3-PVU AIP 069 - Runway Lighting - Plans IFB.pdf
PDF 37 MB Posted
- Attached to
- Provo Airport Lighting Replacement Project
- Solicitation number
- PR2026001027
- Issued by
- Utah County, Utah
About this file
Runway Lighting Project Plans - Provo Municipal Airport
This document is a comprehensive set of design plans and specifications for the Provo Municipal Airport Runway Lighting Replacement Project (AIP 069) sponsored by Provo City Corporation and managed by the Federal Aviation Administration. The project encompasses the installation of new LED runway lighting systems, runway end indicator lights (REILs), precision approach path indicators (PAPIs), and associated electrical infrastructure across Runways 13/31 and 18/36, along with supporting taxiway systems. The scope of work includes the removal of existing lighting fixtures and electrical duct banks (approximately 86 runway edge lights, 16 runway threshold lights, and associated PAPI systems), installation of new LED L-861 runway edge lights, L-861E threshold lights, L-850C in-pavement lights, L-881 PAPI systems, and approximately 15,674 to 27,064 linear feet of various electrical conductors and conduit installations. The project is organized into three construction phases: Phase 1 (5 calendar days) focusing on Runway 18/36 modifications within the Runway 13/31 object free zone; Phase 2 (10 calendar days) addressing Runway 13/31 edge and threshold lights plus PAPI installation at Runway 31; and Phase 3 (40 calendar days) completing Runway 18/36 lighting and PAPI installation at Runway 18, with a total project duration of 33 calendar days excluding nighttime closures. The contract was issued for bid on June 4, 2026, with runway closures scheduled during nighttime hours (7:00 PM to 5:00 AM) and daytime restrictions on Runway 18/36 during Phase 3 (7:00 AM to 7:00 PM).
The project requires strict compliance with FAA Advisory Circular 150/5370-2G for operational safety during construction, including foreign object debris (FOD) management, navigation aid protection, and coordination with airport operations through Notice to Airmen (NOTAM) procedures. All contractor work must conform to the National Electrical Code, FAA specifications (FAA-C-1217f, FAA-C-1391b, FAA-STD-019e), and local Utah codes. The contractor is responsible for obtaining all necessary permits including FAA 7460-1 notices, CDPHE stormwater permits, and fugitive dust permits, with costs borne by the contractor. Environmental requirements include archaeological monitoring during excavation in designated areas, erosion control measures per FAA AC 150/5370-10, and daily wildlife inspections to prevent hazardous wildlife attractions. Contractor access is limited to three designated gates with required security badges and airport familiarization training for key personnel, while all personnel must maintain 24-hour radio contact with airport operations. The project requires submission of a Quality Control Plan fourteen days prior to construction commencement, as-built drawings throughout the project, material submittals at least ten days prior to ordering, and final inspection and approval by the resident engineer before any area reopens to aircraft operations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE I
RUNWAY 13-31
LIGHTING
TA
XI
W
AY
B
TAXIW
AY C
RUNW
AY 18/36
TAXIWAY A SCHEDULE II
RUNWAY 31 PAPI
REPLACEMENT
RUNWAY 13/31
SCHEDULE III
RUNWAY 18/36
LIGHTING
(NON-FEDERAL)
SHEET NAME:
SHEET NO:
DRAWN BY:
PROJECT NO:
DATE ISSUED:
DESIGNED BY:
CHECKED BY:
35 South 400 West St, Suite 200 St. George, UT 84770
435.673.4677
NU
MB
ER
DA
TE
DE
SC
RI
PT
IO
N
IS
SU
AN
CE
S
CH
ED
UL
E
IS
SU
ED
F
OR
B
ID
/04 /20
PROVO MUNICIPAL AIRPORT
VICINITY MAP
NOT TO SCALE
SITE PLAN
NOT TO SCALE
PROJECT TEAM SCHEDULES OF WORK
35 South 400 West St Suite 200
435.673.4677 St. George, UT 84770
2026 RUNWAY LIGHTING PROJECT
PROVO, UTAH
PVU
UTAH
PROVO
SALT
LAKE
CITY
GREEN
RIVER
ST. GEORGE
LOGAN
• SCHEDULE I •
RUNWAY 13-31 LIGHTING
AIP PROJECT NO. 3-49-0027-069-2026
SPONSORED BY
· PROVO CITY CORPORATION
· FAA - FEDERAL AVIATION ADMINISTRATION
La yo ut T ab N am e:
C O
VE
R
S H
EE
T
W :\A cq ui si tio ns \J
VI
\p ro je ct s\
PV
U
\A
IP
X X
- 2
R un w ay
Li gh tin g\
F- C
AD
\P
LA
N
S\
1-
PV
U -X
X- G
1-
C O
VR
.d w g
Pl ot te d
By :N od ic h, A le x
Pl ot te d:
Ju ne
, 2
6, :0
7:
P M
La st
S av ed B y:
M
.V illa nu ev a, /5 /2
9:
:0
AM B.A.H.
C.L.G.
AIP-069
G001
COVER SHEET
PR
OV
O, U
TA
H
R
UN
W
AY
LI
GH
TI
NG
P
RO
JE
CT
AI
P
NO
. 3
-4 9-
-0
-2
PR
OV
O
AI
RP
OR
T
B.A.H.
6/04/2026
• SCHEDULE II •
RUNWAY 31 PAPI
REPLACEMENT
• SCHEDULE III •
RUNWAY 18-36 LIGHTING
(NON-FEDERAL)
SUMMARY OF APPROXIMATE QUANTITIES
ITEM NO. ITEM DESCRIPTION UNITS
SCHEDULE I SCHEDULE II SCHEDULE III
ESTIMATE AS BUILT ESTIMATE AS BUILT ESTIMATE AS BUILT
C-105 MOBILIZATION LS 1 1 1
L-108a INSTALL #8 AWG L-824C, 5000V, WIRE LF 0 0 15,674
L-108b INSTALL #6 AWG BARE COPPER COUNTERPOISE, INCLUDING GROUND RODS
AND TERMINATIONS LF 0 0 18,747
L-108c INSTALL #8 AWG THWN-2, 600V, WIRE LF 0 0 27,064
L-108d INSTALL #6 AWG L-824C, GROUND WIRE LF 0 0 6,766
L-110a INSTALL 1-2" SCH. 40 PVC CONDUIT, DIRECT EARTH BURIED LF 0 0 18,396
L-110b INSTALL 1-2" SCH. 40 PVC CONDUIT, CONCRETE ENCASED LF 0 0 351
L-115a INSTALL NEW L-827B JUNCTION BOX EA 0 0 2
L-125a REMOVE EXISTING RUNWAY EDGE LIGHT, COMPLETE EA 86 0 62
L-125b REMOVE EXISTING RUNWAY THRESHOLD LIGHT, COMPLETE EA 16 0 16
L-125c REMOVE EXISTING PAPI SYSTEM FROM EXISTING CONCRETE
FOUNDATIONS, COMPLETE EA 0 1 1
L-125d INSTALL NEW LED L-861 RUNWAY EDGE LIGHT ON EXISTING BASE, COMPLETE EA 86 0 0
L-125e INSTALL NEW LED L-861E RUNWAY THRESHOLD LIGHT ON EXISTING BASE, COMPLETE EA 16 0 0
L-125f INSTALL NEW LED L-850C IN-PAVEMENT RUNWAY EDGE LIGHT ON EXISTING
BASE, COMPLETE EA 2 0 0
L-125g INSTALL NEW LED L-861 RUNWAY EDGE LIGHT ON NEW BASE, COMPLETE EA 0 0 63
L-125h INSTALL NEW LED L-861E RUNWAY THRESHOLD LIGHT ON NEW BASE, COMPLETE EA 0 0 16
L-125i INSTALL NEW LED L-849E REIL, COMPLETE EA 0 0 2
L-125j INSTALL NEW LED L-881 PAPI SYSTEM ON EXISTING FOUNDATIONS, COMPLETE EA 0 1 1
T-901a SEEDING WITH HYRDOMULCH AC 0 0 2
SHEET NAME:
SHEET NO:
DRAWN BY:
PROJECT NO:
DATE ISSUED:
DESIGNED BY:
CHECKED BY:
35 South 400 West St, Suite 200 St. George, UT 84770
435.673.4677
NU
MB
ER
DA
TE
DE
SC
RI
PT
IO
N
IS
SU
AN
CE
S
CH
ED
UL
E
IS
SU
ED
F
OR
B
ID
/04 /20
La yo ut T ab N am e:
G
W :\A cq ui si tio ns \J
VI
\p ro je ct s\
PV
U
\A
IP
X X
- 2
R un w ay
Li gh tin g\
F- C
AD
\P
LA
N
S\
2-
PV
U -X
X- G
2-
IN
D
X.
dw g Pl ot te d By
:N od ic h, A le x Pl ot te d:
Ju ne
, 2
6, :0 7:
P
M La st S av ed
B y:
M .V illa nu ev a, /4
/2
:4 2:
A
M B.A.H.
C.L.G.
AIP-069
G002
INDEX OF DRAWINGS &
SUMMARY OF
APPROXIMATE
QUANTITIES
PR
OV
O, U
TA
H
R
UN
W
AY
LI
GH
TI
NG
P
RO
JE
CT
AI
P
NO
. 3
-4 9-
-0
-2
PR
OV
O
AI
RP
OR
T
B.A.H.
6/04/2026
Sheet List Table
SHEET
NUMBER SHEET TITLE
G001 COVER SHEET
G002 INDEX OF DRAWINGS & SUMMARY OF APPROXIMATE QUANTITIES
G003 GENERAL NOTES
G004 MASTER LEGEND & ABBREVIATIONS
G005 SURVEY CONTROL PLAN
G006 CONSTRUCTION SAFETY AND PHASING PLAN - OVERALL
G007 CONSTRUCTION SAFETY NOTES
G008 CONSTRUCTION SAFETY AND PHASING PLAN - PHASE 1
G009 CONSTRUCTION SAFETY AND PHASING PLAN - PHASE 2
G010 CONSTRUCTION SAFETY AND PHASING PLAN - PHASE 3
G017 ENVIRONMENTAL EXHIBIT
E001 ELECTRICAL LEGEND
E101 ELECTRICAL DEMOLITION PLAN
E102 ELECTRICAL DEMOLITION PLAN
E103 ELECTRICAL DEMOLITION PLAN
E104 ELECTRICAL DEMOLITION PLAN
E105 ELECTRICAL DEMOLITION PLAN
E106 ELECTRICAL DEMOLITION PLAN
E201 ELECTRICAL GEOMETRY PLAN
E202 ELECTRICAL GEOMETRY PLAN
E203 ELECTRICAL GEOMETRY PLAN
E204 ELECTRICAL GEOMETRY PLAN
E205 ELECTRICAL GEOMETRY PLAN
E206 ELECTRICAL GEOMETRY PLAN
E207 ELECTRICAL GEOMETRY PLAN
E208 ELECTRICAL GEOMETRY PLAN
E209 ELECTRICAL GEOMETRY PLAN
E210 ELECTRICAL GEOMETRY PLAN
E211 ELECTRICAL GEOMETRY PLAN
E212 ELECTRICAL GEOMETRY PLAN
E213 ELECTRICAL GEOMETRY PLAN
E214 ELECTRICAL GEOMETRY PLAN
E250 ELECTRICAL DETAILS
E251 ELECTRICAL DETAILS
E252 ELECTRICAL DETAILS
E253 ELECTRICAL DETAILS
GENERAL NOTES
1. IF DURING THE CONSTRUCTION PROCESS, CONDITIONS ARE
ENCOUNTERED WHICH COULD INDICATE A SITUATION THAT IS NOT
IDENTIFIED IN THE PLANS OR SPECIFICATIONS, OR REPRESENT A
SIGNIFICANT DIFFERENCE BETWEEN THE CONTRACT DOCUMENTS AND
FIELD CONDITIONS, THE CONTRACTOR SHALL CONTACT THE ENGINEER
IMMEDIATELY.
