26-0441 - PD.pdf
PDF 80 KB Posted
- Solicitation number
- N4008526R9078
About this file
This is a Project Description document for an HVAC chiller unit installation contract at Camp Lejeune, North Carolina. The contractor is required to provide and install new HVAC Chiller units at seven building locations: FC230, FC400, 58, 205, 213, 323, and 914. The work must be completed while the facility remains operational, requiring the contractor to minimize disruption to normal facility operations during the entire construction period.
Supervision requirements allow for a single qualified individual to serve as Superintendent, Quality Control Manager, and Safety & Health Officer, provided that person meets all qualifications as defined in the project specification. This flexibility in staffing requirements permits cost-effective project management while maintaining necessary oversight of installation quality, safety, and operational compliance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT DESCRIPTION
This scope of work is to be accomplished at Bldg.’s FC230, FC400, 58, 205, 213, 323, 914 on board Camp Lejeune NC. Contractor will provide and install new HVAC Chiller units at each location.
SPECIAL SCHEDULING
The facility/activity will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the facility/activity.
SUPERVISION
One person may fill the roles of Superintendent, Quality Control Manager, and Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.