This document is an amendment to Solicitation Number 333302-24RF-0010040 for the Smithsonian Institution's Tropical Research Institute (STRI) to replace and reinforce the roof of the Tupper Library in Panama. The solicitation is for construction services to complete the work described in the specifications and drawings. The applicable NAICS code is 236220 Commercial and Institutional Building Construction, with an estimated construction budget between $1-5 million. The contract will be a fixed-price construction contract.

The key details are:

  • The proposal due date is September 23, 2024 at 3:00 PM EST.
  • A pre-bid conference and site visit are scheduled for August 8-9, 2024.
  • Questions and clarifications must be submitted by August 22, 2024.
  • Proposals must be submitted electronically to DropBox.
  • The contractor must be registered in SAM.gov and legally licensed to operate as a construction company in Panama.
  • The document also provides responses to various RFIs regarding the project specifications, drawings, and requirements.

View the file

Other files

File Type Posted
33330224RF0010040 Amendment 2.pdf PDF
HVAC Repl. plan.pdf PDF
33330224RF0010040 RFP.pdf PDF
230417 Reglamento de Seguridad para Contratistas de STRI.pdf PDF
2079202_Final Drawings.pdf PDF
2079202_Final Specs.PDF PDF
2079202 - Tupper Library Roof.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

33330224RF0010040

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

OCON

Washington DC 20013-7012 PO Box 37012

MRC 1200

OCON

OCON

Washington DC 20013-7012 PO Box 37012

MRC 1200

SMITHSONIAN INSTITUTION

207920208/05/20240001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

08/05/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Solicitation Number 333302-24RF-0010040 Replace and Reinforce Roof for Tupper Library amended as follows:

1. Responses to RFI's

THE PROPOSAL DUE DATE IS September 23, 2024, at 3:00PM EST.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Thomas Dempsey

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

# Discipline Reference Query SF Reply Attachment

1 DWG

Checking files sent, the file 2079202_Final Drawings.pdf contains page 18 (A-DT-504) twice and no page 19. Please clarify.

Attached is the A505-DT sheet, which corresponds to sheet 19 of 65 in the set RFI 001 2 DWG Detail for temporary access partition of annex Refer to attachment RFI 002 3 DWG Details for AC replacement for the annex Refer to attachment RFI 003

4 Admin

RFP 52.211-S0099

Para. 32: would local alternatives be acceptable even if they dont meet the technical requirements?

Local alternatives must meet the technical requirements to be acceptable.

5 Admin

RFP Clause 52.213-S0094 Confirm precedence among Technical Specs, RFP & Design.

As mentioned in the RFP, precedence will be in the following order: 1. The Schedule.

2. Solicitation, Instructions, and Conditions (RFP).

3. Amendments to the Solicitation.

4. Contract Clauses.

5. Specifications.

6. The Drawings: large scale details, small-scale details, standard size plans, sections and elevation drawings.

7. Other Documents, Exhibits, and Attachments

6 Admin RFP Section E Will the Designer Firm perform the Inspection? No, inspection is going to be performed by STRI

7 Admin RFP Section E Does the Inspection have the authority to stop any work activity?

No, inspection does not have the authority to stop any work activity. Only the COTR has the authority to stop any work.

8 Admin 01 00 00

Para. 8: To avoid losses to third parties property, will the North parking be evacuated during construction?

The parking area will be designated for activities such as roof lifting and moving heavy materials. The contractor must indicate in their schedule the time these parking spaces will be occupied.

9 Admin 01 00 00 Para.13: indicate applicable standards (Chapter & Paragraph) for coodination drawings.

The contractor is responsible to comply with all applicable codes and standards indicated in the contract documents and spec. Attached a reference list of posible applicable codes and standards for coordination drawings.

9. Standards and codes references for coordination.pdf

10 Admin 01 00 00 Para. 24: indicate approx area designated for Contractor Use.

A space will be designated for the contractor’s use near the roundabout, without affecting the parking spaces. The contractor must assign a security guard for their camp due to the area where it is located.

11 Admin 01 31 00 Para. 1.7.D: Response time of RFI's when the progress depend upon the RFI's answer? The RFI will be addressed as soon as possible; however, the response time remains as specified.

12 Admin 01 40 00 Para. 1.03.E: List all preconstruction tests Spec 01 40 00 1.03 E only refers to the definition of Preconstruction tests.

13 Admin 01 40 00 Para. 1.03.F & 1.03H.1: provide list of acceptable testing agencies

Testing agencies are chosen by the contractor and approved by STRI. However, they must comply with the specifications and be authorized in Panama.

14 Admin 01 40 00 Para. 1.08.B & 1.08.C: Indicate applicable equipment for these reports

The applicable equipment will be the necessary ones to complete the required work and/or tests. It must be validated that the equipment is in good condition and calibrated.

15 Admin 01 40 00 Para. 1.09.G: provide list of acceptable agencies.

Agencies are chosen by the contractor and approved by STRI. However, they must comply with the specifications and be authorized in Panama.

Demolition 02 41 19 para. 1.01: It is understood that demolition of existing CCTV and Burglary system items will be performed by STRI. Confirm otherwise

It must be carried out by the contractor under the supervision of STRI personnel.

