This is a Performance Work Statement (PWS) for Facilities and Lighting Maintenance Services at Joint Base Pearl Harbor Hickam, Oahu, Hawaii, under solicitation number N6247826R2431. The contract is an Indefinite Delivery Indefinite Quantity (IDIQ) performance-based service acquisition with a base period and four option periods, plus an option to extend services. The scope encompasses both recurring and non-recurring work including facilities maintenance, repair, alteration, and lighting services across multiple Navy installations on Oahu, with work organized into 18 annexes covering general information, management and administration, and technical requirements for facility systems such as swimming pools, solar hot water systems, HEMP shelters, photovoltaic systems, reverse osmosis systems, high security doors, and interior/exterior lighting systems across numerous buildings totaling hundreds of thousands of square feet.

Key technical requirements include preventive maintenance programs performed at specified frequencies (daily, monthly, quarterly, semi-annual, annual, and biennial schedules); emergency, urgent, and routine work response times (1 hour, 5 working days, and 30 calendar days respectively); NAVFAC Maximo computerized maintenance management system data entry and reporting; comprehensive safety and environmental compliance programs; quality management and inspection systems; and specialized personnel requirements including a Project Manager, Quality Manager, Site Safety and Health Officer, Environmental/Energy Manager, and various certified technicians. Contractor-furnished items include all labor, equipment, tools, and materials; the Government furnishes facilities, utilities at standard rates, and Government-furnished property in as-is condition. The contract incorporates extensive security requirements including DBIDS access control, background investigations, controlled information protection, and access restrictions to sensitive areas at Pearl Harbor Naval Shipyard and other installations. Non-recurring work is priced using unit priced labor (UPL) and unit priced tasks (UPT) with coefficients applied to a government unit price list; recurring work pricing uses monthly, quarterly, and annual unit prices across multiple ELINs organized by facility and work type.

View the file

Other files

File Type Posted
26R2431_Amend06.pdf PDF
26R2431_Amend04.pdf PDF
26R2431_Amend03.pdf PDF
26R2431_Amend02.pdf PDF
26R2431_RFIs_No2_05292026.pdf PDF
26R2432_RFI_No1_05192026.pdf PDF
26R2431 PreProposal_AttendanceSheet.pdf PDF
26R2431 PreProposal_Brief.pptx PPTX presentation
26R2431 Notices and Attachments_Amd01.pdf PDF
Attach 2_Request For Information.xlsx XLSX spreadsheet
26R2431 Notices and Attachments.pdf PDF
WD 15-5689.pdf PDF
26-2431 OPS.xlsx XLSX spreadsheet
Solicitation - N6247826R2431.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

14-26-2431 0100000, Page 1 of 4

0100000 – General Information Spec Item Title 1 General Information

1.1 Outline of Services

1.2 Acquisition of Additional Work

1.3 Background Information

1.4 Navy PBSA Approach

1.5 Standard Template

1.6 Related Information

1.7 Verification of Workload and Conditions

1.8 Contractor's Knowledge

1.9 Technical Proposal Certification

0100000, Page 2 of 4

0100000 – General Information Spec Item Title Description 1 General Information

1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work Statement (PWS) for FACILITIES AND LIGHTING MAINTENANCE SERVICES at Joint Base Pearl Harbor Hickam, Oahu, Hawaii and outlying areas supported by this installation by means of a performance-based contract that is comprised of both Recurring Work and Non- Recurring Work Items.

The PWS is organized into annexes. Annex 1 is "General Information".

Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements.

The annex numbers are identified as 1 through 18 in the description column, but the fully expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).

Annex 1 General Information Annex 2 Management and Administration Annex 3 Command and Staff – Not Applicable Annex 4 Public Safety – Not Applicable Annex 5 Air Operations – Not Applicable Annex 6 Port Operations – Not Applicable Annex 7 Ordnance – Not Applicable Annex 8 Range Operations– Not Applicable Annex 9 Health Care Support– Not Applicable Annex 10 Supply– Not Applicable Annex 11 Personnel Support– Not Applicable Annex 12 Morale, Welfare and Recreation Support – Not Applicable Annex 13 Galley– Not Applicable Annex 14 Housing– Not Applicable Annex 15 Facilities Support

Annex 1502000 Facilities Investment Annex 16 Utilities – Not Applicable Annex 17 Transportation– Not Applicable Annex 18 Environmental– Not Applicable

1.2 Acquisition of

Additional Work

The Government reserves the right to acquire additional services at additional locations, within the scope of the annexes and areas included in Spec Item 1.1 Outline of Services, in addition to the services and locations identified in the requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the non-recurring work provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.

