Summary of Pre-Bid Meeting Agenda and Notes
This document is a pre-bid meeting agenda and notes from October 13, 2026, for the Ashland Creek Water Treatment Plant project hosted by the City of Ashland, Oregon. The project encompasses construction of a new drinking water treatment plant at the existing treatment plant site, including raw water conveyance, pressure reduction, chemical pretreatment, filtration, filtered water storage and pumping, chemical storage and metering, water and sewer lines, and facility commissioning. The base bid includes construction of a new water treatment plant and bypass pipeline, while Alternate A includes a solar array and Alternate B includes a battery energy storage system. The mandatory pre-bid meeting was held on October 13, 2026, at the Community Development Building in Ashland. Bids are due November 5, 2026, at 1:00 p.m. to the City Engineering Office at either 20 East Main Street (mailing) or 51 Winburn Way (in-person delivery). City Council approval for award is scheduled for November 17, 2026, with Notice to Proceed to be issued in Spring 2027. Substantial Completion is required 1,005 calendar days after NTP, with Final Completion at 1,095 calendar days. Project work hours are restricted to 6:00 a.m. to 6:00 p.m., Monday through Friday, with construction activity restricted during Jackson County Fire Season (May 15 to mid-September/mid-October). A site tour to the new water plant site was conducted immediately following the pre-bid meeting.
Contractor prequalification using the City of Ashland Contractor Prequalification Application 2025-27 is required, with applications due by November 1, 2026 (five days prior to bid opening). The City will also accept prequalification applications from the City of Medford and Oregon Department of Transportation. All contractors and subcontractors must hold current Oregon Construction Contractors Board licenses. Bid security, lists of proposed subcontractors and suppliers, First-Tier Subcontractor Disclosure Forms, evidence of authority to do business in Oregon, contractor's license numbers, and bidder qualification statements with supporting documentation must be submitted with bids. Late bids will not be accepted. No DBE or Good Faith Efforts requirements currently apply, though the City is pursuing State Revolving Funds that may impose such requirements. The project does not have set-asides. Questions must be submitted to Pierre Kwan (pierre.kwan@hdrinc.com) by October 26, 2026, at 5:00 p.m., with the final addendum issued by October 29, 2026. Addendum No. 1 was issued October 14, 2026, to address questions and provide the geotechnical report. The City will coordinate utility coordination for construction power (Ashland Electric), water (hydrant meter), secondary conductors, and construction notifications. The Contractor is responsible for constructing signage and managing material ordering during the extended award-to-NTP period, with the City supporting long lead-item procurement and payment for offsite-stored materials.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Bid Meeting Agenda Project: Ashland Creek Water Treatment Plant Owner: City of Ashland, OR
Subject: Pre-Bid Meeting Location: Community Development Building 51 Winburn Way, Ashland, OR 97520
Date: October 13, 2026 Notes by: Pierre Kwan
I. Introductions
A. Opening Statement: This meeting is intended to disseminate information to the potential bidders.
Statements made in this meeting and included in the distributed meeting minutes are not binding unless included in the bid documents and/or included in an addendum issued prior to the receipt of bids.
B. This meeting is mandatory for submitting bids.
C. Introduce the project team.
Owner’s Project Team
Position Name Phone Number
Email Address
Public Works Director Scott Fleury 541-488-5587 scott.fleury@ashland.or.us
Deputy Public Works Director
Chance Metcalf 541-488-5587 chance.metcalf@ashland.or.us
Water Treatment Plant Supervisor
Alistair Andre 541-488-5345 alistair.andre@ashland.or.us
Construction Management Team
Position Name Phone Number
Email Address
Project Manager Kevin Christiansen 503-995-2736 Kevin.Christiansen@hdrinc.com
Construction Manager
TBD TBD TBD
Design Team
Position Name Phone Number
Email Address
Project Manager Pierre Kwan 206-826-4735 pierre.kwan@hdrinc.com
Design Manager Gabriel Alvarado 505-830-5449 gabriel.alvarado@hdrinc.com
D. Introduction of prospective bidders in attendance – skipped due to the number of attendees.
II. Project Summary mailto:scott.fleury@ashland.or.us mailto:chance.metcalf@ashland.or.us mailto:alistair.andre@ashland.or.us mailto:Kevin.Christiansen@hdrinc.com mailto:pierre.kwan@hdrinc.com mailto:gabriel.alvarado@hdrinc.com
A. Project Goals
1. Base bid – Construction of a new water treatment plant and new pipeline at the existing water treatment plant that bypasses all of the treatment processes.
