1b. 46 43 62 - BALLASTED FLOCCULATION SYSTEM.pdf
PDF 260 KB Posted
- Attached to
- Ashland Water Treatment Plant
- Solicitation number
- S-KA0010-00018090
- Issued by
- Jackson County, Amity City, Oregon
About this file
This is a specification document for a ballasted flocculation system component of the Ashland Creek Water Treatment Plant project in Ashland, Oregon. The specification establishes comprehensive requirements for the design, supply, installation, and performance of a ballasted flocculation system that will serve as the coagulation/clarification/sedimentation process for the new drinking water treatment facility. The system is designed for two process trains (one duty, one standby) with a peak design flow of 5,000 gallons per minute per train and minimum flow of 1,200 gallons per minute. Acceptable manufacturers include Veolia Actiflo Turbo and WesTech RapiSand, with the basis of design based on the Actiflo system; contractors selecting alternate systems are responsible for associated engineering and cost changes. The seller must provide all materials, equipment, controls, accessories, testing, and startup services with initial microsand supply of minimum 16.8 tons and 400 gallons of polymer for startup. Bids for the overall project are due November 5, 2026 at 1:00 p.m. Pacific Time, with a mandatory pre-bid conference scheduled for October 13, 2026 at 10:00 a.m.
The performance guarantee period extends for one year from documented substantial completion based on demonstration testing results, with specific turbidity performance requirements: effluent turbidity of 2.0 NTU or less when influent turbidity is 100 NTU or less, and effluent not exceeding 5 NTU at least 95 percent of the time when influent turbidity ranges from 101 to 2,000 NTU. The seller is responsible for all costs associated with equipment or operational modifications required to meet performance guarantees and related training implementation, while owner costs cover re-training during the testing period. All contractors and subcontractors must hold current Oregon Construction Contractors Board licenses in good standing, with prequalification required and valid through August 31, 2027. The specification includes detailed requirements for control systems using Rockwell Automation Allen-Bradley CompactLogix PLC hardware with PanelView Plus7 operator interface terminals, NEMA 4X stainless steel enclosures, and EtherNet/IP communication integration with the plant-wide SCADA system. Comprehensive submittals required include shop drawings, electrical schematics, panel layouts, wiring diagrams, performance data, and warranty documentation prior to concrete placement.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HDR Project No. 10193663 City of Ashland September 2026
City of Ashland Water Treatment Plant Issued for Bidding
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 1
SECTION 46 43 62
BALLASTED FLOCCULATION SYSTEM
PART 1 - GENERAL
1.1 SUMMARY
A. Seller shall supply all labor, materials, equipment, tank accessories, controls, appurtenances, testing, and startup services for the ballasted flocculation system complete and operable in accordance with the requirements specified herein. The Contractor is responsible for providing a complete installation of the equipment furnished by the Seller.
1. The Contractor is responsible for all material and labor related to concrete and grout work for the Ballasted Flocculation System as required by the system selected by the Contractor.
In addition, the Contractor shall furnish and install all additional equipment items, interconnecting piping, valves, fasteners, pipe supports, instruments, power and control wiring, and all other appurtenances required to provide a complete and operable system.
2. Contractor shall note that all ballasted flocculation systems may have differing requirements and the basis of design depicted on the drawings are based on a single Seller’s system.
Contractor shall obtain approved shop drawings prior to placing concrete and will be responsible for any and all changes in the design required due to the system the Contractor has selected to provide.
B. Ballasted Flocculation system Performance Guarantee and Equipment Warranty requirements.
C. Some equipment associated with the Ballasted Flocculation system to be furnished by others is identified in this Section.
D. Related Specifications include but are not necessarily limited to:
1. Division 00 - Procurement and Contracting Requirements.
2. Division 01 - General Requirements.
3. Division 40 – Process Interconnections.
4. Section 43 21 00 – Pumping Equipment – Basic Requirements.
5. Section 46 31 90 – GAC Filter Media.
1.2 QUALITY ASSURANCE
A. Reference Standards:
1. American National Standards Institute (ANSI).
2. American Society of Mechanical Engineers (ASME).
3. ASTM International (ASTM).
4. American Water Works Association (AWWA).
5. American Welding Society (AWS).
6. Institute of Electrical and Electronic Engineers (IEEE): 519, Recommended Practices and
Requirements for Harmonic Control in Electrical Power Systems.
7. Instrument Society of America (ISA).
8. National Electrical Code (NEC).
9. National Fire Protection Association CNFPA).
10. International Building Code, 2015 (IBC).
11. International Fire Code, 2018 (IFC).
12. NSF/ANSI 61-2017 - Drinking Water System Components
13. Where reference is made to one of the above standards, the revision in effect at the time of
Bid opening shall apply unless otherwise noted.
B. Ballasted Flocculation System:
1. Single Seller shall provide all materials, equipment, incidentals, and appurtenances and be responsible for designing, furnishing, coordination, proper sizing and performance of all systems components for a complete operating system.
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 2
a. The Seller shall also provide Special Services during the construction of the Project to include but not be limited to coordination with the Contractor, installation assistance, including written and verbal instructions, to the Contractor to assure proper installation, inspection of the completed installation, operator training (initially and any additional training specified), start-up assistance to the Contractor, commissioning, acceptance testing field services as specified, operation and maintenance manuals and any other services as specified further in these Documents.
