Section 33 71 02.doc
DOC document 91 KB Posted
- Attached to
- Request for Proposals- New Modular office, including demolition, at the William J. Hughes Technical CEnter
- Solicitation number
- 25350
About this file
Section 33 71 02 (doc)
View the file
Other files
Show 40 more
Latest 50 of 149 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Modular Office Building No. 365
2016005
SECTION 33 71 02
UNDERGROUND ELECTRICAL DISTRIBUTION
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASSOCIATION OF EDISON ILLUMINATING COMPANIES (AEIC)
AEIC CS8
(2013) Specification for Extruded Dielectric Shielded Power Cables Rated 5 Through 46 kV
ASTM INTERNATIONAL (ASTM)
ASTM B3
(2013) Standard Specification for Soft or Annealed Copper Wire
ASTM B496
(2014) Standard Specification for Compact Round Concentric-Lay-Stranded Copper Conductors
ASTM B8
(2011) Standard Specification for Concentric-Lay-Stranded Copper Conductors, Hard, Medium-Hard, or Soft
ASTM F512
(2012) Smooth-Wall Poly (Vinyl Chloride) (PVC) Conduit and Fittings for Underground Installation
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 386
(2006; INT 1 2011) Standard for Separable Insulated Connector Systems for Power Distribution Systems Above 600V
IEEE 400.2
(2013) Guide for Field Testing of Shielded Power Cable Systems Using Very Low Frequency (VLF)
IEEE 404
(2012) Standard for Extruded and Laminated Dielectric Shielded Cable Joints Rated 2500 V to 500,000 V
IEEE 48
(2009) Standard for Test Procedures and Requirements for Alternating-Current Cable Terminations Used on Shielded Cables Having Laminated Insulation Rated 2.5 kV through 765 kV or Extruded Insulation Rated 2.5 kV through 500 kV
IEEE C2
(2012; Errata 1 2012; INT 1-4 2012; Errata 2 2013; INT 5-7 2013; INT 8-10 2014; INT 11 2015) National Electrical Safety Code IEEE Stds Dictionary (2009) IEEE Standards Dictionary: Glossary of Terms & Definitions
INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)
NETA ATS
(2013) Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA TC 6 & 8
(2013) Standard for Polyvinyl Chloride (PVC) Plastic Utilities Duct for Underground Installations
NEMA TC 7
(2013) Standard for Smooth-Wall Coilable Electrical Polyethylene Conduit
NEMA TC 9
(2004) Standard for Fittings for Polyvinyl Chloride (PVC) Plastic Utilities Duct for Underground Installation
NEMA WC 70
(2009) Power Cable Rated 2000 V or Less for the Distribution of Electrical Energy--S95-658
NEMA WC 74/ICEA S-93-639
(2012) 5-46 kV Shielded Power Cable for Use in the Transmission and Distribution of Electric Energy
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70
(2014; AMD 1 2013; Errata 1 2013; AMD 2 2013; Errata 2 2013; AMD 3 2014; Errata 3-4 2014; AMD 4-6 2014) National Electrical Code
SOCIETY OF CABLE TELECOMMUNICATIONS ENGINEERS (SCTE)
ANSI/SCTE 77
(2013) Specification for Underground Enclosure Integrity
TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)
TIA-758
(2012b) Customer-Owned Outside Plant Telecommunications Infrastructure Standard
U.S. DEPARTMENT OF AGRICULTURE (USDA)
RUS Bull 1751F-644 (2002) Underground Plant Construction
UNDERWRITERS LABORATORIES (UL)
UL 1072
(2006; Reprint Jun 2013) Medium-Voltage Power Cables
UL 467
(2007) Grounding and Bonding Equipment
UL 486A-486B
(2013; Reprint Jan 2016) Wire Connectors
UL 510
(2005; Reprint Jul 2013) Polyvinyl Chloride, Polyethylene and Rubber Insulating Tape
UL 651
(2011; Reprint May 2014) Standard for Schedule 40 and 80 Rigid PVC Conduit and Fittings
UL 83
(2014) Thermoplastic-Insulated Wires and Cables
UL 94
(2013; Reprint Jan 2016) Standard for Tests for Flammability of Plastic Materials for Parts in Devices and Appliances
1.2 RELATED REQUIREMENTS
Section 26 00 00 BASIC ELECTRICAL MATERIALS AND METHODS applies to this section, with the additions and modifications specified herein.