2. ALL REFERENCES TO ANY PUBLISHED STANDARDS SHALL REFER TO THE
LATEST REVISION OF SAID STANDARD, UNLESS SPECIFICALLY STATED
OTHERWISE.
3. PROJECT PAY ITEMS PROVIDED ARE TO BE INCLUSIVE OF ALL WORK TO BE
PERFORMED AS SHOWN. ALL WORK NOT IDENTIFIED WITH A SPECIFIC PAY
ITEM SHALL BE CONSIDERED REQUIRED WORK TO COMPLETE THE
PROJECT AND IS TO BE INCIDENTAL TO THE COST OF PROJECT PAY ITEMS
PROVIDED.
4. WHENEVER, IN THE CONTRACT DOCUMENTS, THE WORDS "PROVIDE",
"FURNISH", "INSTALL", "FURNISH AND INSTALL", OR SIMILAR WORDS ARE
USED, IT SHALL BE UNDERSTOOD THAT THE INTENT OF THE CONTRACT
DOCUMENTS IS TO PROVIDE FOR THE CONSTRUCTION AND COMPLETION
IN EVERY DETAIL THE WORK DESCRIBED. IT IS FURTHER INTENDED THAT
THE CONTRACTOR SHALL FURNISH ALL LABOR, SUPERVISION, MATERIALS,
EQUIPMENT, TOOLS, TRANSPORTATION, SUPPLIES, TESTING, AND
INCIDENTALS REQUIRED TO COMPLETE THE WORK IN ACCORDANCE WITH
THE DRAWINGS (PLANS), SPECIFICATIONS, AND TERMS OF THE CONTRACT.
5. CONTRACTOR SHALL KEEP A SET OF AS-BUILT DRAWINGS ON-SITE AND
MAKE AVAILABLE TO THE ENGINEER AT ALL TIMES. AS-BUILT SET SHALL
BE SUBMITTED TO THE ENGINEER AT THE COMPLETION OF THE JOB.
CONTRACTOR SHALL BE RESPONSIBLE FOR RECORDING ALL AS-BUILT
INFORMATION DURING THE PROJECT. THE CONTRACTOR SHALL NOTE,
AND BRING TO THE ENGINEER'S ATTENTION, ANY DISCREPANCIES
BETWEEN THE CONTRACT DOCUMENTS AND ACTUAL FIELD CONDITIONS.
6. ALL DAMAGE TO UTILITIES, PAVEMENT, EQUIPMENT, OR STRUCTURES
FROM CONSTRUCTION ACTIVITIES SHALL BE IMMEDIATELY REPORTED TO
THE RESIDENT ENGINEER. THE RESIDENT ENGINEER SHALL DETERMINE
WHETHER REPAIR OR REPLACEMENT IS NECESSARY. ALL REPAIR
METHODS SHALL BE SUBMITTED TO THE RESIDENT ENGINEERFOR
REVIEW AND APPROVAL PRIOR TO INITIATING THE WORK. REPAIRS SHALL
BE MADE AT NO ADDITIONAL COST TO THE SPONSOR AND TO THE
APPROVAL OF THE ENGINEER.
7. THE CONTRACTOR SHALL PROVIDE WORKMANSHIP AND MATERIALS THAT
ARE OF GOOD QUALITY AND COMPLY WITH THE REQUIREMENTS OF THE
CONTRACT DOCUMENTS.
8. CONTRACTOR SHALL PROVIDE WORK, EQUIPMENT AND MATERIALS THAT
COMPLY WITH FAA REQUIREMENTS, NATIONAL ELECTRICAL CODE,
NATIONAL ELECTRICAL SAFETY CODE, AND ALL LOCAL CODES.
9. CONTRACTOR SHALL PROVIDE THE NECESSARY NUMBER OF RADIOS FOR
HIS/HER WORKFORCE.
10. SWEEPER(S) SHALL BE AVAILABLE AT ALL TIMES TO CLEAN FOREIGN
OBJECT DEBRIS (FOD) FROM HAUL ROUTE OR OTHER AREAS ADJACENT TO
CONSTRUCTION ACTIVITY. CONTRACTOR SHALL CONSTANTLY MONITOR
AIRCRAFT MOVEMENT AREAS FOR FOD AND IMMEDIATELY REMOVE ALL
DEBRIS.
11. PRIOR TO OPENING OR CLOSING A RUNWAY OR TAXIWAY, THE
CONTRACTOR MUST, THROUGH THE AIRPORT, GIVE NOTICE USING THE
NOTICE TO AIRMEN (NOTAM) SYSTEM OF PROPOSED LOCATION, TIME AND
DATE OF COMMENCEMENT OF CONSTRUCTION AND THE DURATION OF
THE CLOSURE.
12. FOURTEEN (14) DAYS PRIOR TO THE BEGINNING OF WORK, THE
CONTRACTOR SHALL SUBMIT A QUALITY CONTROL PLAN WHICH INCLUDES
A WORK SCHEDULE AND PROPOSED CONSTRUCTION METHODS
CONSISTENT WITH THE PHASING PLAN STATED IN THE DESIGN.
13. THE CONTRACTOR SHALL HAVE A MINIMUM OF ONE (1) CURRENT COPY OF
THE APPROVED PLANS (INCLUDING ANY CHANGE ORDERS,
SUPPLEMENTAL AGREEMENTS, FIELD DIRECTIVES, ETC.), ONE (1)
CURRENT COPY OF THE APPROPRIATE STANDARDS AND SPECIFICATIONS,
AND A COPY OF ANY PERMITS AND EXTENSION AGREEMENTS NEEDED FOR
THE JOB, ON SITE AT ALL TIMES.
14. DESIGNS CONTAINED HEREIN ARE BASED ON SPECIFIED EQUIPMENT. THE
CONTRACTOR SHALL BE RESPONSIBLE FOR ANY REDESIGN FOR
EQUIPMENT SUBSTITUTIONS TO THE APPROVED SPECIFICATIONS AT NO
ADDITIONAL COST TO THE SPONSOR. THE CONTRACTOR SHALL PROVIDE
MATERIAL SUBMITTALS,SAMPLES AND DESIGN DRAWINGS FOR THE
ENGINEER'S APPROVAL A MINIMUM OF SEVEN (7) DAYS PRIOR TO
ORDERING.
15. ALL MATERIALS, WORKMANSHIP, AND CONSTRUCTION OF PUBLIC
IMPROVEMENTS SHALL MEET OR EXCEED THE STANDARDS AND
SPECIFICATIONS SET FORTH IN THE APPLICABLE STATE AND FEDERAL
REGULATIONS. WHERE THERE IS CONFLICT BETWEEN THESE PLANS AND
THE SPECIFICATIONS, OR ANY APPLICABLE STANDARDS, THE HIGHER
QUALITY STANDARD SHALL APPLY. ALL WORK SHALL BE INSPECTED AND
APPROVED BY THE RESIDENT ENGINEER.
16. DIMENSIONING FOR LAYOUTS AND CONSTRUCTION ARE NOT TO BE
SCALED FROM ANY DRAWINGS. IF PERTINENT DIMENSIONS ARE NOT
SHOWN, CONTACT THE ENGINEER FOR CLARIFICATION AND RECORD
DIMENSIONS ON AS-BUILT DRAWINGS.
17. TOPSOIL SHALL BE REMOVED AND STOCKPILED PRIOR TO GRADING
OPERATIONS. PAYMENT FOR RE-HANDLING OF TOPSOIL SHALL NOT BE
MEASURED FOR PAYMENT.
18. CONTRACTOR SHALL HAVE A COPY OF THE CURRENT FAA ADVISORY
CIRCULAR AC 150/5340-1 (CURRENT VERSION) "STANDARDS FOR AIRPORT
MARKINGS" ON SITE AT ALL TIMES. ANY DISCREPANCY BETWEEN
INFORMATION SHOWN ON THE PLAN SHEETS AND THE ADVISORY
CIRCULAR SHALL BE COORDINATED WITH THE ENGINEER FOR DIRECTION.
QUALITY CONTROL/QUALITY ASSURANCE
1. FOURTEEN (14) DAYS PRIOR TO THE BEGINNING OF WORK, THE
CONTRACTOR SHALL SUBMIT A QUALITY CONTROL PLAN WHICH INCLUDES
A WORK SCHEDULE AND PROPOSED CONSTRUCTION METHODS
CONSISTENT WITH THE PHASING PLAN STATED IN THE DESIGN.
PERMITTING
1. PRELIMINARY PERMITTING INFORMATION WILL BE SUBMITTED BY THE
ENGINEER PRIOR TO AWARD OF CONTRACT. SPECIFIC ITEMS THAT WILL
NEED TO BE COMPLETED BY THE CONTRACTOR INCLUDE BUT ARE NOT
LIMITED TO SUPPLYING NECESSARY BONDING, PAYMENT OF ALL FEES,
REVIEW OF ALL CALCULATIONS AND ASSUMPTIONS MADE BY THE
ENGINEER PRIOR TO AWARD. THE CONTRACTOR IS RESPONSIBLE FOR
OBTAINING ALL NECESSARY PERMITS INCLUDING, BUT NOT LIMITED TO, AN
FAA 7460-1 NOTICE OF PROPOSED CONSTRUCTION OR ALTERATION, A
CDPHE STORMWATER PERMIT, AND A FUGITIVE DUST PERMIT. THE
CONTRACTOR SHALL BE RESPONSIBLE TO PAY FOR THE COST TO OBTAIN
ALL PERMITS.
2. THE CONTRACTOR SHALL SUBMIT A COPY OF ALL PERMITS REQUIRED FOR
THE PROJECT TO THE ENGINEER, FOR HIS REVIEW.
SITE ACCESS AND STAGING
1. THE CONTRACTOR IS REQUIRED TO OBTAIN A WATER METER FROM THE
CITY OF PROVO WATER DIVISION FOR ACCESS TO CONSTRUCTION WATER
FROM AN ON AIRPORT LOCATION. A WATER SOURCE ON AIRPORT
PROPERTY AND THE PRICE OF WATER WILL BE COORDINATED AT THE TIME
OF BIDDING.
2. DURING CONSTRUCTION, THE CONTRACTOR SHALL MINIMIZE
DISTURBANCES TO ALL CONSTRUCTION AREAS AND ACCESS ROUTES.
THIS INCLUDES EQUIPMENT AND VEHICULAR RUTS CREATED IN ANY
PAVEMENTS, ANY HAUL/ACCESS ROADS, OR ANY INFIELD/SAFETY AREAS.
THE CONTRACTOR SHALL BE RESPONSIBLE FOR ANY DAMAGE TO
EXISTING FACILITIES OR ROADS. REPAIRS SHALL BE MADE AT NO
ADDITIONAL COST TO THE SPONSOR AND TO THE SATISFACTION OF THE
ENGINEER. HAUL ROUTE BRIDGES SHALL BE CONSTRUCTED AT HAUL
ROUTES CROSSING EXISTING AIRFIELD PAVEMENT. COSTS ASSOCIATED
WITH HAUL BRIDGE CONSTRUCTION WILL BE CONSIDERED INCIDENTAL TO
MOBILIZATION.
