26_007 TSPLOST Milling and Resurfacing Year 5.docx

DOCX document 209 KB Posted

Attached to
26-007 TSPLOST MILLING and RESURFACING YEAR 5
Solicitation number
PE-72650-NONST-2026-000000041
Issued by
Talbot County, Georgia

About this file

This is an Invitation to Bid (ITB) document issued by the City of Griffin, Georgia, for TSPLOST Milling and Resurfacing Year 5 work. The City seeks qualified contractors to provide materials, equipment, labor, and services including traffic control for milling, resurfacing, and striping work on approximately 9.51 miles of street comprising 20 named streets within Griffin. The scope includes full-width milling, Type 2 9.5mm asphalt resurfacing, thermoplastic striping, and traffic control services. Work must commence within 15 days of Notice to Proceed and be completed within 90 calendar days, with work hours from 7 AM to 6 PM. The bid submission deadline is April 16, 2026, at 2:00 PM, with bids opened publicly. A pre-bid meeting is scheduled but not mandatory; attendance is considered in the evaluation criteria. The resulting contract will not exceed one year with four renewal options for a total period not exceeding five years. Pricing must remain firm for the initial contract term.

Bid evaluation will be based on lowest responsive and responsible bid considering ability to meet specifications, quality of workmanship, timeliness of completion, references, guarantees, warranties, and value-added services. The City reserves the right to accept the best-evaluated response rather than the lowest monetary bid. Bidders must submit two copies plus one original in a sealed package and complete online supplier registration with required E-Verify affidavit and W-9 form prior to award. Performance and Payment bonds equal to 110 percent of the contract amount are required within 10 days of Notice of Intent to Award. Bidders must provide minimum three references for similar projects completed within the past 3-4 years and comply with Georgia Department of Transportation specifications, federal requirements including equal employment opportunity and environmental compliance, and insurance requirements including $1,000,000 commercial general liability and workers' compensation coverage. A daily liquidated damages penalty of $250 per day applies after the 90-day completion period expires.

View the file

Other files

File Type Posted
Addendum _1.pdf PDF
Addendum _3.pdf PDF
Addendum _5.pdf PDF
(Revised) 26_007 NOIA (Notice of Intent to Aw.pdf PDF
26_007 NOIA (Notice of Intent to Award) TSPLO.pdf PDF
Addendum _4.pdf PDF
Addendum _2.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF GRIFFIN, GEORGIA

INVITATION TO BID

BID # 26-007

FOR

TSPLOST MILLING and RESURFACING YEAR 5

For all questions about this Bid contact:

Suzanne Partin lpartin@cityofgriffin.com

Deadline:

April 16, 2026 at 2:00 P.M.

IMPORTANT

SUBMITTAL REQUIREMENT

Submittals must be properly labeled to ensure they are not inadvertently opened before the designated time. Affix the label below to the outside of the sealed submittal envelope or delivery package.

If the label below is not used (i.e. in case of some delivery services), it is the supplier’s responsibility to ensure that the information is on the OUTSIDE of the delivery package. Submissions that do not comply may be rejected.

Submittals must also include the required number of copies specified in section 1.2.

Please make sure either the label below or the information on the label appears on the OUTSIDE of the delivery package and is clearly visible. There may be multiple solicitations open at any given time and if the sender organization and bid number are not discernable, your response may not be recorded as properly received.

RESPONSE SUBMITTAL

DELIVER TO:

CITY OF GRIFFIN

PROCUREMENT – 3RD FLOOR

100 S HILL STREET

PO BOX T

GRIFFIN, GA 30224

BID/PROPOSAL #: 26-007

BID/PROPOSAL NAME: TSPLOST MILLING & RESURFACING YEAR 5

DUE ON OR BEFORE: April 16, 2026

COMPANY NAME:

COMPANY ADDRESS:

CONTACT NAME:

CONTACT PHONE & EMAIL:

BID #26-000

1. SECTION I – BID INFORMATION

1.1.PURPOSE
1.2.SCHEDULE OF EVENTS

DATES

1.3.SCOPE OF WORK
1.4.PACKAGING/SUBMISSION REQUIREMENTS
1.5.EVALUATION CRITERIA

1.6. FEDERAL TERMS AND PROVISIONS REQUIRED IN CONTRACT………………………………………………...……………………

2. SECTION II – GENERAL TERMS AND CONDITIONS

2.1.RESTRICTIONS ON COMMUNICATIONS WITH STAFF
2.2.PUBLIC DISCLOSURE AND PROPRIETARY INFORMATION

3. SECTION III –OVERVIEW AND PROCEDURES

3.1.COMPANY BACKGROUND & EXPERIENCE
3.2.REFERENCES
3.3.BID REQUIREMENTS
3.1.INSPECTION AND ACCEPTANCE OF EQUIPMENT (FOR PURCHASE)
3.2.STATEMENT OF EXPERIENCE AND QUALIFICATIONS
3.3.NON-COLLUSION AFFIDAVIT
3.4.HOLD HARMLESS AND INDEMNIFICATION
3.5.BID BONDS (Bid, Performance, Payment)

