3-2503-066 QA No. 1 Flattened.pdf
PDF 1002 KB Posted
- Solicitation number
- GJ27-16
- Issued by
- Washington County, Hildale City, Utah
About this file
This is a Questions and Answers document issued by Hurricane City, Utah for the Sky Mountain Golf Clubhouse Remodel & Facility Addition Project (GJ27-16, Project No. 2503-066). The document, dated August 18, 2026, addresses bidder inquiries submitted prior to the mandatory pre-bid conference scheduled for September 1, 2026. Questions regarding the project must be submitted by September 3, 2026, no later than 5:00 PM MT to Kim Campbell (kim.c@campbelldesign.us) and Emily Hansen (emily.h@jonesanddemille.com). Bid submissions are due by September 10, 2026, no later than 11:00 AM MT at the Office of 147 North 870 West, Hurricane, Utah 84737. Bidding documents are available at https://contractors.jonesanddemille.com/. The document confirms that Hurricane City does not intend to change the bid opening date and references Addendum No. 1 regarding specification details for louver width.
This Q&A document provides clarification on technical specifications and project timeline but contains no information regarding pricing terms, contract value, funding sources, set-asides, or incumbent contractors. Bidders are advised to review the complete solicitation documents to ensure compliance with all requirements, as this posting serves as a courtesy advertisement only and Hurricane City retains responsibility for final procurement decisions and award notifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hurricane City Questions and Answers No. 1 Sky Mountain Golf Clubhouse Remodel (2503-066) Page 1 of 1
QUESTIONS AND ANSWERS NO. 1
DATE: AUGUST 18, 2026
1. What is the width of the louver?
a. See Addendum No. 1
2. Would it be possible to shift the bid date?
a. Hurricane City (Owner) does not intend to change the bid opening date.
Signed: Kim Campbell, Architect
END OF Q&A