2. Alternate A – Construction of a new solar array at the new water treatment plant site
3. Alternate B – Construction of a new battery energy storage system at the new treatment plant site.
B. Site Plan
C. Project Milestones and the Schedule
1. Award
a. November 17, 2026 – Council approval
b. The NTP will be issued on Spring 2027. Time for bid review and permitting.
2. Time for Completion
a. The count of calendar days shall commence on the day following the Contractor’s receipt of the Notice to Proceed,
b. Substantial Completion shall be 1,005 calendar days after the first day.
c. Final Completion shall be 1,095 calendar days after the first day.
3. Review schedule constraints
a. Jackson County Fire Season: May 15 to mid-September to mid-October (weather dependent)
D. Review Project Constraints
1. Project hours – 6:00 AM to 6:00 PM, Monday to Friday.
2. Site access constraints
3. Permit constraints
4. Other constraints
E. Review Site Location and Constraints
F. Project Sequencing
1. All work associated with the new water plant must be completed and operational before the bypass piping at the existing plant site can be constructed.
III. Review Bid Requirements
A. Review the Bid Documents
1. Review documents that are distributed and where they can be obtained
a. Information and Bidding Documents for the Project can be obtained at the following designated website: https://oregonbuys.gov/bso/external/bidDetail.sda?docId=S-KA0010-00018090
2. Review distributed and proposed addendum
a. No addenda issued yet.
https://oregonbuys.gov/bso/external/bidDetail.sda?docId=S-KA0010-00018090
b. Addendum No. 1 to be issued on October 14, 2026. Addendum will address many of the questions already received and issue the geotechnical report.
B. Review Instructions to Bidders
1. Bid and award schedule.
a. Bids due on November 5, 2026 at 1:00 PM. Bid opening on the same day.
2. Review how and where bid will be received.
a. Bids due to City Engineering Office
i. Mailing address: 20 East Main Street, Ashland, OR 97520
ii. In-person delivery: 51 Winburn Way, Ashland, OR 97520
3. Review action to be taken for a late bid submission.
a. 00 21 13-14.03 – Bids received after the date and time prescribed for the opening of Bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened. Owner accepts no responsibility for delays in returning Bids submitted or delivered to the incorrect location.
4. Review what documents are required to be submitted prior to the bids.
a. City of Ashland Contractor Prequalification Application 2025-27.
b. Due five days prior to bid opening, November 1, 2026.
c. City will also accept the completed Contractor Prequalification Applications forms from the City of Medford and the Oregon Department of Transportation.
5. Review what documents are required to be submitted with the bids.
a. Per 00 41 13-Article 2
i. Required Bid security;
ii. List of Proposed Subcontractors;
iii. First-Tier Subcontractor Disclosure Form;
iv. List of Proposed Suppliers;
v. Proposed Major Equipment Form;
vi. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such authority within the time for acceptance of Bids;
vii. Contractor’s license number as evidence of Bidder’s State Contractor’s License or a covenant by Bidder to obtain said license within the time for acceptance of Bids;
viii. Required Bidder Qualification Statement with supporting data.
6. Review where questions should be submitted during the bid phase including the last day/date questions can be submitted.
a. Questions to Pierre Kwan at HDR, pierre.kwan@hdrinc.com
b. Last day to submit questions: Monday, October 26, 2026 at 5:00 PM
c. Last day to issue addendum: Thursday, October 29
C. Environmental Commitments
1. Review environmental requirements and constraints.
2. Review other permits and licenses necessary for the construction of the project shall be obtained by the Owner.
a. None
3. Review other permits and licenses necessary for the construction of the project shall be obtained by the Contractor.
a. See 01 41 24 for list of City of Ashland, Jackson County, and Oregon Department of Environmental Quality permits.
