This is a Request for Proposal (RFP) issued by Boulder County Parks and Open Space (BCPOS) in partnership with the Colorado Department of Transportation (CDOT) and Colorado Parks and Wildlife (CPW) for engineering design services. The RFP seeks qualified contractors to develop 30% CDOT design plans, technical specifications, and detailed cost estimates for a wildlife crossing system on US-36 between Boulder and Lyons, specifically between St. Vrain Creek (MP 21.8) and Left Hand Creek (MP 27.95). The proposed system will include one overpass, three underpasses, and associated mitigation components such as exclusionary fencing, jump-outs, and driveway improvements to reduce wildlife-vehicle collisions and improve habitat connectivity. The project addresses the identified high-priority wildlife crossing corridor in the top 5% of problematic road segments in CDOT regions, with 40% of Boulder County's reported wildlife-vehicle collisions occurring in this stretch between 2010 and 2020. A mandatory pre-proposal meeting is scheduled for November 18, 2026, at 10:30 a.m. MST via Microsoft Teams, and proposals from firms not represented at this meeting will not be accepted. Work will not commence until the County issues a Notice to Proceed following contract execution.
The selected contractor will be compensated on a time and materials basis, with payment retained until all data deliverables are 100% compliant with County requirements. Contractors must submit invoices on company letterhead detailing project name, dates, work performed, invoice number, amount due, and current return address, subject to the terms and conditions of the Boulder County-issued Purchase Order. Prior to work commencement, the contractor must provide a current Certificate of Good Standing authorizing business operations in Colorado, comply with all applicable sales and employment taxes, and maintain current insurance certificates meeting the minimum coverage requirements specified in Exhibit A, with no exemptions for owner/sole proprietors or officers. The project is being coordinated in parallel with the Boulder County North Foothills Bikeway Project, and any cost savings from combined survey efforts with that project will be applied to unanticipated time and materials costs within the existing scope of work. The contractor must be authorized to conduct business in Colorado and meet all Boulder County insurance and procurement requirements.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROPOSAL INFORMATION/INSTRUCTIONS
BACKGROUND
The US-36 highway corridor between Boulder and Lyons has been identified as the most problematic in Boulder County for human and wildlife safety due to Wildlife Vehicle Collisions (WVCs). This priority identification comes from several sources and is described in the Colorado Eastern Slope and Plains Wildlife Prioritization Study (ESPWPS) conducted by Colorado Department of Transportation (CDOT) and Colorado Parks and Wildlife (CPW) (link Prioritization Studies – Colorado Wildlife and Transportation Alliance) and released in April 2022. The stretch of US-36 between Nelson Road and Hygiene Road was identified in the ESPWPS as being in the top 5% of problematic road segments in CDOT Regions 1, 2 and 4. Scoring was based on modeling inputs including mortality numbers for focal species, total Wildlife Vehicle Collisions (WVCs), and other inputs. US-36 spans the foothills/plains transition zone within an area of significant acreage supporting migratory wildlife, as well as non-migratory wildlife with larger home ranges. Many individual animals attempt to cross the highway due to seasonal migratory patterns and/or necessary movements to access food resources.
Boulder County's Transportation Management Plan, Update 2020, also concluded that the US-36 section between St. Vrain Creek and Left Hand Creek has the highest probability of high-cost and fatal vehicle crashes with wildlife. The Update shows that 40% of all reported WVCs in Boulder County between 2010 and 2020 occurred within this road stretch.
Wildlife crossings are a proven strategy for reducing human impacts from WVCs, particularly with large and medium-sized fauna, while simultaneously maintaining or restoring wildlife connectivity across transportation corridors. Effective systems function by preventing wildlife access to the roadway and providing animals with secure, designated crossing opportunities that provide safe passage under or over the highway. Within the US-36 corridor, the effectiveness of a wildlife crossing system is enhanced by the extensive network of protected open space, conservation easements, public lands, and undeveloped habitat located both east and west of US-36. Permanent protection of natural habitats and working lands helps ensure the long-term functionality of wildlife infrastructure investments by maintaining habitat quality, reducing future barriers to movement, and preserving landscape connectivity.
This wildlife crossing project seeks to improve the safety of motorists driving the US-36 Corridor by decreasing wildlife-vehicle-collisions (WVCs) as well as swerving and rollover crashes, and improve the safety of wildlife in the region by connecting habitat and decreasing mortality rates.
Since 2024, Boulder County Parks and Open Space (BCPOS) has worked with two consultant teams to produce two commissioned reports which have identified a strategy for a system of wildlife crossings that considers crossing types, locations, spacing and associated features (exclusion fencing). This Project is proposed as a 30% design as a milestone of completion towards continued and future partner led (CDOT, CPW) design levels and eventual construction. The Project is being planned in parallel with the Boulder County North Foothills Bikeway Project as both projects are in the same transportation corridor and will affect each other, US-36 neighboring properties, and the overall landscape https://www.coloradowta.com/prioritization-studies/ https://www.coloradowta.com/prioritization-studies/ https://assets.bouldercounty.gov/wp-content/uploads/2024/08/cpp-north-foothills-bikeway-feasibility-study-20240726.pdf.
