- SWE PROJECT # 23-3455 LAND & WATER CONSERVATION FUND GRANT FOR EASTSIDE PARK REHABILITATION
- Solicitation number
- PE-66812-NONST-2026-000000063
- Issued by
- Columbia County, Georgia
About this file
This is Addendum No. 3 to the Advertisement for Bids issued by the City of Douglas, Georgia for the Eastside Park Rehabilitation project (SWE Project #23-3455). The addendum addresses clarifications and modifications to the bid specifications for this park rehabilitation project. Key deadline information includes a bid submission deadline of 2:00 PM on Tuesday, February 17, 2026, with contractor acknowledgment of the addendum required by 9:00 AM on the same date via email to Nicole.burke@swecivil.com. The question deadline is February 13, 2026 at 9:00 AM. The project engineer is Statewide Engineering, Inc., with contact Stanley A. Evans, P.E. (912-384-7723). Offerers must acknowledge receipt of the addendum or risk rejection of their bids, and any bid changes must reference the solicitation and addendum numbers.
The addendum provides twelve clarifications on project specifications, including confirmation that a Georgia Utility License is not required due to utilities not exceeding 4 feet in depth, and that Subcontractor Affidavits should be submitted with bids where available, with remaining affidavits due upon contract award. Key project modifications include specifications for baseball field improvements such as corrugated yellow fence top protectors, a single base at first base with anchored home base, one centered scoreboard positioned 185 feet from home plate, and permanent pitcher's rubber placement. The addendum mandates outfield grassing and interior baseball field grassing totaling approximately 25,000 square feet using Certified Tiftway 419 Bermuda Grass sod with specific subgrade preparation requirements, and includes reset of two existing playground benches to straight and level in the grading line item.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00030 BidAdv.pdf | ||
| 2_Addendum_2.pdf | ||
| Eastside Park _ Award Letter.pdf | ||
| 00300 BidProposal.pdf | ||
| 1_Addendum_1.pdf | ||
| 4_Addendum_4.pdf | ||
| Bid Opening Notice.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF DOUGLAS, GEORGIA
SWE PROJECT # 23-3455
EASTSIDE PARK REHABILITATION
1. Addendum No. 3 to Advertisement for Bids due 2:00 PM, Tuesday, February 17, 2026, and all related
Contract Documents.
2. To all offerers.
3. Issued by: Project Engineer Statewide Engineering, Inc.
516 East Ashley Street Douglas, Georgia 31533 Contact: Stanley A. Evans. P.E.
Phone: 912-384-7723
4. The above-mentioned solicitation for bids is amended as set forth below. Offerers must acknowledge receipt of this addendum prior to the date specified for receipt of bids, as specified in the Advertisement for Bids, by the following method:
a. By signing and forwarding a copy of this addendum to Nicole.burke@swecivil.com prior to
February 17, 2026 at 9:00 am.
FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE SPECIFIED IN
THE SOLICITATION PRIOR TO THE DATE AND TIME SPECIFIED FOR RECEIPT OF BIDS MAY
RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment, you desire to change an offer already submitted, such change may be made by telegram, letter or facsimile provided such telegram, letter or facsimile makes reference to the solicitation and addendum numbers and is received prior to the date and time specified.
5. DESCRIPTION OF ADDENDUM: City of Douglas, Georgia Eastside Park Rehabilitation
The purpose of this addendum is to advise all bidders of the following:
1. Is a valid Georgia Utility License required for the project? The requirements for the Utility License are described in Attachment “I” in the Spec Book, but we are not requiring it for this project because we do not anticipate utilities to be installed at a depth greater than 4 feet.
2. Are we required to submit the Subcontractor Affidavits (Section 00480) with the bids, or can those be turned in once the contract is awarded? We do ask for all Sub-Contractors to be listed. Please turn in the Affidavits that you can with your bid. Any additional Sub-Contractor Affidavits will be required at the time the project is awarded by the City to the selected Contractor.
3. Does the fenced in area for the electrical racks in Addendum 2 need to be included in the baseball field fencing Line Item 1080? Yes.
4. Baseball field yellow fence top protectors shall be corrugated style. Installed on the foul line fences and outfield fence.
5. Any reference to compacted subgrade shall be 98% of the max dry density in accordance with ASTM D698.
6. There is only 1 scoreboard required for the project. It shall be located beyond the outfield fence, centered,+/- 185’ from home plate.
7. First base shall be a single base, not double as is typical in softball. Also note that the home base shall be anchored.
8. Permanent grassing for erosion control can be established with seed. Refer to sheet EC 3.0 Disturbed Area Stabilization Ds3 Notes.
9. Please include in Line Item 1020 Baseball Field a permanent pitcher’s rubber. This rubber will be in place when the portable mound is removed.
10. Please also include in Line Item 1020 Baseball Field outfield grassing and any grassing inside the baseball field fence shall be established with sod, +/- 25,000 SF. Sod shall be Certified Tiftway 419 Bermuda Grass. Subgrade shall be plowed a minimum of 17”. The top 5” shall be native topsoil mix.
Topsoil mix shall be a minimum of 80% sand, 10% organics, and 10% clay/loam. Contractor is responsible for the establishment and maintenance of the sod until Owner acceptance of the project.
11. Please include in Line Item 1120 Grading Complete a cost to reset the two existing benches at the playground to straight and level.
12. See attached for rough estimates on cut/fill quantities for the project.
13. REMINDER: Deadline for questions is February 13, 2026 at 9:00 AM