1.3 Background Information Facility Maintenance & Repair Services have been typically performed by means of a combination Indefinite Delivery Indefinite Quantity type, performance-based contract that is comprised of both Recurring and Non- Recurring Work Items.

1.4 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts, which are 1) performance outcomes, 2)

0100000, Page 3 of 4

0100000 – General Information Spec Item Title Description measurable standards, 3) consideration of incentives, and 4) performance assessment plan.

1.5 Standard Template Key to implementing the PBSA approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs.

The standard template contains 18 standard annexes. Annex 1 will always contain General Information that is relevant to the entire scope of the contract. Annex 2 contains Management and Administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 and their associated sub-annexes contain the General Information, Management and Administration requirements, Performance Objectives, Related Information, and Performance Standards that are relevant to that technical annex. Except where otherwise stated, Annexes 3 through 18 and their associated sub-annex requirements are not relevant to one another. Within each technical annex and sub-annex, the organization of information and requirements are also standardized. Specification Item 1 will always contain General Information. Specification Item 2 will always contain the Management and Administrative requirements. Specification Item 3 will always contain the Recurring Work requirements.

Specification Item 4 will always contain the Non-Recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items.

Specification Items 3.2 and 3.3 are not considered subordinate to 3.1 nor are they considered subordinate to one another. All costs associated with Annexes 1 and 2 and Specification Items 1 and 2 shall be priced, and their price shall be allocated pro rata share to the Exhibit Line Items.

1.6 Related Information There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:

Informational Notes as used throughout this PWS provides additional information to offerors’ to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 and their associated sub-annexes are subject to this disclaimer. Offerors’ may not rely upon the "Informational Notes" as material representations of the Government. Information provided in "Informational Notes" does not create a contractually binding requirement on either party.

Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.

Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.

Requirement Information further describes client requirements associated with each Performance Objective.

1.7 Verification of

Workload and Conditions

Throughout the PWS, the workload data is generally referred to as being located in Annexes and Attachments. Annexes provides data such as descriptions, specifications, and the statement of work. Attachments

0100000, Page 4 of 4

0100000 – General Information Spec Item Title Description provides data such as system descriptions, maps, floor plans, and tables to represent the type and location of services to be provided.

All facilities, systems, and assets identified in this contract shall be accepted by the Contractor in "AS-IS" condition. The Contractor is fully responsible for all work up to and including the limits of liabilities specified.

As prescribed in FAR 52.237-1, offerors’ or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

1.8 Contractor's Knowledge The Navy expects to receive insightful management from its contractors.

This management shall include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle. Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.

1.9 Technical Proposal

Certification

The Contractor warrants that its proposal including, but not limited to, proposed approaches, staffing, methodology, or work plans, will meet the performance objectives and standards set forth in this contract during execution thereof. The Contractor is not excused from meeting such performance objectives and standards in the event such proposal proves inadequate as conceived or executed to meet such performance objectives and standards. The Contractor understands that it bears all of the cost and performance risk associated with adopting acceptable additional (and/or alternative) means or methods of meeting the performance objectives and standards.

0200000, Page 1 of 36

0200000 – Management and Administration Spec Item Title 2 Management and Administration

