33330224RF0010014 Amendment 0008.pdf
PDF 2 MB Posted
- Solicitation number
- 33330224RF0010014
- Issued by
-
Smithsonian Institution
About this file
This document is Amendment 0008 to a solicitation issued by the Smithsonian Institution for the Renew Cheetah Conservation Station - Africa Trail (CCS-AT) project at the Smithsonian's National Zoo and Conservation Biology Institute in Washington, DC. The key details are:
The solicitation is for a firm-fixed price contract with a 730-calendar day period of performance from the notice to proceed. The scope of work includes mechanical, electrical, and plumbing system upgrades, security and infrastructure improvements, stormwater management, yard renovations, fencing, and pedestrian surface repairs. The project has several critical elements such as coordination with an occupied campus and specialty animal handling systems. The solicitation includes subcontracting goals of 40% small business, with specific percentage goals for small disadvantaged, woman-owned, HUBZone, veteran-owned, and service-disabled veteran-owned small businesses. Amendment 0008 provides responses to RFIs 188-199 and includes additional documents. The bid due date is Thursday, May 30, 2024 at 3:00pm EST.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
33330224RF0010014
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
OCON
Washington DC 20013-7012 PO Box 37012
MRC 1200
OCON
OCON
Washington DC 20013-7012 PO Box 37012
MRC 1200
SMITHSONIAN INSTITUTION
203310805/20/20240008
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
04/01/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Thomas Dempsey
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
A. The Solicitation Number cited above, to Renew Cheetah Conservation Station - Africa
Trail (CCS-AT) at the Smithsonian's National Zoo and Conservation Biology Institute
(NZCBI), located in Washington, DC, is hereby amended as follows:
A.1. Attached hereto and made part of this Amendment Eight are the following:
SI Responses to RFI's for Questions Number 188 to 199 (additional RFI's will be posted soon)
Document H - Restroom Accessories
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED
33330224RF0010014/0008
PAGE OF
2 24
NAME OF OFFEROR OR CONTRACTOR
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
A.2. Offerors shall acknowledge receipt of all amendments to this solicitation signed and dated and submit with proposal.
B. THE BID DUE DATE IS THURSDAY, MAY 30, 2024, AT
3:00PM EST.
Except as provided herein, all other provisions, terms and conditions of the Solicitation remain unchanged.
END OF AMENDMENT EIGHT
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Last Updated: 5/20/2024 Renew Cheetah Conservation Station (CSS) - Africa Trail - Pre Bid RFI Tracker RFI # Company Name RFI RFI Answer 1 Grunley 1. Section L.3. Past Performance requires three projects of similar size and scope, and indicates that, “projects should demonstrate experience working in: an operating urban campus; constrained sites with limited laydown area, and; adjacency to public areas and animal habitats.” Please confirm that the three projects can be adjacent to public areas and/or animal habitats.
Three projects can be adjacent to public areas and/or animal habitats. Higher consideration will be given to projects adjacent to public areas and animal habitats.
2 Abacus Sports I just left you a message regarding the Cheetah project that is out to bid. Your specs and finish schedule call for our Padenpor DLX, but spec seems to be written around a Stonehard product with using Stonclad epoxies and mortars. It reads like the specification have been mixed together.
Which product do you want for these floors ((FLR – 2). Assuming you do want our floor, what thickness do you want?
Please see attached our flooring spec. Padenpor is available in different thicknesses.
Please note the two specs and BOD for each:
1) RESINOUS FLOOR SYSTEM BASIS OF DESIGN STONEHARD STONE CLAD GR, Spec 09 6723
2) RESILIENT FLOORING BOD ABACUS PADENPOR DLX™ – 9/16" CUSHIONED ZOO FLOORING, Spec 09 6567 See sheet A501DT for details
3 WM Schlosser 1.Spec Sec on 051200 Structural Steel Framing (part 1.06-D) calls for “A qualified steel fabricator that is accredited by the International Accreditation Service (IAS) Fabricator Inspection Program for Structural Steel”. Since most local fabricators do not have this IAS accreditation, can this requirement be waived? If not, can you add “or AISC Certified Fabricator Category BU” to this requirement?
IAS and AISC BU certified fabricators are acceptable
It is acceptable to lower the requirements to include AISC Certified Fabricator Category BU (Building Fabricator). - AE / McM
4 Whiting Turner Executive Order (EO) 14603 indicates that all federal projects valued at $35 million and above will require a project labor agreement (PLA) unless a federal contracting agency expressly grants an exception. As the expected project value is under this limit, please confirm if a project labor agreement will be required on this project.
Until further notice, PLA is not required
5 Whiting Turner Based on the technical nature and specialty aspects the project includes, is a bid extension anticipated?
At this time an extension is not being issued
6 Whiting Turner Please clarify if CAD files, or the project model can be shared for use in the RFP submission. CAD files will be shared with the awarded GC. Please note that BIM was not a requirement for the AE to use during document production so the drawings were created using a multitude of software’s including Revit (BIM) and AutoCAD. All bidders should assume 2D CAD only.
7 Whiting Turner Referencing the solicitation, Section L, 52.244-S0013 Subcontractors, Item (b) (1) (Page 149 of 183) notes subcontractors must be named (10) days after subcontract execution. This seems to contradict Section L, 2. Key Personnel and Subcontractors (Page 177 of 183) where it notes the submission of major subcontractors to include organization plans, resumes, past projects ,etc.
Please confirm if subcontractors may be named following success award and are not required to be named as part of the bid submission process.
