3-2. RFP Wildlife Crossing Specifications.pdf

PDF 184 KB Posted

Attached to
US36 Wildlife Crossings 30% Engineering Design Project
Solicitation number
RFP-332-26
Issued by
Boulder County, Colorado

About this file

Summary

This file contains specifications for wildlife crossings as part of the US-36 Wildlife Crossings 30% Engineering Design Project, a collaborative effort between Boulder County Parks & Open Space (BCPOS), the Colorado Department of Transportation (CDOT), and Colorado Parks and Wildlife (CPW). The project solicits proposals from qualified engineering design contractors to develop 30% CDOT design plans, technical specifications, and detailed cost estimates for a multi-species wildlife crossing system on US-36 in Boulder County between Left Hand Creek (Milepost 27.95) and St. Vrain Creek (Milepost 21.8). The design scope includes one overpass and three underpasses with associated exclusionary fencing, jump-outs, existing structure improvements, road and driveway improvements, construction access points, and staging areas. The primary infrastructure footprints are located within CDOT's Right of Way, with the exception of the proposed overpass location, which will also involve BCPOS property, and any additional property impacts will be identified during the design phase.

The project represents a large multi-year effort for Boulder County, with this initial phase focused on generating the 30% design deliverables necessary for advancement. Specific response dates, due dates, site visit requirements, and bidder's conference details are not explicitly stated in the file provided. Pricing terms, funding sources, contract duration, and renewal options are not documented in this specifications document. Contractors interested in this opportunity should reference the Boulder County procurement process submittal instructions and direct inquiries to procurement@bouldercounty.gov.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

Boulder County Parks & Open Space (BCPOS) seeks professional engineering services to further develop the Boulder County US-36 Wildlife Crossings 30% Engineering Design Project from a ~10% plan to a 30% plan set ready for the Colorado Department of Transportation (CDOT) to accept for final design and construction. The Contractor is expected to follow processes and guidelines provided by the Colorado Department of Transportation (CDOT) when conducting this project. The CDOT Roadway Design Guide (latest online version of each Chapter) is expected to guide the design of this Project, notably Chapters 11-17. Construction Specifications will also follow CDOT Construction Standard Format and latest online version at the time of work. The CDOT Style Guide for Writing Specifications latest version will also be a guiding document.

Consultant coordination will be required with, but not limited to, the following known agencies:

CDOT, CDOT Specialty Units (Utilities, ROW, Environmental, ITS, Traffic, Geotechnical, Staff Bridge), Federal Highway Administration (FWHA), CPW, U.S. Fish and Wildlife Service, U.S. Army Corps of Engineers, Boulder County Departments, City of Boulder, Town of Lyons, and interested public groups. The design will also assume federal funding criteria from the Federal Highway Administration (FHWA).

The Contractor is expected to build upon the previous work that produced the reports in Attachments E and F, the US36 Wildlife Crossing Assessment, Prioritization and Cost Estimation Study and the Refined Recommendations - Wildlife Crossing System on US Highway 36 Reports.

The most recent report (Dudek, 2026) reviewed and refined the recommendations made by the prior report (Benesch, 2024). The refined designs (Dudek, 2026) have been reviewed, accepted and are supported by CDOT, Colorado Parks and Wildlife (CPW), City of Boulder, and the Town of Lyons. The current designs have identified potential underpasses at MP 22.6, MP 25.0, and MP 26.3; a potential overpass at MP 24.75; and potential tie-ins and enhancements to the existing bridge crossings at MP 21.8 (St. Vrain Creek) and MP 27.95 (Left Hand Creek): see Attachment A:

Project Vicinity Map, and Attachment B: Refined Crossing Structure Recommendations Map for more detail. The Contractor will evaluate each for fatal flaws and if found, recommend other topographical locations if needed and assess those locations.