3. BEFORE ESTABLISHING SITE ACCESS AND HAUL ROUTES, THE
CONTRACTOR SHALL OBTAIN APPROVAL FROM THE ENGINEER. WHEN
POSSIBLE, ACCESS/HAUL ROUTES SHALL UTILIZE EXISTING ROADS. THE
CONTRACTOR SHALL MAINTAIN AIRPORT SECURITY AT ALL TIMES.
4. CONTRACTOR SHALL EXAMINE THE EXISTING PAVEMENTS THAT WILL BE
USED FOR HAULING OF MATERIAL AND EQUIPMENT, AND DETERMINE THE
PAVEMENTS ABILITY TO WITHSTAND CONTRACTOR OPERATIONS WITHOUT
CAUSING DAMAGE TO THE PAVEMENT. ANY DAMAGE CAUSED BY THE
CONTRACTOR SHALL BE REPAIRED BY THE CONTRACTOR TO THE
APPROVAL OF THE ENGINEER AND AT NO ADDITIONAL COST TO THE
SPONSOR.
5. CONTRACTOR SHALL BE REQUIRED TO PROVIDED NON-POTABLE WATER
FOR CONSTRUCTION PURPOSES. CONTRACTOR SHALL BE RESPONSIBLE
FOR STORAGE OF NON-PORTABLE WATER. ANY STRUCTURES ERECTED IN
SUPPORT OF WATERING OPERATIONS SHALL MEET FAA FAR PART 77
CLEARANCES FOR ALL AIRCRAFT AND BE APPROPRIATELY LIT AS A
HAZARD TO THE FLYING PUBLIC. NON-PORTABLE WATER USED FOR P-152
OR DUST CONTROL SHALL BE INCIDENTAL TO THE PROJECT BID ITEMS.
6. DURING ANY NIGHTTIME OPERATIONS ALL AREA LIGHTING SHALL BE
FACED IN DIRECTIONS AS DIRECTED BY THE ENGINEER. AT NO TIME SHALL
LIGHT PLANTS BE LEFT RUNNING WHEN CONSTRUCTION OPERATIONS ARE
NOT IN PROCESS.
7. ALL AREAS THAT ARE DISTURBED BY CONTRACTOR OPERATIONS, SHALL
BE SEEDED PER T-901 SEEDING. ALL EROSION CONTROL COSTS ARE
INCIDENTAL TO CONSTRUCTION AND WILL NOT BE PAID SEPARATELY.
8. ALL CONTRACTOR EMPLOYEES SHALL BE REQUIRED TO PARK IN THE
CONTRACTORS DESIGNATED STAGING AREA ONLY AND SHALL BE DRIVEN
TO THE PROJECT SITE BY DESIGNATED CONSTRUCTION VEHICLES.
9. CRAWLER TRACKED VEHICLES SHALL NOT BE ALLOWED ON PAVED
SURFACES. TRACKED VEHICLES MUST BE MOVED ACROSS PAVED
SURFACES ON A WHEELED VEHICLE.
10. WHENEVER CONSTRUCTION TRAFFIC IS REQUIRED TO CROSS AN ACTIVE
RUNWAY, TAXIWAY, TAXILANE, OR INTERRUPT NORMAL TRAFFIC FLOW ON
APRONS OR RAMPS, THE CONTRACTOR SHALL PROVIDE FLAGGERS AT
THE CROSSING(S) AS REQUIRED BY THE CONSTRUCTION PHASING
DRAWINGS OR AS DIRECTED BY THE ENGINEER OR THE AIRPORT
(INCIDENTAL TO ITEM C-105).
UTILITIES
1. PRIOR TO COMMENCING WORK, IT SHALL BE THE RESPONSIBILITY OF THE
CONTRACTOR TO CONTACT THE APPROPRIATE UTILITY AGENCIES, UTILITY
NOTIFICATION CENTERS, AND TO FIELD VERIFY THE LOCATIONS AND
DEPTHS, THROUGH UTILITY LOCATES AND POTHOLES, OF ALL EXISTING
UTILITIES WITHIN THE PROJECT LIMITS, STAGING, AND HAUL ROUTE
AREAS.
2. THE EXISTING UTILITY LOCATIONS SHOWN ON THE PLANS ARE
APPROXIMATE AND SHALL NOT BE SCALED FOR EXACT LOCATION.
LOCATION OF EXISTING DUCT BANK, CIRCUITING, UTILITIES AND
STRUCTURES SHOWN ON THESE DRAWINGS IS BASED ON AVAILABLE
INFORMATION AND IS NOT WARRANTED TO BE EXACT, NOR IS IT
WARRANTED THAT ALL OF THESE ITEMS ARE SHOWN.
3. CONTRACTOR SHALL CONTACT AND COORDINATE WITH THE
APPROPRIATE UTILITY AGENCIES WHEN WORKING ON OR WITHIN THE
PROXIMITY OF AN AGENCIES UTILITY. IT SHALL BE THE RESPONSIBILITY OF
THE CONTRACTOR TO RELOCATE ALL EXISTING UTILITIES THAT CONFLICT
WITH THE PROPOSED IMPROVEMENTS SHOWN ON THESE PLANS.
4. ANY INTERRUPTION OF AN EXISTING SYSTEM OR UTILITY SERVICE SHALL
BE COORDINATED AND APPROVED BY THE AIRPORT AND THE AUTHORITY,
AGENCY, OR UTILITY HAVING JURISDICTION, PRIOR TO STARTING WORK
INCLUDING CONTACTING THE AIRPORT AND FAA.
5. CONTRACTOR IS RESPONSIBLE FOR DAMAGES TO EXISTING UTILITIES.
REPAIRS DEEMED NECESSARY BY THE ENGINEER WILL BE COMPLETED BY
THE CONTRACTOR AT NO ADDITIONAL COST TO THE SPONSOR. SEE
SECTION 50 OF THE CONTRACT DOCUMENTS AND THE "CONSTRUCTION
STAKING AND LAYOUT" NOTES CONTAINED IN THESE GENERAL NOTES
SHEETS FOR ADDITIONAL NOTES REGARDING UTILITY LOCATES.
6. THE CONTRACTOR SHALL COORDINATE AND COOPERATE WITH THE CITY,
COUNTY, AND ALL UTILITY COMPANIES INVOLVED, WITH REGARD TO
RELOCATIONS OR ADJUSTMENTS OF EXISTING UTILITIES DURING
CONSTRUCTION, AND TO ASSURE THAT THE WORK IS ACCOMPLISHED IN A
TIMELY FASHION AND WITH A MINIMUM DISRUPTION OF SERVICE. THE
CONTRACTOR SHALL BE RESPONSIBLE FOR CONTACTING ALL PARTIES
AFFECTED BY ANY DISRUPTION OF ANY SERVICE.
7. WHERE NEW DUCT BANKS OR OTHER UTILITIES ARE NEAR EXISTING
UTILITIES, THE CONTRACTOR SHALL HAND EXCAVATE AROUND THE
EXISTING UTILITIES IN ORDER T0 PREVENT DAMAGE. THE CONTRACTOR
SHALL BE RESPONSIBLE FOR IMMEDIATELY REPAIRING ANY UTILITY
DAMAGED DURING CONSTRUCTION.
8. WHEN INSTALLING NEW UTILITIES UNDER EXISTING PAVEMENT THE
CONTRACTOR SHALL NEATLY SAW CUT AND REMOVE THE EXISTING
PAVEMENT PRIOR TO INSTALLING THE CONDUIT. THE CONTRACTOR SHALL
BE RESPONSIBLE FOR REPLACING ANY PAVEMENT REMOVED OR
DAMAGED DURING THE UTILITY INSTALLATION PROCESS. ALL WORK
REQUIRED TO REMOVE AND REPAIR PAVEMENT SHALL BE INCLUDED IN
THE INSTALL NEW UTILITY BID ITEM.
9. THE CONTRACTOR SHALL SEQUENCE INSTALLATION OF UTILITIES IN SUCH
A MANNER AS TO MINIMIZE POTENTIAL UTILITY CONFLICTS. IN GENERAL,
STORM SEWER AND SANITARY SEWER SHOULD BE CONSTRUCTED PRIOR
TO INSTALLATION OF THE WATER LINES AND DRY UTILITIES.
10. CONTRACTOR SHOULD EXPECT TO ENCOUNTER WATER IN LIGHT CANS,
JUNCTION CANS AND STRUCTURES. CONTRACTOR RESPONSIBLE FOR
DEWATERING AT NO ADDITIONAL COST TO THE OWNER.
11. THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ALL
UNDERGROUND UTILITIES PRIOR TO BEGINNING CONSTRUCTION. THE
CONTRACTOR MAY UTILIZE THE FOLLOWING TOLL FREE TELEPHONE
NUMBER PROVIDED BY “UTAH 811". THIS NUMBER IS APPLICABLE
ANYWHERE WITHIN THE STATE OF UTAH.
SUBMITTALS
1. THE CONTRACTOR SHALL SUBMIT A DETAILED LISTING OF ALL SUBMITTALS
(E.G., MIX DESIGNS, MATERIAL CERTIFICATION, AND PRODUCT
INFORMATION) AND SHOP DRAWINGS REQUIRED BY THE TECHNICAL
SPECIFICATIONS.
2. THE CONTRACTOR SHALL PROVIDE MATERIAL SUBMITTALS FOR THE
ENGINEER'S APPROVAL AT LEAST TEN (10) DAYS PRIOR TO ORDERING.
TRAFFIC CONTROL
1. THE CONTRACTOR IS RESPONSIBLE FOR COORDINATING AND PROVIDING
ALL REQUIRED TRAFFIC CONTROL FOR THE PROJECT'S ACCESS
LOCATIONS, INCLUDING ANY REQUIREMENTS OF UDOT OR CITY OF PROVO.
ALL ASSOCIATED COSTS ARE INCIDENTAL TO CONSTRUCTION AND WILL
NOT BE PAID SEPARATELY.
2. THE CONTRACTOR SHALL SUBMIT A TRAFFIC CONTROL PLAN IN
ACCORDANCE WITH LOCAL JURISDICTIONAL REQUIREMENTS FOR
APPROVAL PRIOR TO THE START OF ANY CONSTRUCTION ACTIVITIES.
CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING AND MAINTAINING
ANY AND ALL TRAFFIC CONTROL DEVICES.
MATERIAL SUPPLY AND DISPOSAL
1. ALL MATERIALS MUST BE OBTAINED FROM AN UNDESIGNATED SOURCE
UNLESS OTHERWISE IDENTIFIED IN THE PLANS OR SPECIFICATIONS.
2. ALL WASTE MATERIALS SHALL BE REMOVED FROM THE AIRPORT
PROPERTY AT NO COST TO THE SPONSOR UNLESS OTHERWISE DIRECTED
BY THE SPONSOR.
3. CONTRACTOR TO SALVAGE ALL ELECTRICAL WIRE, LIGHT CAN BASES,
EDGE LIGHTS AND ISOLATION TRANSFORMERS. ALL SALVAGED
MATERIALS WILL BE THE PROPERTY OF THE AIRPORT. SALVAGED
MATERIALS SHALL BE NEATLY STACKED ON WOODEN PALLETS AND
BANDED TO THE PALLET.