Subcontractors are required to be named as part of the bid submission process.
8 Whiting Turner Referencing the solicitation, the FUNDING INCREMENT portion lists “Testing and Commissioning” as a cost line item (Page 14 of 183). Please define this line item as an independent commissioning consultant will be held by Smithsonian as outlined in specification section 01 9113, 1.1 A
Confirmed Smithsonian will provide an independent commissioning consultant, but the does not diminish the contractor's contract requirements for prejunctional testing and operational verifications.
9 Whiting Turner Referencing the solicitation, Section L, L.3. 52.216-1 Type of Contract notes a Firm Fixed Price contact will be utilized but does not clarify contact type. Can a sample contact be provided for review?
This is a Firm Fixed Price Contract. Reference Federal Acquisition Regulations (FAR) Part 16 Types of Contracts, specifically FAR 16.202. A sample will not be provided.
10 Whiting Turner Referencing the solicitation, Section C (Page 15 of 183) notes schedule duration of 730 calendar days from Notice to Proceed (NTP) and reference target schedule dates. Schedule requirements per Specification Section 010000 is reference under L.29.1.A of the solicitation (page 175/183) but does not provide any information on schedule milestones.
a.Please verify the an cipated No ce to Proceed for the project.
b.Please provide a schedule outline including a NTP, phases of work, target dates/milestones and required substantial completion and required completion dates.
c.Please clarify any work constraints through the years of the project.
In response to several questions:
SI Milestones - After the contract is awarded SI will work with the contractor identifying tasks to be tracked to measure progress. This project is not phased with a NTP date, contract duration, completion date with multiyear funding.
a) October 2024
b) This is a contractor requirement that incorporates means and methods.
c) Multi-Year Funding
11 Whiting Turner Please confirm a cost loaded schedule is required per 1.3.B of specification section 013200. Confirmed
12 Whiting Turner In Specification Section 01 1000 1.6.B work hours are listed as 6:00 AM – 6:00 PM. In Specification Section 01 1000 1.7 C, normal work hours are referenced at 6:00 AM-2:30 PM. Please clarify.
As project requirements change work hours can be adjusted with coordination with the COTR. For this project noise concerns with our adjoining residents has often limited the work hours.
13 Whiting Turner Referencing the solicitation, Section L.31. 52.219-S0097 outlines the Small Business Subcontracting Plan (page 179/183). Please clarify if the Small Business and Small Disadvantaged Business Subcontracting Plan shall be submitted as part of the overall proposal, or submitted by the successful bidder following subcontractor naming (see question #5).
Small Business Subcontracting Plan will be submitted by the successful bidder. See contract clause 52.219-S0097(b) on p. 179.
14 Whiting Turner Referencing the Solicitation, Section F, 52.211-S0025 , (c ), (4), (iii) (Page 21 of 183) references defined allowances for normal inclement weather. Please define the weather allowance to be carried in the contract schedule.
If there are abnormal inclement weather, such as rain, snow or extreme temperature, a time extension may be provided.
15 Whiting Turner Referencing the solicitation, Section H, 52.236-S0030 Availability and Use of Utility Services (Page 28 of 183) and Section H, 52.236-14 (page 116 of 183) please confirm utility consumption on the project will be by The Government.
Confirmed, contingent on the contractor implementing basic energy conservation measures.
16 Whiting Turner Referencing the solicitation, Section L 31. 52.219-S0097 outlines goals of 40% SBE of which includes 7% SDB, 7% WOSB, 4% HubSB, 4% VOSB, and 4 % SDV (page 179 of 183). Section L.4. 52.222-23 notes 28% minority participate and 6.9% female participation (Page 168 of 183). Please clarify if both requirements are correct, and if participation can count for multiple requirements.
Both requirements apply. Participation can count for multiple requirements.
17 Whiting Turner Please clarify if the intent is for field offices to be place w/in the site/Limits of Disturbance, or if an area would be provided outside the LOD. In addition, please clarify if space will be provided outside the LOD for staging and storage of materials.
All field offices and project's operational requirements are required to be place within the site's Limits of Disturbance.
No additional space will be provided outside the LOD for staging and storage of materials.
18 Whiting Turner Specification section 01 1000, 1.6.F outlines traffic control requirements. These requirements include providing one traffic control professional at “each unlocked project vehicle/staff entrance during construction operating hours. It is assumed the “Gate Entrance” outlined on C140 is the sole entry point to the project. Please clarify if additional entry points are required which would require controlled supervision.
All Contractor's project entry pointes will be proposed by the contractor on the Site Utilization Plan submission and approved by COTR.
The Smithsonian is not requiring any project entry points..
19 Whiting Turner Specification section 01 1000 1.7.A.3 notes onsite contractor parking may be arranged in off-season operations. Can timing and costs of this option be shared for bid purposes?
CONTRACTOR PARKING
1. SI will provide one (1) hang tag permit for one (1) parking space for one (1) registered company vehicle to be parked in Lot C at no cost to the contractor.
This vehicle must be clearly marked with a company name and/or logo. The hang tag must be hung from the vehicle’s rear-view mirror in clear view. Employee should use a SI issued Contractor’s Badge for daily lot access.
2. With 48 hours prior notice, the Contractor may request for one (1) vehicle, registered to the company, with identifiable signage to park in the gravel parking lot which is adjacent to Lot C at no cost.
