Attachment 4 GamboaShop Specs 8June2021 Update.pdf

PDF 5 MB Posted

Attached to
(RFP) Refurbishment of Building into Maintenance Shops located at Gamboa, Province of Colon, Republic of Panama
Solicitation number
33330221RF0010028
Issued by

About this file

This pre-solicitation notice announces the Smithsonian Institution's intent to solicit proposals for the remodeling of a building in Gamboa, Panama into maintenance shops. The project scope includes structural concrete work, masonry, metal roofing, drywall, electrical, plumbing, HVAC, security, communications, and fire protection systems. The procurement is open to all businesses globally with an estimated value between $900,000 to $1.2 million. The contract award will be made within 300 calendar days of the notice to proceed based on lowest technically acceptable cost. Proposals are due on June 8, 2021 and must be submitted through www.fbo.gov. Offerors must be legally registered construction companies in Panama with a DUNS and SAM registration. The successful bidder must provide performance and payment bonds totaling 50% and 25% of the construction cost respectively along with insurance coverage of 100% of the offer value.

View the file

Other files

File Type Posted
210729 _ RFI Final Response 3.pdf PDF
1680001 A-302 (R2).pdf PDF
1680001 S-201 (R1).pdf PDF
1680001 S-506 (R1).pdf PDF
Hinge Assembly.png PNG image
1680001 S-102 (R2).pdf PDF
1680001 S-104 (R1).pdf PDF
1680001 S-301 (R2).pdf PDF
1680001 S-502 (R2).pdf PDF
1680001 S-503 (R2).pdf PDF
1680001 C-103 (R1).pdf PDF
Amendment 3.pdf PDF
210726 _ RFI Final Response 2.pdf PDF
Amendment 2.pdf PDF
SOV_Maintenance Shop at Gamboa - REV2.xls XLS spreadsheet
1680001 S-503 (R1).pdf PDF
1680001 P-601 (R1).pdf PDF
Answer to question 145.PNG PNG image
1680001 A-202 (R1).pdf PDF
1680001 A-112 (R1).pdf PDF
1680001 E-100 (R1).pdf PDF
1680001 S-505 (R1).pdf PDF
1680001 P-001 (R1).pdf PDF
Gamboa Infrastructure for reference 01.jpg JPG image
1680001 A-602 (R1).pdf PDF
SOV_Maintenance Shop at Gamboa - REV.xls XLS spreadsheet
1680001 S-502 (R1).pdf PDF
1680001 A-201 (R1).pdf PDF
1680001 P-101 (R1).pdf PDF
Answer to Question 26.jpg JPG image
1680001 E-601 (R1).pdf PDF
16336-S-102_R1.pdf PDF
Answer to question 68.pdf PDF
16336-S-301_R1.pdf PDF
Answer to question 63.PNG PNG image
16336-S-501_R1.pdf PDF
1680001 E-121 (R1).pdf PDF
Answer to question 46.PNG PNG image
1680001 F-501 (R1).pdf PDF
1680001 C-101 (R1).pdf PDF
33330221RF0010028 Amendment 1.pdf PDF
1680001 A-301 (R1).pdf PDF
1680001 A-401 (R1).pdf PDF
Attachment 5 Contractor COVID-19 Prevention and Control Plan Guidelines.pdf PDF
33330221RF0010028.pdf PDF
Attachment 1 Drawings_Gamboa_Maint Shop.pdf PDF
Attachment 2 GAMBOASHOP_SCOPEOFWORK (SOW).pdf PDF
Attachment 3 SOV_Maintenance Shop at Gamboa.xls XLS spreadsheet
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

600 Maryland Avenue, S.W. USPS Mail: OPDC Capital Gallery Suite 5001 MRC 511 Washington, D.C. 20024 P.O. Box 37012 Voice: 202.633.6230 Fax: 202.633.6233 Washington, D.C. 20013-7012

SPECIFICATIONS

PROJECT NO.:

PROJECT TITLE:

FACILITY:

DATE:

This project is approved as being in conformance with applicable provisions of the Smithsonian Directive

(SD) 410.