2.1 Definitions and Acronyms

2.2 General Information

2.2.1 Government Regular Working Hours

2.2.1.1 Observed Federal Holidays

2.2.1.2 Restriction to Contractor Working Hours

2.2.2 Wage Determinations

2.2.3 Requirements Hierarchy

2.3 General Administrative Requirements

2.3.1 Required Conferences and Meetings

2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment

2.3.3 Partnering

2.3.3.1 Informal Partnering

2.3.3.2 Contract Partnering Administration

2.3.3.3 Contract Partnering Session Attendees

2.3.4 Permits and Licenses

2.3.5 Insurance

2.3.5.1 Certificate of Insurance

2.3.5.2 Minimum Insurance Amounts

2.3.6 Protection of Government Property

2.3.7 Directives, Instructions, and References

2.3.8 Invoicing Procedures

2.3.9 Forms

2.4 Government-Furnished Items

2.4.1 Government-Furnished Property (GFP)

2.4.2 Government-Furnished Facilities – Not Applicable

2.4.3 Government-Furnished Vehicles and Equipment – Not Applicable

2.4.4 Government-Furnished Utilities

2.5 Contractor-Furnished Items

2.6 Management

2.6.1 Safeguarding Information

2.6.2 Dissemination of Information

2.6.3 Work Reception

2.6.4 Work Control

2.6.5 Work Schedule

2.6.6 Deliverables

2.6.7 Service Interruptions

2.6.8 NAVFAC Maximo

2.6.8.1 NAVFAC Maximo Data

2.6.8.2 NAVFAC Maximo Method of Data Entry

2.6.8.3 NAVFAC Maximo Access

2.6.8.4 NAVFAC Maximo Training

2.6.9 Quality Management System (QMS)

2.6.9.1 Quality Management (QM) Plan

2.6.9.2 Quality Inspection and Surveillance

2.6.9.3 Quality Inspection and Surveillance Report

2.6.10 Property Management Plan – Not Applicable

2.6.11 System and Equipment Replacement

2.7 Personnel Requirements

2.7.1 Key Personnel

2.7.1.1 Project Manager (PM)

0200000, Page 2 of 36

0200000 – Management and Administration Spec Item Title

2.7.1.2 Quality Manager

2.7.1.2.1 Quality Control Personnel

2.7.1.3 Site Safety and Health Officer (SSHO)

2.7.1.4 Environmental/Energy Manager

2.7.1.5 Certified Industrial Hygienist

2.7.1.6 Certified Pool Operator (CPO) – National Spa Pool Foundation or Other Industry Recognized

Equivalent

2.7.2 Employee Requirements

2.7.2.1 Employee Certification and Training

2.7.2.1.1 Employee Qualification for Work Requiring Neutralization & Repair of GSA Approved Containers

2.7.2.2 Employee Appearance

2.7.2.3 Employee Conduct

2.7.2.4 Identification as Contractor Employee

2.7.2.5 Removal of Employees

2.7.2.6 Proof of Legal Residency

2.7.3 Service Contract Reporting (SCR)

2.8 Security Requirements

2.8.1 Employee Listing

2.8.2 Vehicles

2.8.3 Passes and Badges

2.8.4 Access to Installation

2.8.4.1 DBIDS Program

2.8.4.2 DBIDS Credentials

2.8.4.3 DBIDS Paper Passes

2.8.5 Access to Buildings

2.8.6 Access Arrangements

2.8.6.1 Escort Arrangement for Secured Areas

2.8.7 Security Clearances

2.8.8 Access to Controlled Unclassified Information

2.8.9 Access to Government Information Technology (IT), Operating Technology (OT), and Facility

Related Control Systems (FRCS)

