ID Task
Mode
Task Name Duration Start Finish Predecessors
1 Award - Acceptance 647 days Mon 6/14/21Thu 1/11/24
2 Design Phase 190 days Mon 6/14/21Thu 3/17/22
3 Award 1 day Mon 6/14/21Mon 6/14/21
4 Design Kickoff 5 days Mon 6/14/21Fri 6/18/21 3SS
5 Initial DID Package 20 days Mon 6/14/21Mon 7/12/214SS
6 VA DID Review 20 days Tue 7/13/21 Mon 8/9/21 5
7 2nd DID 20 days Tue 8/10/21 Tue 9/7/21 6
8 VA DID Review and Approval20 days Wed 9/8/21 Tue 10/5/21 7
9 Lessor Developed DID Budget20 days Wed 10/6/21Wed 11/3/218
10 CD 1 40 days Wed 10/6/21Fri 12/3/21 8
11 VA CD Review 20 days Mon 12/6/21Mon 1/3/22 10
12 CD2 30 days Wed 1/5/22 Wed 2/16/2211
13 VA CD Review 20 days Thu 2/17/22 Thu 3/17/22 12
14 Permits 120 days Thu 2/17/22 Mon 8/8/22
15 CZMA and NTPF 120 days Thu 2/17/22 Mon 8/8/22 12
16 Site Permit 60 days Thu 2/17/22 Thu 5/12/22 12
17 Building Permit 60 days Fri 3/18/22 Fri 6/10/22 13
18 TI Negotiation 61 days Fri 3/18/22 Mon 6/13/22
19 Lessor Preparation of
TI Price Proposal
20 days Fri 3/18/22 Thu 4/14/22 13
20 Negotiation of TI 40 days Fri 4/15/22 Fri 6/10/22 19
21 VA Issue NTP 1 day Mon 6/13/22Mon 6/13/2220
22 Construction 417 days Fri 5/13/22 Thu 1/11/24
23 * Early Site Construction120 days Fri 5/13/22 Wed 11/2/2216
24 Shell Construction 300 days Mon 6/13/22Mon 8/21/2317
25 TI Construction 200 days Tue 3/28/23 Thu 1/11/24 24SS+197 days
6/14
6/18
7/12
8/9
9/7
10/5
11/3
12/3
1/3
2/16
3/17
8/8
5/12
6/10
4/14
6/10
6/13
11/2
8/21
1/11
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Project: RLP Template Schedule
Date: Thu 8/13/20 ronken Callout Matches 4.01.F.
ronken Callout Matches 4.01.A.
ronken Callout Does not match 4.01.A., which states 35 days, however, the language is "not later than 35 days" and from a contractual language standpoint 20 days is yes, within 35 days.
ronken Callout Matches 4.01.C. VA DID Review Periods (DID 1 and DID2) match the lease language ronken Arrow ronken Callout Matches 4.01.D. VA DID Review Periods (DID 1 and DID2) match the lease language ronken Arrow ronken Callout Matches 4.01.D.
ronken Callout Matches 4.01.D.
ronken Callout Does not match 4.01.H., which states the Government shall issue NTP within 60 working days. Used 40 days to make schedule work because many of these periods were originally calendar days. 40 working days and 60 calendar days are equivalent. Propose changing 4.01H.
ronken Callout Similar to above, does not match 4.01H. The overall schedule at a desired 31 months only has +/- 672 working days in it, so therefore there is no possible way to have a schedule with 600 working days in it for construction only. The 600 days likely was assumed to be a calendar day calculation. Propose changing 4.01H. to 400 working days