This Project builds upon the previous groundwork of wildlife activity and topographical fit and is intended to meet the following goals:

1. Assess the constructability of the proposed underpass and overpass locations and evaluate alternate locations if needed; utilize expert data collection and review including but not limited to:

2. Road ecology site surveys

3. Transportation investigations to support road modifications

4. Topographic surveys for structures and fencing including CDOT right of way boundaries and surface and subsurface utility identification (Quality Level B- QL-B)

5. Geotechnical investigations and reports in all areas proposed for earthwork

6. Structural engineering design to meet existing conditions

7. Incorporation of environmental reviews related to wildlife and vegetation communities which may be impacted, working closely with BCPOS Wildlife Team and BCPOS Plant Ecology Team

8. Incorporation of cultural resources information provided by the BCPOS Cultural Resource Program Coordinator and follow up on any identified areas, including records review, identification of potential direct or indirect effects to cultural resources, and recommendations for additional survey, documentation, or other cultural resources review as appropriate.

9. Identify critical issues and solutions associated with the design, construction and implementation of the wildlife passage project crossings and system

10. Current ~10% designs accommodate the North Foothills Bikeway, but full assessment of needed infrastructure modifications for the bikeway must be identified. Coordination with the North Foothills Bikeway Design Team is critical and expected

11. Prepare a 30% CDOT plan set, 30% CDOT general and technical specification set, and 30% CDOT construction cost estimate and bid schedule. This will include proposed staging areas and traffic control plans. Inclusion of a Structure Selection Report is required.

12. Provide permit-ready exhibits and marketing materials for use by stakeholders to start the 1041 permit process, raise awareness, and apply for funding for the next phase of the project

The Contractor must provide a 2026-2027 rate sheet for all staff that may be engaged in all tasks.

ADD ALTERNATE PROPOSALS:

The County has described in the Specifications and specified Tasks how the Project is envisioned by the County’s Project Team. Combining tasks in assumed order of sequential completion milestones, allows for levels of completion to be accomplished as separate but related deliverables, to allow for funding flexibility. A bid is required for all five tasks and three packages (base package, Add Alternate A and Add Alternate B), as funding is anticipated for all tasks. Only the timing of the funding is currently unknown but listed in the deliverable section with specific dates listed for each Add Alternate to be initiated through separate Notices to Proceed and separate kickoff meetings.

BASE PACKAGE:

Task 1 - Project Management and Partner Coordination:

Major items of work include, but are not limited to:

1. Project Management and Partner Coordination:

a. Every 2 weeks: Contractor shall manage all meetings and provide meeting agendas and minutes (within one week of meeting) for project meetings scheduled approximately every two weeks and additional design and report review meetings

b. Provide presentations and graphics for these meetings including all coordination

c. Host the meeting, present progress to attendees, and record feedback

2. Contractor shall coordinate and lead quarterly agency partners/leadership meetings (including Colorado Parks and Wildlife (CPW), the Colorado Department of Transportation (CDOT), City of Boulder Open Space and Mountain Parks, Town of Lyons and others.

3. Detailed project schedule: provide a Microsoft Project schedule with detailed milestones and actions required to complete the project including all deliverables. Track milestones as project progresses

4. North Foothills Bikeway Coordination: Contractor to coordinate with the Boulder County North Foothills Bikeway Project, and particularly their consultant, on data sharing, and environmental, cultural, topographic and geotechnical investigations. Ongoing coordination as designs for both projects advance is required to identify areas of conflicting design components.

Task 2 - Site Assessments and Investigations:

Following an initial review and analysis of the background and technical information review, the Contractor shall conduct a meeting with BCPOS to review the information and to develop a list of critical path items for project assessment and design deliverable preparation.

Coordination will be required with, but not limited to, the following known agencies: CDOT; CDOT Specialty Units including Utilities, ROW, Environmental, ITS, Traffic, Geotechnical, Staff Bridge;

FHWA; Colorado Parks & Wildlife; Boulder County Departments including Community Planning & Permitting and Public Works; City of Boulder; landowners along the impacted corridor; and a variety of interested parties not yet identified.

The Contractor shall perform all necessary site assessments and investigations within the planning area to complete the Project, which may include, but not limited to, the following:

1. Site visits to assess existing conditions

2. Site surveys to a level of detail suitable to have an accurate design

3. Geotechnical investigation and other engineering investigations needed for the 30% engineered solution

a. Geotechnical borings, site investigation, analysis and geotechnical report. This includes one test hole at each potential crossing location. Soil samples will be collected by standard penetration tests. Selected soil samples will be tested to determine classifications, moisture, density, resistance values, pH, and sulfites.