Michael J. Carrancho, P.E., Deputy Director Date

Smithsonian Institution

Office of Planning, Design & Construction

TABLE OF CONTENTS

SPECIFICATIONS

DIVISION 1 GENERAL REQUIREMENTS

1. PROJECT INFORMATION

2. SUMMARY OF WORK

3. CONTRACT TIME FOR COMPLETION

4. SCHEDULE OF ALTERNATES FOR BID/PROPOSAL

5. SCHEDULE UNIT PRICES

6. BIDDER/OFFEROR EXAMINATION OF SITE

7. NON-PUBLIC, TENANT AND SECURED SPACES

8. COMMITMENT TO SUSTAINABILITY

9. HOURS OF WORK, WORKDAYS AND GOVERNMENT HOLIDAYS

10. QUALITY ASSURANCE

11. PERMITS, LICENSES & FEES

12. PROTECTION OF THE SITE

13. DEBRIS CONTROL AND DAILY CLEANUP

14. STAGING, STORAGE AND WORK AREAS

15. BONDING AND INSURANCE

16. SUBMITTALS AND REVIEWS

17. TOXIC AND HAZARDOUS SUBSTANCES

18. EXISTING FIRE PROTECTION SYSTEMS

19. GENERAL SECURITY REQUIREMENTS

20. SCHEDULING & PAYMENTS / BAR CHART

21. WARRANTY OF CONSTRUCTION

22. AS-BUILT DRAWINGS

23. JOB-SITE SAFETY

DIVISION 2 SITE WORK

024119 SELECTIVE DEMOLITION

DIVISION 3 CONCRETE

030130 MAINTENANCE OF CAST-IN-PLACE CONCRETE

033000 CAST-IN-PLACE CONCRETE

DIVISION 4 MASONRY

042000 UNIT MASONRY

DIVISION 5 METALS

051200 STRUCTURAL STEEL FRAMING

053100 STEEL DECKING

054000 COLD FORMED METAL FRAMING

055000 METAL FABRICATIONS

DIVISION 6 WOOD AND PLASTIC NOT USED

DIVISION 7 THERMAL AND MOISTURE PROTECTION

072100 THERMAL INSULATION

078413 PENETRATION FIRESTOPPING

079200 JOINT SEALANTS

DIVISION 8 DOORS AND WINDOWS

081113 HOLLOW METAL DOORS AND FRAMES

083323 OVERHEAD COILING DOORS

085113 ALUMINUM WINDOWS

089119 FIXED LOUVERS

DIVISION 9 FINISHES

093013 CERAMIC TILING

095123 ACOUTICAL CEILING TILES

099113 EXTERIOR PAINTING

099123 INTERIOR PAINTING

DIVISION 10 SPECIALTIES

104400 FIRE EXTINGUISHERS, CABINETS AND ACCESORIES

DIVISION 11 EQUIPMENT NOT USED

DIVISION 12 FURNISHINGS NOT USED

DIVISION 13 SPECIAL CONSTRUCTION NOT USED

DIVISION 14 CONVEYING SYSTEMS

DIVISION 21 FIRE SUPRESSION

211313 WET PIPE SPRINKLER SYSTEM

DIVISION 22 PLUMBING

221116 DOMESTIC WATER PIPING

221316 SANITARY WASTE AND VENT PIPING

DIVISION 23 HEATING VENTILATION AND AIR CONDITIONING

238126 SPLIT-SYSTEM-AIR-CONDITIONERS

DIVISION 26 ELECTRICAL

260519 LOW-VOLTAGE ELECTRICAL POWER CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

262416 PANELBOARDS

262726 WIRING DEVICES

262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

265100 INTERIOR LIGHTING

DIVISION 27 COMMUNICATIONS

270528 PATHWAYS FOR COMMUNICATIONS SYSTEMS

DIVISION 28 ELECTRONIC SAFETY AND SECURITY

281311 ADDRESSABLE FIRE ALARM SYSTEM

DIVISION 31 EARTHWORK NOT USED

DIVISION 32 EXTERIOR IMPROVEMENTS

321313 FL CONCRETE PAVING

321373 FL CONCRETE PAVING JOINT SEALANTS

DIVISION 33 UTILITIES NOT USED

END OF TABLE OF CONTENTS

DIVISION 1 – GENERAL REQUIREMENTS

PROJECT INFORMATION

1.1. Smithsonian Facilities Project No. * 1680001

* Maintenance Shops at Gamboa

* Building 78

* Gamboa, Panama

1.2. Smithsonian Institution Contacts:

Contracting Officer

Smithsonian Institution

Office of Contracting

2011 Crystal Drive, Suite 350

Arlington, VA 22202-3709

Contracting Officer's Technical Representative (COTR)

Smithsonian Institution

Smithsonian Facilities – Smithsonian Tropical Research Institute (STRI)

BLDG. 362, (Pastor House) E. S. TUPPER CENTER

TEL. (507)-212-8108 PANAMÁ, REP. OF PANAMÁ

SUMMARY OF WORK

2.1. The Contractor shall furnish all supervision, labor, materials and equipment needed to * provide a Maintenance Shop, at the Smithsonian Institution's * Building 78 (former Santa Cruz

School Building) located at * Gamboa, Panama City, Republic of Panama, as set forth on the

Drawings for Smithsonian Facilities Project No. * 1680001, sheets l through *60 and in these specifications, both dated June 8 2021.

2.2. The Work includes, but is not limited to:

* Selective demolition of existing metal roof and structural concrete.

* Construction of new structural steel framing to support insulated metal sheet roof and walls, including reinforced concrete footings.

* Interior partitioning and finishes for open shop area, and enclosed offices, deposits, IT and electrical rooms, cafeteria, and bathrooms.

* Related mechanical, electrical and plumbing upfit.

* Wet sprinkler system.

2.3. Critical Elements of the Work: The successful Contractor shall be fully qualified to install critical elements of the Work. Prime contractor and subcontractors should possess qualifications, specialized experience, and technical competence with construction projects. The project will require expertise in remodeling/renovation of existing structures which will include the following critical elements of the Work:

o Selective demolition o Reinforced concrete structures and concrete pavements o Masonry walls o Structural steel structures o Doors, windows and finishes o Metal panel and metal sheet walls and roofing systems o MEP systems o Wet sprinklers systems o Fire detection and alarm systems

CONTRACT TIME FOR COMPLETION

3.1. Work under this contract shall begin by the Contractor within ten (10) calendar days after the Notice to Proceed and shall be completed within the total contract time of 300 calendar days.

excluding construction and occupancy permits issuance. All work, including project closeout activities, shall be completed in every respect within the contract time.