1.3 DEFINITIONS
a. Unless otherwise specified or indicated, electrical and electronics terms used in these specifications, and on the drawings, are as defined in IEEE Stds Dictionary.
b. In the text of this section, the words conduit and duct are used interchangeably and have the same meaning.
c. In the text of this section, "medium voltage cable splices," and "medium voltage cable joints" are used interchangeably and have the same meaning.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are [for Contractor Quality Control approval.][for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data Medium voltage cable; G Medium voltage cable joints; G Medium voltage cable terminations; G Sealing Material Composite/fiberglass handholes; G Cable supports (racks, arms and insulators); G Protective Devices and Coordination Study; G The study must be submitted with protective device equipment submittals. No time extension or similar contract modifications will be granted for work arising out of the requirements for this study. Approval of protective devices proposed must be based on recommendations of this study. The Government must not be held responsible for any changes to equipment, device ratings, settings, or additional labor for installation of equipment or devices ordered or procured prior to approval of the study.
SD-06 Test Reports Field Acceptance Checks and Tests; G SD-07 Certificates Cable splicer/terminator; G Cable Installer Qualifications; G
1.5 QUALITY ASSURANCE
1.5.1 Certificate of Competency for Cable Splicer/Terminator
Certification of the qualification of the cable splicer/terminator shall be submitted, for approval, 30 days before splices or terminations are to be made in medium voltage (5 kV to 35 kV) cables. The certification shall include the training, and experience of the individual on the specific type and classification of cable to be provided under this contract. The certification shall indicate that the individual has had three or more years recent experience splicing and terminating medium voltage cables. The certification shall also list a minimum of three splices/terminations that have been in operation for more than one year. In addition, the individual may be required to perform a dummy or practice splice/termination in the presence of the Contracting Officer, before being approved as a qualified cable splicer. If that additional requirement is imposed, the Contractor shall provide short sections of the approved types of cables along with the approved type of splice/termination kit, and detailed manufacturer's instructions for the cable to be spliced. The Contracting Officer reserves the right to require additional proof of competency or to reject the individual and call for certification of an alternate cable splicer.
1.5.2 Cable Installer Qualifications
Provide at least one onsite person in a supervisory position with a documentable level of competency and experience to supervise all cable pulling operations. Provide a resume showing the cable installers' experience in the last three years, including a list of references complete with points of contact, addresses and telephone numbers. Cable installer must demonstrate experience with a minimum of three medium voltage cable installations. The Contracting Officer reserves the right to require additional proof of competency or to reject the individual and call for an alternate qualified cable installer.
1.5.3 Regulatory Requirements
In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the word, "must" had been substituted for "should" wherever it appears. Interpret references in these publications to the "authority having jurisdiction," or words of similar meaning, to mean the Contracting Officer. Equipment, materials, installation, and workmanship must be in accordance with the mandatory and advisory provisions of IEEE C2 and NFPA 70 unless more stringent requirements are specified or indicated.
1.5.4 Standard Products
Provide materials and equipment that are products of manufacturers regularly engaged in the production of such products which are of equal material, design and workmanship. Products must have been in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2-year period must include applications of equipment and materials under similar circumstances and of similar size. The product must have been for sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2-year period. Where two or more items of the same class of equipment are required, these items must be products of a single manufacturer; however, the component parts of the item need not be the products of the same manufacturer unless stated in this section.
