26078 - Addendum 03 - 05.13.2026.pdf

PDF 169 KB Posted

Attached to
Tuluksak Bulk Fuel Upgrades Project
Solicitation number
26078
Issued by
Dillingham Census Area, Alaska

About this file

This is Addendum 03 to an Invitation to Bid issued by the State of Alaska through the Alaska Energy Authority for the Tuluksak Bulk Fuel Upgrades Project (Solicitation No. ITB 26078). The addendum clarifies and modifies the original ITB documents for comprehensive bulk fuel storage and handling improvements, including gravel pads, aboveground fuel storage tanks, steel containment dikes, fuel dispensing systems, fuel piping, and electrical work. The project involves transferring fuel quantities from existing tanks (up to 30,000 gallons each for Corporation and TNC facilities, and 60,000 gallons for School facility) before decommissioning old infrastructure and installing new owner-supplied 30,000-gallon tanks. The ITB due date remains May 19, 2026, at 2:00 PM AKST, with telephonic bid opening conducted at 1-469-810-0642 (Conference ID 366 083 693#). Bidders must acknowledge receipt of the addendum by email prior to the bid deadline. The contractor is responsible for furnishing and installing all tank appurtenances except ladders, catwalks, and shipping plugs on owner-supplied tanks, and must establish temporary fuel storage and retail dispensing facilities to maintain uninterrupted community fuel services throughout construction.

Key clarifications include confirmation that owner-supplied tanks will arrive in Tuluksak no later than July 31, 2026, with revised tank dimensions and specifications for existing tanks TD1 through TD7. The contractor must coordinate with local tank farm owners regarding temporary facility locations and the sequence of tank decommissioning based on fuel inventory levels and community storage needs. Annual fuel consumption estimates are provided from the 2024 Conceptual Design Report as reference for bidding purposes. Material sourcing for the School Tank Farm is not specified, with contractors encouraged to contact Tulkisarmute Inc. manager Agatha Fly at 907-695-6457 (office) or 907-695-2167 (cell) for information regarding staging areas, stockpile locations, and temporary facility coordination. The project remains subject to Build America Buy America Act requirements due to Environmental Protection Agency federal funding, with all materials requiring domestic sourcing unless documented under approved waivers.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 1 of 4 Printed on 5/13/2026

Date: May 13, 2026 Project: Tuluksak Bulk Fuel Upgrades Project Solicitation No.: ITB 26078 Addendum No.: 3

TO ALL PLAN HOLDERS:

The following changes, additions, clarifications, and/or deletions are hereby made part of the ITB Documents for the above noted project, as if fully contained therein. All other terms, conditions, and specifications of the original Invitation to Bid remain unchanged.

Bidders must acknowledge receipt of this Addendum by email prior to the bid due date and time.

The ITB Package is hereby clarified, changed or modified by the following:

CONTRACT PROVISIONS AND SPECIFICATIONS

The ITB Due date and time of May 19, 2026, at 2:00 PM AKST remains unchanged.

The telephonic bid opening will be conducted by calling 1-469-810-0642 and entering Conference I.D. 366 083 693# when prompted.

Page 2 of 4 Printed on 5/13/2026

QUESTIONS AND ANSWERS:

1. Question: Bid item A6 - For the bid is there an estimated quantity of fuel that we will need to filter and transfer to the new tank farm from the old tanks before we decommission the fuel tanks?

Answer: For the purposes of bidding, bidders may assume the following quantities of fuel will need to be transferred from decommissioned tank s to the new tank farms:

• Corporation: Up to 30,000 gallons of fuel.

• TNC: Up to 30,000 gallons of fuel

• School: Up to 60,000 gallons of fuel

2. Question: Are the (3) 30k-Gal tanks at school fuel farm looking to be supplied or are they being furnished by owner like at the colocated tank farm?

Answer: Response: All new 30,000 gallon tanks will be owner supplied.as noted in Specification Section 01 64 00.