3 Upon request SI will provide up to 15 hang tags on a monthly basis for parking spaces for the contractor’s personal vehicles. To obtain the hang tags the contractor must pay in advance with one company check, at rate of $15 per working day. Issued hang tags must be hung from the vehicle’s rear-view mirror in clear view. The exact location of the on-campus parking will be determined NZCBI Park Management on a monthly basis.
4 General Parking is available at $30 per day. For arrivals prior to 8:00 AM a parking pass must be purchased online a minimum of one day in advance. After 8:00 AM payments are to me made to parking attendants in the vehicle check-in lot bus lot. Early arrival parking vouchers must be to be printed and displayed in the windshield for identification.
5 All Vehicles not in compliance with NZCBI Parking Requirements are subject to ticketing and towing by the Smithsonian Police. All costs associated with parking violations shall be the sole responsibility of the Contractor’s personnel.
20 Whiting Turner Please verify not Federal, State or Local Taxes are to be included in the bid amount per Section I, “52.229-3 Federal, State, and Local Taxes” (page 104 of 183) of the bid solicitation.
Total contract price, including applicable taxes, are to be included in the bid amount.
21 Whiting Turner Please verify the “Data Capture (Laser Scan) requirement per specification section 013233.1.3.D is applicable to this project and costs should be carried for the services.
Confirmed, Data Capture (Laser Scan) is required for this project. Scans are required during rough-in, prior to close-in, and at project completion.
22 Whiting Turner Building on temporary utilities noted in Specification Section 01 5000, please verify usage fees of temporary utilizes including gas, water, electricity, discharge are NOT to be included in the bid, and are by Smithsonian.
Confirmed there are no temporary utility usage fees , contingent on the contractor implementing basic energy conservation measures.
23 Whiting Turner Specification Section 015639 1.03.C notes an arborist may be carried by the contractor or COTR at the COTR’s discretion. Please confirm an arborist shall not be carried by the general contractor or provide an outline of timing and services for the bid.
Yes providing a project certified arborist is to be provided by the contractor as required.
24 WM Schlosser Is a bid bond required to be submitted with the bid? Bid bond is not required with the bid. Reference contract clause 52.228-S0014R.
25 WM Schlosser What are the liquidated damages? Liquidated damages does not apply
26 Consigli Is this a Taxable project or Permanent Materials are exempt from sales tax?
Drawing / spec reference: RFP
Taxable Project
27 Consigli Please provide a geotechnical report for this project if available.
Drawing / spec reference: Spec. 01 1000-3 (2.3 bullet item 4).
Geo tech report is not available at this time as it is a work in progress. It will be share with the awarded general contractor
28 Consigli Please provide as-built documentation of existing structures and infrastructures.
Drawing / spec reference: Spec. 01 1000-3 (2.3 bullet item 4).
Refer to demo drawing for most accurate information on existing conditions
29 Consigli Please clarify that the control and management of access gate entrance off North Road will be the responsibility of the General Contractor throughout the construction period. SI will have no use for the gate during the 730 calendar days."
Drawing / spec reference: General / RFP/C140
Control and management of access gate entrance off the North Road will be the sole responsibility of the General Contractor throughout the construction period.
SI personnel will not require any daily operational site access to or thru the job site. SI reserves the right to access the job site at any time.
30 Consigli Please provide the 3D model of the design if available.
Drawing / spec reference: General
Refer to answer #6 above
31 Consigli Due to the technical complexity and specialized nature of certain aspects of the project, Also in few cases a limited number of suppliers/installers, including some niche scope items, Bidders must submit substitute qualifiers at least 14 days before the bid opening. Could SI consider revising the timeline for substitute qualifier submissions to occur after the NTP? Alternatively, should we anticipate a bid extension?
Drawing / spec reference: General / Spec. 03 21 00 (1.5.G)/05 59 64 (1.3.A)
Confirmed bidders must submit substitute qualifiers at least 14 days before the bid opening.
In the event of a bid time extension the contractor's will be notified
32 Consigli The specifications have provided a list of prequalified fabricators and installers for the caging scope components. It's noted that if contractors are not listed, they must have a minimum of ten (10) years' experience in metalwork of this type, along with at least three (3) similar projects involving animal containment. Companies seeking consideration should submit written and photographic evidence of previously completed projects.
Given the interest from other local subcontractors in this scope, could you please provide guidance and clarification on the timeline for requesting consideration.
Drawing / spec reference: General /05 59 64 (1.3.A and 2.2A)
Three workdays for SI's review from the time of the submission to confirm acceptable proposed candidates.
33 Consigli Plan sheet AD101, Keynote #0204, specifies the removal, storage, and reinstallation of sheds according to CORT directions. Please provide the storage/salvage location for the sheds, as well as some datasheets/as-built documents for the existing sheds.
Drawing / spec reference: AD101
Sheds will be moved from the site by SI prior to the start of construction. Moving these sheds is not in contract of the awarded General Contractor
34 Consigli Upon receipt of the notice of award, are there any deliverables or requirements that would be owed prior to receiving the notice to proceed?
Drawing / spec reference: RFP
100% payment and performance bonds and certificate of insurance are required prior to the issuance of the Notice to Proceed.
35 Consigli Which areas will the existing boulders be reset, and where will they be stored until required installation?
Drawing / spec reference:
MMM- If the contractor cannot store them within the Job Site NZP will provide a temporary site with the NZP Campus Grounds.