4. SECTION IV – OTHER GENERAL SPECIFICATIONS

4.1.FORCE MAJEURE
4.2.SUPPLIER'S INVOICE
4.3.TAX LIABILITY
4.4.PAYMENT
4.5.ESTIMATED QUANTITIES
4.6.ASSIGNMENT OR NOVATION OF CONTRACT
4.7.TERMINATION FOR CAUSE
4.8.TERMINATION FOR CONVENIENCE
4.9.TERMINATION FOR FUND APPROPRIATION
4.10.CHANGES
4.11.REPORTING DISPUTES

5. SECTION V –INSURANCE REQUIREMENTS

5.1.STANDARD INSURANCE REQUIREMENTS
5.2.OTHER INSURANCE PROVISIONS

6. REQUIRED IMMIGRATION/ENTITLEMENT AFFIDAVITS FOR GEORGIA

6.1.VENDOR/CONTRACTOR AFFIDAVIT
6.2.SUBCONTRACTORS

7. TITLE VI

BID #26-000

SUPPLIER REGISTRATION

INVITATION TO BID

TSPLOST MILLING & RESURFACING YEAR 5

SECTION I – BID INFORMATION

Information in this section is bid-specific. Any conflicting information stipulated in this section shall supersede the General Terms & Conditions noted in Sections II - VII.

1.1. PURPOSE

The City of Griffin (City) is seeking bids from qualified organizations to provide materials, equipment, labor and necessary services (including traffic control) for milling, resurfacing and striping work on approximately 9.51 miles of street in the City.

1.2. SCHEDULE & SUMMARY

This Invitation to bid will be governed by the following schedule and criteria:

DATES
Release of RequestMonday, March 16, 2026
Pre-Bid Meeting*NO
Questions dueFriday, April 3, 2026 by 2:00 p.m.
Bids dueThursday, April 16, 2026 by 2:00 PM
Copies of Bid Response RequiredTwo, in addition to one original
Public opening*Yes, 100 S. Hill Street Griffin, GA. 30223 4th Floor
Bonds requiredYes, Performance/Payment Bonds ONLY are required prior to contract
(item 3.8)
Project managerJosh Lee jlee@cityofgriffin.com

* The purpose of this meeting will be to provide those interested with an oral presentation of the City’s requirements and to allow for the presentation of questions. Although attendance at the pre-bid meeting is not mandatory, it is considered as part of the evaluation criteria and attendance, or non-attendance will receive either bonus points or demerits applied to the evaluation scores. All interested parties are ‘strongly’ urged to attend. No other meeting is planned.

1.2.

SCOPE OF WORK

The purpose of these specifications is to detail the requirements for the milling and resurfacing work on various streets (approximately 9.51 miles) in Griffin. The grid detailing the needs is included as Attachments at the end of this document. All work as described in the technical specifications is subject to inspection of the City of Griffin Public Works Department, Griffin, GA. It shall be the Supplier’s responsibility to coordinate with the City of Griffin Public Works and Utilities Department for inspection services. All work shall be done in accordance with the laws of the State of Georgia and shall meet or exceed the Georgia Department of Transportation’s Standard Specifications for the Construction of Roads and Bridges, latest edition and any amendments thereto. The following streets will be milled and resurfaced:

STREET
YEAR
LENGTH FEET
LENGTH MILES
CLEVELAND ST
5
206
0.04
COLDWATER CT
5
342
0.06
COLDWATER DR
5
3,304
0.63
COLDWATER LN
5
2,553
0.48
COLDWATER WAY
5
1,741
0.33
CRYSTAL BROOK
5
2,956
0.56
ELLIS RD (EXPERIMENT ST TO NORTH EXPRESSWAY)
5
3,549
0.67
FLYNT ST
5
2,539
0.48
GATE RIDGE RD
5
1,377
0.26
GREENBELT PKWY
5
9,247
1.75
LYNDON AVE
5
3,505
0.66
MADDOX RD (TO CITY LIMITS)
5
7,980
1.51
MAPLEWOOD DR
5
2,897
0.55
PEARL ST
5
502
0.10
PIER POINT
5
245
0.05
SHANDON LN
5
420
0.08
TUSCANY LN
5
928
0.18
WATERFORD WAY
5
1,251
0.24
WEDGEWOOD WALK
5
735
0.14
WILLOW WAY
5
670
0.13
YEAR 5 TOTALS
50,195
9.51

There are multiple markings that will need to be replaced such as stop bars, turn arrows, crosswalks, and traffic loops.

1.2.1. GENERAL

1.2.1.1. SCHEDULE: All work shall be commenced within fifteen (15) days of the Notice to Proceed and shall be completed within ninety (90) calendar days thereafter, unless otherwise specified.

1.2.1.2. HOURS: Work hours will be 7AM until 6PM. Any deviations needed from the standard times must be approved by the project manager.

1.2.1.3. QUANTITIES: The quantities shown are approximates and may be increased or decreased as required to satisfy the needs of the City. Any changes in the quantities are to be billed and paid for at the unit prices of the final contract.

1.2.1.4. WORK ORDER CHANGES: The City, without invalidating any contracts awarded based on this Invitation to Bid, may order changes within the general scope of the services required to complete the work, by altering, adding to and/or deducting from the services to be performed. If any changes under this clause cause an increase or decrease in the Bidder’s total cost of or time required for, the performance of any part of the work, an equitable adjustment shall be made by mutual agreement, and the Contract shall be modified in writing accordingly. All such work order changes shall be in writing.