The existing wildlife crossing system plan includes incorporation of two existing creek bridge crossings, one overpass, and three underpasses intended to provide crossing opportunities for a range of large-, medium-, and small-bodied wildlife species. Current locations proposed are (See Attachment B):
• MP 22.6 arch or bridge underpass
• MP 24.75 bridge overpass
• MP 25.0 arch underpass
• MP 26.3 bridge underpass
• Tie-in to the existing bridge crossings at MP 21.8 (St. Vrain Creek)
• MP 27.95 (Left Hand Creek)
Additional planned mitigation components—including multi-species wildlife exclusion fencing, escape ramps (jumpouts), deer guards (at driveways, roads), and other supporting infrastructure—are critical to the overall effectiveness of the crossing system.
With review and approval from CDOT and CPW, the current approach applies a multi-focal species framework that considers species-specific movement patterns, habitat associations, and crossing requirements to determine crossing locations and spacing. The current design recommendations also account for foreseeable future changes that may influence wildlife movement patterns and crossing effectiveness, including implementation of the Boulder County North Foothills Bikeway along US-36, potential wildlife exclusion fencing associated with Department of Commerce- NTIA facilities on Table Mountain, and other future changes in land use, transportation infrastructure, wildlife management, or environmental conditions.
The selected firm will perform survey, geotechnical investigations, constructability analysis, cost estimation, and more to inform the 30% design. There may be cost savings associated with combining efforts with the Boulder County North Foothills Bikeway Team project existing survey efforts (Right of Way boundaries, surface and subsurface utilities, geotechnical), but this will be a time and materials contract and thus any cost savings will be applied to unanticipated time and materials costs within the existing scope of work that may arise during the project time frame.
CONTRACT LANGUAGE:
The selected proposer will be required to enter into a Boulder County Procurement Contract and meet all insurance requirements as required prior to any work beginning. Work will not commence until the County has issued a Notice to Proceed to the selected Contractor.
In the event the selected Contractor is unable to commence work as agreed to, the County may rescind the RFP award and proceed to award the contract to another proposer based on the RFP or proceed in any lawful manner the County deems necessary.
https://assets.bouldercounty.gov/wp-content/uploads/2024/08/cpp-north-foothills-bikeway-feasibility-study-20240726.pdf https://assets.bouldercounty.gov/wp-content/uploads/2024/08/cpp-north-foothills-bikeway-feasibility-study-20240726.pdf
AUTHORIZATION TO START WORK:
The selected Contractor will be issued a Notice to Proceed (NTP) once the contract has been executed. Work shall not commence until the Contractor has received the NTP from the County.
CERTIFICATE OF GOOD STANDING:
A copy of your business’ State issued certificate is required, if awarded. Contractor shall be authorized to do business in the State of Colorado and shall provide the County with a current Certificate of Good Standing evidencing such authorization. Furthermore, Contractor shall be responsible for all applicable sales and employment taxes.
INSURANCE REQUIREMENTS:
The insurance requirements are specified in Exhibit A. Current Insurance Certificates must be on file with the Parks and Open Space Department prior to any work relating to this Project commencing.
All proposers are instructed to thoroughly review all the stated insurance requirements for this Project, the insurance requirements stated are the minimum and standard for Boulder County Government, for this Project. All hired contractors are required to meet the insurance requirements, as stated, for contracted services as part of the Boulder County contracting process. Owner/Sole Proprietors/Officer are not exempt from the county’s insurance requirements and coverage limits. Please refer to the Insurance Requirements in this RFP.
THIS OFFICE IS OPEN MONDAY THROUGH THURSDAY FROM 8:00 A.M. THROUGH 4:30 P.M.
PAYMENT FOR SERVICES:
Contractors are instructed to review the Data Requirements section specifically for all data related deliverables. Payment will be retained until the data submitted is 100% compliant with the County requirements as detailed.
The selected Contractor will be paid on a time and materials basis.
Contractor shall submit, in writing, to Boulder County, a request for payment. Invoices shall be submitted on company letterhead and include, but not limited to, depending on the activity completed, designated project name, date(s), type of work performed. Additionally, all invoices should contain the current date, invoice number, amount due and current return address.
Additionally, payment for Project awarded is subject to the terms and conditions of the Boulder County issued Purchase Order.
PRE-PROPOSAL MEETING:
A Mandatory Pre-Proposal meeting is scheduled, starting promptly at 10:30 a.m. MST on November 18, 2026, via Microsoft Teams. See Pre-Proposal Meeting Information document for details.
Proposals from firms not represented at the mandatory pre-proposal meeting will not be accepted.
ATTACHMENTS:
The following documents and attachments are included in this RFP.
Specifications Evaluation Criteria Data Requirements Proposal Tab Sample contract Pre-bid meeting information EXHIBIT A – Insurance Requirements issued by Boulder County Risk Management Attachment A: Project Vicinity Map Attachment B: Refined Crossing Structure Recommendations Map Attachment C: Contractor Qualification Statement Attachment D: US 36 Wildlife Crossing Assessment, Prioritization and Cost Estimation Study Attachment E: US 36 Structure Figures Attachment F: Refined Recommendations Wildlife Crossing System on US Highway 36 Boulder County