View the file

Other files

File Type Posted
Amendment 6 - RLP 36C10F20R0061 James J Howard Replacement Leaase 09-21.pdf PDF
36C10F20R0061_9.docx DOCX document
Attachment 2_Submittal - Disinfection Rental.pdf PDF
SF 30 Amendment 5 36C10F20R0061.pdf PDF
Amendment 5 - RLP 36C10F20R0061 James J Howard Replacement Leaase 09-03.pdf PDF
07 - Appendix F-Janitorial Services and Site Maintenance FINAL.pdf PDF
36C10F20R0061_8.docx DOCX document
Questions and Answers.pdf PDF
36C10F20R0061_7.docx DOCX document
James J Howard - Pre-bid Presentation 08-17-2020.pdf PDF
09 - 36C10F20R0061 - Proposal Compliance Matrix - VA 8-25.pdf PDF
36C10F20R0061_6.docx DOCX document
Amendment 4 - RLP 36C10F20R0061 James J Howard Replacement Leaase 8-25.pdf PDF
SF30 A0004 36C10F20R0061.pdf PDF
FAR 52.204-25 and GSAR 552.204-70 Addendum.pdf PDF
SF 30 Amendment 3 36C10F20R0061.pdf PDF
Appendix C.1- FINAL Agency Specific Requirements.pdf PDF
RLP Amendment 3- 36C10F20R0061.pdf PDF
Appendix D-FINAL Lease Code Compliance.pdf PDF
36C10F20R0061_5.docx DOCX document
Pre Bid Registration Information .pdf PDF
RLP Amendment 2 - 36C10F20L0013 - James J. Howard CBOC - VA Lease - L100.pdf PDF
36C10F20R0061_4.docx DOCX document
SF30 A0001 James J Howard.pdf PDF
Amendment I - 36C10F20L0013 - James J. Howard CBOC - VA Lease - L100.pdf PDF
36C10F20R0061_3.docx DOCX document
21 - 36C10F20R0061 - GSA Form 12000 for Prelease Fire Protection and Life Saftey.pdf PDF
14 - 36C10F20R0061 - Past Performance Questionnaire - VA Brick NJ CBOC.pdf PDF
25C - 36C10F20R0061 Monmouth County Wage Determination 1-31-2020.pdf PDF
27 - SF328-18 Foreign Ownership Financial Representation.pdf PDF
10 - 36C10F20R0061 - GSA Form 1364 - Proposal to Lease Space.pdf PDF
22 - 36C10F20R0061 - Contractor Confidentiality Certificate_Physical Security Design.pdf PDF
15B - 36C10F20R0061- GSA_Form_3518-SAM.pdf PDF
26 - 36C10F20R0061 - Pre-Proposal Meetng Registration Form - VA Brick (5).pdf PDF
13 - 36C10F20R0061 - Form VA 10091 - VA FSC Vendor File Request Form.pdf PDF
18 - 36C10F20R0061 - GSA Form 3516 - Solicitation Provisions.pdf PDF
09 - 36C10F20R0061 - Proposal Compliance Matrix - VA Brick .docx DOCX document
12 - 36C10F20R0061 - GSA Form 1217 - Lessors Annual Cost Statement.pdf PDF
11 - 36C10F20R0061- Attachment No. 1 to GSA Form 1364.xlsx XLSX spreadsheet
25A - 36C10F20R0061 - Labor Standards Provisions VA Brick 6-17-2020.pdf PDF
24 - 36C10F20R0061 - SF330.pdf PDF
17 - 36C10F20R0061 - VA 6500.6 - IT SECURITY PROGRAM.pdf PDF
25B - 36C10F20R0061 - Ocean County Wage Determination as of 01-31-2020.pdf PDF
20 - 36C10F20R0061 - Certificate of Building Energy Performance - SF255.pdf PDF
15A - 36C10F20R0061 - GSA Form 3518.pdf PDF
29A - RLP Template Schedule.pdf PDF
23 - 36C10F20R0061- GSA527.pdf PDF
08 - 36C10F20R0061 - Offering Entity Acknowledgement Form.docx DOCX document
28 - Covered Telecommunications Equipement or Services Representation.pdf PDF
16 - 36C10F20R0061 - VA 6500 - VA RULES OF BEHAVIOR.pdf PDF
Show 40 more