Demolition 02 41 19 Para. 1.01.A.4: it is understood that non-reusable systems will be identified/labeled by Others before NTP. Provide precise instructions otherwise

Non of the elements indicated on the construction document as "to be demolished, removed, disassembled, eliminated, discarded, disposed, replaced" or similar will be reused. For the existing infrastructure that feed the Annex upper floors that require to remain operative Refer to the attachment. Existing devices to remain (located on walls that wont be modified) such as electrical outlets, telecomunicacion outlets, security devices, etc.) shall be reconnected to their corresponding panel / rack. For existing devices to remain the contractor have to consider to Re-route and replace pipes/cables to reconect them to their correspondant feeder, refer to exisiting conditions set of plans (reply to RFI 20)

17. Exist infra running from room 113 to annex.pdf

17. Telecom Improv 1997.ZIP

17. Special syst. 1993.TIF

Smithsonian Institution Office of Planning, Design and Construction Construction Division

STRI BRANCH

DATE: August,2024 PROJECT NAME: Replace and Reinforce Roof for Library PROJECT LOCATION: Tupper PROJECT No.: 2079202

REQUEST FOR INFORMATION FINAL RESPONSE

Demolition 02 41 19 Para. 1.01.B: indicates fiberglass as existing hazardous material. During Bid Conference it was mentioned existing asbestos. Please provide precise information

As mentioned during the initial conference of the BID process, asbestos is not expected to be present. However, due to the age of the structure, proceed with caution and notify the STRI team if asbestos is found. Regarding fiberglass, which is highly likely to be present in the ducts, dispose of the waste in plastic bags labeled as fiberglass and transport it to a landfill. For further information on waste handling and personal protection, please refer to the attached Panama Canal regulation, which provides comprehensive guidelines for managing this type of waste.

18. Fiberglass.pdf

Demolition 02 41 19 Para. 1.02: Where to dispose fiberglass per approved Estudio de Impacto Ambiental

The project did not include an Environmental Impact Study (EIA) as it was not required based on the project's characteristics. The procedure for disposing of fiberglass will be explained in Comment #18.

Electrical 26 05 05

Para. 1.03: provide precise information about the existing infrastructure running wthin the ceiling space, so we can estimate the required work. Refer to the attachment. 20.Exisisting conditions

Electrical 26 05 19 Para. 2.01.C: confirm design complies with this paragraph

The design complies with this section since all conductors were selected based on 125% , which corresponds to the breaker capacity.

22 Electrical 26 05 19 Para. 1.02: confirm design complies with Smithsonian Design Standards The design complies with the Smithsonian Design Standards.

Electrical 26 05 19 Part 4 - Remarks: provide answers to Designer remarks

1. All conductors shall comply with the THWN insulation required by the SI.

2. The condition of the grounding mesh shall be verified by the contractor, and it must be ensured that it complies with section 26 05 26 Grounding And Bonding For Electrical systems.

24 Electrical 26 05 33 Para. 2.01.A.2 & 2.01.B.1: confirm minimum conduit size The minimum conduit size used shall be ¾ in accordance with SI.

Electrical 26 05 33 Part 4 - Remarks: provide answers to Designer remarks

1- The minimum pipe size used shall be ¾ in accordance with SI.

2- The specifications of the SI in document 26 05 33 Part 2.01.B.2 must be followed as well as those established in drawing 501-DT in note 11. If any changes are required, this must be notified and approved by COTR.

3- When the piping is underground or embedded, PVC piping should be used to avoid the issue of corrosion due to the environment in Panama.

4- Scale 80 PVC should be used as specified in the SI. If any changes are required, this must be notified and approved by COTR.

26 Electrical 26 24016 Para 2.01.A: confirm design complies with referenced Design Standard The design complies with the Smithsonian Design Standards.

Electrical Dwg E-LP-101 Lighting Schedule: provide manufacturer, & catalog number and mounting height

Refer to attachment 27.Lighting reference info.ZIP

Electrical Dwg E-PP-104 Outlets in referenced Deck: Considering existing floor will not be modify, provide instructions for the electrical conduit for these receptacles

Currently, there are three electrical outlets in the computer area. The wiring will be taken from the nearest existing outlet and routed on the surface inside the reference desk to redirect it to the two outlets shown in the plan.

Please note that these outlets are located under the cabinetry, so the use of surface-mounted boxes will not affect circulation or activities.

Electrical Dwg E-PP-104 Electrical Symbols: provide manufacturer and catalog number

• Conventional Duplex Outlet: Leviton 5325-W or similar

• Wall Switch with light: Leviton L5611-2W or similar

• Electrical Panelboard: G.E. TL30420C or similar

• Safety Switch: G.E. TGN3323R or similar

• TV output: 40681-W or similar

• CDL: the light control may be with a 3-gang box with 3 single pole switches. Can be 3 of Leviton L5611-2W.

Electrical Dwg E-DG-601 Floor Plans do not show location for IP, PNL C & PNL D

The locations for IP, PNL C, and PNL D are shown on the E-PP-104 plan. Specifically, the IP is located on the exterior wall adjacent to Room 111, PNL C is in the closet adjacent to 1CORR-2, and PNL D is situated in Room 113. All these locations are detailed on the floor plan.

Electrical Dwg E-DG-601 We assume that no work is required where no changes are shown

Correct. The plan includes both the existing and the new one-line diagrams. Therefore, if an element in the new diagram remains the same as in the existing diagram, no changes are required for that element.