1.5.4.1 Alternative Qualifications
Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory field operation for not less than 6000 hours, exclusive of the manufacturers' factory or laboratory tests, is furnished.
1.5.4.2 Material and Equipment Manufacturing Date
Products manufactured more than 3 years prior to date of delivery to site are not acceptable, unless specified otherwise.
PART 2 PRODUCTS
2.1 CONDUIT, DUCTS, AND FITTINGS
2.1.1 Duct Sealant
UL 94, Class HBF. Provide high-expansion urethane foam duct sealant that expands and hardens to form a closed, chemically and water resistant, rigid structure. Sealant must be compatible with common cable and wire jackets and capable of adhering to metals, plastics and concrete. Sealant must be capable of curing in temperature ranges of 2 degrees C to 35 degrees C (35 degrees F to 95 degrees F). Cured sealant must withstand temperature ranges of -29 degrees C to 93 degrees C (-20 degrees F to 200 degrees F) without loss of function.
2.1.2 Fittings
2.1.2.1 PVC Conduit Fittings
NEMA TC 3.
2.1.2.2 PVC Duct Fittings
NEMA TC 9.
2.2 LOW VOLTAGE INSULATED CONDUCTORS AND CABLES
Insulated conductors must be rated 600 volts and conform to the requirements of NFPA 70, including listing requirements. Wires and cables manufactured more than 12 months prior to date of delivery to the site are not acceptable. Service entrance conductors must conform to UL 854, type USE.
2.2.1 Conductor Types
Cable and duct sizes indicated are for copper conductors and THHN/THWN unless otherwise noted. Conductors No. 10 AWG and smaller must be solid. Conductors No. 8 AWG and larger must be stranded. All conductors must be copper.
2.2.2 Conductor Material
Unless specified or indicated otherwise or required by NFPA 70, wires in conduit, other than service entrance, must be 600-volt, Type THWN/THHN conforming to UL 83. Copper conductors must be annealed copper complying with ASTM B3 and ASTM B8.
2.2.3 Jackets
Multiconductor cables must have an overall PVC outer jacket.
2.2.4 In Duct
Cables must be single-conductor cable.
2.2.5 Cable Marking
Insulated conductors must have the date of manufacture and other identification imprinted on the outer surface of each cable at regular intervals throughout the cable length.
Identify each cable by means of a fiber, laminated plastic, or non-ferrous metal tags, or approved equal, in each manhole, handhole, junction box, and each terminal. Each tag must contain the following information; cable type, conductor size, circuit number, circuit voltage, cable destination and phase identification.
Conductors must be color coded. Provide conductor identification within each enclosure where a tap, splice, or termination is made. Conductor identification must be by color-coded insulated conductors, plastic-coated self-sticking printed markers, colored nylon cable ties and plates, heat shrink type sleeves,or colored electrical tape. Control circuit terminations must be properly identified. Color must be green for grounding conductors and white for neutrals; except where neutrals of more than one system are installed in same raceway or box, other neutrals must be white with a different colored (not green) stripe for each. Color of ungrounded conductors in different voltage systems must be as follows:
a. 208/120 volt, three-phase
(1) Phase A - black
(2) Phase B - red
(3) Phase C - blue
b. 480/277 volt, three-phase
(1) Phase A - brown
(2) Phase B - orange
(3) Phase C - yellow
c. 120/240 volt, single phase: Black and red
2.3 LOW VOLTAGE WIRE CONNECTORS AND TERMINALS
Must provide a uniform compression over the entire conductor contact surface. Use solderless terminal lugs on stranded conductors.
a. For use with copper conductors: UL 486A-486B.
2.4 MEDIUM VOLTAGE CABLE
Cable (conductor) sizes are designated by American Wire Gauge (AWG) and Thousand Circular Mils (Kcmil). Conductor and conduit sizes indicated are for copper conductors unless otherwise noted. Insulated conductors must have the date of manufacture and other identification imprinted on the outer surface of each cable at regular intervals throughout cable length. Wires and cables manufactured more than 12 months prior to date of delivery to the site are not acceptable. Provide single conductor type cables unless otherwise indicated.
