About this file
This is a Special Provisions document for the City of Tallahassee's Martin Luther King Jr. Drainage Improvements Project in Florida. The project addresses chronic stormwater retention and localized flooding at the intersections of Barbourville Drive and Young Street with MLK Jr. Boulevard, as well as the northbound lane segment between these intersections. The scope of work includes reconstruction of the MLK Jr. northbound lane and curb and gutter, installation of new stormwater curb inlets and a new 18-inch reinforced concrete pipe (RCP) outfall that will connect to the existing City stormwater system at the Rudy Hubbard and MLK Boulevard intersection. The project will reduce existing lane width to establish positive longitudinal gutter grade while preserving an existing 63-inch Live Oak tree within the right of way. Two environmental permits have been secured by the City: a Northwest Florida Water Management District Environmental Resource Permit (Exemption Number PDEX-073-325542-1) and a City of Tallahassee Natural Features Inventory/Environmental Impact Analysis Exemption (TEX250027).
Construction operations are subject to distinct scheduling requirements based on project location. For residential areas (MLK Jr. Boulevard, Young Street, and Barbourville Drive), construction shall occur between 7:30 a.m. and 7:00 p.m. Monday through Friday, and 8:00 a.m. to 6:00 p.m. on Saturday, with no Sunday work permitted. For the collector roadway (Rudy Hubbard Way), construction shall occur between 9:00 a.m. and 4:00 p.m. Monday through Friday, and 8:00 a.m. to 6:00 p.m. on Saturday and Sunday. No construction operations that would disturb water, sewer, gas, or electric services are permitted on weekends. The City reserves the right to modify work and lane closure hours at any time without providing additional compensation to the contractor, though time extensions may be granted for City-directed restrictions.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROVISIONS
ENVIRONMENTAL PERMITS
Subarticle 7-2.1 of the Standard Specifications is expanded by the following:
The following permits have been secured by the City and apply to this Contract. Copies of these permits are included in the Supplemental Information section of these Contract Documents:
Northwest Florida Water Management District:
Environmental Resource Permit – Permit Exemption Number PDEX-073-325542-1
City of Tallahassee:
Natural Features Inventory / Environmental Impact Analysis Exemption – TEX250027
CONSTRUCTION OPERATIONS (RESIDENTIAL: MLK Jr. Blvd, Young Street, Barbourville Drive)
Subarticle 8-3.4 of the Standard Specifications is expanded by the following:
All construction operations shall be scheduled to begin no earlier than 7:30 am and to end no later than 7:00 pm Monday through Friday, and to begin no earlier than 8:00 am and to end no later than 6:00 pm on Saturday. No construction operations are to be scheduled on Sundays. No construction operations are to be scheduled on Saturdays if construction would cause a disturbance to water, sewer, gas, or electric services.
The City reserves the right to limit the Contractor’s work and/or lane closure hours at any time during the project duration from those hours identified within these documents. The Contractor agrees to make no claim for additional compensation as a result of this decision by the City.
However, the Contractor may be entitled to an extension of time for such acts by the City, only for the number of days which the City determines to be due to such acts.
CONSTRUCTION OPERATIONS (COLLECTOR ROADWAY: RUDY HUBBARD WAY)
Subarticle 8-3.4 of the Standard Specifications is expanded by the following:
All construction operations shall be scheduled to begin no earlier than 9:00 am and to end no later than 4:00 pm Monday through Friday, and to begin no earlier than 8:00 am and to end no later than 6:00 pm on Saturday and Sunday. No construction operations are to be scheduled on Saturdays or Sundays if construction would cause a disturbance to water, sewer, gas, or electric services.
The City reserves the right to limit the Contractor’s work and/or lane closure hours at any time during the project duration from those hours identified within these documents. The Contractor agrees to make no claim for additional compensation as a result of this decision by the City.
However, the Contractor may be entitled to an extension of time for such acts by the City, only for the number of days which the City determines to be due to such acts.