32 Electrical DWG T-DT-501 Confirm if cable tray supply/installation is included in the SOW Yes, the supply and installation of cable trays are included in the Scope of Work (SOW).

33 Electrical DWG T-DT-501 DT-4: If it is included in the SOW, indicate size of grounding cable The grounding cable size for the DT-4 in Drawing T-DT-501 is 6 AWG Cu.

Plumbing PDT-501 Sheet 65 to 65

General Note No.1: The toilets will remain unchanged both in the supply network com in the drainage Network, however sanitary appliance may be replaced, according to customer requirements . If replacement is required, provide technical specifications

Replacements of the sanitary appliances for the exisitng toilets is not part of the Scope for this BID.

Plumbing PPP101 Sheet 63 to 65 Provide technical specifications for the 4"x2" floor drain. What type of test is required for the connection between the new pipe and the existing one.

Attached is the reference sheet for the technical specifications of the 4"x2" floor drain. Regarding the test, given that the task only involves replacing the drain nozzle and is intended only for air maintenance purposes, no testing is required for the connection between the new pipe and the existing one.

35. ficha sumidero_referencia.pdf

Sprinkler Systems F-DG-603 Are the pipes and valves in the pump room maintained? Nothing needs to be replaced, yes or no

In the pump room, only the control station serving the library on the ground floor will be replaced (it will be 4 inches in diameter).

The contractor shall consider that everything that is not indicated to be replaced is working appropiatly and if any maintenance work is required will be coordinated with the SF-STRI Maintenance department through the COTR.

37 Sprinkler Systems F-DG-603 There are two types of pipe sizes 2-1/2" and 4", please clarify which is the correct size The correct size is 4 inches.

Sprinkler Systems F-DG-603 Provide information on the riser devices to be supplied Attached is the reference sheet with the information on the riser devices to be supplied. 38. manifold 30.72-SPAL.pdf

AC Systems

We require the Plans of the upper area where the temporary equipment is required in order to know the capacity of the equipment to be installed.

Refer to the SF reply on RFI 003.

AC Systems See attached fig No.1 indicate the capacity table of the heaters that are in the supply ducts of the UMAS. The specified equipment in questión 40 and 41 are a heating thermostat and a low-limit discharge thermostat, these devices are part of the existing humidity and temperature control system. These devices will not be needed for the new equipment. The new system needs to be included with its own, new thermostats and humidity sensors, as per specified in control diagram M-602-DG.

AC Systems See attached fig No.2 indicate what type of accessory the one highlighted in light blue would be, if we should consider it in the new quote.

Refer to Reply of RFI 40

AC Systems See attached fig No.3

The dampers that are in the grids on return walls are Fire damper or Fire Smoked Damper.

It´s a Combination Fire and Smoke Dampers

AC Systems See attached fig No.4

The UE-3 duct gates are Fire damper or Fire Smoked Damper.

It´s a Combination Fire and Smoke Dampers

AC Systems See attached fig No.5

What is the description for this accessory indicated in the UMA 2 supply duct?

It´s a Smoke Damper

AC Systems Please indicate whether the new units are to be fitted into any existing control system. If so, what brand of existing equipment would be.

The existing units are not connected to a building control system, but have a control system in the unit itself, using sensors in the ducts and a digital termostat that control the valve that modulate the flow of the refrigerated water.

New units should use the same type of control system, which is shown in the M-602-DG control diagram.

46 AC Systems The condensate pan of the handling unit must be made of stainless steel? Not necessarily, but it must be a corrosion resistant material 47 AC Systems The units will be double walled? Yes 48 AC Systems Do UMAS require AHRI, AMCA, ISO 9001, ISO 14001 certification? Yes, AHRI Standard 430, AHRI Standard 410, UL listed, AMCA 611, ISO 9001 & ISO 14001

49 AC Systems We must assume that the existing shut-off valves are 100% operational? Yes. The contractor shall assume that the shut-off valves are 100% operational.

STRUCTURE

We request structural plans of the existing roof, truss sections, number and size of purlin, gauge of roof sheets, etc.

Refer to attachment.

Download link:

https://www.dropbox.com/scl /fo/8sybwckmtttithms1rlgt/AH xL5MzUlwFfKYJMKIkaMhU?rlk ey=1onnj7ds9n9r3xjz1ld4di6p 9&dl=0

STRUCTURE DWG A-SC-301/S-SC-303

In structural frame 8 it is indicated to place a new truss (truss CH-8) on an existing truss, during the site visit the existing truss could not be observed, everything indicates that it does not exist or that it is embedded within the wall of the second floor, please provide the details of the supports of this new truss considering that in plan A-SC-301 and S-SC-303 it is shown adjacent to the wall of the second floor of the building. Additionally, the project does not consider the intervention of the walls of the upper floors.

It will be assumed that the existing truss is located as indicated in the plans. If is determine during construction that the truss is not correctly positioned, the A/E will develop an alternative structural proposal in coordination with the contractor to address the issue. Any additional costs incurred will be recognized.

STRUCTURE dwg S-SC-301 Provide the connection detail between the new truss on the existing triangular truss, confirm the quantity; or the new truss will not rest on the existing one?

The new Truss will not rest over the existing triangular truss. It will rest over it on the columns.