3. Question: In spec section 33 56 13 1.2.4, I’m taking this to understand that the contractors are supplying and installing all appurtenances across all tanks, even if they’re furnished by owner?

Answer: The owner supplied tanks will not be equipped with any appurtenances except for ladders, catwalks, and appropriate plugs for shipping purposes. Contractor is responsible for furnishing and installing all tank appurtenances.

4. Question: The decommissioning schedule shown on sheet G1.4 appears to include incorrect volumes for the existing Corporation Horizontal Diked Tanks (tanks TD1 and TD2); please confirm.

Answer: Revise the volumes shown for existing tanks TD1 and TD2 to 30,000 gallons each.

5. Question: When is the expected date that the Owner supplied fuel tanks will arrive on site?

Answer: The owner provided tanks are being shipped via AML. Below is a message received from AML regarding the shipment into Tuluksak: “We’re tentatively estimating arrival into Bethel towards the end of the month (May) and will begin planning trips to

Tuluksak once operations are wrapped up. Historically we’ve arrived early to mid-June, however, we’ve been seeing lingering ice condition this season so please reach out for updates as we’re getting into early June, and we’ll help advise as we continue onwards”.

For bidding purposes, bidders may assume that the tanks will arrive in Tuluksak no later than July 31, 2026.

6. Question: Ref DWG G1.5 & G1.6- Please confirm diameter, height/length, and if tanks are vertical or horizontal in the tank schedules?

Answer: Revise the existing tank dimensions shown on these sheets as follows:

• TD 3 and TD 4 - Both tanks are vertical, single wall tanks with approximate dimensions of 9’-8” in diameter by 12’ tall.

• TD 5 - Tank is a single wall horizontal tank with approximate dimensions of 3.5’ diameter by 7 ‘long.

• TD 6 and TD 7 - Both tanks are vertical single wall tanks with approximate dimensions of 12’ diameter by 30’ tall.

Page 3 of 4 Printed on 5/13/2026

7. Question: Refence DWG C1.3 & Spec 31 23 00 1.5 Material Sources:

A. Question: Where is the material to be sourced for the School Tank Farm?

Answer: The material source is not specified. Most recent projects have sourced fill material from Bethel.

B. Question: Is there a place to stockpile the imported materials?

Answer: Bidders are encouraged to contact Tulkisarmute Inc. manager Agatha Fly for information on available staging and material stockpile areas.

Agatha Fly Tulkisarmute Inc.

907-695-6457 (office) 907-695-2167 (cell) tulkisarmuteinc@yahoo.com

C. Question: Is it anticipated that a temporary tank farm will be needed for the Co- Located Tank Farm?

a. Question: If so, where is the preferred location?

Answer: The contractor will be responsible for all required temporary facilities necessary to provide uninterrupted fuel storage and retail dispensing services in the community throughout construction. Contact Agatha Fly above for information regarding potential temporary tank farm / retail dispensing facility location. It is anticipated that the contractor will relocate and re-utilize the existing corporation-owned bulk / dispensing tanks for temporary retail fuel dispensing facilities. However, all coordination will need to be worked out between the contractor and the local tank farm owners.

b. Question: Can any of the tank farms be decommissioned prior to establishment of the new Co-Located Tank Farm?

Answer: The sequence for decommissioning existing tank farms will depend upon the amount of fuel present in each tank at the time of the project and coordination between the contractor and the individual tank owners. As long as local fuel storage and retail dispensing needs are met, the tank farm decommissioning can run independent of constructing the new co-located facility.

c. Question: What is the required amount of Fuel Storage needed through the winter, if temporary tank Farms are an option?

Answer: For the purposes of bidding, bidders may assume the following annual fuel consumption by user (Source: 2024 Conceptual Design Report).

The contractor is responsible for confirming the required fuel storage capacity with each facility owner prior to implementing any temporary storage facilities mailto:tulkisarmuteinc@yahoo.com

Page 4 of 4 Printed on 5/13/2026

END OF ADDENDUM #03