WORKING NEAR STRUCTURES
1. THE STRUCTURES SHOWN OR DEFINED IN THE CONTRACT DOCUMENTS
AND PLANS HAS BEEN DESIGNED ONLY FOR LOADS ANTICIPATED ON THE
STRUCTURE DURING ITS SERVICE LIFE. CONTRACTOR SHALL PROVIDE
ALL REQUIRED ENGINEERING AND OTHER MEASURES TO ACHIEVE THE
MEANS, METHODS, AND SEQUENCES OF WORK. REQUIRED ENGINEERING
MAY INCLUDE, BUT IS NOT LIMITED TO:
· LAYOUT
· DESIGN FOR FORMWORK, SHORING, AND RESHORING
· DESIGN OF CONCRETE MIXES
· ERECTION PROCEDURES WHICH ADDRESS STABILITY OF THE FRAME
DURING CONSTRUCTION
· WELD PROCEDURES
· DESIGN OF TEMPORARY BRACING OF WALLS FOR WIND, SEISMIC, OR SOIL
LOADS
· SURVEYING TO VERIFY CONSTRUCTION TOLERANCES
· EVALUATION OF TEMPORARY CONSTRUCTION LOADS ON STRUCTURE DUE
TO EQUIPMENT AND MATERIALS
· STRUCTURAL ENGINEERING TO RESIST ANY OTHER LOADS NOT
IDENTIFIED ON DESIGN DRAWINGS.
SHEET NAME:
SHEET NO:
DRAWN BY:
PROJECT NO:
DATE ISSUED:
DESIGNED BY:
CHECKED BY:
35 South 400 West St, Suite 200 St. George, UT 84770
435.673.4677
NU
MB
ER
DA
TE
DE
SC
RI
PT
IO
N
IS
SU
AN
CE
S
CH
ED
UL
E
IS
SU
ED
F
OR
B
ID
/04 /20
La yo ut T ab N am e:
G
W :\A cq ui si tio ns \J
VI
\p ro je ct s\
PV
U
\A
IP
X X
- 2
R un w ay
Li gh tin g\
F- C
AD
\P
LA
N
S\
3-
PV
U -X
X- G
3-
N O
TE
.d w g
Pl ot te d
By :N od ic h, A le x
Pl ot te d:
Ju ne
, 2
6, :0
7:
P M
La st
S av ed B y:
M
.V illa nu ev a, /5 /2
9:
:2
AM B.A.H.
C.L.G.
AIP-069
G003
GENERAL NOTES
PR
OV
O, U
TA
H
R
UN
W
AY
LI
GH
TI
NG
P
RO
JE
CT
AI
P
NO
. 3
-4 9-
-0
-2
PR
OV
O
AI
RP
OR
T
B.A.H.
6/04/2026
ABBREVIATIONS
AB ABANDONED
AC ACRE
ADG AIRPORT DESIGN GROUP
ARFF AIRPORT RESCUE AND FIRE FIGHTING
AOA AIRPORT OPERATIONS AREA
BMPS BEST MANAGEMENT PRACTICES
BP BEGINNING POINT OF ALIGNMENT
C CURVE
CL CENTERLINE
CY CUBIC YARD
Δ DELTA ANGLE
DIP DUCTILE IRON PIPE
DIW DIRTY INDUSTRIAL WASTE
E EASTING COORDINATE
EA EACH
EDB ELECTRICAL DUCT BANK
EF EACH FACE EL ELEVATION
EL ELECTRICAL LINES
EOP EDGE OF PAVEMENT
EP ENDING POINT OF ALIGNMENT
EW EACH WAY
FAA FEDERAL AVIATION ADMINISTRATION
FES FLARED END SECTION
FID FLIGHT INFORMATION DUCT (FAA)
FOD FOREIGN OBJECT DEBRIS
FOMO FIXED OR MOVEABLE OBJECT
GAL GALLON
HDPE HIGH DENSITY POLYETHYLENE PIPE
ID INSIDE DIAMETER
ILS INSTRUMENT LANDING SYSTEM
INV INVERT
INT INTERSECTION
JFD JET FUEL DISTRIBUTION
L LENGTH
LF LINEAL FEET
LLWAS LOW LEVEL WIND SHEAR ALERT SYSTEM
LS LUMP SUM
MGAL THOUSAND GALLON
MH MANHOLE
MO MONTH
N NORTHING COORDINATE
NGS NATURAL GAS
NO. NUMBER
NOAA NATIONAL OCEANOGRAPHIC &
ATMOSPHERIC ADMINISTRATION
NIC NOT IN THIS CONTRACT
NTP NOTICE TO PROCEED
NTS NOT TO SCALE
OC ON CENTER
OH OVERHEAD LINES
OS OFFSET FROM ALIGNMENT
OSHA OCCUPATIONAL SAFETY & HEALTH
ADMINISTRATION
PB ELECTRICAL PULL BOX
PC POINT OF CURVATURE
PCR POINT OF REVERSE CURVATURE
PGL PROFILE GRADE LINE
PI POINT OF INTERSECTION
PPVC PERFORATED UNDERDRAIN PIPE
PT POINT OF TANGENT
PVC POINT OF VERTICAL CURVATURE
PVC POLYVINYL CHLORIDE
PVI POINT OF VERTICAL INTERSECTION
PVT POINT OF VERTICAL TANGENT
R RADIUS
RCP REINFORCED CONCRETE PIPE
ROFA RUNWAY OBJECT FREE AREA
RPZ RUNWAY PROTECTION ZONE
RSA RUNWAY SAFETY AREA
RW RUNWAY
SAF SANITARY SEWER (FORCE MAIN)
SAG SANITARY SEWER (GRAVITY)
SDG STORM WATER DRAINAGE (GRAVITY)
SF SQUARE FEET
SHT SHEET
SOI SAND/OIL INTERCEPTOR
SPA SPACES
STA STATION
STL STEEL
SY SQUARE YARD
T1F TYPE 1 DE-ICING FLUID
TW TAXIWAY
TOFA TAXIWAY OBJECT FREE AREA
TSA TAXIWAY SAFETY AREA
TYP TYPICAL
UG UNDERGROUND
UMH UNDERDRAIN MANHOLE
VC VERTICAL CURVE
VSR VEHICLE SERVICE ROAD
WMD WASTE WATER MANAGEMENT
WWF WELDED WIRE FABRIC
UDOT STATE DEPARTMENT OF TRANSPORTATION
PVU PROVO AIRPORT
MASTER LEGEND
WAT WAT
SAN SAN
UD UD
RSA RSA
ROFA ROFA
UCO
SDG
C
S
T
HH
E
TSA TSA
TOFA TOFA
BRL BRL
UMH
COMMUNICATIONSSITE
SAFETY & NAVAIDS
ELECTRICAL
XXXXXXXXXXXX
XX
ROW ROW
EXISTING L-824C
CONDUCTOR (1)
EXISTING APRON
FLOODLIGHT
EXISTING AIRPORT
BEACON
EXISTING L-824C
CONDUCTORS (2)
EXISTING POWER MARKER
EXISTING ELECTRICAL
JUNCTION BOX
EXISTING TAXIWAY
GUIDANCE SIGN
EXISTING ELECTRICAL
HANDHOLE
EXISTING POWER POLE
EXISTING ELECTRICAL DUCT (CE)
EXISTING ELECTRICAL DUCT (DEB)
EXISTING STORM SEWER
EXISTING WATER AIR
VALVE
EXISTING UNDERDRAIN
MANHOLE
EXISTING STORM FLARED
END SECTION
EXISTING UNDERDRAIN
CLEANOUT
EXISTING UNDERDRAIN
INSPECTION PIT
EXISTING STORM
MANHOLE
EXISTING STORM INLETEXISTING TELEPHONE
PEDESTAL
EXISTING WATER FIRE
HYDRANT
EXISTING UNDERDRAIN
EXISTING WATER LINE
EXISTING SANITARY SEWER LINE
EXISTING BUILDING RESTRICTION LINE
EXISTING TAXIWAY OBJECT FREE AREA
EXISTING TAXIWAY SAFETY AREA
EXISTING RUNWAY OBJECT FREE AREA
EXISTING RUNWAY SAFETY AREA
CARD READER
DOUBLE GATE
FENCE POST
GATE CONTROLER
SINGLE GATE
AIRCRAFT TIE DOWN
EXISTNG ASPHALT
MILLINGS AREAEXISTING GRAVEL AREA
EXISTING ASPHALT
PAVEMENT
EXISTING CONCRETE
PAVEMENT
EXISTING SURVEY
MONUMENT
EXISTING BUILDING
EXISTING WAY FINDING
SIGN
EXISTING LEASE LINE
EXISTING EASEMENT LINE
EXISTING RIGHT-OF-WAY LINE
EXISTING PROPERTY LINE
EXISTING GUARD RAIL
EXISTING FENCE (SPLIT RAIL)
EXISTING FENCE (BARBED WIRE)
EXISTING FENCE
EXISTING SWALE FLOW LINE
ABANDON ITEM
REMOVE ITEM
EXISTING WETLAND
AREA
EXISTING PAVEMENT
EXISTING CENTERLINE
EXISTING MINOR CONTOUR
EXISTING MAJOR CONTOUR
EXISTING TRENCH DRAIN
EXISTING PAINT
MARKING
EXISTING CABLE MANHOLE EXISTING CABLE
PEDESTALCATV CATV
T TMH
TP
EXISTING TELEPHONE
JUNCTION BOX
EXISTING TELEPHONE
MANHOLE
EXISTING TELEPHONE
POLE
EXISTING FIBER OPTIC
MANHOLEFOPT
EXISTING JET FUEL VAULTEXISTING JET FUEL
UNDERGROUND PIT
EXISTING JET FUEL LINE
MARKEREXISTING JET FUEL VALVE
EXISTING JET FUEL FILL
STATION
EXISTING JET FUEL
CATHODIC PROTECTION
EXISTING JET FUEL LOW
POINT
EXISTING JET FUEL HIGH
POINT
EXISTING JET FUEL TEST
STATION
CP
JF
HP
T S
JFD
VAULT
JF
F
JF
LP
EXISTING NATURAL GAS
METER
EXISTING NATURAL GAS
VALVE
EXISTING NATURAL GAS
MANHOLE
EXISTING NATURAL GAS
LINE MARKER
G
G G
G
EXISTING SANITARY
SEWER
EXISTING SANITARY
SEWER
SCO
EXISTING WATER METER
EXISTING WATER
MANHOLE
EXISTING WATER LINE
MARKER
EXISTING WATER WELL EXISTING WATER VALVE
EXISTING WATER TEST
STATION
EXISTING WATER
CATHODIC PROTECTION
EXISTING IRRIGATION
VALVE
EXISTING IRRIGATION
CONTROL BOX
W PFW
WELL
TS CP
SPR
CON
EXISTING PAPI SYSTEM
EXISTING MALS LIGHT EXISTING MALS LIGHT BAR
EXISTING MALS STROBE
LIGHT
EXISTING MALS STROBE
LIGHT BAR
EXISTING LOCALIZER
SYSTEM EXISTING VASI SYSTEM
EXISTING WIND CONE EXISTING WIND SOCK
EXISTING REIL EXISTING AWOS SYSTEMAWOS
EXISTING VOR SYSTEM EXISTING AIRFIELD
ANTENNA
EXISTING TORNADO SIREN
RPZ RPZ EXISTING RUNWAY PROTECTION ZONE
NAVAID CRITICAL AREA
GC CR
EXISTING NATURAL GAS
CATHODIC PROTECTIONCP
EXISTING DEICING FLUID
MANHOLE
EXISTING DEICING FLUID
INLET
EXISTING DEICING FLUID
VALVE
ADF ADF
EXISTING STORM
HEADWALL
J
E EXISTING ELECTRIC METER
EMH
EXISTING ELECTRICAL
MANHOLE
EL EL
GAS GAS
OPT OPT
CBL CBL
COM COM
FUEL FUEL EXISTING JET FUEL LINE
EXISTING COMMUNICATION LINE
EXISTING FIBER OPTIC LINE
EXISTING ELECTRICAL LINE
EXISTING CABLE LINE
EXISTING NATURAL GAS LINE
ET EXISTING PAD MOUNTED
TRANSFORMER
EXISTING TRANSFORMER
BANK
EXISTING GROUND ROD
EXISTING ELECTRIC VAULT
A EXISTING CIRCUIT
INDICATOR
TEL TEL EXISTING TELEPHONE LINE
EXISTING RUNWAY
DISTANCE REMAINING SIGN
X X
X
X
EXISTING DOUBLE
PARKING LOT LIGHT
EXISTING SINGLE PARKING
LOT LIGHT
EXISTING STREET LIGHT
EXISTING RUNWAY EDGE
LIGHT (IN PAVEMENT)
EXISTING RUNWAY EDGE
LIGHT (ELEVATED)
EXISTING RUNWAY
CENTER LIGHT
EXISTING RUNWAY END
LIGHT (IN PAVEMENT)
EXISTING RUNWAY END
LIGHT (ELEVATED)
EXISTING RUNWAY GUARD
LIGHT
EXISTING TAXIWAY
CENTER LIGHT
EXISTING TAXIWAY EDGE
LIGHT (ELEVATED)
EXISTING TAXIWAY EDGE
LIGHT (IN PAVEMENT)
EXISTING TAXIWAY EDGE
REFLECTOR (IN PAVE.)