Bedrock samples will be collected and evaluated

b. The geotechnical report will include a summary of bore logs, laboratory testing, retaining wall foundation redesign, shallow foundation design, deep foundation design, and lateral resistance values. The report will include Engineering Geology sheets indicating location of borings

c. The report shall identify geologic hazards, in the vicinity of the project, and shall determine if these features will be impacted by construction. In the event disturbance of geologic hazards is anticipated due to construction, mitigation to reduce the risks of disturbance to the sensitive area shall be recommended

d. Identification of geotechnical issues and concerns associated with locations

4. Procurement and review of any as-built documentation of existing CDOT and utility infrastructure and original bridge and road design and construction documents

5. Design Hydraulics and Hydrology: provide flow analysis and storm sewer requirements on how to drain the overpass and underpass bridge and consideration of ponding in the underpasses and existing structure retrofits

6. Identify wetlands in crossings areas utilizing standard wetland delineation techniques and field documentation. Provide mapping of locations of wetlands and mitigation strategies if needed. A wetland delineation report will be prepared in addition to field work and mapping. Coordinate with the North Foothills Bikeway project team on currently available wetland mapping efforts for the corridor to inform additional survey efforts.

7. Traffic and Safety Impacts: review traffic counts and Region 4 Lane Closure strategies and provide recommendations for maintaining traffic during construction. Include a discussion of potential safety issues related to traffic and operations in the areas of the crossings. Identify the potential impacts to traffic as a result of the proposed construction and identify mitigation strategies. Review ADT, seasonal considerations, accident history related to WVDs, Region 4 lane closure policy, available detours, and acceptable design speed and evaluate the effects of these factors on construction cost and time. Provide Conceptual Detour of phasing plans as appropriate to ensure traffic is maintained during construction

8. Coordinate with partners, landowners and the North Foothills Bikeway Team to incorporate required features related to the Bikeway path, driveways, road tie-ins, gates, fencing, passages and other influences

9. Right of Way evaluation: review County provided mapping for easement line and evaluate potential impacts outside of that easement

10. Incorporation of review comments from internal and external partners

All site assessments and investigations shall be incorporated as appropriate into Design Deliverables.

Add Alternate A:

Task 3 - 30% CDOT Plans and Specifications:

A preliminary draft 30% Design Plan Set and Technical Specifications and final draft 30% Design Plan Set and Technical Specifications shall be submitted for review and approval by BCPOS, Boulder County Bikeways Team, and agency partners. The Contractor shall provide changes as necessary to the design plan and written responses to all comments or edits made by Boulder County and partner reviewers.

The Contractor shall prepare Specifications for the Project based on Colorado Department of Transportation (CDOT) standards, and provided BCPOS specifications for revegetation, stormwater control and cultural and environmental protection. The Specifications shall cover all aspects of the Project, not limited to a detailed summary of work, engineers estimate, bid schedule, measurement & payment, and associated Project Special Provisions and Standard Special Provisions.

Expected Plan Sheets (not all inclusive): title sheet; standard plans list; general notes; typical sections; summary of approximate quantities (per structure); tabulation of earthwork (per structure); tabulation of removals and fencing (per road mile); tabulation of guardrail and surfacing (per structure); tabulation of delineators and drainage (per structure); survey tabulation sheet; project control diagram; removal plans (per structure); geometric layout (per structure); US-36 plan and profile (per structure); detour plan and profile (per structure); US-36 and other impacted roads detour cross sections (per structure); grading plan (per structure);

drainage plan and profile (per structure); wildlife fencing plan; deer ramp locations; fencing details; bridge drawings; shoring; pile slicing; culvert drawings; existing bridge and culvert enhancement drawings; stormwater management plan (per structure and fencing); SWMP site maps; revegetation plan including schedule, notes, details, seed mixtures (per structure and fencing); tabulation of signs and pavement markings; US-36 signing and striping plan; tabulation of construction traffic control; phasing plan; landscape plans; utility plans; ITS plans; US-36 cross sections.

