Q _ A - VA Rolla Outpatient Clinic.pdf

PDF 169 KB Posted

Attached to
X1DB--VA Outpatient Clinic, Rolla, Missouri
Solicitation number
36C10F22R0047
Issued by

View the file

Other files

File Type Posted
Rolla RLP Amendment 6.pdf PDF
Rolla RLP Amendment 5 - GSA Template 3516.pdf PDF
Rolla RLP Amendment 5.pdf PDF
Rolla RLP Amendment 5 - GSA Template 3517B.pdf PDF
36C10F22R0047 0004_1.docx DOCX document
Rolla OPC - Amendment 4.pdf PDF
Q _ A - Rolla.pdf PDF
RLP Amendment No. 3 - Rolla.pdf PDF
36C10F22R0047 003.docx DOCX document
Facility Security Level II.pdf PDF
1 - GSA L100.pdf PDF
36C10F22R0047 0003.docx DOCX document
04 - Appendix C - Janitorial.pdf PDF
FSL II CLINICS (003).pdf PDF
FAR 52.204-24 Representation (003).pdf PDF
RLP Amendment 2 - Final.pdf PDF
FORM 1364.pdf PDF
36C10F22R0047 0002_1.docx DOCX document
36C10F22R0047 1_2.docx DOCX document
02A - Appendix A.1 - Program For Design.pdf PDF
36C10F22R0047 1_1.docx DOCX document
VA RLP Rolla FINAL Amendment 1.pdf PDF
05A - Appendix D.1 ASR.pdf PDF
24 - Telecom.docx DOCX document
16 - VA Handbook 6500 Appendix D.pdf PDF
05C - Appendix D.3 LV Systems.pdf PDF
04A - Appendix C.1 Lease Design Narrative (LDN).docx DOCX document
05E - Appendix D.5 ORP Risk Assessment Plan.pdf PDF
05D - Appendix D.4 - Lease Code Compliance.pdf PDF
21 - Seismic Forms.pdf PDF
06B - Appendix E.2 OIT Extra Small Campus Spt Ctr Dsgn Rolla CBOC 20210514.pdf PDF
04B - Appendix C.2 Room Data Matrix.xlsx XLSX spreadsheet
03 Appendix B.1 - Conceptual Floor Plan.pdf PDF
36C10F22R0047_1.docx DOCX document
15 - Form 527 Contractor Qualifications and Fin Info.pdf PDF
25 - Contractor Confidentiality Certificate.pdf PDF
26 - FAR Clause 52.209-5 Responsibility Matters Cert.pdf PDF
01 - VA RLP Rolla FINAL.pdf PDF
27 - FAR Clause 52.204-10 Reporting Exec Comp.pdf PDF
07 - Offering Entity Ack Form.pdf PDF
10 - Att 1 to 1364.pdf PDF
19 - 3517B General Clauses.pdf PDF
9 - Proposal to Lease Form 1364.docx DOCX document
22 - Cert of Building Engy Perf.pdf PDF
06D -Appendix E.4 Basic Guidance - TR Design Checklist.pdf PDF
05B - Appendix D.2 FSL II.pdf PDF
08 - Compliance Matrix.pdf PDF
11 - Annual Cost Statement Form 1217.pdf PDF
20 - Form 12000 FPLS.docx DOCX document
13 - Past Performance Questionnaire.pdf PDF
Show 40 more

Latest 50 of 62 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question Answer We have compared the Room Contents list and the concept plan and there are discrepancies.

Mostly small differences, but one of the examples is (8) staff toilets called for in the room contents list that are not shown on the plan.

8 staff toilets are required.

RLP 3.06 (S) and (T), state that 2 Green Globe checklists need to be completed. I think the intent would be EITHER a GG‐NC or a GG‐SI be filled out depending on if we propose new construction or just a TI. Also, paragraph 3.10 requires LEED ID+C for this project. We believe this paragraph should be deleted and that the intent would be to meet the Green Globes requirements in 3.06 and NOT LEED.

Green Globes certification is required; LEED is not. Please see updated Form L100.

They are requiring separate staff parking, but do not give a breakdown of staff to patient. Also, are there any requirements to secure the staff parking with gates for example.

The developer is expected to design the space to accommodate 400 parking spaces. A portion shall be designated for staff/patient during the design phase of the project. No gates to separate staff/patient are expected.

ASR II, 3., a.: Confirm size of pad required and max. size of vehicle, since the ASR requires ‘adequate turning radius’.