2. It is the Seller’s responsibility to provide all parts, equipment, materials, and components required for a complete and functional system to the specified limits. If the Seller’s system must control a piece of equipment to ensure proper operation of the system and it is not included in the Seller’s scope of supply, it shall become the Contractors responsibility to provide at no additional cost to the Owner.
3. The Seller shall be responsible for the design, supply, and installation of all wiring, including power, control, and signal, and conduit for all equipment preassembled on a common skid.
4. The Contractor shall be responsible for the supply and installation of all wiring, including power, control and signal, and conduit for all equipment not preassembled on a skid or supplied by the Seller. The Contractor will also be responsible to furnish and install all interconnecting control, signal and power cabling between the Seller supplied skids and the others.
5. The Contractor shall be responsible to furnish and install all interconnecting control, signal and power cabling to integrate the System into the Owner’s plant wide control and SCADA system.
1.3 SUBMITTALS
A. Submit complete shop drawings in accordance with the requirements of Section 01 33 00, Submittals for Procurement Contracts. Submit complete design and manufacturing data for the
System as follows:
1. Process and instrumentation diagrams for complete Ballasted Flocculation system including all equipment and instrumentation to be controlled by the Seller’s system.
2. Installation drawings showing all important details of construction, dimensions, and anchor bolt locations.
3. Descriptive literature, bulletins, and/or catalogs of the equipment.
4. A complete total bill of materials for all equipment.
5. Data on the characteristics, features, and performance of the equipment.
6. Electrical Schematics, panel layouts, field wiring diagrams, instrumentation sheets, and product data sheets for all electrical equipment being supplied by the Ballasted Flocculation system Seller.
a. Panel exterior layout drawings to scale and shall indicate the following:
1) Panel materials of construction, dimensions, and total assembled weight.
2) Panel access openings.
3) Conduit access locations.
4) Front panel device layout.
5) Nameplate schedule:
a) Nameplate location.
b) Legend which indicates text, letter height and color, and background color.
c) Short Circuit Current Rating (SCCR) marking per NFPA 70 or statement of exception. Include any required calculations.
6) Layouts of graphic panels or mosaic displays.
b. Panel interior layout drawings shall be drawn to scale and shall indicate the following:
1) Sub-panel or mounting pan dimensions.
2) Interior device layouts.
3) PLC general arrangement layouts.
4) Wire-way locations, purpose, and dimensions.
5) Terminal strip designations.
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 3
6) Location of external wiring and/or piping connections.
7) Location of lighting fixtures, switches and receptacles.
c. Wiring diagrams shall consist of the following:
1) Panel power distribution diagrams.
2) Control and instrumentation wiring diagrams.
3) PLC I/O information:
a) Model number of I/O module.
b) Description of I/O module type and function.
c) Rack and slot number.
d) Terminal number on module.
e) Point or channel number.
f) Programmed point addresses.
g) Signal function and type.
4) Wiring diagrams shall identify each wire as it is to be labeled.
5) OIT graphics.
6) Description of controls.
7. The total weight of the equipment including the weight of the single largest item.
8. Complete motor drive data.
9. Equipment anchoring calculations.
10. Complete data and drawings on control system.
11. Manufacturer catalog cut sheets for enclosure, finish, panel devices, control auxiliaries, and accessories.
12. Electrical load calculations for each panel:
a. Total connected load.
b. Peak electrical demand for each panel.
13. Climate control calculations for each panel.
a. Verify that sufficient dissipation and/or generation of head is provided to maintain interior panel temperatures within the rate operating temperatures of panel components.
14. Signed warranty documents.
1.4 BALLASTED FLOCCULATION SYSTEM PERFORMANCE GUARANTEE
A. Seller guarantees that the Ballasted Flocculation process will perform as set out in these specifications when erected in accordance with the process design basis and detailed design approved by Seller, and if operated at conditions in accordance with Seller’s process design basis, operating instructions (to include chemical type and dosage instructions), and any modifications or revisions thereof, all as furnished in writing by Seller, directly or indirectly, to the Contractor.
B. The Ballasted Flocculation system Performance Guarantee performance requirements are as follows:
Ballasted Flocculation Performance Guarantee Performance
Requirements
Parameter Requirement
Design Influent flow per train 5,000 gpm
Raw water turbidity less than or equal to 100 NTU
Effluent less than or equal to 2.0 NTU
Raw water turbidity 101 NTU up to 2000 NTU
Effluent not greater than 5 NTU not less than 95% of the time*
Raw water source, summer Reeder Reservoir water blended with Talent
Irrigation District water
Raw water source, winter Reeder Reservoir water
C. Performance Guarantee.
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 4
1. The period of the Performance Guarantee shall be limited to 1 year from the date of documented substantial completion based on the results of demonstration testing. If, within the 1-year Performance Guarantee Period, the Ballasted Flocculation system is operated under and meets the specified Performance Guarantee conditions listed in the table in Part
1.4.B, then the Ballasted Flocculation system shall be construed as sufficient with respect to the Process Performance Guarantee. Owner shall schedule the performance test with the
Seller, giving at least 7 days notice. Determination of Ballasted Flocculation system performance in relation to the Process Performance Guarantee shall be evaluated twice, once under the summer and once under the winter for each of the water quality conditions in Part 1.4.B and shall be based on a 1-hour rolling average over three days of the
SCADA records of continuous on-line measurement. Seller’s total liability under the
Performance Guarantee will be discharged, and the Owner will have no further recourse against Seller or any claims for recovery hereunder with respect to such Performance
Guarantee.