EXISTING TAXIWAY EDGE
REFLECTOR (ELEVATED)
PF EXISTING ELECTRIC
POWER FRAME
JET FUEL
IRG IRG EXISTING IRRIGATION LINE
NATURAL GAS
SANITARY SEWER
STORM SEWER & UNDERDRAIN
WATER & IRRIGATION
X X
X
X
X X
X
X
X X
SHEET NAME:
SHEET NO:
DRAWN BY:
PROJECT NO:
DATE ISSUED:
DESIGNED BY:
CHECKED BY:
35 South 400 West St, Suite 200 St. George, UT 84770
435.673.4677
NU
MB
ER
DA
TE
DE
SC
RI
PT
IO
N
IS
SU
AN
CE
S
CH
ED
UL
E
IS
SU
ED
F
OR
B
ID
/04 /20
La yo ut T ab N am e:
G
W :\A cq ui si tio ns \J
VI
\p ro je ct s\
PV
U
\A
IP
X X
- 2
R un w ay
Li gh tin g\
F- C
AD
\P
LA
N
S\
5-
PV
U -X
X- G
5-
LG
N
D .d w g
Pl ot te d
By :N od ic h, A le x
Pl ot te d:
Ju ne
, 2
6, :0
8:
P M
La st
S av ed B y:
M
.V illa nu ev a, /7 /2
8:
:3
AM B.A.H.
C.L.G.
AIP-069
G004
MASTER LEGEND &
ABBREVIATIONS
PR
OV
O, U
TA
H
R
UN
W
AY
LI
GH
TI
NG
P
RO
JE
CT
AI
P
NO
. 3
-4 9-
-0
-2
PR
OV
O
AI
RP
OR
T
TW A1
TW A2
TW A3
TW A4
TW A5
TAXIWAY D
TAXIWAY B
TA
XI
W
AY
C
R U
N W
AY
8/
RUNW
AY 13/31
RW 31
RW 13
PVU D
A 121
PVU K
( IN FEET )
GRAPHIC SCALE
1000500500
SURVEY NOTES:
1. REFER TO GENERAL NOTES FOR ADDITIONAL INFORMATION.
2. CONTRACTOR SHALL VERIFY AIRPORT AND PROJECT
CONTROL POINTS PRIOR TO CONSTRUCTION ACTIVITIES AND
REPORT DISCREPANCIES TO THE ENGINEER.
3. CONTRACTOR SHALL PROTECT AND PRESERVE THE AIRPORT
SURVEY CONTROL STATIONS.
4. IF THE PROJECT TEMPORARY SURVEY CONTROL IS
DISTURBED DURING CONSTRUCTION ACTIVITIES, THE
CONTRACTOR IS RESPONSIBLE FOR ESTABLISHING NEW
TEMPORARY CONTROL POINTS AS NECESSARY.
PACS - PRIMARY AIRPORT CONTROL STATION
SACS - SECONDARY AIRPORT CONTROL STATION
PROJECT TEMPORARY SURVEY CONTROL POINT
RUNWAY END MONUMENT
SURVEY LEGEND
RUNWAY END DATA
RW END STATION NORTHING EASTING ELEVATION DESCRIPTION
13 100+00 7252665.72 1575518.38 4496.80 BRASS CAP
31 186+00 72455541.66 1580334.87 4492.73 PUBLISHED
(BM) ELEVATION BENCHMARK, (G) GPS DERIVED ELEVATION, (P) PUBLISHED ELEVATION
PROJECT DATUM STATEMENT
COORDINATE SYSTEM: NAD83 (2011)
STATE PLANE ZONE: UTAH CENTRAL ZONE 4302
UNITS: U.S. SURVEY FEET (SFT)
GEOID MODEL: GEOID18
PROJECT COORDINATES ARE STATE PLANE GROUND COORDINATES.
PROJECT BROUGHT TO GROUND AT 'A 121' (OLD PACS)
LAT: 40°13'08.51898" N
LONG: 111°43'10.20886" W
ELLIPSOID HEIGHT: 4436.69 FT
NAVD88 ELEVATION: 4494.09 FT (VERTICAL BM)
GROUND SCALE FACTOR: 1.0002909246
'PVU K', THE PRIMARY AIRPORT CONTROL STATION (PACS), IS TO BE HELD
AS THE SITE VERTICAL BENCHMARK.
LAST SURVEY WAS COMPLETE BY WOOLPERT ON 04/29/2023
SHEET NAME:
SHEET NO:
DRAWN BY:
PROJECT NO:
DATE ISSUED:
DESIGNED BY:
CHECKED BY:
35 South 400 West St, Suite 200 St. George, UT 84770
435.673.4677
NU
MB
ER
DA
TE
DE
SC
RI
PT
IO
N
IS
SU
AN
CE
S
CH
ED
UL
E
IS
SU
ED
F
OR
B
ID
/04 /20
AIRPORT SURVEY CONTROL DATA
POINT NAME PID NORTHING EASTING ELEVATION DESCRIPTION
A 121 (OLD PACS) LO0518 7,248,583.98 1,579,122.03 4494.09 (P) BRONZE SURVEY DISK
PVU K (NEW PACS) 7,250,553.753 1,578,012.833 4491.72 (BM) STAINLESS STEEL ROD
PVU D (SACS) LO1152 7,248,276.39 1,576,790.52 4498.19 (BM) BRONZE SURVEY DISK
(BM) ELEVATION BENCHMARK, (G) GPS DERIVED ELEVATION, (P) PUBLISHED ELEVATION
La yo ut T ab N am e:
G
W :\A cq ui si tio ns \J
VI
\p ro je ct s\
PV
U
\A
IP
X X
- 2
R un w ay
Li gh tin g\
F- C
AD
\P
LA
N
S\
6-
PV
U -X
X- G
6-
SU
R
V.
dw g Pl ot te d By
:N od ic h, A le x Pl ot te d:
Ju ne
, 2
6, :0 8:
P
M La st S av ed
B y:
M .V illa nu ev a, /7
/2
9:
:3
AM B.A.H.
C.L.G.
AIP-069
G005
SURVEY CONTROL
PLAN
PR
OV
O, U
TA
H
R
UN
W
AY
LI
GH
TI
NG
P
RO
JE
CT
AI
P
NO
. 3
-4 9-
-0
-2
PR
OV
O
AI
RP
OR
T
TOFATOFATOFATOFA
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
TOFATOFATOFATOFATOFA
TO
FA
TO
FA
TO
FA
TO
FA
TOFA
TOFA
TOFA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSA
RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSA
ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA
ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA
ROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
R
SA
RSA
TSA TSA TSA TSA TSA TSA TSA TSA TSA
TOFA
TOFA
TOFA
TOFA
TOFA
TOFA
TOFA
TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA
TOFATOFATOFATOFA
TSA
TSA
TSA
TSA
TSA
TSA
TSA
TOFA
TSA
TSA
TSA
TSA TSATSATSATSATSATSATSA
TS
A
TS
A
TS
A
TS
A
TS
A
TSATSATSATSATSA TSATSATSATSA TSA
TS
A
TS
A
TS
A
TS
A
TS
A
TS
A
TS
A
TSA
TOFA
TOFA
TOFA
TOFA
TOFA
TO
FA
TO
FA
TO
FA
TO
FA
TO
FA
TS
A
TS
A
TS
A
TS
A
TS
A
TS
A
TO
FA
TO
FA
TO
FA
TO
FA
TO
FA
TO
FA
ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA
TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA
TSA TSA
TOFA TOFA
TSA
X
X
X
X
X
X
X
X
X
X
X
X
X X X X X X X X X
X X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X X
X X
X
X
X
X
X
X X X X X
XX
X
X
X
X
XX
X
X
X
TW
A
TW
A
TW
A
3 TW
A
TW
A
TA
XI
W
AY
D
TA
XI
W
AY
B
TAXIW
AY C
RUNW
AY 18
/36
RUNWAY 13/31
TAXIWAY A
PHASE 2
PHASE 3
PHASE 1 PHASE 2
PHASE 3
SHEET NAME:
SHEET NO:
DRAWN BY:
PROJECT NO:
DATE ISSUED:
DESIGNED BY:
CHECKED BY:
35 South 400 West St, Suite 200 St. George, UT 84770
435.673.4677
NU
MB
ER
DA
TE
DE
SC
RI
PT
IO
N
IS
SU
AN
CE
S
CH
ED
UL
E
IS
SU
ED
F
OR
B
ID
/04 /20
( IN FEET )
GRAPHIC SCALE
700350350
PROJECT SCHEDULE - 33 CALENDAR DAYS
SCHEDULE /
PHASE DURATION
PHASE 1 5 CALENDAR DAYS
PHASE 2 10 CALENDAR DAYS
PHASE 3 40 CALENDAR DAYS
302520151050 35 40 45 50 55
RUNWAY CLOSURE PROCEDURE FOR NIGHT WORK
THE FOLLOWING PROCEDURE HAS BEEN ESTABLISHED FOR PREPARING FOR A
NIGHT TIME RUNWAY CLOSURE AND FOR REOPENING THE RUNWAY THE NEXT
MORNING.
1. HOLIDAY/OPERATIONAL RESTRICTIONS.
A. RUNWAY NIGHT CLOSURES WILL NOT BE ALLOWED DURING THE
FOLLOWING PERIODS:
· JULY 4 TO JULY 5, 2026.
2. PREPARATION FOR NIGHT TIME CLOSURE.
A. CONTRACTOR TO NOTIFY THE ENGINEER THAT A NIGHT TIME CLOSURE
WILL BE REQUIRED WITH A MINIMUM NOTICE OF 24 HOURS.