STRUCTURE DWG S-DT-502

Detail DC-A/S-502 indicates placing a plate on the existing column, currently we have the upper chord of the truss resting on the column which would not allow the requested plate to be placed, please expand on how to make the connection of the new truss on the column

The structural detail considers a special shape to be fabricated (based on a Wideflange shape) in order to weld around the existing elements without having to dismantle or cut any element of the triangular truss. See attatchment (DC-B /S-507) This Element consist of a new WF 8x24 Column with a cut off area to accomodate the upper support on the existing trus (pinned support as can be seen in existing drawign extract).

53. 1981-07 Tupper Library

STRUCTURE DWG S-DT-502

Detail DC-C/502 does not show the lower chord tubes and the diagonals of the existing truss, please expand the connection of the w8x24 column section to the existing column considering the existing tubes.

See comment above.

STRUCTURE DWG S-SC-303 Please send details of the connection between the trusses of axes 1-8 with the trusses of axis B.

All trusses are welded connections as typical. See Geometry of Truss CH1 and Structural Framework 8

56 PAINTING SECTION 09 90 00 Section 05 12 00 cited in paragraph 1.2 does not appear in the specifications Please refer to Section 05 12 23. The section 05 12 00 is the main title.

PAINTING SECTION 09 90 00

In paragraph L, (1 to 10) it mentions the different types of cleaning for structural steel, but does not indicate which one to use, please confirm which will be the cleaning method for new structural steel elements, trusses, plates, columns

Typically, the painting system selected by the contractor (Bidder) depends on the recommended Manufacturer´s instructions. Please investigate with a Supplier which the specs match with the requirements, then propose the surface preparation level as per SSPC.

PAINTING SECTION 09 90 00 What type of primer will be used for corrosion control on structural steel? latex system?

Refer to Reply on RFI 57

PAINTING SECTION 09 90 00 What type of primer will be used for corrosion control on structural steel? latex system?

Refer to Reply on RFI 57 60 PAINTING SECTION 09 90 00 What type of finishing paint will be used on structural steel? Latex system? Refer to Reply on RFI 57

61 PAINTING SECTION 09 90 00

Will it be necessary to remove the paint and repaint the existing truss to be maintained? If so, what cleaning method would be acceptable? Refer to Reply on RFI 57

DEMOLITION 02 41 19

In paragraph 3.02 PROGRAMMING, items to be rescued for delivery to the owner, point f. steel structures, please list which elements of the structure to be removed must be delivered and to what location.

No elements will be delivered.

DEMOLITION 02 41 19

1.02 submittals, AUTHORIZATIONS paragraph, does part of the demolition include fiberglass in any area?

Refer to the SF reply on RFI 018.

COORDINATION 01 31 00

Considering that the perimeter area of the project will remain acƟve, will STRI request a special perimeter enclosure? in terms of type of material, height, color.

Refer to attachment.

64. Temporary perimeter enclosure

COORDINATION 01 31 00

Will the parking area in front of the project be allowed to be used as maneuvering area when removing and installing the roof structure?

Yes, the parking area in front of the project will be allowed to be used as a maneuvering area when removing and installing the roof structure.

66 Architecture A-SH-601 How many keys should be included per door? Include three (3) keys per lock. Cormax locks shall be used for Smithsonian projects.

67 General General Should the cost of construction and occupancy permit taxes be included in our scope? Yes, all permit taxes shall be included.

Electrical E-DG-601

Can the work required for interconnections or adjustments within operational environments be done during daytime hours, or is a special work schedule required?

It can be done during regular hours but must be coordinated 48 hours before.

General General What would be the final position for placing the camp?

A space will be designated for the contractor’s use near the roundabout, without affecting the parking spaces. The contractor must assign a security guard for their camp due to the area where it is located.

70 Telecomunication T-GI-001 Are special systems included in the scope? (CCTV, Access control, Voice and data) Yes

Structure S-SC-301 Is a specific type of material required for the temporary roof?

No, the material will be suggested by the contractor and approved by the design manager, as long as it offers adequate coverage.

Structure S-SC-301 Should this temporary roof be installed only beneath the existing roof? If it is installed this way before removal, it would need to be placed under the current visible trusses. However, the resulting height is not ideal. Have you considered any other options to address this situation?

The contractor will be responsible for managing the logistics of installing the temporary roof and evaluating the most suitable options to ensure an effective installation.

Structure S-SC-301

Upon evaluating the activities, we realized that it might be necessary to work around the exterior perimeter of the building, for example, to install the A/C equipment or others demolitions.

Therefore, we request that you consider restricting access to people around the perimeter of the work area.

This can be coordinated during the construction.

74 Finishes A-NP-102 The finishes plan mentions painting all existing walls. Please confirm. Correct.

Finishes A-NP-102 Will it only be internal painting, or does it include external painting as well?

External areas will also be painted, as they will be affected during the work.

The specifications for the external painting are as follows:

1. Washing of External Walls stained with foreign substances and detachment of the paint that is in poor condition and loose. Use a biocide product similar to Jomax or D/2.

2. Sealing of external cracks by means of sealants for external cracks (depending on the affected areas) of manufacturers Glidden, Sherwin Williams or similar products.

3- Application of Base Sealant The contractor will use Benjamin Moore sealant

4. Apply the finish paint to at least two (2) layers. The paint should be anti-fungus in matte finish Benjamin Moore exterior paint.

Architecture A-IF-901 Is the furniture included within the scope of this project?

No, as indicated in the furniture plan A-103RP, the only furniture included in the scope is the reference desk, which is custom-made and has its details specified in drawing A-901IF.