36 Consigli Regarding existing 10' WRF and sliding gate - are they intended to remain in place during construction?
Drawing / spec reference: C-110CD, C-111CD, Yes
37 Consigli Regarding the existing sliding gate: Will the 10-foot tall sliding gate remains open during construction, while the construction entrance gate is managed by the General Contractor for the work?
Drawing / spec reference: C-110CD, C-111CD, Correct - SI is willing to discuss other operational procedures for the existing gate's operation and fulling securing to work site on and off hours. For Example Gate placed in a Manual Mode or having the Contractor's Posted Guard with a gate operation Badge
38 Consigli The pedestrian egress outside the LOD in conjunction with the Construction Gate and the 10-foot Sliding Gate is undefined and unclear. How is SI planning to facilitate public access from Parking Lot A to the asphalt walks outside of the LOD leading to the SI Zoo?
Drawing / spec reference: C-110CD, C-111CD, C-140CSC, C-141CSC
Please review the enclosed site utilization plan.
Public will not be able to enter the limits of construction's exclusion barriers.
39 Consigli On sheet C-141CSC, the design of the 6' chain-link fence aims to restrict public access to the northwest and west sides of the CCS site (specifically S8, S1, and part of S2 yards). Can the SI make a modification to the layout of the 6' chain-link fence to completely block off the entire asphalt walk for enhanced public safety and to optimize construction and public flow around the site? This could, possibly, involve relocating the 6' CLF to the outer edge of the asphalt walk in the NW and west directions.
Drawing / spec reference: C-110CD, C-111CD, C-140CSC, C-141CSC
Reference to enclosed document "A", site utilization plan
40 Grunley Section 011000 requires both a Traffic Safety Officer and Flaggers. Can the Traffic Safety Officer also be a Flagger or does this need to be a separate full time person?
If the individual meets the requirements and work load of both positions, yes this can be the same person.
41 Grunley Please clarify how many full time flaggers are required? Minimum of one per open access point at all times. Contractor shall determine staffing levels based upon work flow and safe operations for this difficult project access point.
42 Grunley The Safety Manager is listed as a key personnel. Does this person need to be on site full time? No, but a minimum of weekly documented visits.
43 Grunley Please consider a week extension to the RFI submission deadline. Contractor will be officially notified in the event of a time extension.
44 Grunley The Factor 2 - Key Personnel and Subcontractors requirements identifies Commissioning as one of the elements of work to name a subcontractor for. The commissioning section states that Smithsonian will be hiring the Commissioning Agent. Please confirm that the commissioning element of work may be deleted.
Refer to answer #8 above
45 Grunley The Factor 2 - Key Personnel and Subcontractors requirements identifies Structures as one of the elements of work to name a subcontractor for. Structures is inclusive of several subcontractors.
Please identify which trades you expect to see named subcontractors for under the Structures
Above ground building structures
46 Grunley Sheet S001FP (VI) and Section 014000 paragraph 1.2.B calls for contractor to be responsible for all tests and inspections, even ones explicitly assigned to the Owner. Please confirm testing and inspections called out in sections 032100, 055965, 321316 as owner engaged, are to be by contractor.
Confirmed the contractor shall provide all of the project's testing and verification services required within the contract's documents. This statement overrides all other references for "Owner to Provide".
47 Grunley C-150CU shows an electrical duct bank crossing Olmsted Walk which will require trenching. Are there any specific phasing or work hour restrictions when performing this work?
Contractor is required to maintain a 8' wide ADA compliant access walkway to pass thru the work area during the Zoo's open times. Contractor my schedule off hours work as required to complete this task safely.
48 HSU Development Reference: Resinous Flooring Question: Per Specification Section 096723 the approved manufacturers are Stonhard and Abacus Animal Flooring. Will the Smithsonian accept other manufacturers that meet the performance requirements for the Resinous Floors?
Substitutions request must meet the performance requirements of the specs / basis of design product and will be for review and consideration
49 HSU Development Reference: Permits Question: Per Specification Section 013100 – Paragraph 1.3.G.a DC Storm Water Management and Sediment Control Permits will be required. Have these permits been applied for by the Civil Engineer on the Design Team?
Drawings have been submitted for permitting plan review to DOEE for Storm Water Management and Sediment Control permits. This is still processing and will more than likely take a few month before permits are granted. Our goal is to have the permits ready when the awarded GC is selected, but this is unpredictable as we cannot control DOEE processing times
50 HSU Development Reference: Record Drawings Question: Per Specification Section 017839 the awarded GC is to provide electronic files of the Record Drawings. Will the awarded GC be provided with the electronic files of the Design Drawings for preparation of the Record Drawings?
Yes
51 HSU Development Reference: Site Usage Question: Will all the animals be removed from the project site prior to the start of this project?
Yes
52 HSU Development Reference: RFP, Page 177, Section L.29, 2.B – Resumes, “Key personnel include Sr. Project Manager, Superintendent, CQC Representative, Safety Manager…” Question: Will offerors be permitted to dual-hat key personnel roles?
Yes, but workloads and skill levels are a factor.
53 HSU Development Reference: RFP, Page 178, Section L.29, 3.A – Past Performance, “If possible, identify past projects in the Past Performance Information Retrieval System (PPIRS) by Project Title, Agency Client Name, and PPIRS Contract Number.”
Question: Please confirm that the evaluation team will be using CPARS instead of PPIRS. PPIRS retired on January 15, 2019, and was merged into CPARS.gov.
Correct
54 HSU Development 12.Reference: RFP Page 178, Sec on L.29, 3.A Past Performance, “Provide three projects of similar size and complexity where the Offeror was the Prime Contractor.