2. The Owner shall operate the Ballasted Flocculation system during the Performance
Guarantee period in accordance with the design basis and within the range of operational control and monitoring requirements as detailed by the Seller in the Operations and
Maintenance documentation or in subsequent Seller furnished operational modification guidelines and revisions. The Owner shall also be responsible for operating the Plant during the Performance Guarantee period, for collecting the turbidity data, influent and effluent data such as flow, turbidity in NTU, for recording chemical use and dosage data, for carrying out all laboratory tests, for maintaining any online instrumentation according to the manufacturer’s specified intervals, and for keeping detailed testing records including the date and type of any action taken.
3. Sampling and analytical support during the demonstration testing period shall be the responsibility of the Contractor.
4. It is understood and agreed that any mechanical corrective work necessary to cause the
Ballasted Flocculation system to meet the Performance Guarantee will be performed by
Seller, the Owner, or their respective contractors at times mutually agreed upon by Seller and the Owner.
5. Costs associated with implementation of equipment or operational modifications or modification of equipment required to bring the Ballasted Flocculation system into compliance with the Performance Guarantee, and those costs associated with training required to implement an equipment modification or operational change, shall be borne by the Seller.
6. Costs associated with re-training or additional training of Owner’s personnel during the
Performance Guarantee testing period shall be borne by the Owner.
7. Ballasted Flocculation system performance records will be retained by the Owner until the
Performance Guarantee has been satisfied and will be comprised of all daily log sheets, operator notes, sample inspections, and instrument charts produced as part of plant operations. Upon Seller’s request, Owner will furnish copies of such records to Seller for their review towards identification of potential process equipment or operational modifications as required to meet the Performance Guarantee requirements.
8. If the Owner chooses not to document or is unable to conduct adequate Performance Testing due to problems unrelated to the Seller’s equipment after the plant has achieved stable operation during the 12-month Guarantee Period, the Performance Guarantee will be assumed to have been met.
9. If, during the Performance Guarantee period, it appears that the requirements of the
Guarantee are not being met, Seller will have the right to have the Ballasted Flocculation system portion of the Treatment Plant operated at such conditions as it may deem necessary or advisable for purposes of determining the nature or cause of the failure of the plant to meet the Guarantee, provided such operating conditions are in accordance with good engineering practice and the Owner’s safety rules enforced at the plant site, and thereafter will have the right to make or have made such adjustments as it deems necessary or advisable in order to meet such guarantee and the right to make or have made, at its own
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 5 expense, such alterations or modifications to the Ballasted Flocculation system equipment as it deems necessary or advisable.
10. The Owner will promptly notify Seller when each guarantee parameter under the
Performance Guarantee has been met and, if necessary, of the failure of the plant to meet any such guarantee, specifying the respect in which such guarantee has not been met.
11. The Seller will not be responsible in any way for non-fulfillment of the Performance
Guarantee due to deficiencies in the plant with respect to materials, equipment (other than equipment furnished by Seller), workmanship, or services, including but not limited to:
a. Defective materials or mechanical condition or deficient performance of equipment utilized in the Ballasted Flocculation system’s auxiliary parts supplied by Contractor.
b. Noncompliance with the Process Design Basis for the Ballasted Flocculation system and/or noncompliance with operating instructions to include system Seller’s recommendations on proper chemical feed rates and types, or revisions of any of these, furnished or approved in writing by Seller to Contractor or defective conditions or performance of any materials, equipment (other than equipment furnished by Seller) or work supplied by or contracted for by anyone other than Seller.
c. Failure of the Contractor to furnish adequate utilities, such as, but not limited to, electricity, air, water, etc. as well as an adequate operating force.
d. Mechanical failure of any of the equipment or component parts thereof due to ordinary wear and tear or any other cause.
e. Failure of Contractor to perform any of the responsibilities and obligations assumed by it in accordance with the provisions hereof.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Seller shall be responsible for designing, furnishing, coordination, proper sizing, and performance of all systems components for a complete operating system.
B. Acceptable Sellers
1. Veolia Actiflo Turbo.
2. WesTech RapiSand.
3. Or approved equal.
C. Submit requests for substitution in accordance with Section 01 25 13.
D. The basis of design and drawings are based on the Actiflo system by Veolia. Contractor shall be responsible for the cost of any changes that may be required to accommodate alternate systems and equipment by other manufacturers, including, but not limited to, structural, mechanical, and electrical work. Contractor shall also pay any additional engineering costs necessary for revisions of drawings and specifications required to accommodate alternate equipment. Any proposed alternate must comply with these
Specifications and Contractor must properly document supplier experience under equivalent design conditions, quality, performance and reliability equivalent to that specified herein.