Area for standard size semi‐truck (53 feet) and room for it to maneuver.

At Canteen, will a gate or grill be required to secure the canteen area when it is closed?

No. This will be an area for vending machines only. A gate is not required.

ASR V, 1, n,: ‘Provide storage space by main restrooms’. Is this lessor space and what is being stored in this space and how big? This room is not shown on the concept plan.

Yes it is lessor (RSF) space. It is shown as "HAC Space" near staff corridor across from main server/IT room. Appendix D.1, paragraphs(V)(1)(n)(i) and (V)(1)(n)(iii) shall be deleted.

Can TI payments be made progressively during the course of construction based on percentage of work completed?

No

Will the TI be amortized or a lump sum payment? Refer to L100 Section 1.08

What is the sustainable design requirement? RLP 3.10 indicates LEED ID+C. Lease 3.48 indicates Green Globes NC Two Globes.

Green Globes certification is required; LEED is not. Through Amendment 2, Paragraph 3.10 has been deleted. GG‐NC is the design criteria.

Appendix D.5 ORP Risk Assessment Plan appears to be a document for VA responses, not Lessor or A/Es. What is the purpose of this document and what is the requirement?

Through Amendment 2, this document has been removed as a requirement.

Appendix E.1 OIT Design Template shows Telecommunications Rooms. Are these rooms identified on Appendix B.1 Conceptual Floor Plan as "Area 21 Support IT" rooms measuring 170 SF

Yes. These rooms are identified on the conceptual floor plan.

They are in addition to the Main Server Room in the question below.

Please note: these questions and answer are for clarification purposes only. Please refer to the Request for Lease Proposal for requirements related to this solicitation.

RLP NO: 36C10F22R0047

VA Outpatient Clinic, Rolla, MO

Appendix E.2 OIT Extra Small Campus shows plans for a data center. Is this room identified as the larger IT room shown on Appendix B.1 Conceptual Floor Plan as measuring 780 SF?

Yes, conceptual floor plan includes a Server Main IT room measuring 780 SF.

Several ASR documents reference a mobile tech pad for future use. Are there any reference documents for the mobile trailer to use as a basis of design. Specifically for turning radiuses and structural loads along with any power/data hookup requirements?

Turning radiuses must accommodate for a standard size semi‐ truck (53 feet). Basis for design for concrete pad to support a structural load of 70,000 pounds. Basis for design to include 3 phase 480V power, and data. Pedestal for power and data connection (and underground conduits) required.

Is an emergency backup power generator required for this facility? If so, what are the systems requiring backup and run times?

Standby Generator listed in 4.6.1 is not a requirement for this project but will remain in the LDN for awareness.

Please confirm Order of Precedence of documents provided, Design Guidelines, FGI, etc. For example, if the ASR and VA Design Guideline conflict in information provided, which infromation should the design team incorporate into the pricing and design?

Any conflicts should immediately be brought to the attention of the Contracting Officer.

Please confirm mechanical components that are to be provided in Core and Shell pricing vs TI pricing allowance.

Please refer to Amendment 2, updated Appendix 1, GSA Template L100 for VA, Section 3 for building shell requirements.

Please confirm requirements of Progressive Collapse are to be integrated into design of single story building as noted per Lease Document 3.45 / Item 4 / Paragraph B.

Please refer to Amendment 2, Appendix 1, GSA Template L100 for VA.

Please confirm if building is to meet Two Green Globes or LEED Certified?

Lease 3.48 / 3.49 indicates building to achieve Two Green Globes for New Construction and Tenant Interiors. RLP 3.10 Green Building Rating Certification for Tenant Interiors indicates LEED‐ IC+C Certified Level for project TI's. Please confirm sustainability requirements for project.

Green Globes certification is required; LEED is not. Through Amendment 2, paragraph 3.10 has been deleted.

ASR II General Site Requirements / Item 4 / Paragraph B indicates "Staff entry to have larger covered entry with awning…." Please confirm what the sizing is referencing. Staff covering to be larger than what?

This is a design element that will be addressed during the post award phase of the project (part of TI pricing).

Per Section V / Item F / Para III ‐ Please confirm requirement "One toilet shall be designed so that a staff member shall observe patient in private without any view to the patient corridor" There appears to be an internal VA note in red asking "*Is this a Requirement?*".

This is referring to one of the blue water toilets in the Lab area.