Question: Please clarify whether three projects is the maximum number of projects offerors can submit, or if offerors can submit more than three projects.
Contractor is limited three best example project's
55 HSU Development Reference: RFP Page, Section L.29, 3.B, Past Performance, Technical, “Provide a completed Contractor’s Qualifications Statement (AIA Document A-305)”.
Question: Please confirm whether offerors are required to submit Exhibits A – E as part of the AIA 305 form.
Bidders are to submit Exhibits A-E of the AIA 305 Form
56 HSU Development Reference: Parking Question: Please advise if a parking space will be designated for the project superintendent.
Refer to answer #19 above
57 HSU Development Reference: Outer Walkway Closed Question: At the site-walk it was mentioned that a section of the outer visitor walkway will be closed off by SI for the duration of the project. Please confirm/ indicate the limits that will be closed to the public.
Refer to answer #39 above
58 HSU Development Reference: Laydown Question: Is there a designated laydown area for this project?
Not outside of the limits of construction
59 HSU Development Reference: AD-101-FP Note 0204 Question: At the site-walk it was mentioned that these sheds could be stored onsite. Please confirm.
Refer to answer #33 above
60 Whiting Turner Question: Please clarify if another site visit may be set up for any subcontractors and vendors who were not able to attend.
No, just public areas during the Zoo's Hours
61 Whiting Turner Referencing the solicitation, Section C (Page 15 of 183) notes schedule duration of 730 calendar days from Notice to Proceed (NTP). Please clarify if this duration is for construction or include owner FFE, move-in, etc. leading to opening. If the latter, please provide a layout/timeframe for activities following construction.
All owner's activities will be held off until after the contractor's substantial completion date.
62 Whiting Turner The Davis Bacon wadge rates provided as part of the solicitation do not include power equipment operators (excavator, bulldozer, skid steer, loader, roller, paver, backhoe, sweeper, etc.) or truck drivers (off road truck, on road truck, water truck, tri-axel truck, low boy, etc.). Please provide operator rates for use on the proposal.
Both Davis Bacon Wage Determination DC20240002 (Building) and DC20240001 (Heavy) shall apply. Prior to Award, the most current version shall apply.
63 Whiting Turner Specific Notes 3 and 9 from drawing P401, and specific notes 6 and 7 from drawing P402 reference to see the "Zoo Consultant Drawings." When comparing the drawing sets, this note seems to be referencing the architectural drawings. More specifically, the barn floor plans (A-001 & A-002), as they show details on the installation of the animal drinkers in the barns. Please confirm “Zoo Consultant Drawings” is in reference to these architectural drawings.
This is correct.
All drawings in sequence A 000 FP Key Plan to A016 DT Cheetah Chute are the zoo consultant drawings. A/E
64 Whiting Turner Referencing the solicitation, Section C.2 SCOPE OF WORK notes “the structural foundation for the stations must be replaced and raised up…” (page 16 of 183). However, details 4/S503 shows the foundations and new floor elevation being lowered. Please confirm this detail.
The erosion concerns are being addressed by the regrading of the yards by the project civil engineer. Confirmed that the foundations and the new floor slabs should be constructed per structural details. - A/E
65 Whiting Turner Specification Section 012300, 3.1.1.a notes “items a. 1,2,3”. There is only “1” item listed in this base bid alternate. Please confirm items “2,3” are not missing.
Confirmed that "3.1.1.a" only has one (1) item, the list itself is correct. -A/E
66 AMPP Basic Coating Inspector
Due to high VOC content and irregular supply chain of coatings specified in 099611, can the coating system specified in 099600 be used for the areas called to be coated with 099611?
All bids should be based on the coatings per the Contract documents. - A/E These coating align with SI NZP standards
67 Consigli Concerning the sheet metal flashing details specified for the A500’s, they require 12-gauge stainless steel, essentially plate metal. It's worth noting that a standard sheet metal brake may lack the capacity to bend metal of this thickness. Moreover, this option is notably more expensive, approximately 25 times the cost of standard 24-gauge sheet metal. This seems to be an oversight.
Please clarify.
Drawing / spec reference: A500's
The A 500 set has multiple types and gauges of steel specified within that series.
1- When a gauge of flashing is not specified, defer to the spec 07 7100 2- A 503 DT 3, 4, 5, 6, 7, 8, 13 have a typo and should read “22GA SS FLASHING” 3- A 502 DT 1, 2, 10, 11, have a typo and should read “22 GA PTD. METAL FLASHING COLOR TBD
EXTERIOR ACRYLIC LATEX PAINT”
Contractor should identify specific notes and details where they think there are similar typos to be reviewed on a case-by-case basis. A/E
68 Consigli Please provide a list equipment/items that is provided by SI (Zoo) and install by Contractors Drawing / spec reference: ITB
Reference to enclosed document "D", equipment schedule for updates for sheet A602SH Any items identified on any schedule as “PROVIDED BY SI” should be assumed to be installed by contractor
69 Consigli Drawing / spec reference: Metal welded mesh enclosures are specified as galvanized with chain-link and steel posts, etc.; however, these are not the types of products that few pre-qualified fabricators and installers listed on spec can provide. Would COTR-SI consider aluminum and stainless steel products? If not, please provide additional pre-qualified fabricators and installers for this work.
