This is an exemption verification letter from the Northwest Florida Water Management District (NWFWMD) to the City of Tallahassee regarding the MLK Jr. Boulevard Stormwater Improvements Project (Application #PDEX-073-325542-1). The letter, dated July 21, 2025, confirms that the project is eligible for an exemption under 62-330.051(2) and will not require a District permit. The exemption also constitutes an express waiver of water quality certification under Section 401 of the Clean Water Act. The project addresses localized flooding at the intersections of Barbourville and Young with MLK Jr. Boulevard by reducing existing lane width, establishing positive longitudinal gutter grade, constructing new stormwater curb inlets, and installing an 18-inch reinforced concrete pipe (RCP) outfall that will connect to the existing City stormwater system at the Rudy Hubbard and MLK Boulevard intersection. The project will include reconstruction of the MLK Jr. northbound lane, curb, and gutter while preserving an existing 63-inch Live Oak tree.

The exemption verification applies only to the NWFWMD's regulatory requirements and does not relieve the applicant of meeting permit requirements from other agencies. Contact information for questions regarding the exemption was provided as Brandy Parker at (850) 951-4669. The document was issued by Selina Potter, P.E., Bureau of Regulatory Permits, with a Certificate of Service dated July 21, 2025, confirming proper notification to all applicable parties.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

July 21, 2025

Margaret A Bryant City of Tallahassee 408 N Adams St Tallahassee, FL 32301-1110

Re: MLK Jr. Blvd Stormwater Improvements Application # PDEX-073-325542-1 (Please reference the above number on all correspondence)

Dear Margaret A Bryant:

The Northwest Florida Water Management District (District) received your application on July 17, 2025 requesting an exemption verification for the referenced project.

Based on the information provided, the District has determined that the project is eligible for an exemption under 62-330.051(2). Therefore, the project will not need a District permit pursuant to rule reference.

This exemption also constitutes an express waiver of water quality certification under Section 401 of the Clean Water Act, 33 U.S.C. Section 1341. Pursuant to Rule 62-330.062, F.A.C., State Water Quality Certification is waived for activities that are exempt under rule 62-330.051 or 62-330.0511, F.A.C.

This exemption verification only applies to the requirements of the District and does not relieve you of meeting the permit requirements of other agencies. Please contact Brandy Parker at (850) 951- 4669 if you have any questions.

Sincerely, Selina Potter, P.E.

Bureau of Regulatory Permits

MLK Jr. Blvd Stormwater Improvements PDEX-073-325542-1

CERTIFICATE OF SERVICE

I hereby certify that on the below date, a true and correct copy of the foregoing document and all attachments were sent to the applicant and/or their representative(s), and any party having made a written request for notice of agency action, and that section 120.60(3), Florida Statutes has been satisfied.

July 21, 2025 Regulatory Support Specialist I Date

File details come from the government source that posted it. Updated .