2.8.10 Access to Navy Marine Corps Intranet (NMCI)

2.8.11 Employee Status

2.9 Contractor Safety Program

2.9.1 Contractor Safety Requirements

2.9.1.1 Experience Modification Rate (EMR)

2.9.1.2 OSHA Days Away From Work, Restricted Duty, or Job Transfer (DART) Rate

2.9.2 Accident Prevention Plan (APP)

2.9.3 Activity Hazard Analysis (AHA)

2.9.4 Safety and Occupational Health (SOH) Risks and Compliance Plans

2.9.4.1 Alcohol and Drug Abuse Prevention Plan

2.9.4.2 Chemical Hazard Communication Program

2.9.4.3 Confined Space Program

2.9.4.4 Critical Lift Plan

2.9.4.5 Fall Prevention and Protection Plan

2.9.4.6 Pathogen Exposure

2.9.4.7 Control of Hazardous Energy (lockout/tagout)

2.9.5 Crane Operations

2.9.5.1 Crane Inspections

2.9.5.2 Rigging Gear

2.9.5.3 Crane Operators

2.9.6 Accident and Damage Reporting

0200000, Page 3 of 36

0200000 – Management and Administration Spec Item Title

2.9.6.1 Accident Reporting and Notification Criteria

2.9.7 Fire Protection

2.9.8 Monthly On-Site Labor Report

2.9.9 OSHA Citations and Violations

2.9.10 Safety Inspections and Monitoring

2.9.11 Safety Certification

2.9.12 Safety Apparel on Jobsites

2.9.13 Emergency Medical Treatment

2.9.14 Excavations

2.10 Environmental Management and Sustainability

2.10.1 Energy Management Program

2.10.1.1 Water Conservation Plan – Not Applicable

2.10.1.2 Energy Efficient Products

2.10.2 Environmental Protection

2.10.2.1 Sampling, Testing and Laboratory Services – Not Applicable

2.10.2.2 ODS Requirements for Refrigerant Recycling – Not Applicable

2.10.2.3 Solid Waste Management and Recycling

2.10.2.4 Non-Regulated Waste Disposal

2.10.2.5 Regulated Waste Disposal

2.10.2.6 Universal Waste

2.10.2.7 Spill Prevention, Containment, and Clean-up

2.10.2.8 Hazardous Material Management

2.10.2.9 Protection of Endangered and Threatened Species (Flora and Fauna)

2.10.2.10 Noise Control

2.10.2.11 Salvage

2.10.2.12 Asbestos Containing Material (ACM)

2.10.2.13 Clean Air Act (CAA)

2.10.3 Sustainable Procurement and Practices

2.10.3.1 Environmentally Preferable Products

2.10.3.2 Use of Recovered Materials

2.10.3.3 Use of Biobased Products

2.11 Disaster Preparedness

2.12 Technical Library

2.13 Warranty Management

2.14 Recurring Work Procedures

2.14.1 Recurring Work Preparation of Proposals

2.14.2 Notification to the Government for Work Above the Recurring Work Limitations

2.14.3 Recurring Work Exhibit Line Item Numbers (ELINs)

2.15 Non-Recurring Work

2.15.1 Unit Priced Task (UPT) Work (Non-Negotiated)

2.15.1.1 Acceptance and Performance

2.15.1.2 Invoicing and Receiving Payment

2.15.2 Unit Priced Labor (UPL)Work (Negotiated)

2.15.2.1 Non-recurring Work Preparation of Proposals

2.15.2.1.1 Labor Requirements

2.15.2.1.2 Direct Material and Construction Equipment Requirements

2.15.2.2 Issuance of Final Task Order

2.15.2.3 Coefficient

2.15.3 Non-Recurring Work ELINS

0200000, Page 4 of 36

0200000 - Management and Administration Spec Item Title Description 2 Management and

Administration

2.1 Definitions and

Acronyms

Definitions and Acronyms are listed in Attachment 0200000-01.

2.2 General

Information

2.2.1 Government

Regular Working Hours

The Government's regular working hours are from 0700-1600, five days per week, Monday through Friday, except observed Federal holidays. Exceptions to the regular hours of operation are detailed in subsequent sections of this PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours must be authorized by the KO prior to commencement of work.

2.2.1.1 Observed Federal

Holidays

The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.

2.2.1.2 Restriction to

Contractor Working Hours

If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours per Deliverables. Excludes work to be performed during specified hours.

2.2.2 Wage

Determinations

Wage Determinations are included in Attachment 0200000-02.

2.2.3 Requirements

Hierarchy

Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.

Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.

2.3 General

Administrative Requirements

2.3.1 Required

Conferences and Meetings

The Contractor shall attend administrative and coordination meetings. The Contractor shall provide sign-in sheets and prepare minutes of all meetings and submit per Deliverables for review and comments. Comments received within two working days shall be incorporated into the minutes and a copy of the final revision shall be submitted per Deliverables for concurrence.

2.3.2 Training for

Maintenance and Operation of New and Replacement Systems and Equipment

When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.

2.3.3 Partnering The Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who may receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and sub-contractor teams, including senior management personnel must participate.

0200000, Page 5 of 36

0200000 - Management and Administration Spec Item Title Description

The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps. NAVFAC P-204 Facility Support Contracts Partnering Guide contains the framework necessary for consistent implementation of partnering for Facility Support Contracts (FSCs).

2.3.3.1 Informal Partnering The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.

The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.

The Partners will determine the frequency of the follow-on sessions.

2.3.3.2 Contract Partnering

Administration

Upon award, the ACO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering.

A partnership agreement, The Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process.

Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.

The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.

2.3.3.3 Contract Partnering

Session Attendees

The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.

President/Vice President

* Project Manager

* Quality Manager Site Safety and Health Officer

2.3.4 Permits and

Licenses

The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Deliverables.

2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Deliverables as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause

52.228-5, INSURANCE – WORK ON A GOVERNMENT

0200000, Page 6 of 36

0200000 - Management and Administration Spec Item Title Description

INSTALLATION. This insurance must be maintained during the performance period.

2.3.5.1 Certificate of

Insurance

The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.

2.3.5.2 Minimum

Insurance Amounts

The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:

Comprehensive General Liability: $500,000 per occurrence

Automobile Liability: $200,000 per person, $500,000 per occurrence per bodily injury, $20,000 per occurrence for property damage

Workmen's Compensation: As required by Federal and state worker's compensation and occupational disease statutes

Employer's Liability coverage: $100,000, except in states where worker's compensation may not be written by private carriers

Other as required by state law

2.3.6 Protection of

Government Property

During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of Contractor negligence under this contract to their original condition at no cost to the Government.

2.3.7 Directives, Instructions, and References

Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in Attachment 0200000-03. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.

2.3.8 Invoicing

Procedures

Refer to Section G for invoicing instructions. Refer to Invoice Form in Attachment 0200000-04 for sample.

