Additional Government Responses to RFI Questions 5.31.2022.pdf

PDF 62 KB Posted

Attached to
Y1PC-JBNC Phase 5C Construction RFP Solicitation - Amendment 005
Solicitation number
36C10F22R0027
Issued by

About this file

This document contains government responses to follow up questions on solicitation number 36C10F22R0027 for the expansion of Jefferson Barracks National Cemetery Phase 5C in St. Louis, Missouri. The Department of Veterans Affairs, Office of Construction and Facilities Management anticipates awarding a firm fixed price contract for the project. Key details include a contract award date within 120 calendar days of the proposal due date, a notice to proceed within 60 calendar days of award, requirements for six rovers and temporary turnarounds with a 50 foot radius to be constructed, and clarification that the contractor staging area location is still under consideration and alternate locations may be used.

View the file

Other files

File Type Posted
36C10F22R0027 0005.docx DOCX document
Wage Determination MO20220001 06.03.2022.pdf PDF
Additional Government Responses to RFI Questions 6.9.2022.docx DOCX document
Wage Determination MO20220001 05.27.2022.pdf PDF
CS 103 657PC2313.23M JBNC BD Drawings 28 October 2020 r2 27 May 2022.pdf PDF
36C10F22R0027 0004.docx DOCX document
Wage Determination MO20220001 05.06.2022.pdf PDF
PAST PERFORMANCE QUESTIONNAIRE.docx DOCX document
36C10F22R0027 Solicitation JBNC Phase 5C.docx DOCX document
Government Responses to RFI Questions 36C10F22R0027 5.24.2022.pdf PDF
657PC2313.23M JBNC BD Drawings 28 October 2020 pg 45 to 68.pdf PDF
JBNC Phase 5C Add Alternate 1 Drawings.pdf PDF
JBNC Pre-Proposal Conference and Site Visit Walk-through .pptx PPTX presentation
657PC2313.23M JBNC BD Drawings 28 October 2020 pg 1 to 44.pdf PDF
Photos of Alternate 1.pdf PDF
657PC2313.23M JBNC Phase 5C Expansion Specifications 28 Oct 2020pdf.pdf PDF
36C10F22R0027 0003.docx DOCX document
36C10F22R0027 0001.docx DOCX document
36C10F22R0027 0002.docx DOCX document
36C10F22R0027 0001.docx DOCX document
JBNC Pre-Proposal Conference and Site Visit Walk-through .pptx PPTX presentation
657PC2313.23M JBNC Phase 5C Expansion Specifications 28 Oct 2020pdf.pdf PDF
Wage Determination MO20220001 04.08.2022.pdf PDF
657PC2313.23M JBNC BD Drawings 28 October 2020 pg 1 to 44.pdf PDF
PAST PERFORMANCE QUESTIONNAIRE 4.28.2022.docx DOCX document
JBNC Phase 5C Add Alternate 1 Drawings.pdf PDF
657PC2313.23M JBNC BD Drawings 28 October 2020 pg 45 to 68.pdf PDF
36C10F22R0027 Solicitation JBNC Phase 5C.docx DOCX document
Pre-Proposal Inquiry (PPI) Form.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI SUBMISSSION LOG

SOLICITATION NUMBER 36C10F22R0027

Government Responses to follow up RFI Questions

JEFFERSON BARRACKS NATIONAL CEMETERY PHASE 5C

Question No.

Reference (Sect/Para/Page)

QUESTION GOVERNMENT RESPONSE

RE

Questions

2, 63

What date are contractors to assume for contract award?

What date are contractors to assume for NTP?

Within 120 calendar days of proposal due date as stated in the solicitation.

Within 60 calendar days from award date.

RE

Questions

4, 6

This is not shown on the plans.

Please clarify how much of

Roadway B is to be constructed for the NTP.

Please provide sizes, locations, and details for any required temporary turn around(s).

See attached sketch.

Turnarounds to have a 50’ radius.

RE

Questions

5, 8

Please clarify how this area is to be both a “Contractor Trailer and

Staging Area” and turned over to the cemetery within 275 days as an

ETO In-Ground Cremains Area.

Contractor will need to utilize the “Contractor Trailer and Staging Area” for greater than 275 days.

Assume this location for Contractor Access and Staging.

Alternate locations are under consideration.

RE

Question

Answer is unclear. Are contractors directed to replace any identified “slope meadow seed” areas with

“sod”?

Means and Methods - this method was used on a previous phase.

RE

Questions 23, 24, 25

How many rover units is the contractor to supply?

Six Rovers will be required.