B. CONTRACTOR SHALL TAKE WEATHER FORECASTS INTO CONSIDERATION
SO THAT ALL ANTICIPATED WORK CAN BE COMPLETED WITHIN THE
ALLOCATED CLOSURE TIMES.
C. ENGINEER SHALL COORDINATE WITH AIRPORT STAFF.
D. AIRPORT STAFF WILL ISSUE A NOTAM FOR THE RUNWAY CLOSURE.
E. NIGHT TIME CLOSURES ARE LIMITED TO BETWEEN 7:00 PM AND 5:00 AM.
F. MEET ONSITE 30 MINUTES PRIOR TO CLOSURE TO DISCUSS NIGHT WORK
AND PREPARE FOR MOBILIZATION.
3. ACCESS TO CLOSED RUNWAY.
A. NO PERSONNEL, EQUIPMENT, OR MATERIAL WILL BE ALLOWED ON THE
RUNWAY OR IN THE SAFETY AREA PRIOR TO 6:30 PM.
B. AIRPORT STAFF WILL NOTIFY THE ENGINEER THAT THE LAST FLIGHT HAS
LANDED, THE RUNWAY IS CLEAR, AND THE NOTAM CLOSURE IS IN PLACE.
C. ENGINEER WILL NOTIFY THE CONTRACTOR, WHO WILL PLACE THE LIGHTED
X'S OVER THE RUNWAY NUMBERS ON BOTH ENDS.
D. THE RUNWAY LIGHTS SHALL BE DEACTIVATED DURING THE CLOSURE
PERIOD.
E. THE CONTRACTOR WILL HAVE ACCESS TO THE ENTIRE RUNWAY AND
SAFETY AREA DURING THE CLOSURE PERIOD.
4. REOPENING A CLOSED RUNWAY.
A. CONTRACTOR SHALL BE RESPONSIBLE FOR INSPECTING THE ENTIRE
RUNWAY AND TAXIWAY SYSTEM TO ENSURE THAT FOD IS CLEANED UP.
B. THE SAFETY AREA MUST BE GRADED TO MEET ALL SAFETY CRITERIA.
C. ALL SURFACE MARKINGS SHALL BE COMPLETED PRIOR TO OPENING TO
AIRFIELD TRAFFIC.
D. INSTALL TAPERS, IF NECESSARY, AT DROPS IN PAVEMENT.
E. REACTIVATE THE RUNWAY LIGHTS.
F. CONTRACTOR TO REMOVE LIGHTED X'S PRIOR TO 4:30 AM.
G. ALL PERSONNEL, EQUIPMENT, OR MATERIAL SHALL BE CLEAR OF THE
RUNWAY AND THE SAFETY AREA PRIOR TO 4:30 AM.
H. CONTRACTOR SHALL NOTIFY ENGINEER WHEN THEY ARE CLEAR OF THE
RUNWAY PRIOR TO 4:30 AM.
I. THE ENGINEER SHALL NOTIFY THE AIRPORT STAFF THAT THE RUNWAY IS
CLEAR.
J. AIRPORT STAFF WILL INSPECT THE AIRFIELD PAVEMENT AND SAFETY
AREA STARTING AT 4:30 AM.
K. THE CONTRACTOR SHALL BE PRESENT DURING THE INSPECTION AND
SHALL IMMEDIATELY REMEDY ANY SAFETY CONCERNS THAT AIRPORT
STAFF IDENTIFIES.
L. AIRPORT STAFF WILL CALL THE RUNWAY CLEAR FOR AIRFIELD TRAFFIC.
RUNWAY SAFETY AREA
TAXIWAY SAFETY AREA
RUNWAY OBJECT FREE AREA
TAXIWAY OBJECT FREE AREA
RUNWAY PROTECTION ZONE
CONTRACTOR GATE ACCESS
RSA RSA
CONTRACTOR HAUL ROUTE
(2 WAY TRAFFIC)
TSA TSA
RPZ RPZ
TOFA TOFA
ROFA ROFA
NAVAID CRITICAL AREA
AOA FENCEX X
PHASING LEGEND
PHASE 1
PHASE 2
PHASE 3
RUNWAY CLOSURE MARKER
TAXIWAY CLOSURE MARKER
FLASHER BARRICADE
LIFE & SAFETY ROUTE
AIRCRAFT ROUTE
CONTRACTOR
STAGING AREA
CONTRACTOR
STAGING AREA
CONTRACTOR
ACCESS
CONTRACTOR
ACCESS
CONTRACTOR
ACCESS
La yo ut T ab N am e:
G
W :\A cq ui si tio ns \J
VI
\p ro je ct s\
PV
U
\A
IP
X X
- 2
R un w ay
Li gh tin g\
F- C
AD
\P
LA
N
S\
0-
PV
U -X
X- G
6-
C
PL
N .d w g
Pl ot te d
By :N od ic h, A le x
Pl ot te d:
Ju ne
, 2
6, :0
8:
P M
La st
S av ed B y:
Al ex .N od ic h, /4 /2
4:
:0
PM
B.A.H.
C.L.G.
AIP-069
G006
CONSTRUCTION
SAFETY AND PHASING
PLAN - OVERALL
PR
OV
O, U
TA
H
R
UN
W
AY
LI
GH
TI
NG
P
RO
JE
CT
AI
P
NO
. 3
-4 9-
-0
-2
PR
OV
O
AI
RP
OR
T
B.A.H.
6/04/2026
SAFETY & OBJECT FREE AREAS
RUNWAY 13/31
RUNWAY SAFETY AREA (RSA) 250' FROM RW CENTERLINE
RUNWAY EXTENDED SAFETY AREA (RSA) 1000' FROM RW END
RUNWAY OBJECT FREE AREA (ROFA) 400' FROM RW CENTERLINE
RUNWAY OBJECT FREE ZONE (ROFZ) 200' FROM RW CENTERLINE
RUNWAY 18/36
RUNWAY SAFETY AREA (RSA) 75' FROM RW CENTERLINE
RUNWAY EXTENDED SAFETY AREA (RSA) 300' FROM RW END
RUNWAY OBJECT FREE AREA (ROFA) 250' FROM RW CENTERLINE
RUNWAY OBJECT FREE ZONE (ROFZ) 200' FROM RW CENTERLINE
TAXIWAY A
TAXIWAY SAFETY AREA (TSA) 59' FROM TW CENTERLINE
TAXIWAY OBJECT FREE AREA (TOFA) 93' FROM TW CENTERLINE
TAXIWAY B
TAXIWAY SAFETY AREA (TSA) 59' FROM TW CENTERLINE
TAXIWAY OBJECT FREE AREA (TOFA) 93' FROM TW CENTERLINE
TAXIWAY C
TAXIWAY SAFETY AREA (TSA) 59' FROM TW CENTERLINE
TAXIWAY OBJECT FREE AREA (TOFA) 93' FROM TW CENTERLINE
TAXIWAY D
TAXIWAY SAFETY AREA (TSA) 59' FROM TW CENTERLINE
TAXIWAY OBJECT FREE AREA (TOFA) 93' FROM TW CENTERLINE
SHEET NAME:
SHEET NO:
DRAWN BY:
PROJECT NO:
DATE ISSUED:
DESIGNED BY:
CHECKED BY:
35 South 400 West St, Suite 200 St. George, UT 84770
435.673.4677
NU
MB
ER
DA
TE
DE
SC
RI
PT
IO
N
IS
SU
AN
CE
S
CH
ED
UL
E
IS
SU
ED
F
OR
B
ID
/04 /20
1. COORDINATION
ALL COORDINATION WILL TAKE PLACE THROUGH THE RESIDENT
ENGINEER AND PROVO AIRPORT (PVU) DEVELOPMENT MANAGER &
OPERATIONS MANAGER. NO CLOSURES WITHIN THE MOVEMENT AREAS
WILL BE PERMITTED WITHOUT A NOTAM IN PLACE FOR EACH SPECIFIC
CLOSURE. PRIOR TO COMMENCEMENT OF ANY WORK, THE
CONTRACTOR SHALL GIVE 72 HOURS ADVANCE NOTICE TO THE
RESIDENT ENGINEER AND AIRPORT OPERATIONS FOR FILING OF ALL
NOTAMS.
A WEEKLY CONSTRUCTION PROGRESS MEETING WILL BE REQUIRED TO
DISCUSS ALL OPERATIONAL SAFETY TOPICS THAT HAVE BEEN
AFFECTED OR WILL BE AFFECTED IN THE NEAR FUTURE. IN
ATTENDANCE WILL BE THE CONTRACTOR, RESIDENT ENGINEER, AND
PVU PERSONNEL.
ANY CHANGES TO SCOPE OR SCHEDULE MUST BE NOTIFIED TO THE
RESIDENT ENGINEER AND PVU DEVELOPMENT AND OPERATIONS
MANAGERS. ALL PARTIES WILL EVALUATE THE IMPACT OF THE CHANGE
AND WILL DETERMINE THE MEASURES NEEDED TO MAINTAIN A SAFE
CONSTRUCTION SITE.
THE FAA AIR TRAFFIC OPERATORS WILL BE NOTIFIED IMMEDIATELY IF
ANY CHANGES AFFECT AIRCRAFT MOVEMENT. ALL COMMUNICATIONS
WITH THE FAA TOWER WILL BY HANDLED BY AIRPORT OPERATIONS.
AIRPORT RUNWAYS AND TAXIWAYS SHOULD REMAIN IN USE BY
AIRCRAFT TO THE MAXIMUM EXTENT POSSIBLE.
AIRCRAFT USE OF AREAS NEAR THE CONTRACTOR'S WORK SHOULD BE
CONTROLLED TO MINIMIZE DISTURBANCE TO THE CONTRACTOR'S
OPERATION.
CONSTRUCTION THAT IS WITHIN THE SAFETY AREA AND OBJECT FREE
ZONE OF AN ACTIVE RUNWAY, TAXIWAY, OR APRON MUST BE
PERFORMED WHEN THE RUNWAY, TAXIWAY, OR APRON IS CLOSED OR
USE-RESTRICTED AND INITIATED ONLY WITH PRIOR PERMISSION FROM
THE AIRPORT OPERATOR AND WITH PROPER NOTAMS IN PLACE.
THE CONTRACTING OFFICER, AIRPORT OPERATOR, OR OTHER
DESIGNATED AIRPORT REPRESENTATIVE MAY ORDER THE
CONTRACTOR TO SUSPEND OPERATIONS; MOVE PERSONNEL,
EQUIPMENT, AND MATERIALS TO A SAFE LOCATION; BARRICADE ANY
OPEN TRENCHES AND STAND BY UNTIL AIRCRAFT USE IS COMPLETED.
2. PHASING
THIS PROJECT CONSISTS OF THREE PHASES. SEE CONSTRUCTION
SAFETY DRAWINGS FOR PHASING REQUIREMENTS.
CONTRACTOR TO NOTIFY RESIDENT ENGINEER AND PVU
DEVELOPMENT MANAGER & OPERATIONS MANAGER IF A CHANGE IN
SCHEDULE IS NEEDED.
3. AREAS AND OPERATIONS AFFECTED BY
CONSTRUCTION ACTIVITY
ALL WORK WITHIN AIRPORT OPERATIONS AREA (AOA) SHALL CONFORM
TO ADVISORY CIRCULAR 150/5370-2G, OPERATIONAL SAFETY ON
AIRPORTS DURING CONSTRUCTION.