Task 4 - 30% Construction Cost Estimate and Bid Schedule:

The Contractor shall provide quantities and 2030 cost estimates for each bid item design element necessary to construct all proposed structures and required fencing. Also provide Microsoft Project schedule identifying high level milestones associated with final design and construction of the project.

Add Alternate B:

Task 5 - Exhibits and Outreach Material Preparation:

Provide permit-ready exhibits for use by Boulder County to start the 1041 permit process, raise awareness, and apply for funding for the next phase of the project.

Provide professionally prepared marketing materials for use by project partners for donation solicitation as well as awareness of the project.

1. Materials to include high-quality renderings of the overpass, and at least one of the underpass structures

2. Microsoft PowerPoint presentation

BOULDER COUNTY RESPONSIBILITIES:

1. Provide the Contractor with a Notice to Proceed (NTP), indicating approval to proceed with the work and phases described herein

2. Designate a person to act as the County’s contact with respect to the services related to this project. The County will monitor all scopes of work and be available during normal business hours and days of the week to answer any questions, and address any issues that may arise

3. Provide the Contractor with all available information pertinent to completing project deliverables

4. Work with County and CDOT to provide LiDAR data of project limits, high resolution aerial photos, and horizontal alignments in InRoads of the as-built mainline

BCPOS will work with the Contractor throughout the Project and review all draft and final documents and provide comments to the Contractor within two (2) weeks of submittals.

CONTRACTOR RESPONSIBILITIES:

The Contractor shall provide all work necessary to complete Tasks.

General Terms:

All engineering reports must be prepared under the direction of and stamped by a professional engineer or engineer currently licensed in the State of Colorado.

The design documents must be in conformance with generally accepted engineering practices and comply fully with all applicable codes and regulations, anticipated permits, as well as any potential funding agency requirements.

Two hard copies of all work products will be delivered together with all electronic files.

In addition to hard copies of all reports and design documents, all reports and written documentation shall be submitted electronically as Microsoft Word files and design documents shall be submitted as AutoCAD 2026 or equivalent electronic drawing file (most current electronic versions). Additionally, submittals are required to be in compliance with the Data Requirements listed in this RFP.

All contractors need to maintain professionalism if interacting with members of the public.

Promptly communicate any conflicts or concerns that may arise to the BCPOS Project Manager.

Subcontractors:

The Contractor is required to disclose to Boulder County the complete business name(s), Statement of Qualifications and proof of insurance for all potential subcontractors that will be assigned to this project before work begins.

Boulder County reserves the right to deny the services of subcontractors that are deemed unqualified to complete specific contract deliverables.

Contractor acknowledges complete responsibility for the actions or inactions of its subcontractors.

Contractor will be responsible for the compliance of all subcontracting parties with the terms of the contract and with any applicable local, state or federal laws or regulations.

Contractor shall be solely responsible for the timely payment of its subcontractors.

DELIVERABLES:

1. 1/11/27 Estimated NTP issued by County for BASE PACKAGE

2. 1/19/27 Kickoff meeting to review Contractor proposed project schedule and discuss initial background investigation and plans for environmental reviews including coordination with BCPOS Wildlife Team, BCPOS Plant Ecology Team, BCPOS Cultural Resource Program Coordinator and Boulder County US-36 North Foothills Bikeway Team

3. On-going meeting facilitation and project schedule updates; meeting agendas and minutes for weekly meetings, monthly meetings with the Bikeways Team to coordinate the data sharing and collection efforts and design concepts, and quarterly agency partners/leadership meetings (including Colorado Parks and Wildlife (CPW) and the Colorado Department of Transportation (CDOT)

4. On-going Coordination with the Boulder County US-36 North Foothills Bikeway Team on preliminary design and environmental, cultural, topographic and geotechnical investigations

5. 1/20/27 Initiation and 2/16/27 completion of topographic surveys for structures and fencing including CDOT right of way boundaries and surface and subsurface utility identification (Quality level B)

6. 1/20/27 Initiation and 6/1/27 completion of geotechnical investigations and reports in all areas proposed for earthwork

7. 2/3/27 Estimated: NTP issued by County for ADD ALT A

8. ADD ALT A estimated kickoff meeting: 2/8/26

9. 2/16/26 Submittal of 30% Plan sheet list

10. 2/22/27 – 03/19/27: Contractor coordinates with BCPOS Cultural Resource Program

Coordinator and incorporates County-provided cultural resources screening information into development of the 30% design.