2.4.1 Cable Configuration
Provide Type MV cable, conforming to NEMA WC 74/ICEA S-93-639 and UL 1072. Provide cables manufactured for use in direct burial applications. Cable must be rated 5 kV with 133 percent insulation level.
2.4.2 Conductor Material
Provide concentric-lay-stranded, Class B conductors. Provide soft drawn copper cables complying with ASTM B3 and ASTM B8 for regular concentric and compressed stranding or ASTM B496 for compact stranding.
2.4.3 Insulation
Provide ethylene-propylene-rubber (EPR) insulation conforming to the requirements of ANSI/NEMA WC 71/ICEA S-96-659 and AEIC CS8.
2.4.4 Shielding
Cables rated for 2 kV and above must have a semiconducting conductor shield, a semiconducting insulation shield, and an overall copper tape shield for each phase.
2.4.5 Neutrals
Neutral conductors must be copper, employing the same insulation and jacket materials as phase conductors, except that a 600-volt insulation rating is acceptable.
2.5 MEDIUM VOLTAGE CABLE TERMINATIONS
IEEE 48 Class 1; of the molded elastomer, prestretched elastomer, or heat-shrinkable elastomer. Acceptable elastomers are track-resistant silicone rubber or track-resistant ethylene propylene compounds, such as ethylene propylene rubber or ethylene propylene diene monomer. Separable insulated connectors may be used for apparatus terminations, when such apparatus is provided with suitable bushings. Terminations, where required, must be provided with mounting brackets suitable for the intended installation and with grounding provisions for the cable shielding, metallic sheath, or armor. Terminations must be provided in a kit, including: skirts, stress control terminator, ground clamp, connectors, lugs, and complete instructions for assembly and installation. Terminations must be the product of one manufacturer, suitable for the type, diameter, insulation class and level, and materials of the cable terminated. Do not use separate parts of copper or copper alloy in contact with aluminum alloy parts in the construction or installation of the terminator.
2.5.1 Separable Insulated Connector Type
IEEE 386. Provide connector with steel reinforced hook-stick eye, grounding eye, test point, and arc-quenching contact material. Provide connectors of the loadbreak or deadbreak type as indicated, of suitable construction for the application and the type of cable connected, and that include cable shield adaptors. Provide external clamping points and test points. Separable connectors must not be used in manholes/handholes.
a. 200 Ampere loadbreak connector ratings: Voltage: 15 kV, 95 kV BIL. Short time rating: 10,000 rms symmetrical amperes.
b. 600 Ampere deadbreak connector ratings: Voltage: 15 kV, 95 kV BIL. Short time rating: 25,000 rms symmetrical amperes
2.6 TAPE
2.6.1 Insulating Tape
UL 510, plastic insulating tape, capable of performing in a continuous temperature environment of 80 degrees C.
2.6.2 Buried Warning and Identification Tape
Provide detectable tape.
2.6.3 Fireproofing Tape
Provide tape composed of a flexible, conformable, unsupported intumescent elastomer. Tape must be not less than 0.762 mm (.030 inch) thick, noncorrosive to cable sheath, self-extinguishing, noncombustible, adhesive-free, and must not deteriorate when subjected to oil, water, gases, salt water, sewage, and fungus.
2.7 PULL ROPE
Plastic or flat pull line (bull line) having a minimum tensile strength of 890 N (200 pounds).
2.8 GROUNDING AND BONDING
2.8.1 Driven Ground Rods
Provide solid copper ground rods conforming to UL 467 not less than 19 mm (3/4 inch) in diameter by 3.1 m (10 feet) in length. Sectional type rods may be used for rods 20 feet or longer.