This is a requirement. Please disregard the comment "*IS THIS A REQUIREMENT?*" from Appendix D.1(V)(f)(iii). The toilet is required as described.

Please note: these questions and answer are for clarification purposes only. Please refer to the Request for Lease Proposal for requirements related to this solicitation.

Please confirm construction of police suite walls: 8" block core walls (V Special Space Req / Item J / Para 1) or if walls are to be "built to underside of deck with mesh" utilizing gypsum board construction (IV Security Requirements / Item 8 / Para A‐ii).

Please refer to Amendment 2, which supplies developers with an updated Appendix D.2, Facility Security Level II document.

Please confirm red note adjacent to Paragraph Title CANTEEN ‐ V Special Space Req / Item L. Will a gate of some sort be required to lock off canteen when it's closed? Is this a requriement to be provided within the design?

No. This will be an area for vending machines only; a cash register will not be present.

Per Section V / Item Q / Para VII ‐ Please confirm automatic door locations in "high traffic or transfer areas" within the PMR area.

Main Entry and Exits to the building. Main Doors into each department (from public areas). All patient toilets. "High traffic or transfer areas" to be further verified during the post award phase of the project.

Per the statement "As appropriate to the scope of the project, the AE firm will employ additional professional specialists including but not limited to blast design engineer..." 'Please confirm if this project is required to contract a Blast Design Engineer as part of the Design Build Team.

Please refer to the updated Form L100, Appendix 1, for details regarding this question.

There are references to 2 different manufacturers along with reference to an “existing” solution.

This building is new and doesn’t have an existing solution. What manufacturer is preferred for Physical Access Control for this project?

Lenel OnGuard Physical Access Control System is required for compatibility with the main campus security office.

Per 4.11.8.9. Wireless Communications it states square footage of Wi‐Fi points based on facilities with and without Real Time Location Systems. Please confirm if this faciltiy will require Real Time Location Sytems as part of the scope?

Real Time Locations systems are not part of this scope

Regarding Intrusion Detection Systems ‐ due to multiple exterior doors required by the facility, where should control pads be located and is there a minimum quantity required?

This will be addressed during the post award/design phase of the project. Please also refer to Amendment 2, which supplies developers with an updated Appendix D.2, Facility Security Level II document.

Per Section 3.45 / Paragraph B / Item 1 "Window glazing, with a performance condition appropriate to the identified Facility Security Level" is required. Appendix D.2 refers to the lease for window design characteristics. Per The Risk Management Process for Federal Facilities: An Interagency Security Committee Standard ‐ Appendix B: Countermeasures "No special measures are required" for Blast Resistance Windows in a Level II facility. Please confirm no blast requirements for windows.

Please refer to Amendment 2, which supplies developers with an updated Appendix D.2, Facility Security Level II document. Blast film is not required for windows.

Please note: these questions and answer are for clarification purposes only. Please refer to the Request for Lease Proposal for requirements related to this

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 6 ‐ MULTI‐SPECIALTY CLINIC:

Room Code TRPR1 – Patient Care Room, Enhanced Exam, 180 Unit Area PFD quantifies two (2) total, Conceptual Floor Plan indicates only one (1) total.

Please confirm room quantity required in this area.

There should be only 1 Procedure Room as shown in the Conceptual Floor plan I Multi‐Specialty.

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 16 ‐ STAFF SUPPORT AREA Room Code LR001 ‐ Locker, Staff Personal Property, 20 Unit Area PFD quantifies one (1) total, Conceptual Floor Plan does not have this Room Please confirm if this room is required to be incorporated into the floor plan

There should not be lockers under the Staff Support section. Per the conceptual plans lockers are located on end caps and shown within their specific departments.

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 16 ‐ STAFF SUPPORT AREA Room Code SRE01 ‐ Storage, equipment, 80 Unit Area PFD quantifies two (2) total, Conceptual Floor Plan does not have these Rooms Please confirm if this room is required to be incorporated into the floor plan

There should only be 1 of these rooms in the staff corridor behind radiology.

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 16 ‐ STAFF SUPPORT AREA Room Code TNPG1 – Toilet, Staff, 60 Unit Area PFD quantifies five (5) total, Conceptual Floor Plan indicates eight (8) total Please confirm number of rooms required to be incorporated into floor plan

8 Toilets are indicated in Staff Area in the Plan and on RCL. There should be 8 plus the additional ones in the plan that are called out as LESSOR provided sf. The PFD is incorrect.

