This document contains a pre-solicitation notice and slides from a pre-proposal conference for an expansion project at Fort Sam Houston National Cemetery. The Department of Veterans Affairs will award a firm-fixed price contract between $50-100 million to provide design and construction services for the Phase 3 expansion. Key work includes developing 50 acres for approximately 35,100 additional gravesites, roads, drainage, landscaping, buildings, security and communication upgrades. Offerors must be service-disabled veteran-owned small businesses. The performance period is 810 days with early turnover of a columbarium section at 365 days. The solicitation number is 36C10F21R0017. Questions are due by April 23rd and proposals are due May 12th, with an anticipated award date of August 30th, 2021 and notice to proceed of September 15th, 2021.
The pre-proposal conference slides provide additional details on the scope of work breaking out contract line items, specifications around insurance and bonding, liquidated damages, and milestones. Site plans and an overview of the expansion areas are also included.
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IAS
Fort Sam Houston National Cemetery
Phase 3 Cemetery Development San Antonio, TX
Solicitation – 36C10F21R0017 Project # 846-045
Pre-Proposal Conference April 21, 2021
Fort Sam Houston National Cemetery
Phase 3 Cemetery Development San Antonio, TX
Solicitation – 36C10F21R0017 Project # 846-045
Pre-Proposal Conference April 21, 2021
1 Office of Construction and Facilities Management
AgendaAgenda
� Opening Remarks � NCA Mission � Solicitation Summary � Milestones � Project Scope and Overview � Site Walkthrough
2 Office of Construction and Facilities Management
Opening RemarksOpening Remarks
� Introduction of VA Representatives:
VA CFM: Alea Barnes, Contracting Officer VA CFM: Bryan Bodner, Project Manager VA CFM: Josh Mathis, Senior Resident Engineer NCA FSHNC: Aubrey David, Director NCA FSHNC: Robert Winkler, Asst Director NCA FSHNC: Graham Wright, Asst Director
3 Office of Construction and Facilities Management
NCA MissionNCA Mission President Abraham Lincoln pledged the nation:
“To care for him who shall have borne the battle and for his widow and his orphan.”
That remains VA’s motto today.
The National Cemetery Administration honors Veterans and their families with final resting places in national shrines and with lasting tributes that commemorate their service and sacrifice to our Nation.
4 Office of Construction and Facilities Management
Solicitation OverviewSolicitation Overview
� Solicitation is 100% set aside for Service- Disabled Veteran Owned Small Business (SDVOSB) in accordance with 38 U.S.C.
8127(d).
� SDVOSB Offerors must be registered in SAM and registered & verified in VIP prior to submission and at the time of award, to be considered SDVOSB.
� Annual Representation and Certification
� https://www.sam.gov/SAM/ � Vendor Information Pages (VIP)
� https://www.vip.vetbiz.va.gov/
5 Office of Construction and Facilities Management
VAAR 809.406-2
Cause for Debarment
VAAR 809.406-2
Cause for Debarment
(a) In addition to the causes listed in FAR 9.406-2, the SDO may debar contractors, based upon a preponderance of the evidence, for
(1) Misrepresentation of Veteran-owned small business (VOSB) or service- disabled, Veteran-owned small business (SDVOSB) status; or
(2) Any deliberate violation of the limitation on subcontracting clause requirements for acquisitions under subpart 819.70.
(b) The SDO shall debar for a period of not less than five years, pursuant to 38 U.S.C. 8127(g), Enforcement Penalties for Misrepresentation, any business concern that has willfully and intentionally misrepresented the status of that concern as a small business concern owned and controlled by Veterans or as a small business concern owned and controlled by service-disabled Veterans pursuant to this subsection.
(1) “Willful and intentional” misrepresentations, for the purpose of debarment actions taken pursuant to subsection (b), are defined as misrepresentations concerning the status of the concern as a small business concern owned and controlled by Veterans or as a small business concern owned and controlled by service-disabled Veterans resulting in an admission, criminal conviction, civil judgment, or administrative decision related to fraud or other criminal acts.
(2) Debarment of a business concern pursuant to subsection (b) shall include the debarment of all principals in the business concern. Debarment shall be for a period of not less than five years.
6 Office of Construction and Facilities Management
Solicitation Overview Service-Disabled
Veteran-Owned Small Business Solicitation Overview
Service-Disabled Veteran-Owned Small Business
� VA Office of Small and Disadvantaged Business Utilization (OSDBU) Washington, D.C.
http://www4.va.gov/osdbu/
Contact OSDBU for information on � Joint Ventures � Teaming Agreement � Mentor Protégée (See VAAR 819-71) � CVE verification
7 Office of Construction and Facilities Management
� Project Cost Range
� Between $50,000,000 and $100,000,000 � Contract Type: Firm Fixed Price � Evaluation Method: Best Value/Trade-Off � Buy American Act Applies –
� 52.225-11 � 52.225-12 Alt I & Alt II
� Construction Wage Rate Requirements (Davis Bacon Act) Applies - TX20210007 - 01.01.2021
� Federal , State, and Local Tax (FAR Clause 52.229-3) � Shall be include it in offeror’s proposal price
8 Office of Construction and Facilities Management
� Contract Line Item Numbers (CLINs 001-005)
� CLIN 001: Base Bid – ETO – Columbarium #4 � CLIN 002: Base Bid – Construction of all remaining work designated
“Phase 3” in the contract documents � CLIN 003: Base Bid – Fabricate, Deliver, and Off-Load Precast Crypts � CLIN 004: Add Alternate #1 – Add Access Roads � CLIN 005 : Add Alternate #2 – Repair Existing Roads
� Period of Performance � 810 calendar days after the Notice to Proceed for base bid and any/all add alternate work.