3.2. The start date and completion date shall be as stated in the Notice to Proceed issued by the Contracting Officer.

SCHEDULE OF ALTERNATES FOR *BID/PROPOSAL

4.1. The following is a brief Statement of the Work identified for *bid/proposal alternates.

The complete description of the Work is identified elsewhere in the drawings and specifications.

BASE *BID/PROPOSAL:

All works included in bid documents.

ALTERNATE 1: ADD (or) DEDUCT

No alternates prices to be requested in the Solicitation.

SCHEDULE OF UNIT PRICES

5.1. The unit prices in the supplied Schedule of Values (SOV) format, shall be submitted as part of the *bid/ proposal. The Smithsonian reserves the right to accept or reject any or all unit prices.

5.2. The Contractor agrees that, in the event that the Contractor is directed by the Smithsonian to increase or decrease the quantities of work required by the contract documents on items listed in the Schedule of Values, the contract amount shall be adjusted based on the following unit prices.

5.3. Unit prices shall include the furnishing of all materials, labor, equipment and services necessary for or incidental to the execution of the work specified. Unit prices shall include all direct and indirect costs, overhead, taxes, insurance and profit.

5.4. These unit prices shall be binding upon the Contractor for the duration of the project. No escalation or other variation shall be allowed.

5.5. If requested by the Smithsonian, the Contractor shall provide material, equipment and personnel to verify or determine changes in quantities. Contractor measurements and calculations shall be subject to verification by the COTR.

5.6. Schedule of Required Unit Prices: Refer to the Supplied Excel format for the SOV document.

*BIDDER/OFFEROR EXAMINATION OF SITE

6.1. Every effort has been made to indicate all work necessary to complete the project as identified. All *bidders shall carefully examine the premises during the *bid period and satisfy themselves as to the extent, nature and location of the work, general and local conditions, particularly those bearing on transportation, disposal, handling and storage of materials, availability of labor, water, electric power, access routes, uncertainties of the weather, type of equipment and facilities needed for the successful execution of the Work.

6.2. Before the *bid opening date, *bidders may view the project site on an appointment basis. Any comments, information or discussion during the site visit shall not modify the contract documents. *Bidders shall make an appointment to view the site by contacting:

Ms. Carolina I. Vasquez - Chief of Construction

Telephone No. 6674-6734

Email: vasquezc@si.edu

Smithsonian Institution

BLDG. 362, (Pastor House) E. S. TUPPER CENTER

PANAMÁ, REP. OF PANAMÁ

6.3. Pre-Bid Conference and Site Visit: Before the *bid opening date, a scheduled pre-bid conference and site visit will be announced by the Contracting Officer. The purpose of the scheduled meeting is to provide an opportunity for all bidders to review the project site. Any comments, information or discussion during the site visit shall not modify the contract documents.

6.4. This project requires special arrangements to visit the site between the hours of 9:00AM and 3:00PM for access to a non-public area. Access to the site may be restricted at times other than during the scheduled visit.

NON-PUBLIC, TENANT AND SECURED SPACES

7.1. Certain tenant spaces, non-public spaces, utility and equipment rooms and other areas related to or used for purposes of storage, conservation and scientific research may have restricted access.

7.2. The Contractor shall identify to the COTR as soon as possible, but no less than two (2) working days in advance, any occupied areas that the Contractor must access that are located outside the limits of the project site. The Contractor shall identify in writing:

7.2.1. Restricted areas to be accessed.

7.2.2. Specific reason for needing access.

7.2.3. Nature of the work to be performed.

7.2.4. Date(s) and hours needed to complete construction work activity.

COMMITMENT TO SUSTAINABILITY

8.1. The Smithsonian Institution is a trust instrumentality of the United States (recognized as a tax-exempt organization under Section 501(c)(3) of the Internal Revenue Code) and although not an Executive Branch of the U.S. Government, is committed to planning, designing, constructing, maintaining and operating its owned and leased buildings and facilities consistent with Federal environmental and energy management requirements, as listed in the Smithsonian Facilities

Codes, Standards and Guidelines document, to the maximum extent practical.

mailto:vasquezc@si.edu

CONTRACTOR USE OF PREMISES

HOURS OF WORK, WORKDAYS AND

GOVERNMENT HOLIDAYS

9.1. Work shall be performed under this contract during the normal workdays of Monday through Saturdays except Panamanian National Holidays as specified herein and the normal work hours of 7:00 AM to 3:30 PM from Monday to Fridays and 7:00AM to 12:00PM on Saturdays.

9.2. For each occasion the Contractor intends to work on Sundays or Panamanian National holidays or during hours other than those indicated above, the Contractor shall obtain written permission from the COTR, at least three (3) working days in advance.

9.3. The Contractor shall reimburse the Smithsonian Institution for security and inspection services provided by the Smithsonian when the Contractor chooses to work outside the normal workdays and hours, as identified herein. However, the Contractor will not be charged for SI overtime security and inspection services, if, in the opinion of the COTR, the work cannot be done during the normal workdays and hours due to requirements of the Smithsonian.

QUALITY ASSURANCE

10.1. The Contractor shall provide for quality control, inspections, testing and re-testing as necessary for all work, including that of subcontractors, to assure compliance with the contract documents.