2.2 GENERAL
A. This specification establishes specific requirements and features for the Ballasted Flocculation equipment, but do not purport to cover all details necessary for a complete and operable
Ballasted Flocculation system. Ancillary and accessory devices, within the confines of the
Ballasted Flocculation system Seller’s scope, necessary for system performance shall be included by the Seller whether specified or not.
B. The equipment covered by these Specifications is intended to be standard process equipment of proven ability as manufactured by reputable manufacturers having experience in the production of such equipment.
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 6
C. The nameplate ratings for the motors shall not be exceeded, nor shall the design service factor be reduced when its piece of equipment is operating at any point on its characteristic curve.
D. The location, size, and type of all piping associated with the Ballasted Flocculation system shall be as shown on the Drawings, or as required by the supplied equipment.
E. All wetted components and materials in contact with process water shall be NSF 60/61
Certified.
2.3 DESCRIPTION OF THE SYSTEM
A. The Ballasted Flocculation system is a compact coagulation/clarification/sedimentation process that uses microsand for enhanced flocculation and settling. Raw water is passed through automated strainers before ozone contact and subsequent calcium thiosulfate addition to quench any remaining ozone. Alum coagulant, soda ash, polymer, and microsand are added to the raw water at various feed points. The Ballasted Flocculation system has tanks to mix chemicals and then agglomerate and grow particles into high density flocs commonly called ballasted flocs, which are then separated from the process flow by the use of the inclined settling plates or tubes in a settling tank. The sludge/microsand mixture collected at the bottom of the settling tank is then pumped to hydrocyclones where the sludge is separated from the microsand by the centrifugal force of the vortex action. The recovered clean microsand is then returned to the
Ballasted Flocculation system and the separated sludge is continuously discharged to sanitary drain. Overflow from the settling tank flows to the filter which is outside the Seller’s scope.
B. The design criteria for the Ballasted Flocculation system are as follows:
1. Number of process trains: 2 (1 duty, 1 standby).
2. Process design flow (peak conditions): 5,000 gpm per train.
3. Process design flow (minimum flow): 1,200 gpm.
C. As a minimum, the Ballasted Flocculation system Seller shall include the following equipment for each process train:
1. One mixer for the coagulation tank, and two vortex baffles (304 SS).
2. One mixer for the maturation tank.
3. One draft tube or baffles for the maturation tank(s) (304 SS).
4. One sludge scraper assembly, including support bridge, for settling tank.
5. One set of high impact polystyrene or polyvinyl chloride lamella settling tubes with supports (304 SS).
6. One set of collection troughs with supports (both troughs and supports 304 SS).
7. Contractor to provide One manually electrically actuated blowdown plug valve.
8. One microsand (recirculation) pump, each pump system to include: rubber lined sand/slurry pump, pump seal water stations, seal water flow switches, suction and discharge isolation valves, flush connections, and pressure indicators/transmitters and high and low pressure switches manifolded with diaphragm seals and isolation valves.
9. One hydrocyclone each with underflow and overflow pipe, pressure gauge assembly, complete with diaphragm seals and isolation valves and 304 SS supports.
10. Microsand delivery pipes, which includes the recirculation piping between the ballasted flocculation system, microsand pumps, and hydrocyclones, shall be designed procured and provided installed by the Seller Contractor. Seller shall ensure recirculation piping is constructed out of materials that are compatible with project requirements.
11. Microsand and chemicals for start-up
a. Microsand: minimum 16 8 tons.
b. Polymer: minimum 400 gallons.
D. Conduit and Wire:
1. All skid-mounted equipment, valves, and instruments shall be pre-wired to two NEMA 4X, stainless steel junction boxes mounted to the unit. One junction box shall be designated for signal wire and one junction box shall be designated for power wire.
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 7
2. Contractor shall provide equipment disconnects with NEMA 4X, stainless steel enclosures shall be provided for all motors.
3. pH Probe and Turbidimeter shall be mounted to handrail and inserted into Settling Tank
4. All motors to be run to a local disconnect mounted to the handrail. Then run conduit under the grating to each unit.
5. Ability to remove the grating with conduit in place is required.
6. Flexible conduit is to be run from the motor enclosure and terminate at the extents of the tank (At the top of side of the tank depending on the equipment location).
7. Contractor is responsible for supplying and installing all electrical wiring, control wiring, conduit, fittings, junction boxes, supports, and ancillary power and control equipment to and between vendor supplied gear.
E. Ballasted Flocculation Control System:
1. Shall include a Main Control Panel with NEMA 4X rated enclosure and Train Control
Panels with NEMA 4X rated enclosures.
a. The Main Control Panel shall include Programmable Logic Controller (PLC) hardware:
1) Shall provide automatic controls and monitoring of each train.
2) Shall receive 120 VAC, 1-phase power with through the door disconnect.
3) Shall include a UPS to keep PLC and OIT energized for 10 minutes upon loss of input power.
4) Managed ethernet switch.
5) Submittal shall clearly indicate required branch circuit size for the control panel.
b. A Train Control Panel shall be provided for each Ballasted Flocculation train.
