temperature of surface of hardened concrete.

b. When ambient air temperature rises above 29.4 degrees C (85 degrees F), record maximum and minimum air temperature in each 24 hour period; record minimum relative humidity; record maximum wind velocity; record maximum temperature of surface of hardened concrete.

11. Inspect the reinforcing steel placement, including bar size, bar spacing, top and bottom concrete cover, proper tie into the chairs, and grade of steel prior to concrete placement. Submit detailed report of observations.

12. Observe conveying, placement, and consolidation of concrete for conformance to specifications.

13. Observe condition of formed surfaces upon removal of formwork prior to repair of surface defects and observe repair of surface defects.

14. Observe curing procedures for conformance with specifications, record dates of concrete placement, start of preliminary curing, start of final curing, end of curing period.

15. Observe preparations for placement of concrete:

a. Inspect handling, conveying, and placing equipment, inspect vibrating and compaction equipment.

11-01-18

01 45 29 - 10

b. Inspect preparation of construction, expansion, and isolation joints.

16. Observe preparations for protection from hot weather, cold weather, sun, and rain, and preparations for curing.

17. Observe concrete mixing:

a. Monitor and record amount of water added at project site.

b. Observe minimum and maximum mixing times.

18. Measure concrete flatwork for levelness and flatness as follows:

a. Perform Floor Tolerance Measurements FF and FL in accordance with

ASTM E1155. Calculate the actual overall F- numbers using the inferior/superior area method.

b. Perform all floor tolerance measurements within 48 hours after slab installation and prior to removal of shoring and formwork.

c. Provide the Contractor and COR with the results of all profile tests, including a running tabulation of the overall FF and FL values for all slabs installed to date, within 72 hours after each slab installation.

19. Other inspections:

a. Grouting under base plates.

b. Grouting anchor bolts and reinforcing steel in hardened concrete.

C. Laboratory Tests of Field Samples:

1. Test compression test cylinders for strength in accordance with ASTM

C39. For each test series, test one cylinder at 7 days and one cylinder at 28 days. Use remaining cylinder as a spare tested as directed by Resident Engineer. Compile laboratory test reports as follows: Compressive strength test shall be result of one cylinder, except when one cylinder shows evidence of improper sampling, molding or testing, in which case it shall be discarded and strength of spare cylinder shall be used.

2. Make weight tests of hardened lightweight structural concrete in accordance with ASTM C567.

3. Furnish certified compression test reports (duplicate) to Resident

Engineer. In test report, indicate the following information:

a. Cylinder identification number and date cast.

b. Specific location at which test samples were taken.

c. Type of concrete, slump, and percent air.

d. Compressive strength of concrete in MPa (psi).

11-01-18

01 45 29 - 11

e. Weight of lightweight structural concrete in kg/m3 (pounds per cubic feet).

f. Weather conditions during placing.

g. Temperature of concrete in each test cylinder when test cylinder was molded.

h. Maximum and minimum ambient temperature during placing.

i. Ambient temperature when concrete sample in test cylinder was taken.

j. Date delivered to laboratory and date tested.

3.9 REINFORCEMENT:

A. Review mill test reports furnished by Contractor.

B. Make one tensile and one bend test in accordance with ASTM A370 from each pair of samples obtained.

C. Written report shall include, in addition to test results, heat number, manufacturer, type and grade of steel, and bar size.

D. Perform tension tests of mechanical and welded splices in accordance with ASTM A370.

3.10 SHOTCRETE: (NOT USED)

3.11 PRESTRESSED CONCRETE: (NOT USED)

3.12 ARCHITECTURAL PRECAST CONCRETE: (NOT USED)

3.13 MASONRY:

A. Mortar Tests:

1. Laboratory compressive strength test:

a. Comply with ASTM C780.

b. Obtain samples during or immediately after discharge from batch mixer.

c. Furnish molds with 50 mm (2 inch), 3 compartment gang cube.

d. Test one sample at 7 days and 2 samples at 28 days.

2. Two tests during first week of operation; one test per week after initial test until masonry completion.

B. Grout Tests:

1. Laboratory compressive strength test:

a. Comply with ASTM C1019.

b. Test one sample at 7 days and 2 samples at 28 days.

c. Perform test for each 230 m2 (2500 square feet) of masonry.

C. Masonry Unit Tests:

1. Laboratory Compressive Strength Test:

11-01-18

01 45 29 - 12

a. Comply with ASTM C140.

b. Test 3 samples for each 460 m2 (5000 square feet) of wall area.

D. Prism Tests: For each type of wall construction indicated, test masonry prisms per ASTM C1314 for each 460 m2 (5000 square feet) of wall area.

Prepare one set of prisms for testing at 7 days and one set for testing at 28 days.

3.14 STRUCTURAL STEEL: (NOT USED)

3.15 STEEL DECKING: (NOT USED)

3.16 SHEAR CONNECTOR STUDS: (NOT USED)

3.17 SPRAYED-ON FIREPROOFING: (NOT USED)

3.18 TYPE OF TEST:

Approximate Number of Tests Required

A. Earthwork:

Laboratory Compaction Test, Soils:(ASTM D1557 and ASTM D698) 2

Field Density, Soils (AASHTO D1556, D2167, or D6938) 2

Penetration Test, Soils 2

B. Landscaping:

Topsoil Test 1

C. Aggregate Base:

Laboratory Compaction, ASTM D1557 2

Field Density, ASTM D1556 3

Aggregate, Base Course Gradation (AASHTO T27) 2

Wear (AASHTO T96) 2

Soundness (AASHTO T104) 2

D. Asphalt Concrete:

Field Density, ASTM D1188 2

Aggregate, Asphalt Concrete Gradation (AASHTO T27) 2

Wear (AASHTO T96) 2

Soundness (AASHTO T104) 2

E. Concrete:

Making and Curing Concrete Test Cylinders (ASTM C31) 3

Compressive Strength, Test Cylinders (ASTM C39) 2

Concrete Slump Test (ASTM C143) 2

11-01-18

01 45 29 - 13

Concrete Air Content Test (ASTM C173) 2

Unit Weight, Lightweight Concrete (ASTM C567) 2

Aggregate, Normal Weight: Gradation (ASTM C33) 2

Deleterious Substances (ASTM C33) 2

Soundness (ASTM C33) 2

Abrasion (ASTM C33) 2

Aggregate, Lightweight Gradation (ASTM C330) 2

Deleterious Substances (ASTM C330) 2

Unit Weight (ASTM C330) 2

Flatness and Levelness Readings (ASTM E1155) (number of days) 2

F. Reinforcing Steel:

Tensile Test (ASTM A370) 1

Bend Test (ASTM A370) 1

Mechanical Splice (ASTM A370) 1

Welded Splice Test (ASTM A370) 1

It shall be noted that the number of tests listed shall be considered the minimum number of tests required per workday, work area and per areas as specified in sections through the Specifications. Section 3.10 does not show the total number of tests required for the project; only the minimum number as mentioned above.