Drawing / spec reference: 05 59 64
All bids should be based on the Contract documents. Substitutions of aluminum materials will not be considered in the Prebid RFI process. If stainless steel products are equally available and present cost savings to SI, they will be considered only if the substitution requirements of Division 1 are followed in completion. A/E
70 Consigli It appears that the "Graphic Scale" measuring ruler lines shown on C-151 to C-155 do not represent the correct scale, which should be 1"=10'. Please confirm and address.
Drawing / spec reference: C-151-CU thru C-155-CU
Confirmed that the correct scale for the drawings is 1" = 10'.
Please disregard the graphic scale.
71 Consigli Please provide utility as-built of existing wet & dry utilities onsite Drawing / spec reference: C-110-CD & all Utility Plans
See C100 for existing conditions based on SI record documents and survey. - AE
72 Consigli Please provide the depth of the frost line as indicated for the yard hydrant, as detailed on document L-505/3.
Drawing / spec reference: L-505/3
Depth of the frost line is 30" - AE/ SI
73 Consigli Please provide clarification regarding the substrate material at Yard 4 and 5.
Drawing / spec reference: L-118-LS, C-120-CS Existing sod to remain in place at Yards 4 and 5. Reference L-106 PP for requirements at areas of disturbance. - A/E
Awarded GC is responsible for reseeding / regrowing damaged areas of grass in Yards 4 and 5 using zoo mix seed. For example the install of the new cheetah dens will require new grass in the disturbed areas etc.
Refer to L603 schedule for seed and sod requirements in other yards. the 68,965 SF total shown on this sheet is a typo and take offs should be per the hatched areas on the site plans
74 Consigli It was mentioned during the site walk that some of the boulders were existing, while new ones would need to be brought in. Please clarify which areas/types of boulders will be new, and which ones will need to be reset.
Drawing / spec reference: 1.2 Summary of Work, L506/5
See L110 - L113 SP for Habitat Plan Enlargements by yard, which include placement of flat feeder rock, enrichment feeder boulders, and other boulders. As noted, placement to be finalized with COTR. - A/E Assume that SI has a total of 1 flat enrichment feeders in the current exhibit that will need to be relocated by the awarded GC.
Assume that SI has a total of 5 boulders located remotely at the zoo and will needed to be lifted and transported to the exhibit by the awarded GC.
All other boulder and stones to be priced as new per quantities shown on the drawings and provided by the awarded GC.
75 Consigli Regarding the boulders, please provide details on their type, color, and the specified size range.
Drawing / spec reference:
Reference to enclosed document "C", boulders. This shows added supplemental photos of boulder types to the details provided on 5/L-506. Boulder to be naturally worn Note that the boulder used for the enrichment feeders need to have a relatively flat surface on top when set in place. Refer to 5/L-506 Note that the boulder forming the hog exclusion zone need to have a relatively flat face and tight vertical joints as shown in the details so that hogs cannot climb them. Refer to 5/L-506 COTR and SI landscape architect will coordinate hand selection with awarded GC to meet the animal care aesthetics.
Colors to range from natural browns and grays, which will provide a nice variation Sizes are noted on 5/L-506.
SI / AE
76 Consigli The specification states, 'Boulders shall consist of a single geologic type and shall be locally sourced.' Please clarify the intended scope of 'locally sourced'—does it refer to within the DMV region, or are boulders from any region within the US considered acceptable?
Drawing / spec reference: PART 2 PRODUCTS:
2.1 BOULDERS
Refer to answer #74 and 75 above
77 Consigli Historically, sourcing large stones/boulders from quarries has been rather challenging and often requires landscape architects to hand-select them. Please clarify if the landscape architect or A/E will be involved in sourcing and selecting boulders.
Drawing / spec reference:
Refer to answer #74 and 75 above
78 Consigli Note 3 on Drawing P401 references Zoo Consultant Drawings, which are not included in the bid documents. Please provide the Zoo Consultant Drawings.
Drawing / spec reference: P401
Refer to answer #63 above
79 Consigli The animal drinkers are not identified as to which model is required at which location, there are 3 models listed in the Animal Drinkers Specs 224714 Part 2.1 A-3. Please clarify.
Drawing / spec reference: Spec 22 47 14 Part 2.1 A-3.
Refer to barn drinker schedule located on sheet A001FP Animal drinker types and locations are specified in sequence A 000 FP Key Plan to A016 DT Cheetah Chute, the zoo consultant drawings.
80 Grunley On Drawing A601SH, there are details for signage, but there is no signage schedule or indication of how many signs are required for the project. Please provide a schedule for the required signage.
Reference to enclosed document "B", signage plan Signage counts, locations, and mounting types are listed by sign type on A601 SH- All bids should be based on these counts/ types.
All final locations are to be field verified with COTR, after animal containment and door controls are installed.
- A/E
81 Grunley Drawing A601 indicates a number of rooms are to have CWK-1, solid surface casework. Example Room E1 to have CWK-1 above lockers shown on 12/A404EP. These lockers are identified as C-6, which A-602 identifies as metal casework. Please confirm if all casework is to be powder coated stainless, per the FFE schedule or a solid surface casework or plastic laminated per the Finish Schedule.
Please follow A 602 SH FFE schedule, which includes stainless steel casework, powder coated steel casework, and solid surface casework. Plastic laminate is NOT included in the finish schedule.
- A/E Refer to answer #68 above as well
82 Grunley 82 Please disregard specification 064219.
See 123600 manufactured metal casework and 12 3661.16 solid surfacing countertops for solid surface casework. - A/E
83 Grunley Please provide a product line for the Abacus flooring as there are a variety of products from a grass-like system to more rubberized mat products.