1) The Train Control Panels shall include PLC Input/Output modules, pilot devices, indicator lights, motor starters, and VFDs for the associated train.
2) Shall include provisions for manual, local control of the equipment upon loss of communications or failure to the Main Control Panel.
3) Shall communicate with the Main Control Panel via Ethernet communications.
4) Shall receive 460 VAC, 3-phase power with through the door disconnect.
5) Motor starters shall be NEMA type.
6) Submittal shall clearly indicate required branch circuit size for the control panel.
c. The control panels shall be completely assembled, tested, and programmed for the required functionality.
d. Each control panel shall be UL508 listed.
e. Interconnections between control panels shall be provided by the Contractor.
2. Shall be controlled using a PLC based system with Operator Interface Terminals (OITs):
a. PLC hardware shall be Rockwell Automation, Allen-Bradley CompactLogix.
b. OIT hardware shall be Rockwell Automation, Allen-Bradley PanelView Plus7 15-in color with touch-screen and keypad.
c. Shall include provisions for EtherNet/IP communication with the WTP process control system.
d. PLC discrete input points shall be 24VDC type.
e. PLC shall include 20 percent spare I/O capacity, and minimum of 4 each analog input, 2 analog output, and 8 each discrete input, 4 discrete output.
f. Provide PLC and local operator interface programming, configuration, and graphics for control and monitoring of all functions in the ballasted flocculation system.
g. All information available on the Main Control Panel local operator interface shall be configured to be made available to the WTP process control system using PLC
“produced and consumed tags” as follows:
1) Produced tags: Intended for transmission across the plant SCADA system’s network such that it is available to be read by other controllers and/or the plant
SCADA human machine interface (HMI) system.
2) Consumed tags: Configured to be read by the plant SCADA HMI system across the plant SCADA system’s network.
3) Utilize explicit messaging (not write messages) and message reads
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 8
F. Instrumentation
1. Instrumentation required for control and monitoring of the Ballasted Flocculation system shall be provided by the Seller:
a. At a minimum the instruments shown on the attached PIDs shall be required.
b. Any and all other instruments required by Ballasted Flocculation Seller to meet
Performance Guarantee shall be included in Sellers scope of supply.
2. Seller shall provide at a minimum the following instruments:
a. One influent turbidity analyzer.
b. One influent pH analyzer.
c. Two effluent combination pH and temperature analyzers.
d. Two effluent turbidity analyzers.
e. Two pressure indicating transmitters for recirculation pumping.
f. Two flow indicating transmitters for recirculation pumping.
G. Microsand:
1. Microsand shall meet the following requirements:
a. Material: Silica Sand, SiO2
b. Greater than 99 percent.
c. Toxicity elements (As, Hg): None.
d. Particle density: 2.65 grams/cubic centimeter
e. Effective size: 100 to 120 μm
f. Uniformity coefficient: ≤ 1.77
2. Furnish ballasted flocculation train initial fill plus makeup equivalent to initial fill quantity
(minimum 8 tons of microsand).
2.4 COAGULATION, INJECTION, AND MATURATION MIXERS
A. Each mixer assembly shall consist of a heavy-duty speed reducer, electric motor, baseplate, agitator shaft, and mixing impellers. Mechanical components of the mixers shall be as follows:
1. See Section 01 61 03.
2. The mixer gear drive manufactured to current AGMA Standards. The AGMA calculated drive HP rating shall be stamped on the drive nameplate. Drive housings shall be of high quality close grained cast iron, or fabricated steel, stress relieved and reinforced, and shall be provided with integral or separate baseplates suitable for mounting.
3. Gearing shall be vertical parallel shaft all helical gears or helical spiral bevel to ensure the highest efficiency coupled with the convenience of mounting and maintenance (worn gearing is not acceptable). Gears shall be a minimum AGMA Quality 10 per AGMA standard 390.03. The gears shall be lubricated from a common food grade oil bath.
4. The mixer gear drive shall be designed with an output shaft system suitable for the loadings imposed by the specific duty. The drive’s minimum AGMA service factor shall be 1.5 and based upon motor nameplate horsepower. The service factor shall be based on AGMA
Standards for 24 hour per day moderate shock application. Service factors based on uniform load and motor bhp will not be accepted.
5. All drive bearings shall be of the antifriction type, ball bearings. All bearings within the drive, including output shaft bearings, shall have minimum AFBMA B-10 lives of
50,000 hours when operating at full motor nameplate horsepower at design speed.
6. Each drive must have an effective lubrication of rotating elements without leakage down the output shaft. Output shaft bearings may be grease lubricated, including a high quality lip seal to retain grease.
7. The electric motor drivers shall be suitable for operating in a humid outdoor environment with class F insulation, a 1.15 service factor and TEFC enclosure. The motors shall be squirrel cage induction motors for operation on 3-phase, 60 hertz, 230/460 volt current with synchronous speed of 1800 rpm or less. All motors shall be designed constructed and tested in accordance with applicable IEEE, NEA, and ANSI, standards. Motors for use with VFDs shall be inverter duty.
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 9
8. The lower mixer shaft shall be connected to the upper, or drive output shaft, by means of a rigid flanged or integral coupling.