CONTRACTOR SHALL ADHERE TO REQUIREMENTS AS MENTIONED ON
THIS SHEET, THE CONSTRUCTION SAFETY AND PHASING PLAN (CSPP),
AND CONSTRUCTION SAFETY DRAWINGS. THESE REQUIREMENTS
INCLUDE, BUT ARE NOT LIMITED TO, LIFE & SAFETY ACCESS ROUTES,
AIRCRAFT ROUTES, PEDESTRIAN ROUTES, CONSTRUCTION ACCESS
ROUTES, CONSTRUCTION LIMITS, AND BARRICADE LOCATIONS.
4. PROTECTION OF NAVIGATION AIDS (NAVAIDS)
NAVIGATIONAL AIDS INCLUDE INSTRUMENT LANDING SYSTEM
COMPONENTS.
DURING CONSTRUCTION, NO NAVAID EQUIPMENT WILL BE RELOCATED.
THE CONTRACTOR WILL BE RESPONSIBLE FOR ANY DAMAGE TO THE
EXISTING NAVAIDS AND WILL BE REPAIRED BY THE CONTRACTOR AT NO
COST TO THE AIRPORT.
5. CONTRACTOR ACCESS
CONTRACTOR HAS ACCESS TO THREE (3) GATE TO ENTER THE
AIRPORT. SEE CONSTRUCTION SAFETY DRAWINGS FOR GATE
LOCATION. CONTRACTOR SHALL PROVIDE A GATE GUARD AT THIS GATE
AT ALL TIMES WHEN GATE IS NOT CLOSED AND LOCKED.
CONTRACTOR MOVEMENT SHALL BE RESTRICTED TO THE
PRE-DETERMINED ACCESS ROUTES AS SHOWN ON THE PHASING
SHEETS.
ALL VEHICLES AND EQUIPMENT OPERATING IN THE AOA MUST HAVE
FLAG (DAY ONLY) OR BEACON (DAY AND NIGHT) ATTACHED TO THE
VEHICLE.
6. WILDLIFE MANAGEMENT
CONTRACTOR SHALL ADHERE TO ALL WILDLIFE MANAGEMENT
PRACTICES AS STATED IN ADVISORY CIRCULAR 150/5200-33C,
HAZARDOUS WILDLIFE ATTRACTIONS ON OR NEAR AIRPORTS, AND
CERTALERT 98-08, GRASSES ATTRACTIVE TO HAZARDOUS WILDLIFE.
CONTRACTOR IS RESPONSIBLE FOR COMPLETING A DAILY INSPECTION
FOR TRASH, FOREIGN OBJECTS, AND STANDING WATER ON THE
CONSTRUCTION SITE THAT MIGHT ATTRACT WILDLIFE.
CONTRACTOR SHALL MAINTAIN ALL FENCES AND GATES THROUGHOUT
THE PROJECT TO THE SATISFACTION OF THE RESIDENT ENGINEER.
CONTRACTOR SHALL NOTIFY THE RESIDENT ENGINEER WHEN A
WILDLIFE SIGHTING HAS OCCURRED ON THE PROJECT SITE.
7. FOREIGN OBJECT DEBRIS (FOD) MANAGEMENT
CONTRACTOR SHALL KEEP ALL PAVEMENTS IN THE AOA INCLUDING
APRONS, TAXIWAYS, AND RUNWAYS FREE FROM FOD AT ALL TIMES TO
PREVENT ANY DEBRIS FROM BEING INGESTED INTO AN AIRCRAFT'S
ENGINE OR ANY DEBRIS FROM BEING LAUNCHED DUE TO JET BLAST.
CONTRACTOR IS REQUIRED TO CONTINUOUSLY MONITOR AND
MAINTAIN FOD TO THE SATISFACTION OF THE RESIDENT ENGINEER.
PRIOR TO OPENING ANY PAVEMENT TO AIRCRAFT, THE CONTRACTOR,
RESIDENT ENGINEER, AND AIRPORT OPERATIONS SHALL CONDUCT A
SWEEP OF THE PAVEMENT TO VERIFY THAT THE PAVEMENT IS FREE
FROM FOD.
THE CONTRACTOR IS ADVISED THAT DUST CONTROL, CLEANUP OF
ACTIVE PAVEMENTS, TRACKING DEBRIS ONTO ACTIVE PAVEMENT AND
GENERAL JOBSITE CLEANLINESS IS A SERIOUS SAFETY CONCERN.
FOREIGN OBJECT DEBRIS (FOD) IS CONSIDERED AS ANY ITEM THAT
COULD POSSIBLY IMPACT THE OPERATIONS OF AN AIRPORT OR
ROADWAY. FOD COULD CAUSE INJURY OR DEATH THROUGH INGESTION
IN MOVING AIRCRAFT ENGINES. SPECIFIC ITEMS OF CONCERN INCLUDE,
BUT ARE NOT LIMITED TO; ANY PACKAGING FROM MATERIAL
INSTALLATION, GRAVEL LEFT ON ACTIVE PAVEMENTS, DUST TRACKED
ONTO ACTIVE PAVEMENTS, HAND TOOLS, HARDWARE DROPPED, ETC.
8. HAZARDOUS MATERIAL (HAZMAT) MANAGEMENT
CONTRACTOR SHALL NOTIFY RESIDENT ENGINEER AND AIRPORT
EMERGENCY PERSONNEL IF HAZARDOUS MATERIALS ARE
ENCOUNTERED ON THIS PROJECT.
10. INSPECTION REQUIREMENTS
CONTRACTOR SHALL COMPLETE A DAILY INSPECTION FOR SAFETY ON
THE PROJECT SITE BY COMPLETING THE CHECKLIST PROVIDED IN
ADVISORY CIRCULAR 150/5370-2G, APPENDIX D, CONSTRUCTION
PROJECT DAILY SAFETY INSPECTION CHECKLIST.
THE CONTRACTOR, RESIDENT ENGINEER AND AIRPORT OPERATOR
MUST PERFORM ONSITE INSPECTIONS THROUGHOUT THE PROJECT,
WITH IMMEDIATE REMEDY OF ANY DEFICIENCIES, WHETHER CAUSED
BY NEGLIGENCE, OVERSIGHT, OR SCOPE CHANGE.
CONTRACTOR SHALL COMPLETE A FINAL INSPECTION FOR SAFETY ON
THE PROJECT SITE AT THE END OF EACH PHASE.
11. APPROACH CLEARANCE TO RUNWAYS
RUNWAY THRESHOLDS MUST PROVIDE AN UNOBSTRUCTED APPROACH
SURFACE OVER EQUIPMENT AND MATERIALS. (REFER TO CHAPTER 3 IN
ADVISORY CIRCULAR 150/5300-13B, AIRPORT DESIGN, FOR GUIDANCE.
12. RUNWAY AND TAXIWAY VISUAL AIDS
FLASHER BARRICADES, CLOSED 'X' MARKINGS AND RUNWAY CLOSURE
MARKERS (RCMS) ARE TO BE PLACED AS DETAILED IN THE PLANS AND
IN ALL DESIGNATED AREAS AS SHOWN ON THE CONSTRUCTION SAFETY
DRAWINGS.
APPROVED FLASHER BARRICADES SHALL BE PROVIDED AND
MAINTAINED BY THE CONTRACTOR.
CLOSED 'X' MARKINGS SHALL BE PROVIDED BY THE CONTRACTOR AND
MAINTAINED BY THE CONTRACTOR. (RCMS) SHALL BE PROVIDED BY
THE AIRPORT AND MAINTAINED BY THE CONTRACTOR.
CONTRACTOR TO COVER ALL TAXIWAY EDGE LIGHTS, TAXIWAY SIGNS,
RUNWAY SIGNS, AND APRON EDGE LIGHTS FOR AREAS CLOSED BY
NOTAM TO THE APPROVAL OF THE RESIDENT ENGINEER.
13. MARKING AND SIGNS FOR ACCESS ROUTES
ALL REQUIRED SIGNS AND MARKINGS SHALL CONFORM TO ADVISORY
CIRCULAR 150/5340-18H, STANDARD FOR AIRPORT SIGN SYSTEMS, OR
THE FEDERAL HIGHWAY ADMINISTRATION MANUAL ON UNIFORM
TRAFFIC CONTROL DEVICES (MUTCD).
ALL SIGNS ADJACENT TO AREAS USED BY AIRCRAFT MUST COMPLY
WITH THE FRANGIBLE REQUIREMENTS AS STATED IN ADVISORY
CIRCULAR 150/5220-23A, FRANGIBLE CONNECTIONS.
14. HAZARD MARKINGS AND LIGHTING
PRIOR TO CLOSING ANY AREAS IN THE AOA TO AIRCRAFT OR
EMERGENCY TRAFFIC, CONTRACTOR MUST CLEARLY DEFINE CLOSED
AREAS WITH WARNING LIGHTS, BARRICADES, CLOSED 'X' MARKINGS,
RCMS, AND FLAGS TO THE APPROVAL OF THE RESIDENT ENGINEER.
CONTRACTOR TO REFER TO CONSTRUCTION SAFETY DRAWINGS.
HAZARDOUS AREAS ON THE MOVEMENT AREA WILL BE MARKED WITH
FLASHER BARRICADES. THESE BARRICADES RESTRICT ACCESS AND
MAKE HAZARDS OBVIOUS TO AIRCRAFT, PERSONNEL, AND VEHICLES.
DURING PERIODS OF LOW VISIBILITY AND AT NIGHT, IDENTIFY
HAZARDOUS AREAS WITH RED FLASHING LIGHTS.
OPEN TRENCHES AND EXCAVATIONS MUST BE PROMINENTLY MARKED
WITH RED OR ORANGE FLAGS AND LIGHTS AS APPROVED BY THE
RESIDENT ENGINEER.
15. PROTECTION OF RUNWAY AND TAXIWAY AREAS
SAFETY AREAS - CONTRACTOR SHALL NOT IMPEDE ON THE SAFETY
AREAS WITHOUT A CLOSURE OF THE RUNWAY/TAXIWAY BY MEANS OF
A NOTAM.
OBJECT FREE AREAS - CONTRACTOR SHALL NOT PLACE EQUIPMENT,
MATERIAL, OR STOCKPILES IN THIS AREA. ALL OBJECTS OR MATERIALS
ADJACENT TO THIS AREA SHALL BE PROPERLY MARKED/LIT PER
ADVISORY CIRCULAR 150/5370-2G. CONTRACTOR CANNOT WORK IN
ACTIVE TAXIWAY OBJECT FREE AREA WITHOUT WING WALKERS TO
MAINTAIN A 5' CLEARANCE FROM THE WINGSPAN OF THE AIRCRAFT TO
CONSTRUCTION EQUIPMENT OR MATERIAL.
OBSTACLE FREE ZONE- CONTRACTOR TO PREVENT PERSONNEL,
MATERIAL, AND/OR EQUIPMENT FROM PENETRATING THE OBSTACLE
FREE ZONE AS DEFINED IN ADVISORY CIRCULAR 150/5300-13B.
16. AIRPORT SECURITY
CONTRACTOR SHALL ADHERE TO AIRPORT SECURITY REQUIREMENTS
AT ALL TIMES. SECURITY IDENTIFICATION BADGES AND RELATED
AIRPORT FAMILIARIZATION REQUIREMENTS ARE MANDATORY. KEY
CONSTRUCTION SUPERINTENDENTS AND ANY OTHER PERSONNEL
DEEMED NECESSARY BY THE AIRPORT SHALL BE REQUIRED TO BE
BADGED BY THE AIRPORT, COMPLETE A SECURITY CLASS AND AN
AIRPORT DRIVING CLASS AT THE EXPENSE OF THE CONTRACTOR
PRIOR TO CONSTRUCTION. UNBADGED CONSTRUCTION PERSONNEL
SHALL BE ESCORTED AT ALL TIMES DURING AIRSIDE CONSTRUCTION.