1.2.1.5. WARRANTY: The warranty period shall be for a one (1) year minimum from the date of final acceptance by the City. Work not conforming to these requirements, including substitutions not properly approved and authorized, may be considered as defective. The Bidder also certifies that the services to be rendered pursuant to this Invitation to Bid shall be performed in accordance with the standards customarily provided by an experienced and competent professional rendering the same or similar services.

1.2.1.6. PENALTIES: The City will assess a $250/per day penalty after the ninety (90) day period has expired. This supersedes section 4.1, unless an agreed upon extension of the contract has been approved due to circumstances beyond the control of the contractor.

1.2.1.7. The successful bidder shall not subcontract, transfer, assign, or otherwise dispose of the contract or any portion thereof, without the written consent of the City.

1.2.2. RESURFACING AND STRIPING REQUIREMENTS

1.2.2.1. The Successful Bidder shall perform the resurfacing and striping. Removal and disposal of waste asphalt and dirt shall be the responsibility of the Supplier and at no additional cost to the City.

1.2.2.2. The Successful Bidder shall be responsible for the clearing of right-of-way obstructions (if any) as part of the work to be performed.

1.2.2.3. All striping shall be in accordance with the specifications of the Georgia Department of Transportation and the Manual of Uniform Traffic Control Devices for Streets and Highways (MUTCD).

1.2.2.3.1. Temporary markings are to be placed during the curing process.

1.2.2.4. The City’s project manager will be available to meet on site to discuss any special instructions or potential problems prior to the beginning of the job. They shall also inspect the job site upon completion to ensure all work meets the specifications.

1.3.2.5 Type 2 9.5mm asphalt mix required.

1.3.2.6 Full width milling required.

1.3.2.7 Milled surface can remain open no more than 2 days.

1.3.2.8 Side roads must be milled and paved 20 feet.

1.3.2.9 Contractor must tie into any driveways smoothly

1.3.2.10 Leveling should be completed as needed. Include in pricing or add in misc. pay item.

1.3.2.11 Asphalt should be flush with the lip of the gutter.

1.2.3. TRAFFIC CONTROL REQUIREMENTS

1.2.3.1. The Successful Bidder shall maintain safe and continuous vehicular access at all times, unless otherwise approved by the City of Griffin. The Contractor shall provide all necessary signage and traffic control devices.

1.2.3.2. The Successful Bidder shall provide, erect and maintain all necessary barricades, signage, and suitable and sufficient lights and other traffic control device: shall provide qualified flagmen where necessary to direct traffic; shall take all necessary precautions for the protection of the work and safety of the public. In the event proper traffic control is not taken the City of Griffin will issue a stop work order until the proper safety precautions are in place.

1.2.3.3. Construction traffic control devices and their installation shall be in accordance with the Georgia Department of Transportation and the Manual of Uniform Traffic Control Devices for Streets and Highways (MUTCD).

1.2.3.4. Placement and removal of construction traffic control devices shall be coordinated with Griffin Public Works a minimum of 48 hours in advance. Placement of construction traffic control devices shall be scheduled ahead of associated construction activities.

1.2.3.5. Construction time in street right-of-way shall be conducted to minimize the length of time traffic is disrupted.

1.2.3.6. Construction traffic control devices used intermittently, such as “flagman ahead”, shall be removed and replaced when needed. When working within State or City Highway rights-of-way, provide trained and certified flagmen who have completed a training program approved by the Georgia Department of Transportation.

1.2.3.7. Existing permanent traffic control devices within the construction work zone shall be protected from damage due to construction operations. All permanent traffic control devices requiring temporary relocation due to construction shall be located as near as possible to their original position. Their original position shall be measured for permanent reference points and recorded in a permanent log prior to relocation. Temporary locations shall provide the same visibility to affected traffic as the original position. Relocated permanent traffic controls devices shall be reinstalled in their original positions as soon as possible following construction in the affected location. Any permanent traffic control device damaged during construction due to negligence of the supplier shall be replaced by the supplier at his expense.

1.2.3.8. Construction traffic control devices shall be maintained in good repair, clean and visible to affected traffic for daytime and nighttime operation. Traffic control devices affected by the construction work zone shall be inspected daily.

1.2.3.9. Portable ‘advanced warning’ signs may be used in place of the post mounted signs.

1.2.3.10. Construction warning signs shall be black legend on an orange background. Regulatory signs shall be black legend on a white background. Construction sign panels shall meet the minimum reflective requirements of the Department of Transportation. Sign panels shall be of durable materials capable of maintaining their color, reflective character, and legibility during the period of construction.

1.2.3.11. No highway, road, or street shall be closed to traffic without authorization from the proper authority. It shall be the supplier’s responsibility to determine the exact requirements of the authority having jurisdictions over the right-of-way and no extra compensation will be allowed the supplier for meeting such requirements.

1.2.3.12. The Supplier will be responsible for replacement or repair of any traffic signal loops damaged during milling & resurfacing operations.

1.2.3.13. The City will erect any Low/Soft Shoulder signs that are needed and build/grass the dirt shoulders on the roads/streets that do not have curb and gutter. These areas must be conveyed to the project manager.