9. The agitator shaft shall be of 304 SS. The shaft shall be designed such that the maximum stress shall not exceed 9,000 psi under maximum operating loads. It shall be of overhung design. The use of underwater steady bearings is not permitted. The mixer shaft shall have a maximum operating speed of 0.75 times the natural frequency of the shaft and impeller assembly without the use of stabilizing ring and lower shaft bearing.
10. Mixing impellers shall be constructed of 304 SS or other approved material as recommended by the mixer manufacturer and shall be of bolted construction and shall be connected to the agitator shaft with a hook key for maximum security. The maximum stress in any impeller component shall not exceed 11,000 psi under maximum operating loads.
Mixer gear drive and motor shall be painted with a minimum of a 5 mil coat of epoxy primer. Primer to be equal to Amerlock 400 and a finish coat of Amershield urethane high gloss finish. Paint shall meet EPA and VOC requirements.
11. Upon installation each unit shall be run to demonstrate its ability to operate without overloading, jamming, or excessive vibration during normal operation.
12. The mixers shall be as manufactured by Philadelphia Mixers, Lightnin, Mixtec, or approved equal.
2.5 SLUDGE SCRAPER ASSEMBLY
A. The sludge scraper mechanism shall be suitable for installation in the settling tank. The total load of the scraper mechanism shall be supported from the top deck of the settler tank.
B. The overall mechanism shall be designed for a torque capacity determined when the full volume of sand in the system is collected at the bottom of the settler. Each scraper mechanism shall consist of a drive unit with torque overload protection, center shaft, rake arms, and discharge cone scraper.
C. The drive unit shall be single shaft type rated with a cut-out torque determined when the full volume of sand in the system is collected at the bottom of the settler as provided by the Ballasted
Flocculation Seller.
D. Support Bridge:
1. The entire weight of the scraper drive, shaft, and rake arm assembly shall be supported by the bridge. The bridge shall be constructed of hot-dipped galvanized steel, with aluminum grating and handrails. The grating shall be removable to allow access to the lamella tubes for cleaning. The bridge shall be of sufficient width to allow the operator access past the drive assembly. The bridge shall span as shown on the drawings from the hanging wall to the effluent launder wall.
2.6 DRIVE MECHANISM FOR SLUDGE SCRAPER ASSEMBLY
A. The drive mechanism shall consist of an electric motor, a primary hydraulic reduction unit, a final gear reduction unit (as required), and an overload device (if applicable). All components are directly coupled, eliminating chains and V-belts. The primary reduction unit shall be a parallel-helical multistage gearbox and the final reduction unit shall be a parallel-helical shaft mounted gearbox.
B. Electric Motor
1. Minimum service factor: 1.15
2. Motor enclosure: TEFC with Class F insulation and Class B temperature rise above 40-deg
C ambient.
3. Motors shall be three phase, 60 Hz, 230/460 volts.
4. Motors shall be rated for severe duty.
5. Efficiency shall be determined in accordance with IEEE 112, Test Method B.
6. All motors shall comply with manufacturer’s standard design, construction and testing procedures as defined by applicable IEEE, NEMA, and ANSI standards.
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 10
C. The final gear reduction unit (as required) shall have bearings with a B-10 life in excess of
100,000 hours and be AGMA rated for 10,000,000 cycles when operating at the continuous operating torque. The final gear reduction unit shall be of the planetary/spur gear type and be permanently grease lubricated.
D. The drive motor shall be a “Severe Duty” motor for 3-phase, 60 Hertz, 480 volts service, compatible for use with a variable frequency drive, and have a stainless steel shaft.
E. An overload device shall be attached to the primary hydraulic reduction unit and shall be activated by the hydraulic pressure in the primary reduction unit. The device shall have two adjustable pressure switches so that an alarm circuit may be energized when the load on the mechanism approaches overload, and open the motor circuit when an overload occurs. The overload device shall also have a minimum 6-inch-diameter gage that will indicate the output torque of the drive in ft-lbs.
F. All wetted materials shall be constructed of 304SS.
2.7 SHOP PAINT
A. All non-submerged steel surfaces shall be commercial blast cleaned (SSPC-SP6). All submerged steel surfaces shall be near white blast cleaned (SSPC-SP10). All surface preparation should be
SSPC-SP5 White metal blast.
1. Seller to provide equipment supplier standard coatings (interior and exterior) for steel tank.
2. The center drive mechanism assembly shall be factory finish painted with a polyamide epoxy coating system unless constructed from stainless steel.
3. All machined surfaces subject to corrosion shall be coated with an easily removable rust preventative compound prior to shipment.
2.8 LAMELLA TUBE EQUIPMENT
A. Tubes shall incline at 60 degrees from the horizontal.
B. Material shall be high impact polypropylene, polystyrene or polyvinyl chloride tubes with 304SS supports.
2.9 EFFLUENT COLLECTION SYSTEM
A. Clarified water shall be collected by means of either rectangular or V-notch weir collection troughs, 304 stainless steel. Each trough shall discharge to a common effluent launder.
B. Collection troughs shall be rectangular shaped and fabricated from 304 stainless steel. The troughs shall be sized by the ballasted sedimentation system Seller. Each trough shall be complete with weir plates sized for the maximum design flow.
