36C24118R0304 00002 4HA101 First Floor Asbestos Abatement Plan.pdf

View the file

Other files

File Type Posted
36C24118R0304-0006000.docx DOCX document
36C24118R0304-0005000.docx DOCX document
36C24118R0304-0004000.docx DOCX document
36C24118R0304-00003000.docx DOCX document
36C24118R0304-00002000.docx DOCX document
36C24118R0304-00001000.docx DOCX document
36C24118R0304-00001001.pdf PDF
36C24118R0304-020.pdf PDF
36C24118R0304-017.pdf PDF
36C24118R0304-024.pdf PDF
36C24118R0304-023.pdf PDF
36C24118R0304-016.pdf PDF
36C24118R0304-018.pdf PDF
36C24118R0304-022.pdf PDF
36C24118R0304-015.docx DOCX document
36C24118R0304-019.pdf PDF
36C24118R0304-021.pdf PDF
36C24118R0304-000.docx DOCX document
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GENERAL ASBESTOS REMOVAL NOTES:

1. REMOVAL AND DISPOSAL OF ASBESTOS-CONTAINING MATERIAL (ACM), ASBESTOS-CONTAMINATED ELEMENTS (ACE), AND OTHER POTENTIAL ACM AND ACE (EG, FLOORING, WALLS, AND CAULKING) USING FULL

CONTAINMENT PROCEDURES. REFER TO SPECIFICATION SECTIONS 02 82 11 ASBESTOS ABATEMENT; AND 02 82 13.31 ASBESTOS TRANSITE ABATEMENT FOR ADDITIONAL REQUIREMENTS.

2. GENERAL CONTRACTOR TO SUBMIT FOR EACH MAJOR DECONTAMINATION AREA THE LIMITS OF SEALING OFF THE LOCATION, QUANTITIES OF ASBESTOS MATERIAL, ARRANGEMENTS FOR AUXILIARY ROOMS, THE

ENGINEERING OF THE NEGATIVE AIR SYSTEMS, THE PATH OF ASBESTOS TRANSPORATION TO THE LOADING PLATFORM, AND LOCATION AND CONNECTION TO REQUIRED UTILITIES.

3. INACCESSIBLE OR ENCLOSED ACM IS ASSUMED BASED ON INSPECTION AND CONFIRMATION OF PREVIOUS BUILDING SURVEYS.

4. DRAWINGS DO NOT CLAIM TO IDENTIFY ALL OF THE ACM PRESENT IN THE BUILDING AND SHOULD NOT BE THE SOLE BASIS FOR IDENTIFYING ACM. CDW'S SURVEY WAS PERFORMED WITH LIMITATIONS INHERENT

TO NON-DESTRUCTIVE VISUAL INSPECTIONS. ANY SUSPECT MATERIAL ENCOUNTERED DURING RENOVATION/DEMOLITION THAT IS NOT IDENTIFIED AS BEING NON-ACM SHOULD BE ASSUMED TO BE ACM UNLESS

SAMPLE RESULTS PROVE OTHERWISE.

5. CAULKING NOT TESTED FOR PCBS. CONTRACTOR MUST TEST FOR PCBS TO CONFIRM WASTE STREAM REQUIREMENTS AT NO COST TO OWNER.

6. POTENTIAL ACM AND ACE INCLUDES BUT MAY NOT BE LIMITED TO THE FOLLOWING:

EXTERIOR OLD CAULK AT LENTIL, TYPICAL

EXTERIOR GREY CAULK AT CANOPY, TYPICAL

BLACK SEALANT ON COPPER FLASHING ALONG RAMP/ROOF, TYPICAL

TRANSITE PANELS AT HEATING UNIT, TYPICAL

VAPOR BARRIER BEHIND MASONRY, TYPICAL

HDR Architecture, Inc.

265 Winter Street, Third Flr.

Waltham, MA 02451