Invoices shall be submitted in a format compatible with the most recent Government installed Microsoft Office Version (currently 2010). Invoice data shall be capable of being sorted by CLIN, annex/sub-annex, spec item, spec item title, and ELIN/Sub-ELIN.

2.3.9 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in Attachment 0200000-05.

2.4 Government-

Furnished Items

Except for items identified below as Government-Furnished, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services described in this Performance Work Statement (PWS).

Government-Furnished Items will be provided in "AS-IS" condition and their use is at the option of the Contractor. The total or partial breakdown or failure of Government-Furnished Items shall not relieve the Contractor of the responsibility to perform the requirements of this contract.

The Contractor shall provide periodic servicing, maintenance, and repair of the Government-Furnished Items accepted for use at no additional cost to the Government. Servicing, maintenance, and repair shall be provided in

0200000, Page 7 of 36

0200000 - Management and Administration Spec Item Title Description accordance with the manufacturer’s recommendations. The Contractor shall generate work orders in NAVFAC Maximo per Spec Item 2.6.8 for all servicing, maintenance, and repair activities performed on Government- Furnished Items.

At the completion of the contract, all Government-Furnished Items shall be returned to the Government in the same condition as received, except for reasonable wear and tear. Government-Furnished Items, which becomes worn out due to normal wear and tear, shall be returned to the Government and its replacement shall be the responsibility of the Contractor at no additional cost to the Government. The Contractor shall be responsible for the cost of any repairs or replacement caused by Contractor negligence or abuse.

The Government may inspect Government-Furnished Items at any time and without notice.

2.4.1 Government-

Furnished Property

(GFP)

Per FAR 45.101, “Property in the possession of, or directly acquired by, the Government and subsequently furnished to the contractor for performance of a contract. Government furnished property includes, but is not limited to, spares and property furnished for repairs, maintenance, overhaul, or modification.” Government owned equipment being taken off installation by a contractor is GFP. Example: Items being fixed + spare parts + any materials given to industry are all considered GFP.

Real property, government facilities, inventory/supplies consumed in performance of requirement, vehicles and equipment used only on federal installations - could be considered incidental to performance, or consumables

– not GFP.

2.4.2 Government-

Furnished Facilities

Not Applicable

2.4.3 Government-

Furnished Vehicles and Equipment

Not Applicable

2.4.4 Government-

Furnished Utilities

The Government will make available water and electricity at existing outlets required for the work to be performed under the contract. The Contractor shall provide and maintain, at its expense, the necessary service lines from the existing Government outlets to the work site. Provide and maintain backflow prevention devices on connections to domestic water lines and electrical transformer provisions on connections to electric lines. Meet all Federal, State, local, and installation codes and regulations for backflow prevention devices and electrical transformer provisions. Services required by the Contractor, for which there are no available Government outlets, shall be provided by the Contractor at no cost to the Government.

The Contractor is responsible for the cost of all utilities at all Government-provided facilities and any additional Contractor-owned facilities, at prevailing Naval Station rates. The Contractor will be billed directly for all utilities provided to all Contractor occupied facilities. Utility rates billed to the Contractor will be at the following rates:

1. Electrical - the current rate for electrical services is $111.82 MWH

2. Water - the current rate for water is $13.23 per KGAL

3. Wastewater (Sewage) - the current rate for sewage services is $14.06 per

KGAL, based on 100% of the water consumption

0200000, Page 8 of 36

0200000 - Management and Administration Spec Item Title Description

Variations in Rates: Utility rates are subject to change. Changes in one or more utility rates shall not be basis for adjustment to the contract price or a claim unless the deviation from the quoted price for a utility rate exceeds 15%. When a utility rate varies by more than 15%, the contract price will be adjusted to reflect the amount the actual charge exceeds the rate quoted;

however, the Government will only be liable for the amount of cost exceeding 15% of the rate quoted. For example, if a quoted rate increases by 16%, the Government will only be liable for 1% of the rate increase. Vice versa if the quoted rate decreases by 16%.

2.5 Contractor-

Furnished Items

Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements.

Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.

2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.

2.6.1 Safeguarding

Information

The Contractor shall safeguard controlled unclassified information and information associated with Government property in accordance with the latest revision of CNSSI 1253, DoDI 8582.01, NIST SP 800-53, NIST SP 800-171, SECNAV Defense Industrial Base (DIB) Memo, and applicable contract clauses. At a minimum, this information shall be protected at the moderate confidentiality level as defined in NIST SP 800-171.