2.10 MICROSAND PUMPS
A. General:
1. See Sections 01 61 03 and 43 21 00.
2. Microsand (recirculation) pumps shall be centrifugal rubber lines slurry pump with V-belt drives. The Ballasted Flocculation Seller shall design and size the microsand pumps to meet the system head requirements of their system configuration. Each pump shall be provided with a motor.
3. Manufacturer:
a. Flowserve
b. McLanahan.
c. Or approved equal
4. The pumps shall be designed so that they:
a. Operate at maximum possible efficiency throughout the duty range.
b. Cause no overloading of motors under all operating conditions
c. Are capable of continuous operation.
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 11
d. If centrifugal, shall have a continuously falling head/capacity characteristic curve from no flow to maximum flow conditions to ensure satisfactory parallel operation.
5. Submit all performance curves of the pumps showing head/flow rate, horsepower, efficiency, and net positive suction head requirements over the full operating range.
6. A complete arrangement drawing of each pump shall be provided showing overall dimensions and the weight of the combined pump, motor, and base.
7. The impellers, shafts and all other rotating parts of the pump shall, as a complete unit, be statically balanced to ensure freedom from vibration.
8. Pumps shall be driven by V-belts and sheaves to obtain the required pump speed. Provision shall be made for adjusting belt tension. A fully enclosed, steel belt guard shall be provided in compliance with OSHA requirements.
B. Pump Arrangement/Construction (Centrifugal)
1. Casings shall be cast iron radially split type, for easy maintenance, fitted with replaceable abrasion resistant rubber liners pressure molded to the backing plate and secured to the casing externally by heavy-duty studs and nuts. Rubber liners shall extend through casing nozzles to form natural gaskets between flanges and piping. Flanges shall be slotted for easy assembly and disassembly. For pumps 8 inch and larger, the casing shall be equipped with anti-rotation veins for smooth flow into pump.
2. The impeller is to be balanced and fully enclosed to protect the veins. The impeller shall be abrasion resistant rubber, pressure molded to a ductile iron support skeleton. Impeller to be screwed to the shaft with heavy duty threads running in opposite direction to the shaft rotation for maximum security.
3. Sellers standard gland seal shall be provided for each pump. Stuffing box shall be cast iron or SS with replaceable heavy duty protector plate. The shaft shall be enclosed within the stuffing box by coated stainless steel hook-type sleeve.
4. The pump shall be fitted with a flushless mechanical gland. The mechanical gland shall be suitable for sand slurry service. An external seal water flush is not required but a drip, with suitable drain piping connection, is required.
5. All bearings to be heavy duty anti-friction type completely enclosed in an oil-lubricated cast iron cartridge assembly.
6. All pumps and motors shall be provided with necessary lugs, eye bolts, or other suitable attachments for lifting.
7. The electric motor shall be sized to be non-overloading at all points on the pump performance curve. Motor enclosure shall be TEFC, and suitable for operation in a humid, outdoor environment. Motors shall be for operation on 3-phase, 60 Hertz, 230/460 volt power. All motors shall comply with manufacturer’s standard design, construction, and testing procedures as defined by applicable IEEE, NEMA, and ANSI standards.
a. Motors shall be Inverter duty rated complying with all requirements of NEMA MG 1
Part 31 for definite-purpose inverter-fed motors.
1) At a minimum, applied to motors connected to a VFD.
2) Windings insulated for 1600 peak volts and voltage rise times of 0.1 microseconds.
3) Nameplate identification of meeting NEMA MG 1 Part 31 requirements.
4) Have the following minimum turndown ratio without the use of a blower to provide continuous supply of cooling air over the motor.
a) Variable torque: 10:1.
b) Constant torque: 6:1.
b. Insulated drive end bearing on all motors.
c. Shaft grounding ring on all motors:
1) Factory installed, maintenance free, circumferential, bearing protection ring with conductive microfiber shaft contacting material.
2) Electro Static Technology AEGIS SGR Bearing Protection Ring or approved equal.
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 12
2.11 HYDROCYCLONES
A. The hydrocyclones shall be sized by the Ballasted Flocculation system Seller. The underflow of the hydrocyclones shall be gravity fed to the maturation tank for reuse of the cleaned microsand.
The overflow of the hydrocyclone will be discharged and flow by gravity to the sanitary drain.
B. Manufacturer:
1. Krebs
2. Or approved equal
2.12 BLOWDOWN PLUG VALVES (PV-3216, PV-3226, AND MANUAL VALVES AS SHOWN
ON DRAWINGS)
A. Manufacturers:
1. DeZurik.
2. Henry Pratt.
3. Millikin.
4. ValMatic.
B. Materials:
1. Body: Cast-iron ASTM A126, Class B.
2. Plug: One or two-piece construction ductile iron, ASTM A536 65-45-12 or cast iron, ASTM A126 Class B.
3. Plug facing: Grease and/or petroleum-resistant resilient Neoprene or Buna-N compound, 70
Type A durometer hardness per ASTM D2240.
