Addendum #1 Summary

This Addendum to the Multi-Site Culvert Replacement project is issued by Essex County, New York, on behalf of the Town of Moriah. The project involves the replacement of three culverts: two on Tracy Road over Roe Pond Outlet and one on Witherbee Road over Roe Pond Outlet. Sealed bids were due July 30, 2026, at 2:00 P.M. at the Essex County Purchasing Office. The Addendum introduces significant modifications to the original bid documents, including revised contract times, additional bid items, and clarifications regarding project scope and responsibilities. Key additions include work zone traffic control items (619.01, 619.04, 619.1711), cast-in-place concrete for structures (555.0021), and sheet-applied waterproofing membrane (595.50000018). Culvert 1 closure is limited to a maximum of 12 business days, and all three culverts may be completed simultaneously. Precast materials are available for delivery in late August/early September 2026.

The Addendum clarifies responsibility allocation between the County and Contractor, specifying that the Contractor is responsible for Type III barricades, concrete barriers, short-term closures, and installation of precast components, while the County provides detour signage, precast materials, and various structural components. Shop drawings are available upon request from the low bidder. Special specifications address PG binder requirements for asphalt pavement using polymer or terminal blend crumb rubber modified PG 64V-22 with specific elastomeric properties, and waterproofing membrane installation protocols for culvert joints with designated protective layers. The project is funded through New York State and includes fixed-price adjustment items for field changes, asphalt, fuel, and steel/iron. Two separate bid schedules (Share 1 for Culverts 1 & 2 and Share 2 for Culvert 3) are included with detailed line items for excavation, materials, structural work, and site restoration.

View the file

Other files

File Type Posted
260066-Bid-Plans.pdf PDF
260066_Addendum2.pdf PDF
260066_Addendum3.pdf PDF
260066-Bid-1762.97 Project Manual.pdf PDF
260066-NTB.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ESSEX COUNTY

OFFICE OF THE MANAGER

7551 Court Street · P.O. Box 217 · Elizabethtown, New York 12932 Telephone (518) 873-3332 · Fax (518) 873-3339

Michael Mascarenas Linda M. Wolf County Manager Purchasing Agent

TO: All Bidders

FROM: Linda Wolf, CPA, Purchasing Agent

DATE: July 21, 2026

SUBJECT: Addendum #1 Bid for MULTI-SITE CULVERT REPLACEMENTS: Tracy Road Culvert(s) over Roe Pond Outlet and Witherbee Road Culvert over Roe Pond Outlet

This Addendum, issued to bid document holders of record, indicates changes to the bid documents for the MULTI-SITE CULVERT REPLACEMENTS: Tracy Road Culvert(s) over Roe Pond Outlet and Witherbee Road Culvert over Roe Pond Outlet ES bid opening July 30th, 2026.

[PLEASE SEE ATTACHED PAGES]

ADDENDUM NO. 1:

Multi-Site Culvert Replacement(s): Tracy Road and Witherbee Road over Roe

Pond Outlets Culvert Replacements

Town of Moriah

Essex County, New York

PIN 1762.97; D041779

July 21, 2026

NOTE: This Addendum forms a part of the Contract Documents. Insert it in the Project Manual.

Acknowledge receipt of this Addendum in the space provided on the Bid Form.

PROJECT MANUAL:

1. Added a language to the Contract Times in Chapter 1, Section 8, Contract Times as follows:

a. All three culverts may be completed at once. Closures to Culvert one (1) shall be completed in a maximum of 12 business days and reopened back to traffic.

2. See enclosed bid tabs to replace the current bid tabs in chapter 2 of the Project Manual. Summary of revised contract bid items as follows:

a. Share 1 and Share 2:

i. Added item 619.01 BASIC WORK ZONE TRAFFIC CONTROL.

ii. Added Item 619.04 TYPE III CONSTRUCTION BARRICADE

iii. Added Item 619.1711 TEMPORARY POSITIVE BARRIER - CATEGORY 1

(PINNING PROHIBITED)

b. Share 1:

i. Added Item 555.0021 CONCRETE FOR STRUCTURES, PERFORMANCE for the CIP Headwall for Culvert 2 upstream/inlet headwall.

ii. Removed Item 606.10 BOX BEAM GUIDERAIL

3. Added Special Note:

a. See enclosed PG Binder Special Note to be included in the project manual.