Contractor information and data systems that contain information associated with Government property shall comply with DoD Risk Management Framework (RMF).

The Contractor shall develop Plans of Action and Milestones (POA&Ms) per NIST SP 800-171, track accomplishment, and submit to the Government per Deliverables.

If a cybersecurity incident is encountered or suspected related to any (Contractor or Government) Information Technology (IT) or Operating Technology (OT) systems, including Monitoring and Control Systems, the Contractor shall notify the Government.

2.6.2 Dissemination of

Information

DoD policy limits the dissemination of certain information. Instructions, Directives, and References not releasable to the public, e.g., Floor Plans, Maps, Post Orders, and Standard Operating Procedures, will be made available after contract award to the successful offeror with appropriate credentials and a need to know.

2.6.3 Work Reception The Contractor shall provide the capability to receive, prioritize, correspond, and respond to trouble/service calls and task orders during Government regular working hours and provide a point of contact at a local or toll free

0200000, Page 9 of 36

0200000 - Management and Administration Spec Item Title Description number who can perform the above function during other than Government regular working hours.

2.6.4 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the Government. A status update of any item of work must be provided within two hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours.

The Contractor shall provide work schedules for both Recurring and Non- Recurring Work per Deliverables. At a minimum, work schedules shall include:

Description of service(s) to be accomplished Location Date service(s) are scheduled to be accomplished

2.6.5 Work Schedule The Contractor's work shall not interfere with normal Government business.

In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall provide written notification of any difficulty in scheduling work due to Government controls, per Deliverables. At a minimum, the notification shall include the following:

The date and time the work was initially coordinated.

The name and phone number of the Government person with whom the work was initially coordinated.

The name and phone number of the Government person who prevented the work from being performed as previously coordinated.

The alternative date and time, the Government person requested the work be accomplished.

2.6.6 Deliverables The Contractor shall submit accurate and complete documents within the specified timeframes. The Contractor shall revise/modify deliverables, as directed by the KO, at no additional cost to the Government.

Except where otherwise specified, all deliverables shall be submitted electronically in a Microsoft Office Version 2010 compatible format.

Deliverables shall include the company name, contract number, contract title, date, and shall be unprotected and capable of being sorted by CLIN, work order number, asset number, section, annex/sub-annex, spec item and ELIN/Sub-ELIN or clause. All formulas shall be traceable.

Government acceptance of deliverables shall not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.

2.6.7 Service

Interruptions

If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, COR, affected tenants, and customers in accordance with local procedures. If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO, COR, affected tenants, and customers as soon as practicable

0200000, Page 10 of 36

0200000 - Management and Administration Spec Item Title Description and provide the status of repairs, as directed by the KO, until normal operation is restored.

Scheduled utility outages and interruptions to equipment, system(s) operation, or other services shall be scheduled after hours of operation.

The Contractor shall shutdown, restart, and perform operational checks on all equipment affected by both scheduled and unscheduled utility outages and service interruptions, at no additional cost to the Government.

2.6.8 NAVFAC Maximo Work order, asset, specification, and condition assessment data created by the Contractor is recorded in NAVFAC Maximo for all work performed in 1501000 Facility Management, 1502000 Facility Investment, Annex 16 Utilities sub-annexes and Annex 1700000 BSVE. This spec item should be included in all FSC/BOS contracts above the SAP threshold at Navy PWDs per BMS B-24.8 Facility Support Contractor Data in NAVFAC MAXIMO.

Consult with your local PWD FMD, UEM Director and BSVE Director or FEC FM&S PLC, UEM PLC, and BSVE PLC for further guidance.

The information and format for data submission provided in Section J supports long-term asset management and facilitates transfer to NAVFAC Maximo. These requirements and data format are managed by the FM&S Product Line at the NAVFAC HQ level.

NAVFAC Maximo is the Computerized Maintenance Management System (CMMS) used by the Government for work order history, asset management, and condition assessment. The Contractor shall provide all required data for NAVFAC MAXIMO as identified below:

Informational Note:

Not all supported commands’ assets are included in NAVFAC Maximo. Not all of the modules available within the Maximo application are utilized by NAVFAC and the modules utilized may not be fully implemented.

NAVFAC Maximo does not include a detailed inventory of all assets, components, and equipment that the Contractor is required to service under this contract and may include inaccuracies, omissions, and redundancies.

2.6.8.1 NAVFAC Maximo

Data

Required data fields for work orders are indicated in the Service Provider Information provided in Attachment 0200000-06. Asset inventory data requirements are indicated in the Asset Information provided in Attachment 0200000-07, including additional data for Utilities assets listed in Specification Information in Attachment 0200000-08. Required data for documenting condition assessments is indicated in the Characteristic Meter Reading Information provided in Attachment 0200000-09.