2.8.2 Grounding Conductors
Stranded-bare copper conductors must conform to ASTM B8, Class B, soft-drawn unless otherwise indicated. Solid-bare copper conductors must conform to ASTM B1 for sizes No. 8 and smaller. Insulated conductors must be of the same material as phase conductors and green color-coded, except that conductors must be rated no more than 600 volts. Aluminum is not acceptable.
2.9 Composite/Fiberglass Handholes and Covers
ANSI/SCTE 77. Provide handholes and covers of polymer concrete, reinforced with heavy weave fiberglass with a design load (Tier rating) appropriate for or greater than the intended use. All covers are required to have the Tier level rating embossed on the surface and this rating must not exceed the design load of the box.
2.10 CABLE TAGS IN MANHOLES
Provide tags for each power cable located in manholes. The tags must be polyethylene. Do not provide handwritten letters. The first position on the power cable tag must denote the voltage. The second through sixth positions on the tag must identify the circuit. The next to last position must denote the phase of the circuit and include the Greek "phi" symbol. The last position must denote the cable size. As an example, a tag could have the following designation: "11.5 NAS 1-8(Phase A)500," denoting that the tagged cable is on the 11.5kV system circuit number NAS 1-8, underground, Phase A, sized at 500 kcmil.
2.10.1 Polyethylene Cable Tags
Provide tags of polyethylene that have an average tensile strength of 22.4 MPa (3250 pounds per square inch); and that are 2 millimeter (0.08 inch) thick (minimum), non-corrosive non-conductive; resistive to acids, alkalis, organic solvents, and salt water; and distortion resistant to 77 degrees C (170 degrees F). Provide 1.3 mm (0.05 inch) minimum thick black polyethylene tag holder. Provide a one-piece nylon, self-locking tie at each end of the cable tag. Ties must have a minimum loop tensile strength of 778.75 N (175 pounds). The cable tags must have black block letters, numbers, and symbols 25 mm (one inch) high on a yellow background. Letters, numbers, and symbols must not fall off or change positions regardless of the cable tags' orientation.
2.11 MEDIUM VOLTAGE CABLE TERMINATING CABINETS
Cable terminating cabinets must be hook-stick operable, deadfront construction conforming to the requirements of IEEE C37.20.3, Category A. Provide cabinets with 200 A. loadbreak junctions and elbow-type separable loadbreak connectors, cable parking stands, and grounding lugs. Provide cable terminating equipment in conformance with IEEE 386.
PART 3 EXECUTION
3.1 INSTALLATION
Install equipment and devices in accordance with the manufacturer's published instructions and with the requirements and recommendations of NFPA 70 and IEEE C2 as applicable. In addition to these requirements, install telecommunications in accordance with TIA-758 and RUS Bull 1751F-644.
3.2 CABLE INSPECTION
Inspect each cable reel for correct storage positions, signs of physical damage, and broken end seals prior to installation. If end seal is broken, remove moisture from cable prior to installation in accordance with the cable manufacturer's recommendations.
3.3 Trenching
Excavate trenches for direct-burial cables to provide a minimum cable cover of 610 mm (24 inches) below finished grade for power conductors operated at 600 volts or less, and 765 mm (30 inches) below finished grade for over 600 volts in accordance with IEEE C2. When rock is encountered, remove to a depth of at least 75 mm (3 inches) below the cable and fill the space with sand or clean earth free from particles larger than 6 mm (1/4 inch). Bottoms of trenches must be smooth and free of stones and sharp objects. Where materials in bottoms of trenches are other than sand, a 75 mm 3 inch layer of sand must be laid first and compacted to approximate densities of surrounding firm soil. Trenches must be not less than 12 inches) wide, and must be in straight lines between cable markers Bends in trenches must have a radius consistent with the cable manufacturer's published minimum cable bending radius for the cable installed.