4. A Spill Prevention, Control, and Countermeasures plan is required.
5. Noise/Work Hours—Constraints/Variances: Review contract requirements.
6. Review hazardous and/or contaminated material disposal requirements and constraints.
a. None
IV. Questions
Q1: Will site CAD files be provided to bidders?
A1: No. CAD files will only be provided to the selected Contractor?
Q2: Who pulls the secondary conductors for the new plant?
A2: Ashland Electric will do this.
Q3: Is there water at the site?
A3: There is no water at the site currently. The nearest hydrant is at the road. The selected Contractor will get a hydrant meter from the City.
Q4: Is there power at the site?
A4: There is no power at the site currently. Ashland Electric will work with the selected Contractor to get a construction power drop upon mobilization.
Q5: Is there a sanitary sewer at the site?
A5: There is no sewer at the site currently and there will not be one until the plant is built.
Q6: Does the water tank have cathodic protection and a welded top?
A6: This question will be answered in an addendum.
Q7: Can the bid due date move?
A7: No. The City must keep to this date for various reasons.
Q8: Can City share the required paperwork for the Good Faith Efforts procedures?
A8: This project does not have DBE requirements and there are no Good Faith Effort requirements at this time. Note that the City is pursuing State Revolving Funds for this project. Any DBE and Good Faith Efforts requirements will be made known to the Contractor if the City receives this funding.
Q9: When will Contractor be selected?
A9: City will issue Notice of Intent to Award to the Contactor right after bid opening and prior to Council approval on November 17, 2026.
Q10: There is a long period between Award and NTP. How will Contractor be able to order long lead items during this time?
A10: City will work with the Contractor to order materials during this period.
Q11: How will payment for offsite stored materials be handled?
A11: City will work with the Contractor to measure quantities for payment.
Q12: There will be a lot of construction traffic on Granite Street. How will damage to it be handled?
A12: The City has a separate project to restore and repave the street. That project bids after this treatment plant project is finished. Pavement restoration due to normal heavy traffic is not in the Contractor's scope. The Contractor is responsible for any other damage, such as dropping equipment that causes a pothole.
Q13: How is site access maintained during winter snow events?
A13: The new water treatment plant site will rarely have snow that sticks around. The City already plows the road all the way to the turn off to the existing water treatment plant and can plow further to the job site. There can be heavy snow at the existing water plant and the Contractor will have to coordinate with City if the work at that site occurs during winter.
Q14: How is the cost of civil works for the solar panel alternate handled?
A14: The civil works is site preparation and grading, which is included as part of the Alternate A lump sum per 01 23 00-1.3-A.1.a.
Q15: Are there load restrictions over the new culvert?
A15: No.
Q16: Does the lump sum for the base bid include rock excavation?
A16: Yes.
Q17: There is a volume number for excavation in the drawings. What does the number cover?
A17: This question will be answered in an addendum.
Q18: Who is supplying construction signage?
A18: Contractor supplies signage.
Q19: Who conducts construction notifications?
A19: City will be doing the notifications. Such notifications have already started.
Q20: Can Contractor haul after hours?
A20: Not normally but City may approve hauling after hours on a temporary basis if requested.
Q21: Can the arborist plan be modified to remove additional trees that in the way of the line-of-sight radios?
A21: There is no arborist plan yet. The plan will be developed as part of the permitting process, which Public Works manages. The City will coordinate with the Contractor for identifying what additional trees need to be removed.
Q22: Will the City be open to alternative layouts for the solar panels?
A22: Yes. The selected Contractor can issue an RFI after award for the City’s and HDR’s consideration.
V. Site Tour
A. The site tour to the new water plant site is right after this pre-bid meeting.
B. Bidders interested in seeing the existing water plant are to contact Scott Fleury to make arrangements.
There is very limited parking at the site.