18. DUST CONTROL
CONTRACTOR IS RESPONSIBLE FOR CONTROLLING DUST FROM THE
CONSTRUCTION SITE AT ALL TIMES. CONTRACTOR SHALL HAVE A
WATER TRUCK AND OPERATOR AVAILABLE 24 HOURS A DAY TO
CONTROL DUST. THE PROJECT'S LOCATION IS NEAR ACTIVE RUNWAYS
AND HIGHWAYS AND IS IN A LOCATION THAT EXPERIENCES HIGH WIND.
IT IS CRITICAL FOR THE CONTRACTOR TO KEEP DUST TO AN ABSOLUTE
MINIMUM BOTH DURING CONSTRUCTION, AND AFTER CONSTRUCTION
UNTIL THE EXPOSED SURFACES CONTAIN SUSTAINABLE VEGETATION.
CONTRACTOR SHALL PROVIDE THE RESIDENT ENGINEER AND AIRPORT
OPERATIONS WITH A CONTACT FOR 24 HOUR DUST CONTROL.
17. OTHER LIMITATIONS ON CONSTRUCTION
PROHIBITING OPEN-FLAME WELDING OR TORCH CUTTING
OPERATIONS UNLESS ADEQUATE FIRE SAFETY PRECAUTIONS ARE
PROVIDED AND THESE OPERATIONS HAVE BEEN AUTHORIZED BY THE
AIRPORT OPERATOR (AS TAILORED TO CONFORM TO LOCAL
REQUIREMENTS AND RESTRICTIONS).
PROMINENTLY MARKING OPEN TRENCHES, EXCAVATIONS, AND
STOCKPILED MATERIALS AT THE CONSTRUCTION AND LIGHTING
THESE OBSTACLES DURING HOURS OF RESTRICTED VISIBILITY AND
DARKNESS.
MARKING AND LIGHTING CLOSED, DECEPTIVE, AND HAZARDOUS
AREAS ON AIRPORTS, AS APPROPRIATE. CONSTRAINING STOCKPILED
MATERIAL TO PREVENT ITS MOVEMENT AS A RESULT OF THE
MAXIMUM ANTICIPATED AIRCRAFT BLAST AND FORECAST WIND
CONDITIONS.
NO USE OF TALL EQUIPMENTS (CRANES, CONCRETE PUMPS, AND SO
ON) UNLESS A FAA 7460-1 DETERMINATION LETTER IS ISSUED FOR
SUCH EQUIPMENT.
NO USE OF ELECTRICAL BLASTING CAPS ON OR WITHIN 1,000' OF THE
AIRPORT PROPERTY.
NO USE OF FLARE POTS WITHIN THE AOA.
BEFORE BEGINNING ANY CONSTRUCTION ACTIVITY, THE CONTRACTOR
MUST, THROUGH THE RESIDENT ENGINEER AND AIRPORT OPERATIONS,
GIVE NOTICE USING THE NOTICE TO AIRMEN (NOTAM) SYSTEM OF
PROPOSED LOCATION, TIME, AND DATE OF COMMENCEMENT OF
CONSTRUCTION. THE NOTAM SHOULD STATE THAT "PERSONNEL AND
EQUIPMENT ARE WORKING ADJACENT TO RUNWAY 13/31 AND
ASSOCIATED TAXIWAY CONNECTORS." ALL NOTAMS SHALL BE ISSUED
BY PVU . UPON COMPLETION OF WORK AND RETURN OF ALL SUCH
AREAS TO STANDARD CONDITIONS, THE CONTRACTOR MUST
COORDINATE WITH THE RESIDENT ENGINEER AND VERIFY THE
CANCELLATION OF ALL NOTICES ISSUED VIA THE NOTAM SYSTEM.
THROUGHOUT THE PROJECT DURATION , THE CONTRACTOR MUST:
A. BE AWARE OF AND UNDERSTAND THE SAFETY PROBLEMS AND
HAZARDS DESCRIBED IN ADVISORY CIRCULAR 150/5370-2G,
OPERATIONAL SAFETY ON AIRPORTS DURING CONSTRUCTION.
B. CONDUCT ACTIVITIES SO AS NOT TO VIOLATE ANY SAFETY
STANDARDS CONTAINED IN ADVISORY CIRCULAR 150/5370-2G OR
ANY OF THE REFERENCES THEREIN.
C. INSPECT ALL CONSTRUCTION AND STORAGE AREAS AS OFTEN AS
NECESSARY TO BE AWARE OF CONDITIONS.
D. PROMPTLY TAKE ALL ACTIONS NECESSARY TO PREVENT OR
REMEDY ANY UNSAFE OR POTENTIALLY UNSAFE CONDITIONS AS
SOON AS THEY ARE DISCOVERED.
E. THE CONTRACTOR SHALL ADHERE TO THE REQUIREMENTS,
PROVISIONS, AND PROCEDURES OUTLINED IN CONSTRUCTION
SAFETY PHASING PLAN (SEE DIV. 6 OF THE CONTRACT DOCUMENTS).
ANY CHANGES TO SCOPE OR SCHEDULE MUST BE NOTIFIED TO THE
RESIDENT ENGINEER AND PVU OPERATIONS AND DEVELOPMENT
MANAGER SO THAT NOTAMS CAN BE ISSUED, MAINTAINED, AND
CANCELED.
IN AN EVENT OF AN EMERGENCY, CONTRACTOR SHALL NOTIFY THE
RESIDENT ENGINEER, PVU OPERATIONS MANAGER, AND AIRPORT
EMERGENCY.
9. NOTIFICATION OF CONSTRUCTION ACTIVITIES
5. CONTRACTOR ACCESS (CONTINUED)
ALL VEHICLES WITHOUT PRIOR APPROVAL FROM AIRPORT THAT MUST
TRAVEL IN THE AOA WILL BE ESCORTED BY THE CONTRACTOR. THOSE
VEHICLES ARE REQUIRED TO ADHERE TO ALL RULES AND
REGULATIONS AS SET BY THE PROVO AIRPORT AND ADVISORY
CIRCULAR 150/5370-2G, OPERATIONAL SAFETY ON AIRPORTS DURING
CONSTRUCTION. IDENTIFICATION AND FLAGS/BEACONS MUST BE
ATTACHED TO THE VEHICLE AS STATED IN THE PREVIOUS NOTE.
THE AIRPORT OR ENGINEER WILL CONTACT PVU TOWER WHEN
PERMISSION TO ENTER THE AOA IS REQUIRED.
PROVO GROUND - 119.40 MHZ
HOURS: (JUN.-OCT. 6AM-10PM)(NOV.-MAY 6AM-9PM)
PROVO TOWER - 125.30 MHZ
CONTRACTOR IS REQUIRED TO NOTIFY THE PROJECT ENGINEER PRIOR
TO ENTERING ANY ACTIVE SAFETY AREAS OR OBJECT FREE AREAS.
CONTRACTOR, SUBCONTRACTOR, AND SUPPLIER EMPLOYEES OR ANY
UNAUTHORIZED PERSONS MUST BE RESTRICTED FROM ENTERING AN
AIRPORT AREA THAT WOULD BE HAZARDOUS.
AGENCY NAME AGENCY TYPE TELEPHONE
AIRPORT ADMINISTRATION
AIRPORT
ADMINISTRATION (801) 852-6715
PROVO CITY POLICE DEPARTMENT POLICE DEPARTMENT
(801) 852-6211
OR 911
PROVO CITY FIRE DEPARTMENT FIRE DEPARTMENT
(801) 852-6300
OR 911
BLUE STAKES OF UTAH UTILITY LOCATE (800) 662-4111
9. NOTIFICATION OF CONSTRUCTION ACTIVITIES
(CONTINUED)
La yo ut T ab N am e:
G
W :\A cq ui si tio ns \J
VI
\p ro je ct s\
PV
U
\A
IP
X X
- 2
R un w ay
Li gh tin g\
F- C
AD
\P
LA
N
S\
0-
PV
U -X
X- G
6-
C
PL
N .d w g
Pl ot te d
By :N od ic h, A le x
Pl ot te d:
Ju ne
, 2
6, :0
8:
P M
La st
S av ed B y:
Al ex .N od ic h, /4 /2
4:
:0
PM
B.A.H.
C.L.G.
AIP-069
G007
CONSTRUCTION
SAFETY NOTES
PR
OV
O, U
TA
H
R
UN
W
AY
LI
GH
TI
NG
P
RO
JE
CT
AI
P
NO
. 3
-4 9-
-0
-2
PR
OV
O
AI
RP
OR
T
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
RVZ(E)
TOFATOFATOFATOFATOFA
TO
FA
TO
FA
TO
FA
TO
FA
TOFA
TOFA
TOFA
RSA
RSA
RSA
RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA
RSA
RSA
RSA
RSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSA
RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSA
ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA
ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA
ROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFAROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
RSA
TSA TSA TSA TSA TSA TSA TSA TSA TSA
TOFA
TOFA
TOFA
TOFA
TOFA
TOFA
TOFA
TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA TOFA
TOFATOFATOFATOFA
TSA
TSA
TSA
TSA
TSA
TSA
TSA
TOFA
TSA
TSA
TSA
TSA TSATSATSATSATSATSATSA
TS
A
TS
A
TS
A
TS
A
TS
A
TSATSATSATSATSA TSATSATSATSA TSA
TS
A
TS
A
TSA
TOFA
TOFA
TOFA
TOFA
TOFA
TO
FA
TO
FA
TS
A
TS
A
TO
FA
ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA
TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA
TSA TSA
TOFA TOFA
TSA
X
X
X
X
X
X
XX
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X X X X X X X X X X
X X
X
X
X
X X X X
X
X
X
X
X
XX
X
X
X
TW
A
TW
A
TW
A
3 TW
A
TW
A
TA
XI
W
AY
B
TAXIW
AY C
RUNWAY 13/31
TAXIWAY A
TW
A
TW
A
TW
A
TW
A
TA
XIW
AY B
TAXIW
AY C
RUNW
AY 18/36
RUNWAY 13/31 RW 31RW 13
TW
A
TAXIWAY A
PHASE 1
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
ROFA
X
X
X
X
TA
XI
W
AY
D
RUNW
AY 18/36
SHEET NAME:
SHEET NO:
DRAWN BY:
PROJECT NO:
DATE ISSUED:
DESIGNED BY:
CHECKED BY:
35 South 400 West St, Suite 200 St. George, UT 84770
435.673.4677
NU
MB
ER
DA
TE
DE
SC
RI
PT
IO
N
IS
SU
AN
CE
S
CH
ED
UL
E
IS
SU
ED
F
OR
B
ID
/04 /20
CONSTRUCTION PHASING NOTES
NOTESPHASE 1 MAJOR WORK TO BE COMPLETED
DURATION
5 CALENDAR DAYS
CONTRACTOR ACCESS TIMES
NIGHTTIME ACCESS TO RUNWAY SAFETY AREA
24 HOUR ACCESS TO APPROVED WORK AREAS
ALL AIRPORT OPERATIONS AREAS SHALL REMAIN OPEN AND
UNAFFECTED DURING THIS PHASE WITH THE FOLLOWING
EXCEPTIONS:
· RUNWAY 13/31 AND RUNWAY 18/36 WILL BE CLOSED AT
NIGHT DURING THE…