PERMITS, LICENSES & FEES

11.1. The Contractor shall obtain and pay for all applicable permits and licenses required by

Panamanian Government Agencies and Authorities, including, but not limited to: permits for pedestrian and road markings, construction fences, sidewalk cuts, utility company connections, elevator certificates, waste containers, etc.

PROTECTION OF THE SITE

12.1. The Contractor shall provide adequate protection for all parts of the building, including interior and exterior surfaces, its occupants and contents and grounds wherever work under this contract is performed.

DEBRIS CONTROL AND DAILY CLEANUP

13.1. The Contractor shall regularly clean up the work areas and shall, at all times, maintain the project in as neat and orderly a manner as is consistent with normal operations. Debris resulting from construction operations shall be removed daily from the site by the Contractor. The

Contractor shall keep all access, haul routes and site areas free of dirt, debris and other materials resulting from construction activities.

STAGING, STORAGE AND WORK AREAS

14.1. Before any work is started, the Contractor shall coordinate with the COTR regarding the use of area for staging and storage of materials and equipment.

BONDING AND INSURANCE

15.1. Bonding:

The successful contractor shall submit a Performance Bond of 50% of the construction cost and a

Payment bond: 25% of the construction cost

15.2. Insurance:

Construction All-Risk (CAR) Insurance to cover 100% of the Offer and Civil Liability Insurance with a limit of up to 1M of coverage.

SUBMISSIONS

SUBMITTALS AND REVIEWS

16.1. Contractor Responsibility for Submittals: The Contractor shall provide all required submittals, by technical specification section, in accordance with the contract documents. All submittals, with exception of mockups or samples, are to be submitted electronically by email in

PDF format. The Contractor shall clearly indicate on the submittal that it has been reviewed by the Contractor and found to meet the project requirements. Any items submitted as substitutions shall be clearly identified as such on the submittal and the transmittal document. If shop drawings show variations from the contract documents because of standard shop practices or for other reasons, the Contractor shall provide a separate, written description of variations along with the submittal. The Contractor shall:

16.1.1. Review each submittal for conformance with requirements of the contract documents and coordination with related work.

16.1.2. Determine and verify all field measurements, required material quantities, method of assembly or erection, installation requirements and proper connection to adjoining materials installed by others.

16.1.3. Assure that all submittals use the appropriate units of measure. All drawings and technical data shall be in SI (metric) units for projects designed in SI units. Preprinted literature in other units shall be accompanied by documentation to show conformance to project requirements.

16.1.4. Transmit all required submittals for a technical specification section at the same time unless prior written waiver of this requirement has been provided by the COTR.

16.1.5. Transmit submittals to the COTR in a logical and orderly sequence in accordance with the Submittal Schedule to prevent project delays or adversely impact work by the Smithsonian Institution or other contractors.

16.1.6. Correct and resubmit submittals according to response from the Smithsonian

Facilities Office, Design and Construction Department.

16.1.7. Commence work on items requiring submittals only after all related submittals are reviewed and approved by the Smithsonian. All Work shall conform to approved submittals.

TOXIC AND HAZARDOUS SUBSTANCES

17.1. The Contractor shall submit to the COTR, at least ten (10) working days prior to their intended use, a written list of toxic and hazardous substances that will be used on the project. The

Contractor shall submit a "Material Safety Data Sheet" similar to OSHA Form No. 20 for these substances to identify the following information:

17.1.1. Product Identification

17.1.2. Hazardous Ingredients

17.1.3. Physical Data

17.1.4. Fire and Explosion Hazard Data

17.1.5. Health Hazard Data

17.1.6. Emergency and First Aid Procedures

17.1.7. Reactivity Data

17.1.8. Spill or Leak Procedures

17.1.9. Special Protection Information

17.1.10. Special Precautions

17.2. The Contractor will commit to not using the following toxic and hazardous materials:

17.2.1. Products containing asbestos, urea formaldehyde, polychlorinated biphenyls (PCBs) and/or chlorinated fluorocarbons.

17.2.2. Products containing lead content, including solder or flux containing more than 0.2% lead; domestic water pipe or pipe fittings containing more than 8% lead;

and paint containing more than 0.06% lead.

17.2.3. Chlorofluorocarbon (CFC)-based refrigerants in new base building heating, ventilating, air conditioning and refrigeration (HVAC&R) systems and comprehensive CFC phase-outs when reusing existing base building HVAC equipment.

17.3.4. The Contractor hereby understands that historic properties may contain pre-existing harmful materials and coatings including, but not limited to, arsenic, lead, dioxide, polyvinylchloride (PVC) and asbestos. Upon discovery of hazardous or toxic materials, the Contractor shall alert the COTR immediately.

EXISTING FIRE PROTECTION SYSTEMS

18.1. During the course of the Work, all existing smoke and heat detectors and sprinkler heads must remain operable. Coverings may be applied to protect them from spray coatings or other hazardous conditions only during the actual operations. Coverings must be removed immediately after the operations have concluded. Damaged detectors and sprinkler heads shall be replaced immediately by the Contractor at no additional cost to the Smithsonian Institution. The Contractor shall test replaced detectors and sprinklers after installation to the satisfaction of the COTR.

GENERAL SECURITY REQUIREMENTS

19.1. The Contractor and his employees must comply with security requirements imposed by the Smithsonian Institution, including any necessary security clearances. Failure to inspect the site or obtain knowledge of security regulations shall not relieve the Contractor from security requirements or from performance of any part of the work.