Architecture A-SH-601

In the door plans (sheet 20) , the notes mention 'refer to cutsheets for more information' in certain places. However, these sheetcuts are not visible in the plans. Could you please specify where these sheetcuts can be found?

The cutsheets related to the doors can be found in the attachments. 77. DOORS - CUTSHEETS

Architecture A-SH-601

Will the magnetic lock also be installed on doors 101A and 122? This is mentioned generally in the notes, but it is not specified in the details for these doors."

No, they will not have magnetic locks. The doors equipped with magnetic locks are indicated on drawing T-102TY.

Electrical E-DG-601 Is the only panel to be intervened the new one? Please confirm.

No. The plan includes both the existing and the new one-line diagram. Therefore, if an element in the new diagram differs from the element in the old diagram, the equipment need to be modified according to the new plans.

Fire Alarm F-DG-601 What is the model of the alarm panel on-site? (We couldn't see the label because it was covered)

Simplex-4100-8601

Fire Alarm F-DG-604 Is the clean agent system included in the scope of the project? Yes, everything shown in the plans should be considered part of the scope, including the clean agent system.

Fire Alarm F-DG-604

Should the existing detectors and equipment that need to be dismantled be reused, or will they be fully replaced as indicated in the plan?

All detectors are new, only equipment marked on the plans as existing can be reused.

Fire Alarm F-FA-101

The symbols for these devices shown on the plan (TTP, TDP) are not found in the symbol table.

Those are fire alarm system accessory panels found in the existing conditions survey.

Fire Alarm F-FA-101

Confirm the location of the existing panel. During the visit, it was confirmed that the panel is located in the mechanical room within the building.

According to the existing conditions survey, the fire alarm panel is located in the working area - Room 113.

Fire Alarm F-FA-102

What would be the suggested model for the zone adapter module and the device control module? This is because these modules will be connected with other plants according to the plan.

Simplex 4090-9101, 4090-9106

Fire Alarm Specs section 05 12 23

In section 05 12 23 Structural Steel for Buildings, it is mentioned that the painting system will be according to division 09 90 00 Painting. However, the information in this section is very generic.

Can you provide us with the specific painting system to apply? Type of cleaning, type of product, number of coats, and thickness of the layers?

Refer to Reply on RFI 57

Fire Alarm FX-102 The note on sheet FX-102 indicates that "ALL SPRINKLERS IN ZONE 2 WILL HAVE SPRINKLER GUARDS." Please indicate which is Zone-2.

The following image shows (highlighted) the indication of zone 2 on sheet FX-102. It include the annex building´s ground floor.

Fire Alarm FX-102

The Hydraulic Summary on sheet FX-102 indicates an estimated system demand of 739.85 GPM and a minimum pressure of 57.46 PSI. This sheet also indicates that the fire pump is existing, and on sheet DG-603, the sprinkler system isometric indicates a fire pump with a capacity of 250-GPM

vs. 90-PSI. Please indicate if the replacement of the existing fire pump should be considered or if the pump indicated in the isometric should be maintained, and it is already considered in the design shown on the plans that the capacity of the existing pump is sufficient to meet the estimated demand of the remodeled system.

The existing pump will remain unchanged in this phase of the project. There is another project that will address the conection of the system to a new pump, but it is not part of the scope of this BID.

Fire Alarm DT-503

Please indicate if we should assume in the proposal the cost of using pipes with larger diameters than those indicated on the plans in case the hydraulic calculations show that it is necessary to modify what is indicated in the supplied plans for quotation, or if it is necessary to add sprinklers to achieve the coverage indicated in Notes 7 and 8 of sheet DT-503.

Please base your proposal on the provided plans.

Fire Alarm AD-CP-102

Please indicate if any of the pipes from the existing sprinkler system that we understand are supported by the ceiling that will be demolished can or should be reused.

All pipes must be replaced.

Fire Alarm F-DG-603

Please indicate if the existing control valves, water flow alarms, manifolds, and check valves should be replaced.

All control valves, flow switch, check, drain valves must be replaced.

Fire Alarm F-DG-604

Please indicate if the clean agent suppression system required for the Special Collection area needs to use a specific design concentration to estimate the required amount of agent.

This is specified in the document TECHNICAL REPORT FOR CLEAN AGENT SYSTEM - NOVEC 1230. Refer to the attachment.

92.Tech Report-Novec 1230.pdf

Fire Alarm Specs section 2.01.A.3

In section 2.01.A.3, it is indicated that schedule 40 piping is required for pipes less than 4 inches.

In section 2.01.A.4, it is indicated that threaded couplings and accessories should be used for pipes less than 4 inches. In section 3.01.I.J.1, it is indicated that threaded unions should not be used in pipes with diameters greater than 2 inches. Could you please clarify the requirement? It is usually allowed to use grooved-rolled joints on 2-inch and larger schedule 10 pipes and threaded joints on 1-1/2” and smaller schedule 40 pipes. The use of Listed schedule 10 pipes allows for greater hydraulic efficiency and also reduces the load on the ceiling structure.

The first specification is according to the SI standard, while the latter is according to NFPA 13, The contractor must meet the SI standard for the job.

structure S-SC-301 The roof structure framework requires the detail of sections A’ - A - B’ - B - C’ - C.

