3-Bid Manual Table of Contents (Addendum 6).pdf
PDF 23 KB Posted
- Solicitation number
- US.261117
- Issued by
- Lehigh County, Pennsylvania
About this file
This file is a Table of Contents for the Bid Manual prepared by the Fredericksburg Sewer & Water Authority (FSWA) in Pennsylvania for the Public Water System Upgrade Project, specifically related to Contract 3 – Electrical Construction. The document is organized into ten sections containing front-end specifications, bid forms for five separate contracts (Pipeline Construction, General Construction, Electrical Construction, Plumbing Construction, and HVAC Construction), agreements and bonds, general specifications, and construction specifications across multiple divisions. The electrical construction work consists of furnishing and installing electrical power supply and distribution equipment, standby electrical power generation equipment, electrical conduits and wiring for process equipment, electrical upgrade of Well 6, installation of well controls at new wells 7 and 8, electrical installation of a mixer in the West Water Tower, demolition of electrical service to existing water tower mixers, and installation of an underground 1" PVC conduit between specified facility locations. Sealed electronic proposals via PennBid were due by 2:00 p.m. prevailing time on Wednesday, December 16, 2026. No pre-bid conference is scheduled for this contract; however, site visits may be arranged by contacting the FSWA Operator, Dusty Keller, at 717-304-1061. Questions are submitted through the Public Q & A feature within PennBid.
The bid documents are available at no cost on PennBid at https://pennbid.bonfirehub.com. Each proposal must be accompanied by a bank cashier's check or bid bond in the required form equal to ten percent (10%) of the bid total. This contract is part of a larger project with multiple prime contracts that were previously bid and awarded. The project is located at 2529 State Route 22, Fredericksburg, PA 17026. The bid manual includes provisions addressing Federal Super Cross Cutter Requirements, PENNVEST funding requirements, prevailing wage determination schedules, American Iron and Steel Act requirements consistent with Build America, Buy America provisions, and various compliance documentation including non-collusion affidavits, Act 127 verification forms, public works employment verification forms, workmen's compensation affidavits, and bidder qualifications questionnaires.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE OF CONTENTS
Page
Page numbers are the starting pages within each corresponding Bid Manual Section PDF.
SECTION 1 - FRONT END SPECIFICATIONS
Division 0 - Special Sections Section 00020 - Advertisement and Invitation to Bid Federal Super Cross Cutter Requirements PENNVEST Funding Requirements Prime Contractor DBE Solicitation Effort Help Guide Section 00200 - Instructions to Bidders Section 00440 - Non-Collusion Affidavit Section 00460 - Act 127 Verification Form Commonwealth of Pennsylvania Public Works Employment Verification Form Section 00470 - Affidavit RE Accepting Provisions of the Workmen's Compensation Act Section 00490 - Bidder Qualifications Questionnaire
SECTION 2 - BID FORMS
Bid Forms Section 00411 - Bid Form - Contract 1 - Pipeline Construction Section 00412 - Bid Form - Contract 2 - General Construction Section 00413 - Bid Form - Contract 3 - Electrical Construction Section 00414 - Bid Form - Contract 4 - Plumbing Construction Section 00415 - Bid Form - Contract 5 - HVAC Construction
SECTION 3 - AGREEMENTS & BONDS
Forms of Agreement Section 00521 - Form of Agreement - Contract No. 1 - Pipeline Construction Section 00522 - Form of Agreement - Contract No. 2 - General Construction Section 00523 - Form of Agreement - Contract No. 3 - Electrical Construction Section 00524 - Form of Agreement - Contract No. 4 - Plumbing Construction Section 00525 - Form of Agreement - Contract No. 5 - Heating, Ventilation, and Air Conditioning (HVAC) Construction
Bid Bonds - Penal Sum Form Section 00531 - Contract 1 - Pipeline Construction Section 00532 - Contract 2 - General Construction Section 00533 - Contract 3 - Electrical Construction Section 00534 - Contract 4 - Plumbing Construction Section 00535 - Contract 5 - HVAC Construction
Performance Bonds Section 00611 - Contract 1 - Pipeline Construction Section 00612 - Contract 2 - General Construction Section 00613 - Contract 3 - Electrical Construction Section 00614 - Contract 4 - Plumbing Construction Section 00615 - Contract 5 - HVAC Construction
Payment Bonds Section 00621 - Contract 1 - Pipeline Construction Section 00622 - Contract 2 - General Construction Section 00623 - Contract 3 - Electrical Construction Section 00624 - Contract 4 - Plumbing Construction Section 00625 - Contract 5 - HVAC Construction
FSWA - PUBLIC WATER SYSTEM UPGRADES
Table of Contents - Page 1 of 4
SECTION 4 - GENERAL SPECIFICATIONS