Specified data shall be provided for all work performed in 1502000 Facility Investment. Further instructional information detailing the process for submitting the specified information for NAVFAC Maximo Data Reporting is provided in Attachment 0200000-10.

The Service Provider, Asset, Specification, and Characteristic Meter Reading Interfaces are used in multiple processes for loading data into Maximo by the Government and the format may be updated periodically.

As part of the update the Contractor may be asked to modify the file to add/move columns in their submission. The Contractor shall provide up to 10

0200000, Page 11 of 36

0200000 - Management and Administration Spec Item Title Description extra data elements or columns with as many as 150 characters per element for the Government to define during contract performance at no additional cost to the Government. The Government will provide the Contractor 60 calendar days’ notice of modifications to the Service Provider, Asset, Specification, or Characteristic Meter Reading Interfaces file format.

2.6.8.2 NAVFAC Maximo

Method of Data Entry

The Contractor shall submit asset and specification data in a spreadsheet flat-file following the NAVFAC Maximo Data Reporting process described in the Deliverables section.

The Contractor shall submit asset and specification data in a Pipe Delimited Flat File following the NAVFAC MAXIMO Data Reporting process described in Attachment 0200000-06 through Attachment 0200000-10 per Deliverables section.

In order to demonstrate the ability to properly format the pipe delimited flat file, the Contractor shall provide a Sample Pipe Delimited Flat file prior to contract performance per Deliverables section

The format may be updated periodically. As part of the update the Contractor may be asked to modify the file to add/move columns in their submission.

The Contractor also shall provide up to ten extra data elements or columns with as many as 150 characters per element for the Government to define during contract performance at no additional cost to the Government. The Government will provide the Contractor 60 calendar day notice of modifications to the Service Request, Asset, Specification, or Characteristic Meter Reading Interfaces file format.

2.6.8.3 NAVFAC Maximo

Access

The process for obtaining access and establishing NAVFAC Maximo accounts are detailed in the NAVFAC Maximo System Access Procedures provided in Attachment 0200000-21.

Once accounts have been established, NAVFAC Maximo can be accessed at https://maximo.navfac.navy.mil.

The Contractor shall provide all necessary computer equipment and Internet Service Provider (ISP) accounts to access NAVFAC Maximo for Direct Entry of required data.

A maximum of five NAVFAC Maximo accounts will be approved for the Contractor. Changes of personnel requiring NAVFAC Maximo accounts more than once per year may result in required compensation to the Government for the administrative costs in processing account requests.

2.6.8.4 NAVFAC Maximo

Training

The Government will provide or make available initial training on NAVFAC Maximo to Contractor personnel responsible for direct entry of work order, asset, specification, and condition assessment data. Additional training will be provided by the Government when there are significant changes to the NAVFAC Maximo software or data entry requirements. Training due to changeover of personnel will be the responsibility for the Contractor. The Contractor will be provided a general user guide, local instructions, and other materials by the Government as reference material for the use of NAVFAC Maximo.

2.6.9 Quality

Management System (QMS)

The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and

0200000, Page 12 of 36

0200000 - Management and Administration Spec Item Title Description correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:

Accurate documentation of work processes, procedures, and output measures.

A systematic procedure for assessing compliance with performance objectives and standards.

Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.

Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.

2.6.9.1 Quality

Management (QM) Plan

The Contractor shall develop and submit a QM Plan per Deliverables. The QM Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, the Contractor shall submit the revised QM Plan for acceptance, per Deliverables.

The Contractor’s QM Plan shall include, at a minimum, the following:

• Policy and objectives of Quality Management System (QMS)

• Quality organization o List of personnel o Responsibilities & lines of authority o Training and qualifications

• Approach to assuring quality of services provided and conformance with performance objectives and standards

• Methods and procedures for effective planning, operation and control of processes and performance of work

• Procedures for inspection and surveillance of services to include all contractual requirements.

o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement o Oversight of subcontracted work

• Documentation and records management

• Communication with government (customers)

2.6.9.2 Quality Inspection

and Surveillance

The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be submitted to the COR after completion/termination of the contract per Deliverables.

2.6.9.3 Quality Inspection

and Surveillance Report

The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Deliverables. The Contractor Quality Inspection and Surveillance Report shall include a narrative of events, a tabulated summary and results of the quality inspection and surveillance events performed, inspection-driven corrective actions taken and the results attained, and management process adjustments during the previous month. The Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.