If you have any specific questions, please consult. For now, the provided drawings contain the complete information.

structure AD-EL-201 To carry out the demolition of the roof structure, it will be necessary to demolish a section of the wall of the adjacent building. Is there any inconvenience with this?

No demolition on the wall of the Annex building is desired, If during the execution is dicorvered that is needed and RFI shall be presented to STRI in order to get a formal approval from the COTR. For more details on what to assume refer to SF Reply to RFI 051. Also Refer to the existing structures plans shared on the reply to RFI 050, Detail 2B of the file "1993 Library Roof 3" from the Tupper Library expansion, if was executed as the detail recall, wont be a need for such demolition.

Electrical E-SH-602 What brand and model of the panel is existing?

• MDP : Cutler-Hammer Model: PH304ML400S

• Panel / 1 (A): G.E.

Model: TL4020F

• Panel / 2 (B): G.E.

Model: TL3020F

97 Architecture A-IF-901 Should the installation or placement on-site of the movable furniture that SRTI will supply be contemplated?

No.

Architecture A-IF-901

Are the tables and chairs located in the Special Collection reading area included? More details of this are required.

No, as indicated in the furniture plan A-103RP, the only furniture included in the scope is the reference desk, which is custom-made and has its details specified in drawing A-901IF.

Architecture A-SH-601

What would be the finish of the metal doors? The plans do not indicate the type or color of paint for these.

The finish will be gray, in a shade similar to the existing gray doors.

Structure A-DT-503 An isometric plan of the roof structure is required.

If you have any specific questions, please consult. For now, the provided drawings contain the complete information.

Structure A-DT-503

The detail of the connection of the CH-2 trusses is required as the support for these is not shown in the plans.

The connection details can be found on drawing S-502DT. If these details are insufficient, please specify the exact location where additional details are needed.

102 Architecture A-DT-502 Is it possible to use an alternative brand of ceiling panels?

If required, the contractor must submit alternative brands of ceiling panels to be considered by the design team.

Those brands must meet the specifications outlined in the plans.

Architecture A-DT-502 What brand of wall paint is required?

The color specified in the plans refers to a Sherwin Williams paint palette, but the final paint brand required by STRI is UltraSpec Benjamin Moore.

HVAC M-DT-503 & M-DG-602

For the air handling units on plans M-DT-503 & M-DG-602, a three-way valve is observed in the piping accessories diagram for the equipment. Should this motorized valve be of independent pressure (PICV)?

The three way valve is existing and in case a replacement is needed, it must be of the same type as the existing one.

HVAC M-DT-503 & M-DG-603

There are no indications on the plans for the deinstallation of existing equipment and materials.

Where will these equipment and materials be disposed of, or what will be the logistics for this?

Refer to note 6 on Sheet AD -CP - 102.

HVAC M-DT-504

The existing chilled water pipes that are throughout the library area, will they be replaced from the main stake or only in the machine room?

The existing cold water piping will remain, not to be replaced.

HVAC M-DT-505

For the insulation of the chilled water pipes, it is indicated that it should be polyurethane foam.

Can an insulation similar to Thermaflex be used?

Yes. No specific type of insulation is specified in the SI norms and standards for piping. Minimum piping insulation thickness for cooling systems shall be in accordance with ASHRAE 90.1 Table 6.8.3-2 as mentioned in spec 23 07 19

General General Will payments for water and electricity consumption be your responsibility? Yes, SI will provide water and electricity but the temporary connections are responsibility of the contractor.

General General

We request indications of the type of temporary enclosure that will be used perimeter for the transit of people.

Refer to the reply on RFI 64.

General General

During the visit we requested to be able to have the entire area of the current parking lot that exists in the back, this due to issues of lifting and mobilization of materials. Confirm if it will be like this to be able to contemplate the logistics.

Refer to replay of RFI #8

General General During the tour, we observed several trees that passed part of their branches towards the roof, confirming that we would only be pruning it and that for this reason it does not require any special permit from ANAM.

If it only involves cutting some branches, no permit from ANAM is required.

General General

Confirm if all disconnections and removals of special systems equipment will be carried out by you with your suppliers.

Refer to reply of RFI #16

General General

According to the visit, they indicated that they would be sending a number of ml of pipes and wiring systems to reconsider when removing the ceiling and roof, since we are not sure if part of the existing that feeds the other areas can be maintained.

Refer to reply on RFI 17 & 20.

General General

Confirm that you will be responsible for leaving the area completely clear without furniture or equipment.

Yes, STRI will be responsible for leaving the area completly clear without furniture or equipment.

Architecture A-NP-102 In areas where walls will be removed and floors will be left bare, will we have to remove complete pieces of flooring and replace them in order to follow the same format?

It must be ensured that during the demolition process, damage to the floor pieces is minimized, with the objective of avoiding the complete removal of the tiles. In cases where the damage is significant and it is not possible to repair the affected pieces in situ, it will be necessary to install a new tile as specified in the finish schedule.

Structure General During a visit, a contractor realized that the beam to support the truss that is attached to the building is on the internal axis of the building and not on the side where we are going to work on the truss. They commented that they would send a detail for this connection.

For more details on what to assume refer to SF Reply to RFI 051. Also Refer to the existing structures plans shared on the reply to RFI 050, Detail 2B of the file "1993 Library Roof 3" from the Tupper Library expansion, if was executed as the detail recall the exisitng trust shall be accesible form the side where the work will be excecuted.