Latest 50 of 66 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task

Mode

Task Name Duration Start Finish Predecessors

1 Award - Acceptance 647 days Mon 6/14/21Thu 1/11/24

2 Design Phase 190 days Mon 6/14/21Thu 3/17/22

3 Award 1 day Mon 6/14/21Mon 6/14/21

4 Design Kickoff 5 days Mon 6/14/21Fri 6/18/21 3SS

5 Initial DID Package 20 days Mon 6/14/21Mon 7/12/214SS

6 VA DID Review 20 days Tue 7/13/21 Mon 8/9/21 5

7 2nd DID 20 days Tue 8/10/21 Tue 9/7/21 6

8 VA DID Review and Approval20 days Wed 9/8/21 Tue 10/5/21 7

9 Lessor Developed DID Budget20 days Wed 10/6/21Wed 11/3/218

10 CD 1 40 days Wed 10/6/21Fri 12/3/21 8

11 VA CD Review 20 days Mon 12/6/21Mon 1/3/22 10

12 CD2 30 days Wed 1/5/22 Wed 2/16/2211

13 VA CD Review 20 days Thu 2/17/22 Thu 3/17/22 12

14 Permits 120 days Thu 2/17/22 Mon 8/8/22

15 CZMA and NTPF 120 days Thu 2/17/22 Mon 8/8/22 12

16 Site Permit 60 days Thu 2/17/22 Thu 5/12/22 12

17 Building Permit 60 days Fri 3/18/22 Fri 6/10/22 13

18 TI Negotiation 61 days Fri 3/18/22 Mon 6/13/22

19 Lessor Preparation of

TI Price Proposal

20 days Fri 3/18/22 Thu 4/14/22 13

20 Negotiation of TI 40 days Fri 4/15/22 Fri 6/10/22 19

21 VA Issue NTP 1 day Mon 6/13/22Mon 6/13/2220

22 Construction 417 days Fri 5/13/22 Thu 1/11/24

23 * Early Site Construction120 days Fri 5/13/22 Wed 11/2/2216

24 Shell Construction 300 days Mon 6/13/22Mon 8/21/2317

25 TI Construction 200 days Tue 3/28/23 Thu 1/11/24 24SS+197 days

6/14

6/18

7/12

8/9

9/7

10/5

11/3

12/3

1/3

2/16

3/17

8/8

5/12

6/10

4/14

6/10

6/13

11/2

8/21

1/11

J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J

Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Manual Progress

Project: RLP Template Schedule

Date: Thu 8/13/20 ronken Callout Matches 4.01.F.

ronken Callout Matches 4.01.A.

ronken Callout Does not match 4.01.A., which states 35 days, however, the language is "not later than 35 days" and from a contractual language standpoint 20 days is yes, within 35 days.

ronken Callout Matches 4.01.C. VA DID Review Periods (DID 1 and DID2) match the lease language ronken Arrow ronken Callout Matches 4.01.D. VA DID Review Periods (DID 1 and DID2) match the lease language ronken Arrow ronken Callout Matches 4.01.D.

ronken Callout Matches 4.01.D.

ronken Callout Does not match 4.01.H., which states the Government shall issue NTP within 60 working days. Used 40 days to make schedule work because many of these periods were originally calendar days. 40 working days and 60 calendar days are equivalent. Propose changing 4.01H.

ronken Callout Similar to above, does not match 4.01H. The overall schedule at a desired 31 months only has +/- 672 working days in it, so therefore there is no possible way to have a schedule with 600 working days in it for construction only. The 600 days likely was assumed to be a calendar day calculation. Propose changing 4.01H. to 400 working days