1.2.3.14. No shoulder work will be required on sections that have no curbing or gutter. The City will backfill these shoulders as needed. This information of need must be conveyed to the project manager.

1.2.3.15. Any manholes or water valves that need adjusting are to be raised to the final finished grade. A list of those raised must be conveyed to the project manager.

PACKAGING/SUBMISSION REQUIREMENTS

The following information and/or documents MUST be included with the supplier’s response and in the order listed below:

a. ___ Information/Cover Page (supplied)

b. ___ Bid Response Disclosures & Acknowledgement sheet (supplied). Note: Non-Collusion and Conflict of Interest Disclosures section must be notarized

c. ___ Pricing Sheet (supplied)

d. ___ References Sheet (supplied)

e. ___ Tax Compliance form (supplied)

f. ___ Company Registration paperwork – to be done online*

g. ___ Supplier Affidavit – an additional copy (showing as notarized) of the Supplier (EV) affidavit must be included with response

h. ___ GDOT prequalification documentation

* If a complete and compliant (both required documents uploaded) registration has been submitted online, you may include a statement that you have a completed registration on file. Instructions and forms for registration may be found on the City’s website under Resources.

A checklist for your convenience has been provided at the end of this document. This checklist is for your convenience only and should not be returned with the submittal.

* If a complete and compliant registration has been submitted online, you may include a statement that you have a completed registration on file. Instructions and forms for registration may be found on the City’s website under Resources.

EVALUATION CRITERIA

The basis of selection will be the lowest responsive and responsible bid considering ability to meet the City’s specifications and requirements in addition to price. Other considerations will include, but are not limited to:

· Ability to provide requested service

· Quality of workmanship and products used

· Timeliness of project completion or delivery

· Additional costs to the City

· References

· Guarantees and warranties

· Value added services and/or options

The City reserves the right to accept the BEST-EVALUATED RESPONSE as deemed by the Evaluation Committee, which may or may not be the lowest monetary response.

FEDERAL TERMS AND PROVISIONS REQUIRED IN CONTRACT

The following terms and conditions must appear in any contract entered into the with Successful Bidder related to the services set forth in this RFP.

1) Access to Records. The following access to records requirements applies to the Contract in addition to any requirements that may be elsewhere imposed:

a. Consultant agrees to provide City, the Comptroller General of the United States, or any of their authorized representatives or designees, access to any books, documents papers, and records of Consultant which are directly pertinent to this Agreement for the purposes of making audits, examinations, excerpts, and transcriptions. Consultant shall keep its books documents, papers, and records available for this purpose for at least five years after this Agreement terminates or expires or such longer time as requested by City at any time prior to the expiration of the then applicable time frame. This provision does not limit the applicable statute of limitations.

b. Consultant agrees to permit any of the foregoing parties to reproduce by any means whatsoever or to copy excerpts and transcriptions as reasonably needed.

c. Consultant agrees to provide any of the foregoing parties access to construction or other work sites pertaining to the work being completed under this Agreement, if applicable.

d. Consultant shall ensure that public records that are exempt or confidential and exempt from public records disclosure requirements are not disclosed except as authorized by law for the duration of the contract term and following completion of the contract if Consultant does not transfer the records to City or any authorized or designated federal representative.

2) Environmental Compliance.

a. Consultant shall comply with all applicable standard, orders, or regulations issued pursuant to the Clean Air Act (42 U.S.C. § 1701 et seq.) and the Federal Water Pollution Control Act as amended (33 U.S.C. § 1251 et seq.).

b. Consultant shall report all violations to City, any applicable State agencies, and the regional office of the Environmental Protection Agency.

c. Consultant shall include these requirements in each subcontract exceeding $150,000 financed in whole or in part with federal assistance.

d. Consultant shall comply with the mandatory standards and policies relating to energy efficiency which are contained in the state energy conservation plan issued in compliance with the Energy Policy and Conservation Act (42 U.S.C. § 6201 et seq.).

3) Contract Work Hours and Safety Standards Act.

a. Overtime requirements. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek.

b. Violation; liability for unpaid wages; liquidated damages. In the event of any violation of the clause set forth in Paragraph (a) of this section, the Contractor and any subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such Contractor and any subcontractor responsible therefor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory) for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in Paragraph (a) of this section, in the sum of $26 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in Paragraph (a) of this Section.

c. Withholding for unpaid wages and liquidated damages. The applicable federal funding agency shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the contractor or subcontractor under any such contract or any other federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in Paragraph (b) of this Section.

d. Subcontracts. The Contractor or subcontractor shall insert in any subcontracts the clauses set forth in Paragraphs (a) through (c) of this section and a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The prime Contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor with clauses set forth in Paragraphs (a) through (c) of this Section.