4. Added Special Spec:

a. See enclosed special spec ITEM 595.50000018 – SHEET-APPLIED

WATERPROOFING MEMBRANE to be included in the project manual.

PLANS:

5. Cast in place head wall clarification:

a. Culvert 2 upstream/inlet head wall shall be cast in place. Inserts and railing components will be supplied by the County. Contractor shall install headwall per Culvert 2 detail on

“Miscellaneous Details – 2 on MSD-02, Sheet 17. Cost to be included in Item 555.0021

CONCRETE FOR STRUCTURES, PERFORMANCE.

6. BIN Wall Clarification:

a. The BIN wall section A on ELD-03 is omitted. The County is providing precast cantilever wingwalls with footings under Item 562.03 to be installed and backfilled by the

Contractor. Closure pour is the responsibility of the Contractor.

7. WZP-02 and and WZP-03 :

a. Note 1 on both drawings; the word “Contractor” shall be replaced with “County”.

QUESTION AND ANSWER (Q & A):

8. Q: No contours are provided on the plan set. Can topography information be provided via updated plans showing contours, or an electronic file containing the same information.

A: Contours for bidding will not be provided. Low bidder may request electronic copies of the cadd files.

ADDENDUM TO PROJECT MULTI-SITE CULVERT REPLACEMENTS July 21, 2026

9. Q: Are any overhead lines being moved/deenergized/disconnected on the Culvert #3 site on

Witherbee Road? Out on site it looks like they lie directly over the proposed culvert site, not where they are drawn on the plan sheet 33.

A: Overhead lines are not anticipated to be moved or deenergized for the project. Contractor shall be aware of the location of the overhead lines and adhere to safety requirements as outlined in section 107-05 Health and Safety requirements of the project specifications.

10. Q: Can you send over the shop drawings for the culverts? Looking for pick weights and some more information on what is being cast-in-place onsite. The plans show pre-cast headwalls on each of the site's Typical Sections (i.e. Sheet 21). But, the Miscellaneous details sheet on Sheet 17 indicates

Concrete for Structures. If these are CIP, are they being incidental under each 603 box item?

A: Per special note in the Project Manual shop drawings are available upon request. The miscellaneous details sheet 17 if for precasters information with the exception that item 555.0021 cast in place headwall is required for culvert 2 inlet/upstream headwall. Inserts and railing anchorage will be provided by the County. The remaining installation of concrete reinforcement, form work, chamfers and cast in place concrete is the responsibility of the contractor.

11. Q: Also, culvert #3 has item 555.0011 Footing Concrete, Performance, but I do not see this on the plans. Is this for the downstream headwall mentioned on sheet 145 in the Scope of Work within the project manual? Should this say cutoff wall instead of headwall? Culvert 3 also has item 562.03

Wingwall with Footing on the bid sheet, but the plans mention 603.67000001 Precast Concrete

Wingwall. Is Culvert 3's wingwalls entirely precast?

A: Item 555.0011 Footing Concrete, Performance is intended for the concrete encasement of the existing sewer line at the outlet of Culvert 3, see DWG ST-3-2 and ST-3-4. Note all the wingwalls for culvert 3 are precast provided by the County and installed by the Contractor.

12. Q: Which sites have the BIN Wall that is mentioned on Sheet 14 of the plans

A: Culvert 1 and 2 have precast aprons provided by the County installed by the Contractor.

Culvert 3 have precast wingwalls and footing provided by the County installed by the Contractor under Item 562.03.

13. Q: When will materials be available for delivery?

A: Precast will be available for delivery in late August / early September of 2026.

14. Q: The plans show a traffic detour as part of this project, along with type 3 barricades. There are notes on WZP-01 and WZP-03 saying that “County shall provide the signage and installation for the detour routes”. However, sheets WZP-02 and 04 have a not saying “Contractor shall place confirmation signage…” . Please confirm who is responsible for installing and maintaining the detour and all other related MPT controls. If contractor is responsible for any traffic control, can an item be added (NYSDOT 619)? If barriers etc. are responsibility of contractor, please add these as well.