11. Beginning 3/22/27: Contractor follows up, as directed by the BCPOS Cultural Resource Program Coordinator, on locations identified through cultural resources screening, including potential impacts to historic properties, proximity to known archaeological resources, potential direct or indirect effects, and areas where additional survey or documentation may be warranted.

12. 3/31/27 Estimated: NTP issued by County for ADD ALT B

13. ADD ALT B estimated kickoff meeting: 4/5/27

14. 9/1/27 Provide permit-ready exhibits for use by Boulder County to start the 1041 permit process

15. 9/15/27 Submittal of draft 30% plans, specifications and cost estimate for BCPOS review

16. 9/29/27 Receipt of BCPOS and partner comments on plans and incorporation 9/30/27-

10/15/27

17. 10/15/27 Submittal of final 30% plans for BCPOS review

18. 11/1/27 Submittal of professionally prepared marketing materials for BCPOS review

19. 11/17/27 Submittal of all deliverables (reviews incorporated) to BCPOS

20. 12/8/27 Submittal of final invoice to BCPOS

PERMITS, LICENSES, LOCATES AND CODES:

The selected Contractor shall have full responsibility for identifying and obtaining, prior to the start of work, and for maintaining throughout the term of the Project, any permits and licenses which may be required in order to carry out the work. The Contractor shall also be responsible for following all State and County codes, which may be required in order to carry out the Project.

The Contractor shall also be responsible for all "locates" of all public utilities related to performing work under the terms of this Contract. The Contractor shall also be responsible for insuring that any of its subcontractors performing work on the Project satisfy the provisions of this paragraph.

Contractor is responsible to contact and coordinate with utility companies regarding protection of existing utilities and special requirements at utility crossing locations, as well as other conditions where work is nearby existing utilities. Contractor shall be responsible for all costs of coordination with utilities including, but not limited to, outages, protection or support and any fees for costs from the utility.

CONTRACTOR LICENSING:

It is the responsibility of the selected Contractor to apply for and ensure the appropriate Contractor’s license is obtained.

General contractors, HVAC contractors, and roofing contractors require licensing through the Boulder County Community Planning and Permitting Department. Electricians and plumbers are required to be licensed through the State of Colorado and registered with the Boulder County Community Planning and Permitting Department. Furthermore, it is required for all Architects, Professional Engineers and Professional Land Surveyors to be fully-licensed through the State of Colorado.

SUBCONTRACTORS:

Contractor is required to disclose to County the complete business name(s), Statement of Qualifications (SOQ), and proof of insurance for all potential subcontractors that will be assigned to this Project, should the Contractor be selected. Contractor acknowledges that it is completely responsible for the actions or inactions of its subcontractors. Contractor shall be responsible for the compliance of all subcontracting parties with the terms of the Contract and with any applicable local, state or federal laws or regulations. Contractor shall be solely responsible for timely payment of its subcontractors. Boulder County reserves the right to deny the services of subcontractors that are deemed unqualified to complete specific contract deliverables.

PROJECT COMPLETION SCHEDULE:

The date of completion will be on or by Friday, December 8, 2027.

CONFLICT OF INTEREST:

Any party that has developed, designed or drafted specifications, requirements, statements of work and/or has participated in planning activities for this Project may be excluded from consideration for the award of this Project.

CHANGE ORDERS:

Any unplanned, change orders, modifications or additional services to this Project, shall be submitted by the Contractor, in a separate, written document, including a fee schedule and completion schedule and presented to the County for review. Approval from the County, in writing, must accompany all change order requests.

OVERNIGHT CAMPING:

Boulder County prohibits any overnight camping; all operational staff, including designated security staff, are not authorized to be present at Project site from sunset to sunrise, the open space property will remain closed during these hours to the contractor and its subcontractors and/or designated representatives and/or agents, unless specifically authorized by a BCPOS representative.

HOURS OF OPERATION:

Contractor work hours shall be designated as Monday through Friday, as required. Work on Saturdays and Sundays, nights, and designated Federal Holidays shall not be allowed unless approved, in writing, by the County.