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 19 ‐ LOGISTICS SERVICE Room Code SRSE1 – Storage, Audiology, 100 Unit Area PFD quantifies one (1) total, Conceptual Floor Plan does not have this Room Please confirm if this room is required to be incorporated into the floor plan

This room is in the floor plan in the Audiology dept and near the staff corridor behind the IT room.

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 19 ‐ LOGISTICS SERVICE Room Code SRE01 – Storage, Equipment, 100 Unit Area PFD quantifies one (1) total, Conceptual Floor Plan does not have this Room Please confirm if this room is required to be incorporated into the floor plan.

This room is not in the floor plan nor in the RCL. The PFD is incorrect.

Please note: these questions and answer are for clarification purposes only. Please refer to the Request for Lease Proposal for requirements related to this

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 22 ‐ BUILDING AREA Room Code TNPG1 ‐ Toilet, front and back of Clinic per code req, 0 Unit Area PFD quantifies four (4) total, Conceptual Floor Plan indicates three (3) total Please confirm number of rooms required to be incorporated into floor plan

Toilets that are required by code are responsibility of the Lessor.

Initial take off for toilet counts were done. However, depending on the developers presented plan, these counts could change.

Developer needs to confirm toilets with current codes. The "Conceptual" floor plan indicates multi‐stall toilet rooms as well as family toilet rooms space throughout. It also indicates a couple staff toilets as well. Toilets listed in PFD within departments and in area of Staff Support are in addition to those required by code.

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 22 ‐ BUILDING AREA Room Code LOB02 – Vestibule, 0 Unit Area PFD quantifies one (1) total, Conceptual Floor Plan indicates two (2) total Please confirm number of rooms required to be incorporated into floor plan

There shall be a vestibule at the main entry and one for staff entry. There should be 2 vestibules. Vestibules are required at entries for inclement weather as well as to keep HVAC systems running at peak performance.

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 5 – Behavioral Health Room Code ?? – Alcove, Copier/Supplies Conceptual Floor Plan indicates one (1) total, 28 Unit Area Please confirm room code to be followed within the PFD document for this space

RCL indicates room code as SRE01. However, there is a new room code in the VA matrix for this space which is is SACS1.

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 5 – Behavioral Health Room Code ?? – Toilet, Patient Conceptual Floor Plan indicates one (1) total, 60 Unit Area Please confirm room code to be followed within the PFD document for this space

Room Code is TPG01. This room is listed in the RCL. It does belong in the plan. PFD is incorrect.

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 5 – Behavioral Health Room Code ?? – Alcove, Equipment Conceptual Floor Plan indicates one (1) total, 22 Unit Area Please confirm room code to be followed within the PFD document for this space

Alcove(s), Equipment ‐ two one at 50sf ad 1 at 22sf. Should be

SRE01.

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 4 – Primary Care Room Code ?? – Alcove, Copier/Printer Conceptual Floor Plan indicates one (1) total, 33 Unit Area Please confirm room code to be followed within the PFD document for this space

RCL indicates room code as SRE01. However, there is a new room code in the VA matrix for this space which is is SACS1.

Please note: these questions and answer are for clarification purposes only. Please refer to the Request for Lease Proposal for requirements related to this

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 4 – Primary Care Room Code ?? – Alcove, Equipment Conceptual Floor Plan indicates one (1) total, 38 Unit Area Please confirm room code to be followed within the PFD document for this space

Room Code is SRE01 for Alcove, Equipment.

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 6 – Multi Specialty Room Code ?? – Alcove, Pulmonary Conceptual Floor Plan indicates one (1) total, 33 Unit Area Please confirm room code to be followed within the PFD document for this space

In the Room Contents List equipment for the alcove are listed under the Pulmonary Room. Room code for the alcove can be

SRE01.

Department: 1 ‐ OUTPATIENT / PACT CLINIC (265); Functional Area: 6 – Multi Specialty Room Code ?? – Alcove, Equipment Conceptual Floor Plan indicates one (1) total, 38 Unit Area Please confirm room code to be followed within the PFD document for this space

Room Code is SRE01 for Alcove, Equipment.

ASR notes Ambulance Drive Entry and associated separate entry. Conceptual Floor Plan does not include this room. Please confirm if the Ambulance Drive entry should be combined with the staff entry or located seperately at this facility

See Appendix D.1(II)(4)(c). This will be further clarified in the post‐ award/design phase of the project. A combined ambulance/staff entry is acceptable.