A: Type III Barricades, Concrete barriers, and any short-term closures at each Culvert is the responsibility of the Contractor. Any short-term closures shall be coordinated and approved by the

County. Detour signage and maintenance is the responsibility of the County.

END OF ADDENDUM

Multi-Site Culvert Replacement(s): Tracy Road Culvert(s) over Roe

Pond Outlet and Witherbee Road Culvert over Roe Pond Outlet

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

NUMBER DESCRIPTION QTY UNIT UNIT PRICE IN WORDS (NUMERALS) (NUMERALS)

201.06 CLEARING AND GRUBBING 1 LS ________________________________

Dollars

Cents

203.02 UNCLASSIFIED EXCAVATION AND DISPOSAL 647 CY ________________________________

203.03 EMBANKMENT IN PLACE 768 CY ________________________________

203.21 SELECT STRUCTURE FILL 168 CY ________________________________

203.24010017 SHOULDER BACKUP MATERIAL 40 TON ________________________________

SHARE 1

BID SCHEDULE II- 14

Page Total $__________________

Carry Forward $ __________________

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

206.01 STRUCTURE EXCAVATION 2730 CY ________________________________

206.0201 TRENCH AND CULVERT EXCAVATION 176 CY ________________________________

207.20 GEOTEXTILE BEDDING 212 SY ________________________________

207.26

PREFABRICATED COMPOSITE STRUCTURAL

DRAIN

157 SY ________________________________

209.13 SILT FENCE-TEMPORARY 400 LF ________________________________

304.12 SUBBASE COURSE, TYPE 2 356 CY ________________________________

BID SCHEDULE II- 15

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

NUMBER DESCRIPTION QTY UNIT UNIT PRICE IN WORDS (NUMERALS) (NUMERALS)

404.1989

19 F9 BINDER COURSE ASPHALT, 80 SERIES

COMPACTION

161 TON ________________________________

404.3789

37.5 F9 BASE COURSE ASPHALT, 80 SERIES

193 TON ________________________________

407.0103 STRAIGHT TACK COAT 48 GAL ________________________________

553.030001

TEMPORARY WATERWAY DIVERSION

STRUCTURE

1 EACH ________________________________

553.030002

TEMPORARY WATERWAY DIVERSION

2 EACH ________________________________

555.0021 CONCRETE FOR STRUCTURES, PERFORMANCE 10 CY ________________________________

BID SCHEDULE II- 16

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

568.51 STEEL BRIDGE RAILING (FOUR RAIL) 82 LF ________________________________

568.70 TRANSITION BRIDGE RAILING 256 LF ________________________________

595.50000018 SHEET-APPLIED WATERPROOFING MEMBRANE 1076 SF ________________________________

603.63150515

PRECAST CONCRETE BOX CULVERT (FILL

HEIGHT LESS THAN 24 IN)15 FOOT SPAN 5 FOOT

RISE

31 LF ________________________________

603.64150515

PRECAST CONCRETE BOX CULVERT (FILL

HEIGHT 24 IN OR GREATER) 15 FOOT SPAN, 5

FOOT RISE

41 LF ________________________________

603.67000001

PRECAST CONCRETE WINGWALL UNITS FOR

BOX CULVERTS

74 SY ________________________________

BID SCHEDULE II- 17

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

NUMBER DESCRIPTION QTY UNIT UNIT PRICE IN WORDS (NUMERALS) (NUMERALS)

606.120201

BOX BEAM GUIDE RAILING END ASSEMBLY,

TYPE IIA

8 EACH ________________________________

606.71

REMOVING AND DISPOSING CORRUGATED

BEAM GUIDE RAILING

290 LF ________________________________

606.73

REMOVING AND DISPOSING BOX BEAM GUIDE

RAILING

71 LF ________________________________

610.1605 TURF ESTABLISHMENT PERFORMANCE 147 SY ________________________________

613.04000001

STOCKPILING AND PLACING EXISTING STREAM

BED MATERIALS

93 CY ________________________________

615.01010108 MATERIAL FOR STREAM BED ESTABLISHMENT 93 CY ________________________________

BID SCHEDULE II- 18

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

619.01 BASIC WORK ZONE TRAFFIC CONTROL 1 LS ________________________________

619.04 TYPE III CONSTRUCTION BARRICADE 16 EACH ________________________________

619.1711

TEMPORARY POSITIVE BARRIER - CATEGORY 1

(PINNING PROHIBITED)