4. Shaft bearing bushings: Permanently lubricated TFE or Delrin sleeve type stainless steel or bronze.
5. Valve seats: Welded-in overlay of 90% nickel, (minimum 1/8 IN thick).
6. Stem seal: per AWWA C517, Section 4.4.7.
7. Manual level actuators per Section 40 05 51 – Valves Basic Requirements part 2.3.E. PV-
3216 and PV-3226 only.
2.13 SPARE PARTS
1. One set of mixer seals and bearings and one mixer gear box for pre-coagulation/tank
2. One set of mixer seals and bearing and one mixer gear box for coagulation tank
3. One set of mixer seals and bearings and one mixer gear box for maturation tank
4. One pump impeller
5. Two pump drive belts
6. Two pump packing sets
7. Two hydrocyclone apex tips
8. One calibrated Imhoff cone for operators’ use
9. One spare PLC module of each type used.
10. One spare Ethernet switch.
PART 3 - EXECUTION
3.1 SERVICES OF SELLER
A. Subsequent to the complete testing and startup of all new process systems included in the Project and the Owner’s acceptance of them in accordance with the Contract Documents, should the quality of the effluent (settled water) from the Ballasted Flocculation system cause performance problems for the filters as evidenced by filter runs shorter than 8 hours and/or earlier turbidity breakthrough, reference Section 46 31 90, as compared to the average filtration performance for similar facilities under similar raw water quality conditions, the Ballasted Flocculation Seller shall work with the Owner to investigate and test Ballasted Flocculation operational modifications.
1. Such modifications may include changes in the types or dosages of coagulants, microsand concentration, recirculation rates, or other changes that can reasonably made to correct the
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 13 filter performance problems. In such an event, the Ballasted Flocculation system Seller shall provide a technical representative on-site for up to 2 days at no added cost to the Owner.
3.2 SYSTEM STARTUP
A. The Seller shall provide field services necessary to start-up and test the system as follows required in Section 01 75 00.
B. Functional Demonstration Testing of the Ballasted Flocculation system shall be contingent upon meeting the requirements of the Ballasted Flocculation system Performance Guarantee listed in
Part 1.4.B, as determined by Functional Demonstration testing that shall be conducted over a
3-day (72 hours continuous) period of operation where the raw water turbidity is within the range listed in the Guarantee and the associated chemical feed equipment has previously been fully tested and accepted by the Owner.
1. For the Functional Demonstration Testing, the Ballasted Flocculation system shall be fully maintained and operated without interruption as described in Section 01 75 00.
2. In order to create a feed water meeting criteria listed in Part 1.4.B., the Owner will provide the Contractor with soil harvested locally and the Contractor shall make provisions to slurry the soil into suspension creating a feed water suitable for performing the Functional
Demonstration Testing.
C. Determination of Ballasted Flocculation system turbidity performance during the Functional
Demonstration Testing shall be based on the rolling average of the Plant SCADA records of continuous on-line measurements of the flow rates through the Ballasted Flocculation system and turbidity in the raw water entering a Ballasted Flocculation train and the settled water
(effluent) at the outlet of the same Ballasted Flocculation train.
1. For verification of the accuracy of the on-line turbidity measurements within the Functional
Demonstration Testing period, a minimum of eight pairs of grab samples of both raw and settled water from the Ballasted Flocculation train in operation shall be taken and measured for turbidity using a bench-top turbidimeter that has been calibrated to the manufacturer’s standards.
2. If the average difference between the measured turbidity readings of the on-line and the bench-top turbidimeters is not more than 3 percent for all grab samples taken in the testing period, the on-line turbidimeters will be used to determine raw and settled turbidity for determining compliance with the Guarantee requirements.
3. If the average difference between the on-line and bench-top turbidity measurements is greater than 3% for all grab samples, the measurements averaged over the course of the 3-day period of operation from the calibrated bench-top turbidimeter shall be used to determine Guarantee compliance.
D. If the raw water turbidity exceeds the levels listed in the Performance Guarantee at any time during the Demonstration Testing period, the Seller shall have the right to omit the corresponding settled water turbidity data for that time.
1. Once the raw water turbidity returns to within the guarantee levels, the performance testing will continue.
E. The Contractor shall operate the Ballasted Flocculation system during the Functional
Demonstration Testing period in accordance with the design basis and within the range of operational control and monitoring requirements as detailed by the Seller in the Operations and
Maintenance documentation or in subsequent Seller furnished operational modification guidelines and revisions.
1. The Contractor shall also be responsible for operating the Plant during the Functional
Demonstration Testing period, for collecting the turbidity data, influent and effluent data such as flow, turbidity in NTU, for recording chemical use and dosage data, for carrying out all laboratory tests, and for keeping detailed testing records.
F. The Seller, with Contractor approval, shall be granted sufficient time as required during the
Performance Guarantee testing period to make equipment modifications and control or
BALLASTED FLOCCULATION SYSTEM
46 43 62 - 14 monitoring changes as necessary to bring the Ballasted Flocculation system into compliance, followed by appropriate training of Owner’s personnel to facilitate its performance. Such time shall be added to the 72-hour testing period.
G. Upon completion of the Functional Demonstration Testing per 01 75 00, the Contractor shall perform the Acceptance Test. See 01 75 00.
END OF SECTION