SCHEDULING & PAYMENTS / BAR CHART

20.1. Project Schedule: The Contractor shall submit, to the COTR for approval, a Gantt bar chart project schedule within 10 calendar days after the date of contract award. Submit in PDF and

MS Project formats. No work shall start at the site until the project schedule has been approved by the COTR. The approved bar chart will represent a baseline schedule on which the monthly construction progress will be indicated and submitted to the COTR. The baseline project schedule shall comply with the following:

20.1.1. Weekly breakdown of work activities shall be provided, including interaction between building trades, subdivided by items of work and areas of the project. Items of work shall be grouped and subdivided according to the divisions of the Construction

Specifications Institute (CSI) format.

20.1.2. The start date and completion date shall be consistent with the Contract Time established by the Contracting Officer. Any intermediate deadline dates needed to meet specific requirements for Smithsonian use of portions of the work shall be shown.

20.1.3. Project condition survey activities shall be scheduled not later than the 14th calendar day of the contract time and prior to the start of any site work.

20.1.4. Project closeout activities shall be scheduled for completion in accordance with the requirements for the Contract Time for Completion.

20.1.5. Order dates and projected delivery dates shall be shown for equipment, special devices, hardware, products or other items requiring long lead time.

20.1.6. Required delivery dates for items to be furnished by Smithsonian and installed by the Contractor shall be shown, as well as items to be furnished and installed by

Smithsonian, which will affect the Contractor's work.

20.1.7. Review periods for all submittals and time required for all necessary inspection and/or testing shall be shown.

20.1.8. Dates shall be given for ordering, delivery, installation and testing of major equipment and special materials and equipment.

20.1.9. The Contractor shall specifically identify work activities and dates associated with construction bid alternates.

20.2. Revisions to Baseline Schedules: The Contractor shall submit, to the COTR for approval, all revisions to the approved baseline project schedule. The Contractor shall submit a proposed revision to the schedule, as necessary, along with proposals for construction changes, clearly indicating modifications to the schedule based on the proposal. The Contractor shall also submit, for review and approval, any proposed changes to the schedule due to inability to accomplish the work as planned for any reason. Approved changes to the schedule shall be incorporated into the Project Schedule and it shall be resubmitted as necessary or as requested by the COTR.

20.3. Progress Behind Schedule: If it becomes apparent to the COTR that the overall progress of the project is behind the approved project schedule, then the COTR will notify the Contractor in writing. The Contractor shall submit, to the COTR for approval, a Recovery Schedule and Plan to describe how the Work will be accelerated to meet the Contract Time requirements in accordance with the General Conditions contract clause entitled "Commencement, Prosecution and

Completion of the Work." The Recovery Schedule shall be superimposed on the approved baseline project schedule to demonstrate that proposed recovery activities will accomplish completion of the work by the approved completion date.

20.4. Reporting Progress and Applying for Payment: Each month, the Contractor shall apply for payment and submit a report of the actual construction progress as follows:

20.4.1. By the 25th of each month, the Contractor and the COTR shall have inspected the work to determine percentages complete for each item, projected through the end of the month. The parties shall attempt to reach agreement on each item, but if they cannot reach an agreement the COTR will determine percent complete.

20.4.2. By the last day of the month, the Contractor shall submit an Application for

Payment based on the determined percentages complete for each item. The application shall be submitted in triplicate on the Smithsonian standard Application for Payment form. Each copy of the Application for Payment shall be accompanied by the following:

1. A Progress Schedule identifying the cumulative progress superimposed on the latest revision of the approved Project Schedule. The net progress for the month and applicable dates shall be clearly indicated.

2. A complete set of copies of certified weekly-payroll data for the period and

Certificate of Payment to Caja de Seguro Social de Panama.

20.5. Response to Application:

20.5.1. Payment shall be made only for progress agreed upon by the COTR, performed on original Contract Work or approved modifications, in accordance with the current, approved Project Schedule. Failure to submit the Application in accordance with the specifications will prevent the processing of payments.

20.5.2. Payments shall be sent to the Contractor's banking account. For this purpose, the Contractor shall provide all required information to the COTR once the NTP has been issued. Any changes of information for the sending of wire transfers of progress payments must be made in writing, signed by the Contractor's authorized person and submitted to the Contracting Officer.

Warranty of Construction

21.1. The Contractor shall warrant that the work performed under this contract conforms to the contract requirements and is free of any defect in equipment, materials, design furnishes, or workmanship performed by the Contractor or any subcontractor or supplier at any tier. Unless otherwise stated in the technical sections of the Specifications, the warranty of the Work shall continue for a period of one (1) year from the date of Final Completion status. If Smithsonian takes partial occupancy before Final Completion, then the warranty for that portion shall be in effect for a period of one (1) year beginning on the date of Substantial Completion for that portion of the Work.

21.2. Submission of original warranties for all products, equipment and systems:

The Contractor shall assemble original warranty certificates or notarized copies of warranty certificates executed by the Contractor, subcontractors, suppliers and manufacturers in a tab-indexed three-ring loose-leaf binder with a durable plastic cover. The table of contents shall identify the item covered, the location of the item, the date of Substantial Completion, expiration date of the warranty and the supplier, vendor and installing contractor. Duplicate notarized copies of warranties shall be provided as required by "Manuals for Operation, Maintenance and As-Built Product Data." Include electronic copy in PDF format, on CD.