80 LF ________________________________

620.05 STONE FILLING (HEAVY) 179 CY ________________________________

620.0801 BEDDING MATERIAL, TYPE 1 67 CY ________________________________

623.12 CRUSHED STONE (IN-PLACE MEASURE) 71 CY ________________________________

BID SCHEDULE II- 19

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

625.01 SURVEY OPERATIONS 1 LS ________________________________

627.50140008 CUTTING PAVEMENT 123 LF ________________________________

646.22

DELINEATOR, SNOWPLOWING MARKER,

SUPPLEMENTARYSNOWPLOWING MARKER

PANELS

12 EACH ________________________________

646.32 STEEL POST, 2.0 LB/FT 8 EACH ________________________________

647.41

REMOVE AND STORE SIGN PANEL, SIGN PANEL

ASSEMBLY SIZE I(UNDER 30 SQUARE FEET)

7 EACH ________________________________

645.81 TYPE A SIGN POSTS 7 EACH ________________________________

BID SCHEDULE II- 20

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

697.03 FIELD CHANGE PAYMENT 77000 DC FIXED PRICE: SEE SPECIFICATION

$1.00 $77,000.00

698.04 ASPHALT PRICE ADJUSTMENT 700 DC FIXED PRICE: SEE SPECIFICATION

$1.00 $700.00

698.05 FUEL PRICE ADJUSTMENT 700 DC FIXED PRICE: SEE SPECIFICATION

$1.00 $700.00

698.06 STEEL/IRON PRICE ADJUSTMENT 105 DC FIXED PRICE: SEE SPECIFICATION

$1.00 $105.00

SUBTOTAL BASE BID

(SHARE 1 - CULVERTS

1 & 2)

699.040001 MOBILIZATION 1 LS _________________

BID SCHEDULE II- 21

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

NUMBER DESCRIPTION QTY UNIT UNIT PRICE IN WORDS (NUMERALS) (NUMERALS)

SUBTOTAL BASE BID

(SHARE 1 - CULVERTS

1 & 2)

201.06 CLEARING AND GRUBBING 1 LS ________________________________

203.02 UNCLASSIFIED EXCAVATION AND DISPOSAL 201 CY ________________________________

203.03 EMBANKMENT IN PLACE 315 CY ________________________________

203.21 SELECT STRUCTURE FILL 260 CY ________________________________

203.24010017 SHOULDER BACKUP MATERIAL 15 TON ________________________________

Share 2

BID SCHEDULE II- 22

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

206.01 STRUCTURE EXCAVATION 1932 CY ________________________________

206.0201 TRENCH AND CULVERT EXCAVATION 51 CY ________________________________

206.05 TEST PIT EXCAVATION 2 EACH ________________________________

207.20 GEOTEXTILE BEDDING 120 SY ________________________________

207.26

PREFABRICATED COMPOSITE STRUCTURAL

DRAIN

100 SY ________________________________

209.13 SILT FENCE-TEMPORARY 200 LF ________________________________

304.12 SUBBASE COURSE, TYPE 2 102 CY ________________________________

BID SCHEDULE II- 23

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

NUMBER DESCRIPTION QTY UNIT UNIT PRICE IN WORDS (NUMERALS) (NUMERALS)