Structure

We were unable to obtain the detail of the connection of the new structure with the existing one on axis 8

Details DC-C S507 should apply. It is important to note that Truss type "A" from existing condition drawings is concealed in the exisiting wall, thus exact details of this truss as it has been built are not available. During demolition, the condition of Truss "A" should be evaluated and analyze if this shall be kept and truss CH-8 is built beside, or replaced by CH-8. However, if additional information is needed at the time of execution, this will be provided by the A/E.

Electrical E-PP-104

Reviewing the outlet plans, they are adding new outlets to the customer service furniture. If we are not going to remove that floor, how would we do the installation?

Refer to SF Reply on RFI 028

Architecture A-NP-102

Please indicate the model, format and brand of the current apartment to consider in replacements in the areas to be demolished.

If refering to the Floor finish, the exisitng model/format is not available on the market. The only information that we know is that is a porcelanato. The contractor shall consider what is indicated in the finish schedule for the corresponding areas where the existing floor finish will be affected.

120 Telecomunication General Will the special systems as always be installed by you? Refer to reply of RFI #16

121 General General Please confirm working hours Working hours will be from Monday to Saturday, from 7 AM to 4 PM

General General

Will the existing bathrooms have some type of renovation? Or do they stay on the floor, fixtures and walls as they are?

The existing bathrooms remain the same in terms of finishes (walls and floor) and doors. The only renovation included in the bathrooms are the demolition and replacement of the ceiling finish and ceiling devices as indicated on the Mechanical drawings for those areas.

Architecture A-NP-102 In the finishes box there is an item that indicates: nickel finish covered column. Can you specify exactly what this finish is?

The powder nickel finish at finishes schedule is the name of the finish distributed by MÓZ. They distribute this kind of cover for columns. The specific model that we have specifed is CC100. Details of these elements can be found on drawing A-501DT (DT20, 21,22,23,24). Here is a picture of the powder nickel finish look:

Architecture A-NP-102 What would be the specifications for exterior paint? We only see the one inside. Refer to reply on RFI 75. Colors should match exisiting- codes to be provided by the COTR during the execution.

Architecture A-NP-102 Can you better specify what you mean by patched concrete on the floors? a finish exactly?

By "patched concrete," we are not referring to a specific finish. The existing floor is covered with vinyl, which must first be removed. Next, any cracks in the concrete should be repaired using an appropriate filler or additive (by this repais we are referring to patch concrete). Finally, the concrete must be polished to achieve a smooth surface.

Architecture A-CP-105

In these areas we see that there is no sky marking, is this an error in the plan?

It isn't a draft error, in those parts indicated, there's no ceiling because the roof in those spaces has a different shape. For further clarification, please refer to drawings A-DT-502, DT1, and DT2.

Sprinkler floor F-FX-102

Does the existing sprinkler pump system require any maintenance? What company currently provides this service for warranty issues?

The contractor shall consider that the existing pump system that is not indicated to be replaced is working appropiatly and if any maintenance work is required will be coordinated with the SF-STRI Maintenance department through the COTR.

HVAC M-HP-101 We do not see the thermostat outputs on the plans.

UE02 Thermostat is in RM 113, UE01 Thermostat is in RM 117, UE03 Thermostat is in RM 124. All Thermostats are showed in M-101-HP

Architecture A-CP-105 Above the slatted ceiling, should the ceiling structure be painted?

Yes, the structure above the ceiling should be painted (refer to spec 09 00 00). However, the contractor must propose the painting system based on the manufacturer’s recommendations. The manufacturer will specify the necessary substrate preparation. In principle, it should be the same system used for the new trusses. Typically, this involves SSPC-SP3, depending on the type of paint used. Additionally, the structure below the ceiling must be repaired and painted if any damage occurs during construction (refer to the demolition note).

General Requirements

33330224RF0010040 RFP

SOLICITATION OFFER AND

AWARD

Section M /Evaluation factors for Award 52.247-S0090 Evaluation Factors

Evaluation of offer is described in this section.

But does not specified what % is assigned to the different sections of the offer evaluated Please expand on the evaluation process of the proposal.

During the review of proposals, the technical proposal (plan of accomplishment, key personnel and past performance) is evaluated first, where scores from 1 to 5 are assigned: 1 (Unacceptable), 2 (Marginal), 3 (Acceptable), 4 (Good), and 5 (Outstanding). This evaluation checks that the requirements in the RFP are met and that it is applicable to the project being bid on. After this, prices are evaluated; however, only the prices of bidders who have obtained a score of 3 (Acceptable) or higher in their technical proposal are considered.

General Requirements

01 00 00 Supplementary conditions for construction

8.1 Conditions affecting

contractor's work

"The project area will be vacated" Please confirm what will be removed from project area and what will remain.

The space will be free of movil furnitures and users belngings / equipments (such as computers, latptop, phones, printers, etc.). On site will remain all the fixed elements (such as fixed furnitures, bathrooms accesories, wall, ceilings, doors, etc.) and the main equipments that provide services to the building (OPS and OIT racks & panels, HVAC units, etc.).

General Requirememnts

01 00 00 Supplementary conditions for construction

21. Dust and air quality control

Will it be required to submit a plan to deal with dust and air quality during demolition works? This plan is not required for the technical proposal but will be required for construction.

General Requirememnts

01 00 00 Supplementary conditions for construction

22.1 Noise control

Do we have a no-noise (during demolition in particular) hours during the working day?