It is a rubberized mat product. RESILIENT FLOORING BOD ABACUS PADENPOR DLX™ – 9/16" CUSHIONED ZOO FLOORING, Spec 09 6567 - A/E
84 Grunley Sheet C-100CX shows existing tree stumps and deadfall that is not shown as being removed on Demolition Plan C-100CD. It is to be assumed these existing tree stumps and deadfalls will remain and be reused?
See L102 DP. In addition to site demo shown on this sheet, existing deadfall in existing Yards 1, 2, 4, and 5 to be demolished / removed by the awarded GC -A/E
85 Grunley It was mentioned on the site walk that some of the boulders were existing, and new would need to be brought in. Which areas/types of boulders will be new, and which will need to be reset?
Refer to answer #74 and 75 above
86 Grunley For the new boulders, what type of stone and color is required. Example - Granite, Fieldstone?
Sourcing large stones from quarries is rather challenging, and often requires Landscape Architects to hand select, please clarify.
Refer to answer #74 and 75 above
87 HSU Development Reference: Schedule Updating Question: Per Specification Section 013100 – Paragraph 1.5.D.3 Project Schedule is to be updated after every project meeting. Per Specification Section 013200 – Paragraph 1.4.F updated schedule is to be submitted monthly with the requisition. Is the schedule to be updated after progress meetings or monthly?
The overall project schedule is required monthly with payment requests.
Two weeks' look ahead are required at each meeting.
88 HSU Development Reference: Enlarged Demolition Plan 2/C111CD Question: On this drawing there is a section of storm drain piping that is to be removed that is outside of the limits of disturbance. What are the restrictions for doing work outside the limit of disturbance.
The COTR can temporarily adjust the LOD as required.
89 HSU Development 14.Reference: Bamboo Removal Allowance Question: Per Note 1 on Sheet L-102-DP Contractor is to provide a square foot allowance for additional bamboo removal. How many square feet should be included in this allowance and where should this cost be included in the Bid Form?
Refer to the drawings for the quantity of bamboo to be removed, takes offs / SF calcs can be derived from the hatched areas on sheet L102 Note one is revised to be: "1. DEMOLITION PLAN SHOWS LARGE AREAS OF BAMBOO REMOVAL. CONTRACTOR TO FIELD-VERIFY EXTENT OF BAMBOO.
REMOVAL WITHIN THE PROJECT LIMITS WITH COTR AND SI HORTICULTRUAL STAFF. "
90 HSU Development Reference: Seed & Sodding Question: Per Sheet L-603-SH the table for seeding and sodding calls for 68.965 s.f. of seed and sod. Should this be 68,965 sf?
68.965 sf is a typo and will be removed.
Refer to the schedule for locations of seeding and sodding extents based on the table - quantity take-offs are the contractor's responsibility.
Refer to answer #73 as well above Note (L 603 SH): all planting quantities on schedule take precedence over quantities indicated on drawing.
91 Whiting Turner Question: In Spec Section 012300, 3.1, Add Alternate #2 item b.1 calls for new reinforced concrete at all areas of the service yard but references detail 4/C171 GI which is a heavy-duty asphalt detail.
Please confirm the detail reference should be 4/S501 DT for reinforced concrete in Add Alternate #2 line-item b.1.
Confirmed 3.1.2.b.1 (add alt #2) detail should be for 4/S501 DT reinforced concrete. - AE
92 Whiting Turner Question: Various boulders are called to be salvaged per L-102. L-107 and corresponding enlargements do not clarify which boulders are salvaged and which are new. Please clarify which areas/types of boulders are to be new, and which will need to be reset.
Refer to answer #74 and 75 above
93 Whiting Turner Question: Specification Section 323224 specifies that “Boulders shall consist of single geologic type and shall be locally sourced” but does not give the type of stone and color that boulders are to be.
Please provide and confirm stone type and color of new boulders or sourcing information.
Refer to answer #74 and 75 above Can be sourced within the USA
94 Consigli The bid document lacks details on lacing or tension rods. Please furnish specifics regarding lacing rods or tension rods, including thickness/diameter, and confirm their presence at horizontal connection points on the top, mid-span, and bottom Drawing / spec reference: L-501-DT/3, 4, 5, 7
Fencing details do show details to show 5/8" dia. lacing rods that are welded to vertical posts and horizontal (top mid-san and bottom) rails via 5/8" offset studs spaced 12" o.c. at posts and rails. -A/E (J&J) Lacing rods do not replace the horizontal or vertical structural members. Coordination between the trades responsible for the elements of the animal containment system is the responsibility of the GC, lacing rods are acceptable. All elements within the set and RFI responses are required.
95 Consigli The material specified in the specification for METAL BRAIDED ROPE MESH ENCLOSURES is to be attached to lacing rods. However, the detail shown on L-501-DT/6 depicts the netting case where the product is to be bolted. This is not consistent with the nature of this type of fence, as METAL BRAIDED ROPE MESH ENCLOSURES do not use angle channels. Please provide a detailed clarification.
Drawing / spec reference: 05 59 63 (3.2), L-501/6
Refer to answer #94 above
96 Consigli The attachment method depicted in detail 7 on L-502 involves bolting to the angle iron bar.
However, the specified manufacturers and installers (per specifications) anticipate the need for lacing rods for attachment. Clarification on this detail is requested.