As-Built Record Drawings

22.1 The Contractor shall submit upon completion of the project, Red Marks for SI review and

Final As Build Drawings, printed and digital copies (AutoCAD and PDF format), non limited, to the installation performed by the contractor. In addition, in the As Built drawings include all existing utilities found through the construction of the project. The contractor shall adequately register and detail, dimensions, and locations (including depth) of all found utilities.

22.2 As-Built Record Drawings Submitted: During the progress of the work the Contractor shall maintain a complete and up-to-date set of record prints, open to inspection by the COTR at any time. These prints shall provide a complete and accurate as-built record of all changes to the

Contract Drawings, including rerouting of runs, relocation of items or control points and all other modifications. As-built drawings shall be neatly marked with colored pencils or ink, marked "As-

Built" and signed and dated by the Contractor. Upon completion of the Work and before final payment, the Contractor shall submit the following to the COTR: photographically produced as-built record drawings on 4-mil, double matte, mylar sheets, sized the same as the contract drawings; electronic copies of as-built record drawings in PDF and DWG formats.

22.3 As-Built Record Survey of Underground Utilities Submitted: If outside or underground utilities are part of the work, the Contractor shall furnish, to the COTR for approval, an acceptable and accurately dimensioned survey showing location and elevation of underground storage tanks, all utility lines for water, gas, electrical, sewer, steam, etc., including valves, connections and changes in direction, as installed under the contract, within the property lines and outside the building walls. Points where utility lines emerge from the building shall be located from lot monuments. The survey shall be made to scale and must be marked "As-Built" and signed and dated by the Contractor. The Contractor shall furnish a scanned, digital copy to the COTR as well as a copy on a 3-mil, double matte, mylar sheet or sheets the same size as the contract drawings.

22.4 Close-out Conditions Text and Photographic Documentation Submitted: The Contractor shall prepare a typewritten text and photographic report of observations made during the inspections for project closeout regarding conditions of new work and adjacent items that were examined for the pre-condition survey report. Any defects shall be identified and the Contractor's operations on the defect shall be described. Within ten (10) calendar days after the Final

Inspection, the Contractor shall submit the text and photographic report in PDF format to the

Contracting Officer and the COTR and retain a copy of each for the Contractor’s files.

Job-Site Safety

23.1. Safety Coordinator: The Contractor shall designate a person responsible and accountable for personnel safety at both corporate and project level at the project site for the duration of the project.

Contracts specifically requiring safety or industrial hygiene personnel shall include a copy of their resumes.

Submit Qualifications for the Safety Coordinator.

23.2. Occupational Safety and Health: This contract is subject to Title 29 of the Code of Federal

Regulations, Part 1910 "Occupational Safety and Health Standards" and Part 1926 "Safety and Health

Regulations for Construction" pursuant to the Occupational Safety and Health Act (OSHA) of 1970 administered by the US Department of Labor, Occupational Safety and Health Administration.

23.3 Local Regulations from the Republic of Panama are applicable for this project. Ley No.51, 27 de diciembre del 2005 de la Caja de Seguro Social y Decreto Ejecutivo No.2, 15 de febrero del 2008.

23.4. Report of Accident or Illness: In the event of any accident or illness for which medical assistance is required, any criminal action, or any fire, the Contractor shall notify the appropriate authority (ambulance, police, fire Dept.), Smithsonian Security, and the COTR.

23.5. Contractor Personnel to be contacted: The Contractor shall submit a written list of emergency telephone numbers and names of persons to contact for the General Contractor superintendent and for each major sub-contractor working on the project site. The initial list shall be submitted to the COTR at the Preconstruction Meeting. The list shall be updated and resubmitted to the

COTR as needed.

23.6. Site Specific Safety Plan: Upon award of this contract, the contractor shall provide a Site Specific Safety Plan (SSSP). The SSSP is a safety and health policy and program document and outlines how the contractor will safely conduct their work. This plan shall be job-specific and shall also address any unusual or unique aspects of the project or activity for which it is written.

The SSSP shall interface with the employer’s overall safety and health program, and a copy shall be available on the work site. Any portions of the employer’s overall safety and health program that is referenced in the SSSP shall be included as appropriate.

The plan shall include but not limited to the following:

a. Signature Sheet that must include plan concurrence (e.g., project manager or superintendent, project safety professional, project QC). Provide concurrence of other applicable corporate and project personnel (Contractor).

b. Background Information that must include Brief project description, description of work to be performed, and location; phases of work anticipated these will require a Job Hazard Analysis

(JHA’s).

c. Statement of Safety and Health Policy

d. Responsibilities and lines of Authority

e. Subcontractors and Suppliers

f. Training

g. Safety and Health inspections that include assignment of responsibilities for a minimum daily/weekly job site safety and health inspection during periods of work activity level of technical proficiency needed to perform the inspections, proof of inspector’s training/ qualifications

h. Accident Reporting

i. Risk Management Processes Detailed project-specific hazards and controls shall be provided by a Job Hazard Analysis for each major phase/activity of work, including but not limited to work involving confined space, fall protection, trenching/excavation, crane/rigging, steel erection, hot work, protection of the public, scaffolding, and other activities that involve high risk potential.

j. Pandemic Mitigation Procedures as per the most recent dispositions by the Ministerio de

Salud de Panama (MINSA) and the Government of the Republic of Panama.