3.3.1 Cable Installation
Unreel cables along the sides of or in trenches and carefully place on sand or earth bottoms. Pulling cables into direct-burial trenches from a fixed reel position is not permitted, except as required to pull cables through conduits under paving or railroad tracks.
Where two or more cables are laid parallel in the same trench, space cables laterally at not less than 75 mm (3 inches) apart, except that communication cable must be separated from power cable by a minimum distance of 305 mm (12 inches).
3.3.2 Bends
Bends in cables must have an inner radius not less than those specified in NFPA 70 for the type of cable, or manufacturer's recommendation.
3.3.3 Horizontal Slack
Leave approximately 915 mm (3 feet) of horizontal slack in the ground on each end of cable runs, on each side of connection boxes, and at points where connections are brought above ground. Where cable is brought above ground, leave additional slack to make necessary connections.
3.4 UNDERGROUND CONDUIT AND DUCT SYSTEMS
3.4.1 Requirements
Run conduit in straight lines except where a change of direction is necessary. Provide numbers and sizes of ducts as indicated. Provide a 4/0 AWG bare copper grounding conductor above medium-voltage distribution duct banks. Bond bare copper grounding conductor to ground rings (loops) in all manholes and to ground rings (loops) at all equipment slabs (pads). Route grouding conductor into manholes with the duct bank (sleeving is not required). Ducts must have a continuous slope downward toward underground structures and away from buildings, laid with a minimum slope of 100 mm per 30 m (4 inches per 100 feet). Depending on the contour of the finished grade, the high-point may be at a terminal, a manhole, a handhole, or between manholes or handholes. Provide ducts with end bells whenever duct lines terminate in structures.
Perform changes in ductbank direction as follows:
a. Short-radius manufactured 90-degree duct bends may be used only for pole or equipment risers, unless specifically indicated as acceptable.
b. The minimum manufactured bend radius must be 450 mm (18 inches) for ducts of less than 80 mm (3 inch) diameter, and 900 mm (36 inches) for ducts 80 mm (3 inches) or greater in diameter.
c. As an exception to the bend radius required above, provide field manufactured longsweep bends having a minimum radius of 7.6 m (25 feet) for a change of direction of more than 5 degrees, either horizontally or vertically, using a combination of curved and straight sections. Maximum manufactured curved sections: 30 degrees.
3.4.2 Treatment
Ducts must be kept clean of concrete, dirt, or foreign substances during construction. Field cuts requiring tapers must be made with proper tools and match factory tapers. A coupling recommended by the duct manufacturer must be used whenever an existing duct is connected to a duct of different material or shape. Ducts must be stored to avoid warping and deterioration with ends sufficiently plugged to prevent entry of any water or solid substances. Ducts must be thoroughly cleaned before being laid. Plastic ducts must be stored on a flat surface and protected from the direct rays of the sun.
3.4.3 Conduit Cleaning
As each conduit run is completed, for conduit sizes 75 mm (3 inches) and larger, draw a flexible testing mandrel approximately 305 mm (12 inches) long with a diameter less than the inside diameter of the conduit through the conduit. After which, draw a stiff bristle brush through until conduit is clear of particles of earth, sand and gravel; then immediately install conduit plugs. For conduit sizes less than 75 mm (3 inches), draw a stiff bristle brush through until conduit is clear of particles of earth, sand and gravel; then immediately install conduit plugs.
3.4.4 Multiple Conduits
Separate multiple conduits by a minimum distance of 75 mm (3 inches), except that light and power conduits must be separated from control, signal, and telephone conduits by a minimum distance of 300 mm ([12] inches
3.4.5 Duct Sealing
Seal all electrical penetrations for radon mitigation, maintaining integrity of the vapor barrier, and to prevent infiltration of air, insects, and vermin.