404.1989

19 F9 BINDER COURSE ASPHALT, 80 SERIES

47 TON ________________________________

404.3789

37.5 F9 BASE COURSE ASPHALT, 80 SERIES

56 TON ________________________________

407.0103 STRAIGHT TACK COAT 28 GAL ________________________________

553.030001

TEMPORARY WATERWAY DIVERSION

1 EACH ________________________________

555.0011 FOOTING CONCRETE, PERFORMANCE 5 CY ________________________________

595.50000018 SHEET-APPLIED WATERPROOFING MEMBRANE 660 SF ________________________________

603.63150515

PRECAST CONCRETE BOX CULVERT (FILL

HEIGHT LESS THAN 24 IN)15 FOOT SPAN 5 FOOT

RISE

47 LF ________________________________

BID SCHEDULE II- 24

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

562.03 WING WALL WITH FOOTING 31 SY ________________________________

606.10 BOX BEAM GUIDE RAILING 220 LF ________________________________

606.120101 BOX BEAM END PIECE 4 EACH ________________________________

606.100001 BOX BEAM GUIDE RAILING (SHOP CURVED) 40 LF ________________________________

610.1605 TURF ESTABLISHMENT PERFORMANCE 113 SY ________________________________

613.04000001

STOCKPILING AND PLACING EXISTING STREAM

BED MATERIALS

26 CY ________________________________

615.01010108 MATERIAL FOR STREAM BED ESTABLISHMENT 26 CY ________________________________

BID SCHEDULE II- 25

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

619.01 BASIC WORK ZONE TRAFFIC CONTROL 1 LS ________________________________

619.04 TYPE III CONSTRUCTION BARRICADE 8 EACH ________________________________

619.1711

TEMPORARY POSITIVE BARRIER - CATEGORY 1

(PINNING PROHIBITED)

80 LF ________________________________

620.03 STONE FILLING (LIGHT) 12 CY ________________________________

620.05 STONE FILLING (HEAVY) 118 CY ________________________________

620.0801 BEDDING MATERIAL, TYPE 1 48 CY ________________________________

623.12 CRUSHED STONE (IN-PLACE MEASURE) 86 CY ________________________________

BID SCHEDULE II- 26

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

625.01 SURVEY OPERATIONS 1 LS ________________________________

627.50140008 CUTTING PAVEMENT 51 LF ________________________________

646.22

DELINEATOR, SNOWPLOWING MARKER,

SUPPLEMENTARYSNOWPLOWING MARKER

PANELS

6 EACH ________________________________

646.32 STEEL POST, 2.0 LB/FT 4 EACH ________________________________

697.03 FIELD CHANGE PAYMENT 26000 DC FIXED PRICE: SEE SPECIFICATION

$1.00 $26,000.00

SUBTOTAL BASE BID

(SHARE 2 - CULVERT

3)

699.040001 MOBILIZATION 1 LS

BID SCHEDULE II- 27

ESSEX COUNTY

PIN 1762.97

Brought Forward $_____________.___

ITEM ITEM UNIT PRICE TOTAL

NUMBER DESCRIPTION QTY UNIT UNIT PRICE IN WORDS (NUMERALS) (NUMERALS)

SUBTOTAL BASE BID

(SHARE 2 - CULVERT

3)

BID SCHEDULE II- 28

SPECIAL NOTE

PG BINDER AND MIX DESIGN LEVEL

Requirements of this note apply to all Section 404 Asphalt Pavement items in this contract, except for shim, permeable base, temporary pavements, and miscellaneous, which may use non-modified PG binders such as PG 64S-22 and PG 64H-22.

PG BINDER

Use polymer or Terminal Blend Crumb Rubber modified PG 64V-22 (Very High) meeting the requirements of AASHTO M 332, Standard Specification for Performance Graded Asphalt Binder using Multiple Stress Creep Recovery (MSCR), for the production of asphalt mixtures for this project. In addition, the binder grade must also meet the elastomeric properties as indicated by one of the following equations for %R3.2:

1. For Jnr3.2 ≥ 0.1, %R3.2 >29.371 * Jnr3.2 -0.2633

2. For Jnr3.2 <0.1, %R3.2 > 55

Where:

R3.2 is % recovery at 3.2 kPa Jnr 3.2 is the average non-recoverable creep compliance at 3.2 kPa

When terminal blend CRM PG binder is used, the following shall apply:

• Crumb rubber particles shall be finer than #30 sieve size.

• The CRM PG binder shall be storage-stable and homogeneous.

• The Dynamic Shear Rheometer (DSR) shall be set at 2-mm gap.

• The CRM PG binder shall be 99% free of particles retained on the 600 µm sieve as tested in accordance with Section 5.4 of M 332.

Use of polyphosphoric acid (PPA) to modify the PG binder properties is prohibited for mixtures under this contract. This prohibition also applies to the use of PPA as a cross-linking agent for polymer modification.