4) Equal Employment Opportunity. This provision is applicable to all federally assisted construction contracts, as that term is defined at 41 C.F.R. § 60-1.3. To the extent the Agreement meets this definition, Consultant agrees as follows:

a. The Contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, sexual orientation, gender identity, or national origin. The Contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment without regard to their race, color, religion, sex, sexual orientation, gender identity, or national origin. Such action shall include, but not be limited to the following: employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided setting forth the provisions of this nondiscrimination clause.

b. The Contractor will, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, sexual orientation, gender identity, or national origin.

c. The Contractor will not discharge or in any other manner discriminate against any employee or applicant for employment because such employee or applicant has inquired about, discussed, or disclosed the compensation of the employee or applicant or another employee or applicant. This provision shall not apply to instances in which an employee who has access to the compensation information of other employees or applicants as a part of such employee’s essential job functions discloses the compensation of such other employees or applicants to individuals who do not otherwise have access to such information, unless such disclosure is in response to a formal complaint or charge, in furtherance of an investigation, proceeding, hearing, or action, including an investigation conducted by the employer, or is consistent with the Contractor’s legal duty to furnish information.

d. The Contractor will send to each labor union or representative of workers with which he has a collective bargaining agreement or other contract or understanding, a notice to be provided advising the said labor union or workers’ representatives of the contractor’s commitments under this section, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.

e. The Contractor will comply with all provisions of Executive Order 11246 of September 24, 1965 and of the rules, regulations, and relevant orders of the Secretary of Labor.

f. The Contractor will furnish all information and reports required by Executive Order 11246 of September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the administering agency and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.

g. In the event of the Contractor’s noncompliance with the nondiscrimination clauses of this contract or with any of the said rules, regulations, or orders, this contract may be cancelled, terminated, or suspended in whole or in part and the Contractor may be declared ineligible for further Government contracts or federally assisted construction contracts in accordance with procedures authorized in Executive Order 11246 of September 24, 1965, and such other sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of September 24, 1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.

h. The Contractor will include provisions in Paragraphs (a) through (g) set forth in this subsection in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section 204 of Executive Order 11246 of September 24, 1965, so that such provision will be binding upon each subcontractor or vendor. The Contractor will take such action with respect to any subcontract or purchase order as the administering agency may direct as a means of enforcing such provisions, including sanctions for noncompliance; provided, however, that in the event a Contractor becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of such direction by the administering agency, the Contractor may request the United States to enter into such litigation to protect the interests of the United States. The applicant further agrees that it will be bound by the above equal opportunity clause with respect to its own employment practices when it participates in federally assisted construction work; provided that if the applicant so participating is a State or local government, the above equal opportunity clause is not applicable to any agency, instrumentality or subdivision of such government which does not participate in work on or under the contract.

The applicant agrees that it will assist and cooperate actively with the administering agency and the Secretary of Labor in obtaining the compliance of contractors and subcontractors with the equal opportunity clause and the rules, regulations, and relevant orders of the Secretary of Labor, that it will furnish he administering agency and the Secretary of Labor such information as they may require for the supervision of such compliances, and that it will otherwise assist the administering agency in the discharge of the agency’s primary responsibility for securing compliance.

The applicant further agrees that it will refrain from entering into any contract or contract medication subject to Executive Order 11246 of September 24, 1965, with a contractor debarred from, or who has no demonstrated eligibility for, Government contracts and federally assisted construction contracts pursuant to the Executive Order and will carry out such sanctions and penalties for violation of the equal opportunity clause as may be imposed upon contractors and subcontractors by the administering agency or the Secretary of Labor pursuant to Part II, Subpart D of the Executive Order. In addition, the applicant agrees that if it fails or refuses to comply with these undertaking the administering agency may take any or all of the following actions: cancel, terminate, or suspend in whole or in part this grant (contract, loan, insurance, guarantee); refrain from extending any further assistance to the applicant under the program with respect to which the failure or refund occurred until satisfactory assurance of future compliance has been received from such applicant; and refer the case to the Department of Justice for appropriate legal proceedings.

5) Contracting with Small and Minority Businesses, Women’s Business Enterprises, and Labor Surplus Area Firms.

a. If Consultant intends to subcontract any portion of the work covered by the Agreement, Consultant must take all necessary affirmative steps to assure that small and minority businesses, women’s business enterprises and labor surplus area firms are solicited and used when possible. Affirmative steps must include:

i. Placing qualified small and minority businesses and women’s business enterprises on solicitation lists;

ii. Assuring that small and minority businesses, and women’s business enterprises, are solicited whenever they are potential sources;

iii. Dividing total requirements, when economically feasible, into smaller tasks or quantities to permit maximum participation by small and minority businesses, and women’s business enterprises;

iv. Establishing delivery schedules, where the requirement permits, which encourage participation by small and minority businesses, and women’s business enterprises; and

v. Using the services and assistance, as appropriate, of such organizations as the Small Business Administration and the Minority Business Development Agency of the Department of Commerce.

6) Immigration and Nationality Act

a. Consultant agrees to comply with the terms of the employment provisions contained in 8 U.S.C. Section 1324A(e), Section 274A(e) of the Immigration and Nationality Act.

7) Administrative Remedies for False Claims and Statements

a. Consultant acknowledges that 31 U.S.C. Chap. 38 (Administrative Remedies for False Claims and Statements) applies to Consultant’s actions pertaining to this Agreement.

