CHILLER REPLACEMENT BLDG. 'S FC230, FC400, 58, 205, 213, 323, 914
Solicitation number
N4008526R9078
Issued by

About this file

This is a Submittal Form (dated January 1996) that serves as a tracking and approval mechanism for contractor submissions throughout a construction project lifecycle. The form is designed to document and monitor all required submittals from preconstruction through project closeout phases.

The form tracks two primary categories of submittals: SD-01 Preconstruction Submittals and SD-11 Closeout Submittals, with additional categories for SD-03 Product Data, SD-06 Test Reports, and SD-07 Certificates. Preconstruction submittals include Schedule of Prices, List of Contact Personnel, Construction Schedule, Equipment Delivery Schedule, Accident Prevention Plan (APP), Activity Hazard Analysis (AHA), crane-related documentation (Critical Lift Plans, Work Plans, Operator certifications), Quality Control Plans, Traffic Control Plans, Environmental Protection Plans, Preconstruction Surveys, and various permits and certifications. Closeout submittals encompass Submittal Registers, Complete Submittal Packages, Interim DD1354 Transfer and Acceptance documents, and Military Real Property documentation where applicable. Specialized submittals include third-party certifications for barge-mounted mobile cranes, backflow preventer tests and certifications, MSDS for Class I ODS waivered products, storm water discharge permits, confined space entry permits, crane reports, accident reports, monthly exposure reports, regulatory citations and violations, and certificates of compliance. The form provides columns for tracking action codes, submission dates, approval authority dates, material needed dates, and reviewer dates to ensure systematic management of contractor deliverables throughout the project duration.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACTOR

SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

01 20 00

1.3

01 30 00

1.4.1

01 31 50

1.2

01 32 16

1.2

1.3

01 33 00

1.4.1

1.6.1

01 35 29

1.9

1.10

1.9.1

1.9.1

1.7.1.4

1.14

1.14.1

1.14.3

1.14.4

1.14.5

1.11

1.14.6

Crane Reports

SD-07 CERTIFICATES

Confined Space Entry Permit

Interim DD1354, Transfer & Acceptance

SD-11 CLOSEOUT SUBMITTALS

Submittal Register

Complete Submittal Package

Approving AuthorityContractor Schedule Dates

TITLE AND LOCATION

(Enter Contract Title and Locaiton Here)

Schedule of Prices

List of Contact Personnel

Construction Schedule of Military Real Property (If Applicable)

A C T I V I T Y

N O

T R A N S M I T T A L

N O

(d)

SD-11 CLOSEOUT SUBMITTALS

Contractor Action

DESCRIPTION

ITEM SUBMITTED

(Enter Contractor Name Here)

Crane Work Plan (If Applicable)

Activity Hazard Analysis (AHA)

SD-06 TEST REPORTS

Certificate of Compliance

SD-01 PRECONSTRUCTION SUBMITTALS

SD-01 PRECONSTRUCTION SUBMITTALS

Accident Prevention Plan (APP)

SD-01 PRECONSTRUCTION SUBMITTALS

Equipment Delivery Schedule

SD-01 PRECONSTRUCTION SUBMITTALS

P A R A G R A P H

N O

S P E C

S E C T

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W R

Crane Critical Lift Plan (If Applicable)

Crane Operators (If Applicable)

Reports

Accident Reports

Monthly Exposure Reports

Regulatory Citations and Violations

1.14.7

01 45 10

1.6

01 50 00

1.6.2.1

2.1

3.1

1.3

01 57 19

1.6.1

1.6.4

1.7.2

1.7

1.7

PAGE 1 OF _

Submittals 1.

SCHEDULE

PRE-CONSTRUCTION SUBMITTALS

Complete Submittal Package

ELECTRICAL FEED

PIPING

HVAC EQUIPMENT SPECS

Third Party Certification of Barge-

Mounted Movile Cranes

Qaulity Control Plan (QC Plan)

Backflow Preventer Tests (If Applicable)

SD-01 PRECONSTRUCTION SUBMITTALS

Traffic Control Plan (If Applicable)

SD-11 CLOSEOUT SUBMITTALS

SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE

MSDS for Class I ODS Waivered Product

SD-01 PRECONSTRUCTION SUBMITTALS

Permit for Storm Water Discharge (If applicab

Environmental Protection Plan

Preconstruction Survey

Notice of Intent (If applicable)

CLOSE-OUT SUBMITTALS

SD-03 PRODUCT DATA

Backflow Preventers (If Applicable)

Backflow Preventers Certificate (If Applicable)

SD-06 TEST REPORTS

SD-07 CERTIFICATES

Backflow Tester Certification (If Applicable)