There are no no-noise hours during the working day. However, if it is necessary to suspend noise for a specific activity, it will be coordinated with the contractor.

Metals 05 12 23 Structural steel

1.05 Connection design

requirement

Drawings (in general) show welding connections.

Project specifications make reference to both welded connections and bolted connections.

Will bolted connections be permitted if meet AISC guidelines?

Will bolted connections require a shop drawing signed by a Panama licensed civil engineer?

it is preferable to keep the connections as welded. Process of designing, approving and fabricating bolted connections may increase the total duration of the project.

Demolition DWG AD-XP-101 (Page 2/65) Notas de demolicion, 16

Note 16 of the demolition notes on the referenced drawing states” the contractor must request a “fire system impairment permit from the owner”.

Please list the contractor’s requirements to solicit such permit.

Refer to the attachment for reference on the process and requirements.

135. Appendix N - Fire permint Impairment

Fire Suppression

DWG F-FX-102 (Page 46/65)

In Drawing F-FX-102 there is a note indicating all sprinklers in zone 2, will carry sprinkler's guards, but the limits for zone 2 are not indicated. Can you mark in a box Zone 2 limits?

Refer to reply on RFI 87

Fire Suppression

DWG F-FX-102 (Page 46/65) DWG F-DT-503 (Page 49/65)

Symbology in drawing F-FX-102 shows some installed sprinklers to be relocated and others to be maintained and a note in the same drawing says that all fire sprinkler systems should be removed, additionally a note in drawing F-DT-503 says that we have to reused sprinklers in good shape. As per NFPA 13 and SPEC 211313 3.01.E, we can't reuse sprinklers when they are uninstalled. Can you confirm that all the components and sprinklers to be installed had to be new?

All sprinklers will be replaced

Fire Suppression DWG F-FX-102 (Page 46/65)

Symbology in drawing F-FX-102 shows a new hose cabinet and extinguisher, but we can't find any new one in the drawing; only one existing. Can you confirm if we have to install a new hose cabinet with extinguisher and if it is necessary in what place?. We have to replace the existing hose cabinet and extinguisher?

The cabinet will not be replaced, the existing extinguishers will.

Fire Suppression DWG F-FX-102 (Page 46/65)

In drawing F-FX-102 there are only shown 3 fire stop passes for fire sprinkler pipes. Can you confirm that these are the only fire stop passes needed? Are we need to consider other pipes passes that need fire stop systems? Is the answer is yes, please mark it in the drawing to be taken into account.

All pipes (from all systems not only fire suppression) that penetrate a fire rated wall are required to comply with detail DT2 on sheet A-104. Refer to the location of the fire rated barriers locations on the same sheet (A-104).

Consider that on the annex side the wall are full height and on the reading area (where the roof is going to be replaced) the walls are not full height (to the roof). The contrator need to coordinate the paths and the penetrations barriers accordinly.

Fire Suppression

Can you confirm that the fire pump and fire pump's specs are not included in the scope of this work?

The pump is outside the scope of the project.

Fire Suppression

DWG F-DT-503 (Pag 49/65) 21 13 13 Wet-pipe sprinklers systems

Notes in drawing F-DT-503 says design is based in NFPA 13 2012 but specs 211313 WET-PIPE SPRINKLER SYSTEMS in say NFPA 13 2019. Has the drawings notes more precedence than the specs?

The specification continues as a guide, the project will be governed by the NFPA-2019 regulations.

Fire Suppression Spec 21 13 13 Wet-pipe sprinkler systems, 1.07

Specs 211313 WET-PIPE SPRINKLER SYSTEMS in 1.07 says that the sprinklers heads has to be align with the reflected ceiling and all ceiling-mounted equipment, such as diffusers, lights, security cameras, fire alarm systems, exit signs and other items but we are not the designers. Can you confirm if the designers take into account all these requirements in the design of the fire sprinkler systems?

In the annex area, the sprinklers will be installed 20 cm below the ceiling, while the pipes will be level with the top of the slab. This arrangement ensures there will be no interference with other elements, as the pendant lights hang 10 cm from the ceiling, allowing the pipes to be positioned above them and the sprinklers to be at a lower level. In the rest of the library, the sprinklers will be flush with the ceiling.

We are also considering that trusses will cause interference in some areas.,this interference has been anticipated and is permitted according to norm 10.2.7.1.6 and 10.2.7.2.1.7 from NFP-13_2019.

However, we have identified two lineas of sprinkles that during construction must be relocated 30cm away from the location indicated in the drawings to avoid interference according to the norm. If a detailed plan with this adjustments is required it will be provided once the contractor is selected.

Fire Suppression Spec 21 13 13 Wet-pipe sprinkler systems, 2.03.C.1

Specs 211313 WET-PIPE SPRINKLER SYSTEMS 2.03.C.1 says a wet pipe system shall be provided with a listed relief valve not less than 1/2" set to operate at 175psi or 10 psi in excess of the maximum system pressure, whichever is greater, but in the drawings there are no indication in what place to put this. Please confirm: are we have to include a relief valve in the riser manifold or any other place in the sprinkler system? If the answer is yes, please mark or indicate the place to be installed.

The system pressure is below 175 psi, however the relief valve must be considered in the zone control, as planned for the future

Fire Suppression DWG F-FX-102 (Page 46/65)

The fire sprinkler system drawings do not have any…