8) Remedies

a. If any work performed and/or good delivered by Consultant fails to meet the requirements of the Agreement, any other applicable standards, codes or laws, or otherwise breaches the terms of the Agreement, the City may in its sole discretion:

i. Elect to have Consultant re-perform or cause to be re-performed, at Consultant’s sole expense, any of the work which failed to meet the requirements of the Agreement;

ii. In the case of goods, reject the goods and require Consultant to provide replacement goods that meet the needs of City and the terms of the Agreement;

iii. Hire another Contractor to perform the work and deduct any additional costs incurred by City as a result of substituting contractors from any amounts due to Consultant; or

iv. Pursue and obtain any and all other available legal or equitable remedies.

b. This Section shall in no way be interpreted to limit the City’s right to pursue and obtain any and all other available legal or equitable remedies against Consultant.

9) Compliance with Applicable Laws

a. Consultant agrees to be bound by the terms of the Federally-Funded Subaward and Grant Agreement between the City and FEMA and/or the State of Georgia and any of its agencies if applicable.

b. Consultant agrees to be bound by all applicable state and federal laws, regulations, and Executive Orders.

10) Suspension and Debarment

a. Federal regulations restrict the City from contracting with parties that are debarred, suspended, or otherwise excluded from or ineligible for participation in Federal assistance programs and activities, where the contract is funded in whole or in part with federal funds. Accordingly, a contract or subcontract must not be made with any parties listed on the SAM Exclusions list. SAM Exclusions is the list maintained by the General Services Administration that contains the name of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under certain statutory or regulatory authority. The Consultant can verify its status and the status of its principals, affiliates, and subcontractors at www.SAM.gov.

i. This Contract is a covered transaction for purposes of 2C.F.R. pt. 180 and 2 C.F.R. pt. 3000. As such the Contractor is required to verify that none of the Contractor, its principals (defined at 2 C.F.R. § 180.995), or its affiliates (defined at 2 C.F.R. § 180.905) are excluded (defined at 2 C.F.R. § 180.940) or disqualified (defined at 2 C.F.R. § 180.935).

ii. Consultant must comply with 2 C.F.R. pt. 180, Subpart C and 2 C.F.R. pt. 3000, subpart C and must include a requirement to comply with these regulations in any lower-tier covered transaction it enters into.

iii. This certification is a material representation of fact relied upon by the City. If it is later determined that the Consultant did not comply with 2 C.F.R. pt. 180, Subpart C and 2 C.F.R. pt. 3000, Subpart C, in addition to remedies available to the City, the Federal Government may pursue available remedies, including but not limited to suspension and/or debarment.

11) Byrd Anti-Lobbying Amendment

a. Consultants who apply or bid for an award of $100,000 or more shall file the required certification found below. Each tier certifies to the tier above that it will not and has not used federally appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any federal contract, grant, or any other award covered by 31 U.S.C. § 1352. Each tier shall also disclose any lobbying with non-federal funds that takes place in connection with obtaining any federal award. Such disclosures are forwarded from tier to tier up to the recipient.

b. The certification referenced in Paragraph (a) of this Section is below:

Certification for Contracts, Grants, Loans, and Cooperative Agreements The undersigned certifies, to the best of his or her knowledge and belief, that:

1) No federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the awarding of any federal contract, the making of any federal grant, the making of any federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any federal contract, grant, loan, or cooperative agreement.

2) If any funds other than federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit Standard Form-LLL, “Disclosure Form to Report Lobbying,” in accordance with its instructions.

3) The undersigned shall require that the language of this certification be included in the award documents for all subawards at all tiers (including subcontracts, subgrants, and contracts under grants, loans, and cooperative agreements) and that all subrecipients shall certify and disclose accordingly.

This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by Section 1352, Title 31, U.S. Code. Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.
Consultant, _______________________________________, certifies or affirms the truthfulness and accuracy of each statement of its certification and disclosure, if any. In addition, Consultant understands and agrees that the provision of 31 U.S.C. Chap. 38, Administrative Remedies for False Claims and Statement, apply to this certification and disclosure, if any.
__________________________________________Date: _______________________________
Signature
Name:
Title:

REQUESTS FOR PROPOSAL, INVITATIONS TO BID

GENERAL PROVISIONS

Sections II - VII review the general terms and conditions. Any bid-specific information noted in Section I or in the Specifications & Response Section will take precedence.

2. SECTION II – GENERAL TERMS AND CONDITIONS

All available information, notices and addenda regarding this RFP shall be posted on the City’s website. Effective July 1, 2018, House Bill 489 requires that any solicitation extended by a municipal corporation for goods and services valued at $10,000 or more and any solicitation opportunity extended for public works subject to Chapter 91 of Title 36 of the O.C.G.A. also be posted on the Georgia Procurement Registry (GPR)and the City’s Vendor Registry site.

It is the Supplier’s responsibility to check the City’s and/or GPR website in order to confirm they have the most current information prior to submitting a response. Subsequent to the opening, all status notices will also be posted on the City’s website and GPR.

2.1. RESTRICTIONS ON COMMUNICATIONS WITH STAFF

All questions about this bid must be submitted in the following format:

Company Name

- Question Citation of relevant section of the bid

All questions regarding specification/technical issues must be in writing to the Project Manager for this bid (with a ‘cc’ to Procurement). The Project Manager, contact email and deadline for questions is noted in section 1.2.