Drawing / spec reference: 05 59 63 (3.2), L-502/7
Refer to answer #94 above
97 Consigli Please provide clarification regarding the lacing rods mentioned in the plans as tensioning rods.
Specifically, we need details on whether the tabs provided are intended to support the lacing rods or the cable. (REF: L-503-DT/1 to 7) Drawing / spec reference:L-503DT / details 1 to 7
Refer to answer #94 above
98 Consigli The material specified in the specification for METAL BRAIDED ROPE MESH ENCLOSURES is intended to lace the mesh to the lacing bars rather than being threaded through the tension rod.
Please provide detailed clarification on the lacing process. (REF: L-505/6) Drawing / spec reference: 05 59 63 (3.2), L-505/6
Refer to answer #94 above
99 Consigli Please provide the Storm Drain structure schedule. The provided profiles only mention structures as "Cleanouts," but details such as size, material, type of frame & cover, etc., are not clarified.
Drawing / spec reference: Utility Plans Cleanouts are to be assumed to be the same material as the pipe material - see pipe profiles on C162CU.
Details for cleanout structures are found on C-120 CS Storm drain pipe schedules are located on C-162 CU. - A/E (Bowman)
100 Consigli There are many storm drain/storm profiles or invert elevations that are missing, such as C47, C48, C49, C50 & 51 to 12" PVC pipe & many more Drawing / spec reference: CU DWGs
C47, C48, C49, C50, and C51 have been calculated - see below.
C47 invert = 203.58' C48 invert = 203.59' C49 invert = 203.78' C50 invert = 204.07' C51 invert = 203.41'
- A/E (Bowman)
101 Consigli Please clarify if the woven wire mesh referenced in detail 8 on sheet L-503-DT pertains to the stainless steel braided wire mesh. Additionally, could you please provide the cable diameter for the mesh depicted in this detail?
Drawing / spec reference: L-503-DT / detail 8
"Woven wire mesh" refers to "braided wire mesh. Mesh cable thickness for the visitor rail is 1/16" - A/E (J&J)
102 Consigli Part 3 Section 3.6. Automatic Gas Safety Shutoff Valve Installation – Is an Automatic Gas Safety Shutoff Valve required at the outlet of the new gas meters by others? These valves are spec’d in section 2.6.
Drawing / spec reference: 23 11 23, part 3, 3.6
Safety shut-off valve is by division 23. -A/E (JPA)
103 Consigli Part 3 Section 3.1- I mentions Natural Gas Thermal Mass Flow Meters furnished under Section 230913, Instrumentation and Control Devices for HVAC, they are not identified on the drawings, please clarify as to their size and location.
Drawing / spec reference: 23 11 23, part 3, 3.1
Thermal mass flow meter is not required. - A/E (JPA)
104 Consigli Who is responsible for managing and operating the existing 10-foot-tall sliding gate if it is not intended to remain open during this work?
Drawing / spec reference:
Refer to answer #37 above Contractor is responsible for 100% site security while and contractors staff is on site. When the contractor's staff is not on site project shall be fully secured.
105 Grunley In spec section 089119 FIXED LOUVERS, section 2.3 A Horizontal Drainable-Blade Louver, Extruded Aluminum uses identifications of L-1 and L-2 for the louvers. However, in the Final CD Drawings Part 2, L-1 is used in the FFE Schedule for Lockers, and there is no indication of L-2. Please clarify where the louvers are that pertain to this specification section.
See M401 (notes 3 and 5) and M402 (notes 11 and 13) and interior elevations on A401 - A405 EP and for locations of louvers. - A/E
106 Grunley Please clarify the limits of the existing asphalt to remain on sheet C111CD. This asphalt area is shown as new on sheet C122CS.
Carry cost for new mill and overlay of the existing asphalt shown hatched on sheet CD111 and called out by key note 18.
A portion of the purple hatched area on C122 will be accounted for based on the above direction for mill and overlay, the other portion of the purple hatched area not accounted for based on the mill and overlay shall be new asphalt
107 Grunley In the RFP under section C.2. Scope of Work – it says the “security systems will be replaced in response to AZA inspection and recommendations, and to reduce the deferred maintenance backlog”. Please provide the AZA inspection and recommendations since there are no security or telecom drawings.
Security and Telecom scope are principally captured within the Electrical drawings and specs Ignore "replaced in response to AZA inspection and recommendations"
108 Grunley On Drawing A406DT, Detail 1 and 4, there is a callout for 1001 pointing to the toilet lid cover.
However, in the key notes, 1001 is for Fire Extinguisher Cabinets. Is there a Fire Extinguisher and Cabinet needed for the Barn E Shower Room?
Tags on A 406 DT should refer to the Toilet Accessories Schedule Tags.
Tag 1001 will be added to that schedule as “ABA ACCESSIBLE TOILET” See spec 22 4200 Generic keynotes will be removed from the sheet A406 DT A/E
109 Grunley There is not a plumbing legends/symbols and abbreviations page. Please provide. Plumbing symbols and abbreviations can be found on M001 - A/E (JPA)
110 Grunley On drawing ES 101 there are several mentions of panel "CSM", but this panel is not located anywhere else in the electrical drawings. Please provide a location for this panel.
"CSM" is a typo. It should be "CSB" A/E (JPA)
111 Grunley Please provide the size of the piers in detail 6 / drawing S503DT. Also, please indicate the depth of the footings.
Concrete pier size and reinforcement to be the same as detail 1/S503DT. All bottom of exterior footing elevation to be a minimum of 2'-6" below grade per design notes S001.X.B.
A/E McMullan
112 Grunley Fencing Details on…