3.5 CABLE PULLING
Test existing duct lines with a mandrel and thoroughly swab out to remove foreign material before pulling cables. Pull cables down grade with the feed-in point at the manhole or buildings of the highest elevation. Use flexible cable feeds to convey cables through manhole opening and into duct runs. Do not exceed the specified cable bending radii when installing cable under any conditions, including turnups into switches, transformers, switchgear, switchboards, and other enclosures. Cable with tape shield must have a bending radius not less than 12 times the overall diameter of the completed cable. If basket-grip type cable-pulling devices are used to pull cable in place, cut off the section of cable under the grip before splicing and terminating.
3.5.1 Cable Lubricants
Use lubricants that are specifically recommended by the cable manufacturer for assisting in pulling jacketed cables.
3.6 CONDUCTORS INSTALLED IN PARALLEL
Conductors must be grouped such that each conduit of a parallel run contains 1 Phase A conductor, 1 Phase B conductor, 1 Phase C conductor, and 1 neutral conductor.
3.7 MEDIUM VOLTAGE CABLE TERMINATIONS
Make terminations in accordance with the written instruction of the termination kit manufacturer.
3.8 FIREPROOFING OF CABLES IN UNDERGROUND STRUCTURES
Fireproof (arc proof) wire and cables which will carry current at 2200 volts or more in underground structures.
3.8.1 Fireproofing Tape
Tightly wrap strips of fireproofing tape around each cable spirally in half-lapped wrapping. Install tape in accordance with manufacturer's instructions.
3.9 GROUNDING SYSTEMS
NFPA 70 and IEEE C2, except provide grounding systems with a resistance to solid earth ground not exceeding 25 ohms.
3.9.1 Grounding Electrodes
Provide cone pointed driven ground rods driven full depth plus 300 mm (12 inches), installed to provide an earth ground of the appropriate value for the particular equipment being grounded.
If the specified ground resistance is not met, an additional ground rod must be provided in accordance with the requirements of NFPA 70 (placed not less than 6 feet from the first rod). Should the resultant (combined) resistance exceed the specified resistance, measured not less than 48 hours after rainfall, notify the Contracting Officer immediately.
3.9.2 Grounding Connections
Make grounding connections which are buried or otherwise normally inaccessible, by exothermic weld.
a. Make exothermic welds strictly in accordance with the weld manufacturer's written recommendations. Welds which are "puffed up" or which show convex surfaces indicating improper cleaning are not acceptable. Mechanical connectors are not required at exothermic welds.
3.9.3 Grounding Conductors
Provide bare grounding conductors, except where installed in conduit with associated phase conductors. Ground cable sheaths, cable shields, conduit, and equipment with No. 6 AWG. Ground other noncurrent-carrying metal parts and equipment frames of metal-enclosed equipment. Ground metallic frames and covers of handholes and pull boxes with a braided, copper ground strap with equivalent ampacity of No. 6 AWG.
3.9.4 Trailer Grounding
Provide a 4/0 AWG grounding conductor to trailer frame. Secure the conductor to the trailer frame at intervals not exceeding 457 mm (18 inches). Connect all grounding conductors to the ground loop adjacent to the point of tap.
3.10 EXCAVATING, BACKFILLING, AND COMPACTING
Provide in accordance with NFPA 70.
3.10.1 Reconditioning of Surfaces
3.10.1.1 Unpaved Surfaces
Restore to their original elevation and condition unpaved surfaces disturbed during installation of duct or direct burial cable. Preserve sod and topsoil removed during excavation and reinstall after backfilling is completed. Replace sod that is damaged by sod of quality equal to that removed. When the surface is disturbed in a newly seeded area, re-seed the restored surface with the same quantity and formula of seed as that used in the original seeding, and provide topsoiling, fertilizing, liming, seeding, sodding, sprigging, or mulching.
3.11 FIELD QUALITY CONTROL
3.11.1 Performance of Field Acceptance Checks and Tests
Perform in accordance with the manufacturer's recommendations, and include the following visual and mechanical inspections and electrical tests, performed in accordance with NETA ATS.