0200000, Page 13 of 36

0200000 - Management and Administration Spec Item Title Description

2.6.10 Property

Management Plan Not Applicable

2.6.11 System and

Equipment Replacement

The Contractor shall maintain the integrity and performance of existing energy saving, water conservation or other sustainability design features of systems and equipment in the performance of repair and replacement work.

Except where otherwise specified, replacement components shall be of the same model/style or equivalent as the component being replaced. Substitutes for replacement components must be accepted by the KO prior to use. The KO will furnish available information for the existing systems and equipment.

2.7 Personnel

Requirements

The Contractor shall comply with the personnel requirements stated below:

2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per Deliverables. The Contractor shall provide any additional information requested by the KO or COR necessary to validate their qualifications.

The Contractor shall submit an Organizational Chart per Deliverables showing lines of authority of the key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and on-site supervisor(s) and who they will report directly to for this contract. The key personnel shall be revised as applicable for the contract.

The Contractor shall provide complete resumes for proposed substitutes and any additional information requested by the KO. Proposed substitutes shall have comparable qualifications to those of the persons being replaced. The KO will notify the Contractor within 15 calendar days after receipt of all required information of the consent on substitutions. No change in fixed unit prices may occur as a result of key personnel substitutions.

2.7.1.1 Project Manager

(PM)

The Contractor shall provide a PM and designated alternate, as applicable, who shall have full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be centrally located on-site during the Government's regular working hours and shall be available on-site within one hour after the Government's regular working hours.

The PM shall have at least three years of experience in managing a workforce providing services on contracts of similar size, scope and complexity.

2.7.1.2 Quality Manager The Contractor shall provide a Quality Manager or designated alternate who shall be centrally located on-site at all times when the Contractor is performing work during the Government's regular working hours and shall be available on-site within two hours after the Government’s regular working hours. The Quality Manager or designated alternate shall report directly to a senior corporate official and shall not report directly to the Project Manager.

The Quality Manager or designated alternate shall have fulfilled the following pre-requisite training and experiences before being hired as the Quality Manager under this contract:

The Quality Manager or designated alternate shall have at least three years of experience in preparing and enforcing QMS programs on contracts of similar size, scope and complexity. The Quality Manager or designated alternate may be the same person as the SSHO.

2.7.1.2.1 Quality Control

Personnel

The Contractor shall provide Quality Control personnel whose primary duty and responsibility is to enforce the Contractor’s Quality Management System

0200000, Page 14 of 36

0200000 - Management and Administration Spec Item Title Description on this contract. The Quality Control personnel shall be on-site at all times when the Contractor is performing work during the Government's regular working hours. The Quality Control personnel shall report directly to the Quality Manager and shall not report directly to the Project Manager.

Quality Control personnel shall have fulfilled the following pre-requisite training and experiences before being hired as Quality Control under this contract:

Quality Control personnel shall meet or exceed the qualifications, technical knowledge and experience requirements specified for the personnel performing the work, which they will be inspecting, and have at least three years of experience in enforcing QMS programs on contracts of similar size, scope and complexity.

2.7.1.3 Site Safety and

Health Officer

(SSHO)

The Contractor shall provide a Level 1 SSHO whose primary duty and responsibility is to prepare and enforce the Contractor’s safety program on this contract. The Level 1 SSHO shall ensure the requirements of EM 385-1-1 and 29 CFR 1926.16 are met for the project. The Level 1 SSHO or an equally qualified Designated Representative/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The Level 1 SSHO shall have fulfilled the pre-requisite qualification, training, continuous learning, and experiences describe in the EM 385-1-1 before being hired as the Level 1 SSHO under this contract. The Level 1 SSHO shall not be the same person as the Project Manager, Quality Control Manager, or any other position other than the Level 1 SSHO.

2.7.1.4 Environmental/

Energy Manager

The Contractor shall provide an Environmental/Energy Manager whose primary duty and responsibility is to ensure Contractor operations adhere to the goals and policies of the Environmental Management System, the Installation Energy Plan, and other specified Sustainability requirements affecting this contract. The Environmental/Energy Manager shall develop, implement and monitor environmental strategies, policies and programs that promote sustainable development and examine the contract activities to establish where improvements can be made and ensure compliance with environmental legislation and energy policy.

The Environmental/Energy Manager shall have a minimum two years’ experience with environmental procedures similar to those of this contract;

familiarity with Environmental Management Systems (EMSs); and knowledge of environmental regulations and federal energy laws and policy (including energy and water reduction requirements and renewable energy requirements) that are applicable to operations similar to those of this contract.

2.7.1.5 Certified Industrial

Hygienis…