This document contains government responses to follow up questions on solicitation number 36C10F22R0027 for the expansion of Jefferson Barracks National Cemetery Phase 5C in St. Louis, Missouri. The Department of Veterans Affairs, Office of Construction and Facilities Management anticipates awarding a firm fixed price contract for the project. Key details include a contract award date within 120 calendar days of the proposal due date, a notice to proceed within 60 calendar days of award, requirements for six rovers and temporary turnarounds with a 50 foot radius to be constructed, and clarification that the contractor staging area location is still under consideration and alternate locations may be used.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI SUBMISSSION LOG
SOLICITATION NUMBER 36C10F22R0027
Government Responses to follow up RFI Questions
JEFFERSON BARRACKS NATIONAL CEMETERY PHASE 5C
Question No.
Reference (Sect/Para/Page)
QUESTION GOVERNMENT RESPONSE
RE
Questions
2, 63
What date are contractors to assume for contract award?
What date are contractors to assume for NTP?
Within 120 calendar days of proposal due date as stated in the solicitation.
Within 60 calendar days from award date.
RE
Questions
4, 6
This is not shown on the plans.
Please clarify how much of
Roadway B is to be constructed for the NTP.
Please provide sizes, locations, and details for any required temporary turn around(s).
See attached sketch.
Turnarounds to have a 50’ radius.
RE
Questions
5, 8
Please clarify how this area is to be both a “Contractor Trailer and
Staging Area” and turned over to the cemetery within 275 days as an
ETO In-Ground Cremains Area.
Contractor will need to utilize the “Contractor Trailer and Staging Area” for greater than 275 days.
Assume this location for Contractor Access and Staging.
Alternate locations are under consideration.
RE
Question
Answer is unclear. Are contractors directed to replace any identified “slope meadow seed” areas with
“sod”?
Means and Methods - this method was used on a previous phase.
RE
Questions 23, 24, 25
How many rover units is the contractor to supply?
Six Rovers will be required.