All questions regarding administrative issues must be in writing to the Public Works Consultant:

Address: Suzanne Partin Procurement Coordinator City of Griffin P. O. Box T, Griffin, GA 30224 Email: lpartin@cityofgriffin.com No questions other than written will be accepted. No response other than written will be binding upon the City. Questions will be combined into one list of questions and responses and will be posted as an addendum.

From the issue date of this request until an award has either been made or deemed closed for other reasons, institutions or individuals providing submissions are not permitted to communicate with members of the commission, the evaluation team or City employees, other than Procurement, with regard to the purpose or intent of this document. The exception to this is the submission of written technical questions to the project manager with Procurement copied. The City reserves the right to reject the submission of the offending supplier if this provision is violated.

Any updates or changes to this and related documents will be posted on Georgia Procurement Registry (GPR) and the City’s website (https://vrapp.vendorregistry.com/Bids/View/BidsList?BuyerId=52b8c206-866a-4ed2-b7b8-bef7db8a901b) or by selecting “Resources” and then “Bid Opportunities” from the City home page. It is the Supplier’s responsibility to refer to the websites for any addenda or other pertinent information before responding to this ITB request.

2.2. PUBLIC DISCLOSURE AND PROPRIETARY INFORMATION

All bids and any other public record with respect to solicitation shall be subject to public inspection, upon request, after the posting of the Notice of Intent to Award (NOIA) or Notice of Award (NOA). This is being done in order to protect the integrity of the procurement process unless otherwise required by law. For any Open Records requests, the City may assess fees for the costs of producing these public records as permitted by the Georgia Open Records Act.

Exceptions to the availability of information include 1) bona fide trade secrets meeting confidentiality requirements that have been properly marked and documented; 2) matters involving individual safety as determined by the City; 3) company financial information requested by the City to determine supplier responsibility; and 4) other constitutional protections. All documents that are to be proprietary and confidential are to be clearly marked as such.

Information received in response to this bid request will become the property of the City and will not be returned. If a proposer feels that any information is confidential or proprietary in nature, the proposer must prominently mark and initial such information as “PROPRIETARY INFORMATION”. The City will not release or divulge such information to third parties without the consent of the Proposer unless required to do so by applicable law or order a court of competent jurisdiction.

3. SECTION III –OVERVIEW AND PROCEDURES

Sections II - VII review the general terms and conditions. Any bid-specific information noted in Section I or in the Specifications & Response Section will take precedence.

3.1. COMPANY BACKGROUND & EXPERIENCE

Suppliers that have not contracted with the city in the past 2 years should provide a list of clients for whom similar services, as detailed in this bid, have been provided during the past 3-4 years. References must be for the organization or person submitting the bid. Subcontractor’s references are not acceptable.

The list must include:

Dates of service Name of contact person Title of contact person Phone number of contact person The Supplier will also disclose any services terminated by the client(s) and the reason(s) for termination.

Failure to provide this information will disqualify the bid submission.

3.2. REFERENCES

References should be for historical projects of similar size and scope. Details regarding these references are noted on the Reference page.

3.1.

3.2.

3.3. BID REQUIREMENTS

3.3.1. SPECIAL CONDITIONS

By submitting a bid response, Suppliers certify that their proposals are made without collusion or fraud and they have not offered or received any inducements in connection with their proposals. They further agree that this solicitation and any resulting contract shall be governed in all respects by the laws of the State of Georgia and they shall comply with applicable federal, state and local laws and regulations. Any contracts or leases resulting from the award of a Bid are to be for a period of not more than one year, with four renewal options for a total period not to exceed five years. Any exceptions to this policy must be noted and agreed to by both parties in writing, prior to the issuance of the Notice of Award. Pricing must remain firm for the duration of the initial term of the resulting contract; failure to hold firm pricing for the initial contract will be considered as sufficient cause for termination. Proposal submissions must remain valid for a minimum period of ninety (90) days after the submission due date unless otherwise stipulated.

The City reserves the right to reduce or increase the scope of the project if the lowest responsible and responsive supplier’s submittal is not in line with the budgeted amount for the project. The City, at its sole discretion, reserves the right to increase or decrease the scope of work to facilitate an award. This scope reduction will be enacted only if it is in the best interest of the City and constitutes no guarantee of scope.

The City also reserves the right to add to the contract any future work or purchased goods, with the agreement of the supplier, at prices offered in this bid document. This option will be enacted during the contract or within six months subsequent to the end of the contract, if in the best interest of the City and with the agreement of both parties.

3.3.2.

3.3.3. RESPONSES

In responding to a bid, ALL item numbers with appropriate formatting must show some type of acknowledgment in order for the response to be properly evaluated. Failure to respond to all specification criteria items may be deemed as sufficient reason to reject a submission. If formatting is not provided for a response at the item level, any non-compliance must be clearly marked, detailed and included with the bid response. Any items not identified shall be deemed as in compliance. Suppliers must: 1) complete any/all required forms; 2) indicate agreement or disagreement on each mandatory requirement and, if requested, provide additional information on how the specifications will be exceeded or not met; and 3) provide complete and detailed responses to any and all non-mandatory requirement that can be fulfilled.