Contract Conditions and Special Sections Standard General Conditions of the Construction Contract (EJCDC C-700) Section 00800 - Supplementary Conditions Section 00820 - Duties, Responsibilities, and Limitations of Authority of the RPR Section 00830 - Wage Determination Schedule Section 00850 - Geotechnical Engineering Report
Division 1 - General Requirements Section 01010 - Summary of Work Section 01011 - State and Local Permits Section 01025 - Measurement and Payment Section 01656 - Disinfection of Water Mains Section 01666 - Testing of Water Piping Section 01300 - Submittal Procedures Build America, Buy America Reference Documents (FAQs and Certification Templates) Section 01320 - American Iron and Steel Act Requirements Section 01400 - Quality Control Section 01500 - Construction Facilities and Temporary Controls Section 01570 - Traffic Control Section 01600 - Delivery, Storage and Handling Section 01700 - Contract Closeout
SECTION 5 - CONSTRUCTION SPECIFICATIONS A
Division 2 - Sitework Section 02220 - Excavation, Backfill and Compaction for Structures Section 02225 - Excavation, Trenching, Backfilling, & Compacting Section 02230 - Site Clearing Section 02240 - Dewatering Section 02270 - E & S Control Facilities Section 02300 - Earthwork Section 02446 - Horizontal Directional Drilling Section 02500 - Asphalt Pavement Section 02601 - Manholes Section 02610 - Pipe and Fittings Section 02710 - Sewer Pipe and Fittings Section 02831 - Chain Link Fence and Gates Section 02930 - Seeding Section 02950 - Trees, Plants and Ground Cover
Division 3 - Concrete Section 03300 - Cast-In-Place Concrete Section 03301 - Concrete for Utility Construction Section 03600 - Grout
Division 4 - Masonry Section 04210 - Brick Masonry Section 04300 - Concrete Unit Masonry
SECTION 6 - CONSTRUCTION SPECIFICATIONS B
Division 5 - Metals Section 05500 - Metal Fabrications Section 05515 - Aluminum Stairs and Platforms Section 05520 - Handrails and Railings Section 05530 - Gratings
FSWA - PUBLIC WATER SYSTEM UPGRADES
Table of Contents - Page 2 of 4
Division 6 - Wood and Plastic Section 06100 - Rough Carpentry Section 06112 - Sheathing Section 06114 - Wood Blocking and Curbing
Division 7 - Thermal and Moisture Protection Section 07160 - Bituminous Damp-Proofing Section 07210 - Building Insulation Section 07219 - Sprayed Insulation Section 07410 - Standing Seam Metal Roof Section 07460 - Siding and Soffit Section 07620 - Sheet Metal Flashing and Trim Section 07631 - Gutters and Downspouts Section 07920 - Joint Sealers
Division 8 - Doors and Windows / Doors and Hardware Section 08100 - Fiberglass Reinforced Plastic Doors and Frames Section 08361 - Sectional Overhead Doors Section 08710 - Finish Hardware
Division 9 - Finishes Section 09260 - Gypsum Board System Section 09650 - Resilient Flooring
Division 10 - Specialties Section 10427 - Pipe Identification Section 10441 - Signs Section 10522 - Fire Extinguishers and Accessories Section 10800 - Restroom Accessories
SECTION 7 - PROCESS EQUIPMENT SPECIFICATIONS
Division 11 - Equipment Section 11000 - Common Requirements for Process Equipment Section 11010 - Process Piping, Valves and Appurtenances Section 11220 - Water Tower Mixer Section 11226 - Green Sand Filtration System Section 11315 - Chemical Addition Equipment Section 11900 - Plant Instrumentation
Division 12 - Furnishings Section 12300 - Cabinets and Workbenches
Division 13 - Special Construction Section 13610 - Existing SCADA Modifications Section 13615 - SCADA Control Panels
SECTION 8 - DUTCHLAND SPECIFICATIONS
Dutchland Technical Specifications Section 03310 - Cast-In-Place Concrete for Precast Post-Tensioned Concrete Tank Base Slabs Section 03420 - Precast Post-Tensioned Concrete Tanks - Rectangular (ACI 350)
FSWA - PUBLIC WATER SYSTEM UPGRADES
Table of Contents - Page 3 of 4
SECTION 9 - MECHANICAL HVAC & PLUMBING SPECIFICATIONS
Division 15 - Mechanical Section 15010 - Basic Mechanical Requirements Section 15050 - Basic Mechanical Materials and Methods Section 15060 - Hangers and Supports Section 15083 - Pipe and Tank Insulation Section 15121 - Expansion Compensation Section 15150 - Sanitary Waste and Vent Piping Section 15190 - Mechanical Identification Section 15410 - Plumbing Piping Section 15430 - Plumbing Specialties Section 15440 - Plumbing Fixtures Section 15850 - HVAC Equipment Section 15900 - Air Handling Equipment
SECTION 10 - ELECTRICAL SPECIFICATIONS
Division 16 - Electrical Section 16010 - Electrical General Provisions Section 16100 - Basic Electrical Materials and Methods Section 16111 - Conduit Section 16123 - Building Wire and Cable Section 16130 - Boxes Section 16141 - Wiring Devices Section 16160 - Cabinets and Enclosures Section 16170 - Grounding and Bonding Section 16190 - Supporting Devices Section 16231 - Generator Set Section 16270 - Low Voltage Transformers Section 16400 - Lighting Devices Section 16415 - Transfer Switch Section 16442 - Panelboards Section 16475 - Surge Protection Devices
FSWA - PUBLIC WATER SYSTEM UPGRADES
Table of Contents - Page 4 of 4
File details come from the government source that posted it. Updated .