STRI – MAINTENANCE SHOPS AT GAMBOA

Smithsonian Facilities PROJECT NUMBER 1680001

SELECTIVE DEMOLITION

024119 - 1

SECTION 024119 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Demolition and removal of selected portions of building or structure.

2. Demolition and removal of selected site elements.

3. Salvage of existing items to be reused or recycled.

1.2 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and salvaged or removed and reinstalled.

B. Remove and Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver to Owner ready for reuse.

C. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall where indicated.

D. Existing to Remain: Existing items of construction that are not to be permanently removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

1.3 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

1.4 PREINSTALLATION MEETINGS

A. Predemolition Conference: Conduct conference at Project site.

1. Inspect and discuss condition of construction to be selectively demolished.

2. Review structural load limitations of existing structure.

3. Review and finalize selective demolition schedule and verify availability of materials, demolition personnel, equipment, and facilities needed to make progress and avoid delays.

4. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations.

5. Review areas where existing construction is to remain and requires protection.

024119 - 2

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For refrigerant recovery technician.

B. Proposed Protection Measures: Submit report, including drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection, for dust control and, for noise control. Indicate proposed locations and construction of barriers.

C. Schedule of Selective Demolition Activities: Indicate the following:

1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Ensure Owner's on-site operations are uninterrupted.

2. Interruption of utility services. Indicate how long utility services will be interrupted.

3. Coordination for shutoff, capping, and continuation of utility services.

D. Inventory: Submit a list of items to be removed and salvaged and deliver to Owner prior to start of demolition.

E. Predemolition Photographs or Video: Submit before Work begins.

1.6 CLOSEOUT SUBMITTALS

A. Inventory: Submit a list of items that have been removed and salvaged.

B. Landfill Records: Indicate receipt and acceptance of hazardous wastes by a landfill facility licensed to accept hazardous wastes.

1.7 FIELD CONDITIONS

A. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

1. Before selective demolition, Owner will remove the following items:

a. Stored material.

B. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

C. Hazardous Materials: It is not expected that hazardous materials will be encountered in the

Work.

D. Storage or sale of removed items or materials on-site is not permitted.

E. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

024119 - 3

PART 2 - PRODUCTS

2.1 PEFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Review record documents of existing construction provided by Owner. Owner does not guarantee that existing conditions are same as those indicated in record documents.

C. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

D. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict.

Promptly submit a written report to Architect.

E. Perform an engineering survey of condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective building demolition operations.

1. Perform surveys as the Work progresses to detect hazards resulting from selective demolition activities.

F. Survey of Existing Conditions: Record existing conditions by use of preconstruction photographs.

1. Inventory and record the condition of items to be removed and salvaged. Provide photographs of conditions that might be misconstrued as damage caused by salvage operations.

2. Before selective demolition or removal of existing building elements that will be reproduced or duplicated in final Work, make permanent record of measurements, materials, and construction details required to make exact reproduction.

3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

024119 - 4

B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Owner will arrange to shut off indicated services/systems when requested by Contractor.

2. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated to be removed.

a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.

b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material.

c. Equipment to Be Removed: Disconnect and cap services and remove equipment.

d. Equipment to Be Removed and Reinstalled: Disconnect and cap services and remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.

e. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner.

3.3 PREPARATION

A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

1. Provide temporary weather protection, during interval between selective demolition of existing construction on exterior surfaces and new construction, to prevent water leakage and damage to structure and interior areas.

2. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are exposed during selective demolition operations.

C. Temporary Shoring: Provide and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

1. Strengthen or add new supports when required during progress of selective demolition.

3.4 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.

024119 - 5

2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping, to minimize disturbance of adjacent surfaces. Temporarily cover openings to remain.

3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain fire watch and portable fire-suppression devices during flame-cutting operations.

5. Maintain adequate ventilation when using cutting torches.

6. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and promptly dispose of off-site.

7. Remove structural framing members and lower to ground by method suitable to avoid free fall and to prevent ground impact or dust generation.

8. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

9. Dispose of demolished items and materials promptly.

B. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

3.5 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS

A. Concrete: Demolish in sections. Cut concrete full depth at junctures with construction to remain and at regular intervals using power-driven saw, then remove concrete between saw cuts.

B. Masonry: Demolish in small sections. Cut masonry at junctures with construction to remain, using power-driven saw, then remove masonry between saw cuts.

C. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, then break up and remove.

D. Roofing:

1. Remove existing roofing system down to substrate.

024119 - 6

3.6 DISPOSAL OF DEMOLISHED MATERIALS

A. General: Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Owner's property, remove demolished materials from Project site and legally dispose of them in an approved landfill.

1. Do not allow demolished materials to accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

3. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.

B. Burning: Do not burn demolished materials.

C. Disposal: Transport demolished materials off Owner's property and legally dispose of them.

3.7 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

3.8 SELECTIVE DEMOLITION SCHEDULE

A. Existing Construction to Be Removed: See Drawings.

B. Existing Items to Be Removed and Reinstalled: See Drawings.

C. Existing Items to Remain: See Drawings.

END OF SECTION 024119

SMITHSONIAN FACILITIES PROJECT NUMBER 1680001

MAINTENANCE OF CAST-IN-PLACE CONCRETE 030130 - 1

SECTION 030130 - MAINTENANCE OF CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Removal of deteriorated concrete and subsequent replacement and patching.