9 Office of Construction and Facilities Management
� Early Turnover (ETO) Work � Completion and turn over to the Owner earlier than the final project completion date. See Spec Section 01 00 01-General Requirements � Time period for completion of the ETO work is a specified number of days following the "Notice to Proceed" for the overall project – 365 calendar days
� ETO work identified in plans/specs
10 Office of Construction and Facilities Management
� Bid Bond/Bid Guarantee (SF 24)
� See Solicitation pages 9 & 26 � Bond amount 20% of the offer price but shall not exceed $3,000,000 � Volume II, TAB 2, of your emailed proposal must contain a legible, scanned copy of your Executed Bid Guarantee (SF-24). Please shade any raised seals with pencil lead to make them legible before you scan the bond.
� An original, hard copy, executed Bid Guarantee (on form SF-24) must be mailed to David Bullerwell within 5 business days of the proposal due date/time. See page Solicitation pg 9
� Make sure your bond is in compliance with Far Part 28
� Performance & Payment Bonds (SF 25) Required � Penal sum = 100% of award amount � Required of awardee within 10 calendar days of award.
11 Office of Construction and Facilities Management
� Liquidated Damages - If the Contractor fails to complete each separate part or stage of the work within the time specified in the contract for that part or stage, or any extension, the Contractor shall pay to the Government as liquidated damages:
� ETO - $2,554.48 for each calendar day of delay � All other phases - Actual Damages Incurred
� Insurance � See Solicitation pages 66 & 67 � Certificate of Insurance required prior to commencing work
� Worker’s compensation and employers liability � General Liability � Automobile Liability
12 Office of Construction and Facilities Management
� Pre-Proposal Inquiries (PPI)/Requests for Information (RFI’S) � Use Solicitation PPI Form (Attachment 7)
� Questions Due: April 23, 2021, at 12:00 PM CDT Email to:
� Alea.Barnes@va.gov; and � Bryan.Bodner@va.gov
� The subject line to read “Ft. Sam Houston NC RFP:
36C10F21R0017”
13 Office of Construction and Facilities Management
Submission Instructions
Solicitation Overview Submission Instructions
�Volume I – Technical Proposal (limit 67 pages) Title Page (see Solicitation page 16) Tab 1 – Past Performance
Project Summaries PPQ & CPARS Reports
Tab 2 – Relevant Experience Relevant Team Experience Key Personnel
Tab 3 – Technical Approach Tab 4 – Construction/Project Management
Project Org Chart & Narrative Capacity to Perform Work Quality Control Plan Safety Plan Schedule
14 Office of Construction and Facilities Management
Submission Instructions
Solicitation Overview Submission Instructions
� Volume II – Price Proposal (limit 30 pages) Title Page (see Solicitation page 16) Tab 1 –
Executed Solicitation, Offer and Award Form (SF1442) (pages 1-2).
Offeror shall complete Blocks 14-20C.
Completed Offer Schedule (page 3).
Solicitation Amendments – complete boxes 15A-C (SF 30) for each amendment issued & include a copy in your proposal.
Tab 2 –
Scanned, legible, copy of Executed Bid Guarantee (SF-24) Tab 3 –
Printed copy “Representations and Certifications” as submitted on https://www.sam.gov/SAM/
15 Office of Construction and Facilities Management
Submission Instructions
Solicitation Overview Submission Instructions
� Proposal Submission Instructions Email:
• Submit one (1) copy of the Technical Proposal (Volume I), & one (1) copy of the Price Proposal (Volume II).
Emailed proposals shall be sent to the Contracting Officer at alea.barnes@va.gov by the due date & time shown in Box 13a of solicitation form SF 1442 (or as subsequently amended).
40 mb max file size limit If the file size is greater than 40MB, separate document into multiple files and label files logically & sequentially, for example Volume 1-part 1, Volume 1-part 2, etc.
Adobe PDF is the only file format that will be accepted.
16 Office of Construction and Facilities Management
MilestonesMilestones � 1 Solicitation Issued 4/12/2021
� 2 Pre-Proposal Conference/ Jobsite Walkthrough 4/21/2021
� 2 RFIs Due 4/23/2021
� 2 Proposal Due Date 5/12/2021
� 3 Contract Award (TENTATIVE) 8/30/2021
� 4 Notice To Proceed (TENTATIVE) 9/15/2021
17 Office of Construction and Facilities Management
Project Scope/OverviewProject Scope/Overview
VA Office of Construction &Facilities Management
Bryan Bodner, Project Manager
18 Office of Construction and Facilities Management
Exhibit 1Exhibit 1
19 Office of Construction and Facilities Management
Exhibit 2Exhibit 2
20 Office of Construction and Facilities Management
Site Walk-ThroughSite Walk-Through
� Scheduled to take place immediately upon completion of the pre-proposal conference on Wednesday, April 21, 2021, from approximately 11:00am to 1:00pm (CDT.)
� This jobsite walkthrough/site visit will be in-person only.
This will not be hosted virtually.
� Josh Mathis � No technical questions will be answered today or during the pre-proposal site visit.
� Submit all questions/requests for information (RFIs) in writing per the solicitation.
21 Office of Construction and Facilities Management
Thank you for your interest in this project!