If determined to be in the City’s best interests, a Best and Final Offer (BAFO) may be requested. A BAFO may be requested when:

· The prices for all responsive and responsible submittals exceed budget;

· No single responsive and responsible submittal meets all requirements;

· When all responses are unclear or deficient in one of more areas;

· When the grading scores of two or more submittals require additional evaluation;

· At the discretion of the evaluation team to clarify submittals or to negotiate costs or other deliverables.

3.3.4. PACKAGING OF BID

Submissions must be by the following method:

No e-mail, fax or scanned submissions will be accepted. Hard copies are to be submitted in a sealed package containing an unbound original and the number of copies specified in Section I. The sealed package must be labeled on the outside as follows:

(Supplier Name) BID # (Bid Number) TSPLOST Milling and Resurfacing year 5 (Bid Title)

Supplier response to this bid must consist of the following documents in addition to any bid-specific information requested:

· Pricing

· Schedule of proposed work (when applicable),

· Completion Schedule (when applicable),

· Supplier Registration is to be completed online, with the following forms needing to be uploaded

· Supplier Affidavit (E-Verify) (available online),

· W-9 (available online),

· Some responses may require an additional notarized Supplier affidavit. (See section 1.4),

· The City cannot award a supplier that is not registered and compliant,

· Tax Compliance form (required if over $99,000) (supplied if required),

· Reference list of a minimum of three (3) references (supplied).

3.3.5. SUBMISSION OF BID

The original and specified copies of the bid response must be delivered to the Procurement Department no later than the time and date specified in Section I. Any bid received after stated time or delivered to department other than Procurement will not be accepted. The City of Griffin will not be responsible for any responses not received by the Procurement Department prior to the deadline.

Bids must be submitted to:

City of Griffin Attention: Suzanne Partin – Procurement Coordinator P. O. Box T, Griffin, GA 30224

Or delivered to:

Attention: Suzanne Partin – Procurement Coordinator 100 S Hill Street, 3rd Floor Griffin, GA 30223

*Note: Notify Procurement via email (lpartin@cityofgriffin.com) if submittal is mailed via Post Office (USPS).

3.3.6. ALTERNATE BID DOCUMENTS

Documents prepared by the City must be used for the submission of Bid Response. Alternate bids or bids that deviate from the requirements of this solicitation may not be considered. Suppliers shall not insert in their submission any written statement which will have the effect of making any material change or changes in the Scope of Services or in any contract between the parties covering the subject matter thereof.

3.3.7. ADDITIONAL INFORMATION/ADDENDA

The City will issue responses to inquiries and any other corrections or amendments it deems necessary in written addenda issued prior to the bid opening date. Suppliers should not rely on any representations, statements, or explanations other than those made in this Invitation to Bid and its’ addendums. Where there appears to be a conflict between the Invitation to bid and any addenda issued, the last addendum issued will prevail. It is the Supplier’s responsibility to check for addendums (under Bid Opportunities) on the City’s website.

Suppliers must acknowledge any issued addenda. Bids which fail to acknowledge the supplier’s receipt of any addendum will result in the rejection of the bid if the addendum contains information which substantively changes the City’s requirements.

3.3.8. PROPOSAL PRICING, ERRORS AND OMISSIONS

3.3.8.1. In the event there is a discrepancy between a unit price submitted and the extended price, the unit price will prevail.

3.3.8.2. All corrections, changes or erasures to the proposal submission are to be initialed in ink.

3.3.9. WITHDRAWAL OF BID

A supplier may withdraw his bid before the submittal deadline without prejudice to the supplier by submitting a written request of withdrawal to the Procurement Analyst.

3.3.10. LATE SUBMITTAL, LATE MODIFICATIONS & LATE WITHDRAWALS

Bid submittals received after the bid opening date and time will not be accepted. Modifications received after the bid opening date will not be considered. The City assumes no responsibility for the premature opening of a bid not properly addressed and identified or not delivered to the proper designation.

3.3.11. MINIMUM BID ACCEPTANCE PERIOD

Bids shall be valid and may not be withdrawn for a minimum period of 90 days from the date specified for receipt of bids. Suppliers will be asked for an ‘expiration date’ for the bid submitted, when appropriate. This does not impact the contract price once a bid has been awarded.

3.3.12. DISQUALIFICATION OF BIDS OR SUPPLIERS

Suppliers may be disqualified from participation in the bid process for reasons which include, but are not limited to the following:

3.3.12.1. Evidence of collusion;

3.3.12.2. Attempting to manipulate the submittal pricing for its’ own benefit (i.e. pricing resulting in a failure of the City’s ability to enforce the Contract or impose the remedies intended following breach by Supplier);

3.3.12.3. Being in arrears on any of its existing contracts with the City or in litigation with the City or having defaulted on a previous contract with the City;

3.3.12.4. Being in arrears on taxes owed to the State of Georgia;

3.3.12.5. Poor, defective or otherwise unsatisfactory performance of work for the City or any other party on prior projects which, in the City's judgment and sole discretion, raises other party on prior projects which, in the City's judgment and sole discretion, raises party on prior projects which, in the City's judgment and sole discretion, raises doubts as to Supplier's ability to properly perform the work;

3.3.12.6. Any offering of gifts, unauthorized compensation or other unethical actions to City employees with respect to interest in any business activity; or

3.3.12.7. Any other cause which, in the City's judgment and sole discretion, is sufficient to justify disqualification of the supplier or…