MIX DESIGN

The mixture designs must be developed in accordance with the criteria specified in the asphalt pavement items that are appropriate for the Mixture Design Level of 50 Gyrations.

Note: The PG binder for this project will be modified with polymer or CRM additives to meet the requirements stated above. Handling of the asphalt mixture shall be discussed at pre-construction and pre-paving meetings.

Page 1 of 2 Rev. March, 2026

ITEM 595.50000018 – SHEET-APPLIED WATERPROOFING MEMBRANE

DESCRIPTION

Furnish and install a manually or machine-applied sheet waterproofing membrane in accordance with the contract documents. Include all surface preparation.

MATERIALS

Use a sheet-applied waterproofing membrane meeting the requirements of §717-02.

CONSTRUCTION DETAILS

General - On new structural concrete, the provisions of §557-3.11, Curing, shall be met prior to membrane system placement. Work will not be done during wet-weather conditions. No work will be done when the concrete structural slab surface temperature is below 50°F, or ambient temperatures are below 50°F. The concrete structural slab shall be surface dry at the time of application of the membrane.

The Engineer will verify that atmospheric conditions are favorable for placement of the system based on the manufacturer’s recommendations.

Arrange for the membrane manufacturer to have a competent technical representative at the job site during all phases of preparation and installation.

Supply Material Safety Data Sheets (MSDS) and approved Material Detail Sheets prepared by the membrane manufacturer to the Engineer a minimum of two (2) weeks prior to the scheduled commencement of work. The Material Detail Sheets will contain all material requirements and installation information for each specific waterproofing membrane. The Material Detail Sheets will be accessible at the Department’s Approved List website for reference.

(Bridge Decks) – Begin work no less than (7) calendar days after placement of Portland cement concrete, Portland cement mortar, or epoxy mortar for structural concrete repair. The Engineer may waive the seven-day requirement if the areas of repair can sustain loads without damage or deformation. Subject to the concurrence of the Engineer, if an alternate concrete repair material is used, follow the manufacturer’s instructions for allowable loading.

(Culverts) - Fill the joints between precast culvert sections flush to the culvert slab and sidewall surfaces with a grout conforming to §701-08 Vertical and Overhead Patching Material. In areas where the joints do not line up evenly, taper the grout with a maximum slope of 2:1, from the high side of the joint to the low side, to provide a smooth transition from one unit to the next.

Place the waterproofing membrane over the joints of precast or cast-in-place units following the guidelines of Chapter 19 of the Highway Design Manual, or as indicated on the contract plans and

Material Detail Sheets.

1. On vertical surfaces, the waterproofing membrane will be covered with material conforming to

§705-07 Premoulded Resilient Joint Filler.

2. On horizontal surfaces.

Page 2 of 2 Rev. March, 2026

ITEM 595.50000018 – SHEET-APPLIED WATERPROOFING MEMBRANE

Membrane Protection (Culverts) – To protect the waterproofing membrane from punctures, the following procedures will be used:

a. If select granular fill is specified over the culvert, a 6 inch thick protective layer of concrete sand, meeting the requirements of §703-07 Concrete Sand, will be placed on the membrane.

Or

b. If asphalt pavement using aggregate larger than 3/8 inch is specified directly above the membrane, or if clearances don’t allow for 6 inches of concrete sand, a

1 inch thick (minimum) course of an asphalt pavement with a maximum nominal aggregate size of 3/8 inch will be placed on top of the membrane. The asphalt pavement will be thoroughly compacted with mechanical tampers.

METHOD OF MEASUREMENT

This work will be measured as the number of square feet of sheet-applied, waterproofing membrane satisfactorily installed (measured to the nearest 1 sq ft.). No separate measurement of the vertical faces of curbs, joints, concrete barriers, headers, scuppers, or for the inside surfaces of subdrainage outlets, shall be made. No deductions will be made for holes less than 1 square foot in area.

BASIS OF PAYMENT

The unit price bid per square foot for this item shall include the cost of furnishing all labor, materials, and equipment necessary to complete the work.

No additional payments will be made for any re-priming done in conformance with the requirements of the manufacturer’s detail sheets.