3.11.1.1 Medium Voltage Cables
Perform tests after installation of cable, splices, and terminators and before terminating to equipment or splicing to existing circuits.
a. Visual and Mechanical Inspection
(1) Inspect exposed cable sections for physical damage.
(2) Verify that cable is supplied and connected in accordance with contract plans and specifications.
(3) Inspect for proper shield grounding, cable support, and cable termination.
(4) Verify that cable bends are not less than ICEA or manufacturer's minimum allowable bending radius.
(5) Inspect for proper fireproofing.
(6) Visually inspect jacket and insulation condition.
(7) Inspect for proper phase identification and arrangement.
b. Electrical Tests
(1) Perform a shield continuity test on each power cable by ohmmeter method. Record ohmic value, resistance values in excess of 10 ohms per 1000 feet of cable must be investigated and justified.
(2) Perform acceptance test on new cables before the new cables are connected to existing cables and placed into service, including terminations and joints. Perform maintenance test on complete cable system after the new cables are connected to existing cables and placed into service, including existing cable, terminations, and joints. Tests must be very low frequency (VLF) alternating voltage withstand tests in accordance with IEEE 400.2. VLF test frequency must be 0.05 Hz minimum for a duration of 60 minutes using a sinusoidal waveform. Test voltages must be as follows:
CABLE RATING AC TEST VOLTAGE for ACCEPTANCE TESTING
| 5 kV |
| 10kV rms(peak) |
| 8 kV |
| 13kV rms(peak) |
| 15 kV |
| 20kV rms(peak) |
| 25 kV |
| 31kV rms(peak) |
| 35 kV |
| 44kV rms(peak) |
CABLE RATING AC TEST VOLTAGE for MAINTENANCE TESTING
| 5 kV |
| 7kV rms(peak) |
| 8 kV |
| 10kV rms(peak) |
| 15 kV |
| 16kV rms(peak) |
| 25 kV |
| 23kV rms(peak) |
| 35 kV |
| 33kV rms(peak) |
3.11.1.2 Low Voltage Cables, 600-Volt
Perform tests after installation of cable, splices and terminations and before terminating to equipment or splicing to existing circuits.
a. Visual and Mechanical Inspection
(1) Inspect exposed cable sections for physical damage.
(2) Verify that cable is supplied and connected in accordance with contract plans and specifications.
(3) Verify tightness of accessible bolted electrical connections.
(4) Inspect compression-applied connectors for correct cable match and indentation.
(5) Visually inspect jacket and insulation condition.
(6) Inspect for proper phase identification and arrangement.
b. Electrical Tests
(1) Perform insulation resistance tests on wiring No. 6 AWG and larger diameter using instrument which applies voltage of approximately 1000 volts dc for one minute.
(2) Perform continuity tests to insure correct cable connection.
3.11.1.3 Grounding System
a. Visual and mechanical inspection Inspect ground system for compliance with contract plans and specifications.
b. Electrical tests Perform ground-impedance measurements utilizing the fall-of-potential method in accordance with IEEE 81. On systems consisting of interconnected ground rods, perform tests after interconnections are complete. On systems consisting of a single ground rod perform tests before any wire is connected. Take measurements in normally dry weather, not less than 48 hours after rainfall. Use a portable ground resistance tester in accordance with manufacturer's instructions to test each ground or group of grounds. The instrument must be equipped with a meter reading directly in ohms or fractions thereof to indicate the ground value of the ground rod or grounding systems under test. Provide site diagram indicating location of test probes with associated distances, and provide a plot of resistance vs. distance.
3.11.2 Follow-Up Verification
Upon completion of acceptance checks and tests, show by demonstration in service that circuits and devices are in good operating condition and properly performing the intended function. As an exception to requirements stated elsewhere in the contract, the Contracting Officer must be given 5 working days advance notice of the dates and times of checking and testing.
-- End of Section -- Section 33 71 02 Page 1