2. Floor joint repair.

3. Epoxy crack injection.

4. Corrosion-inhibiting treatment.

5. Polymer overlays.

6. Polymer sealers.

7. Composite structural reinforcement.

B. Related Requirements:

1. Section 051200 "Structural Steel Framing" for concrete repair with structural steel framing.

2. Section 055000 "Metal Fabrications" for concrete repair with steel framing and fabricated devices.

1.3 UNIT PRICES

A. General: Unit prices include the cost of preparing existing construction to receive the work indicated and costs of field quality control required for units of work completed.

1.4 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.5 ACTION SUBMITTALS

A. Product Data: For each type of product. Include construction details, material descriptions, chemical composition, physical properties, test data, and mixing, preparation, and application instructions.

B. Samples for Verification: Cured samples for each exposed product and for each color and texture specified.

MAINTENANCE OF CAST-IN-PLACE CONCRETE 030130 - 2

1. Include Samples of each required type, color, and texture of patching material in the form of patches in drilled holes or sawed joints in sample concrete representative of the range of concrete colors on the building.

2. Include Samples of each required type, color, and texture of polymer-overlay material in the form of cementitious tiles at least 8 inches (200 mm) long by 8 inches (200 mm) wide.

3. Include Samples of each required type, color, and texture of polymer-sealer material in the form of cementitious tiles at least 8 inches (200 mm) long by 8 inches (200 mm) wide.

1.6 INFORMATIONAL SUBMITTALS

A. Qualification Data: For installers and manufacturers.

B. Material Certificates: For each type of portland cement aggregate supplied for mixing or adding to products at Project site.

C. Product Test Reports: For each manufactured bonding agent, cementitious patching mortar, joint-filler, crack injection adhesive, polymer overlay, polymer sealer and composite structural reinforcement, for tests performed by manufacturer and witnessed by a qualified testing agency.

D. Field quality-control reports.

E. Maintenance Program: Submit before work begins.

1.7 QUALITY ASSURANCE

A. Manufacturer Qualifications: Each manufactured bonding agent, cementitious patching mortar, joint-filler, crack injection adhesive, polymer overlay, polymer sealer and composite structural reinforcement, manufacturer shall employ factory-trained technical representatives who are available for consultation and Project-site inspection and assistance at no additional cost.

B. Installer Qualifications: An entity that employs installers and supervisors who are trained and approved by manufacturer to apply packaged patching-mortar materials, epoxy crack injection materials, corrosion-inhibiting treatments, polymer overlays, polymer sealers, and composite structural reinforcement.

C. Maintenance Program: Prepare a written plan for maintenance of cast-in-place concrete, including each phase or process, protection of surrounding materials during operations, and control of debris and runoff during the Work. Describe in detail materials, methods, equipment, and sequence of operations to be used for each phase of the Work.

D. Mockups: Build mockups to demonstrate aesthetic effects and set quality standards for materials and execution.

1. Approval of mockups does not constitute approval of deviations from the Contract

Documents contained in mockups unless Architect specifically approves such deviations in writing.

MAINTENANCE OF CAST-IN-PLACE CONCRETE 030130 - 3

2. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Comply with manufacturer's written instructions for minimum and maximum temperature requirements and other conditions for storage.

B. Store cementitious materials off the ground, under cover, and in a dry location.

C. Store aggregates covered and in a dry location; maintain grading and other required characteristics and prevent contamination.

1.9 FIELD CONDITIONS

A. Environmental Limitations for Epoxies: Do not apply when air and substrate temperatures are outside limits permitted by manufacturer. During hot weather, cool epoxy components before mixing, store mixed products in shade, and cool unused mixed products to retard setting. Do not apply to wet substrates unless approved by manufacturer.

1. Use only Class A epoxies when substrate temperatures are below or are expected to go below 40 deg F (5 deg C) within 8 hours.

2. Use only Class A or B epoxies when substrate temperatures are below or are expected to go below 60 deg F (16 deg C) within 8 hours.

3. Use only Class C epoxies when substrate temperatures are above and are expected to stay above 60 deg F (16 deg C) for 8 hours.

4.

B. Hot-Weather Requirements for Cementitious Materials: Protect repair work when temperature and humidity conditions produce excessive evaporation of water from patching materials.

Provide artificial shade and wind breaks, and use cooled materials as required. Do not apply to substrates with temperatures of 90 deg F (32 deg C) and above.

C. Environmental Limitations for High-Molecular-Weight Methacrylate Sealers: Do not apply when concrete surface temperature is below 55 deg F (13 deg C) or above 95 deg F (32 deg C).

Apply only to dry substrates.

PART 2 - PRODUCTS

2.1 MATERIALS, GENERAL

A. Source Limitations: Obtain each color, grade, finish, type, and variety of product from single source with resources to provide products of consistent quality in appearance and physical properties.

B. VOC Content: Provide materials that comply with VOC limits of authorities having jurisdiction.

MAINTENANCE OF CAST-IN-PLACE CONCRETE 030130 - 4

2.2 BONDING AGENTS

A. Epoxy-Modified, Cementitious Bonding and Anticorrosion Agent: Manufactured product that consists of water-insensitive epoxy adhesive, portland cement, and water-based solution of corrosion-inhibiting chemicals that forms a protective film on steel reinforcement.

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

a. BASF Construction…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .