250319 Addendum #2 - Project Schedule 3.14.25.pdf

PDF 225 KB Posted

Attached to
Material Testing and 3rd Party Inspections
Solicitation number
RFP_F-BSFD-0000000002
Issued by
Gallatin County, Montana

About this file

This document is a detailed project schedule for the Big Sky Fire Department's Fire Station No. 3 project, located in Big Sky, Montana. The comprehensive Gantt chart spans from March 2025 to November 2026, detailing a multi-phase construction timeline across numerous critical path activities. The project schedule encompasses administrative tasks, site preparation, geothermal work, structural framing, concrete phases, exterior and interior construction, mechanical and electrical rough-ins, and closeout activities. Key milestone dates include the GMP Contract Execution on 4/1/25, first day on site on 5/19/25, substantial completion on 10/26/26, and final building turnover on 11/25/26.

The schedule demonstrates a meticulously planned 20-month construction process with intricate dependencies between 233 distinct tasks. The project involves constructing a 10,273 square foot two-story fire station with multiple functional areas including three drive-through bays, sleeping quarters, offices, and support spaces. The schedule highlights specialized construction phases like geothermal well drilling, manifold installations, structural framing, exterior barriers, and interior finish work. The timeline incorporates considerations for winter delays, site preparation, utilities installation, and comprehensive mechanical, electrical, and plumbing rough-in and trim-out work, reflecting a holistic approach to fire station construction in a potentially challenging mountain environment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Duration Start Finish Predecessors Resource Names

1 Administrative 25 days Tue 4/1/25 Mon 5/5/25

2 GMP Contract Executed 0 days Tue 4/1/25 Tue 4/1/25

3 Request P&P Bond 1 day Tue 4/1/25 Tue 4/1/25 2

4 Subcontracts Issued 5 days Tue 4/1/25 Mon 4/7/25 2

5 Permit Delivered 0 days Mon 4/7/25 Mon 4/7/25 4

6 Submittal Assignment 20 days Tue 4/8/25 Mon 5/5/25 4

7 Long Lead Procurement 25 days Tue 5/6/25 Mon 6/9/25

8 Steel - Submit Shop Drawings and

Long Lead

25 days Tue 5/6/25 Mon 6/9/25 6

9 GLB Trusses - Submit Shop Drawings and Long Lead

20 days Tue 5/6/25 Mon 6/2/25 6

10 Mechanical - Submit Shop Drawings and Long Lead

25 days Tue 5/6/25 Mon 6/9/25 6

11 Electrical - Submit Shop Drawings and Long Lead

25 days Tue 5/6/25 Mon 6/9/25 6

12 Geothermal - Submit Shop Drawings and Long Lead

25 days Tue 5/6/25 Mon 6/9/25 6

13 Plumbing - Submit Shop Drawings and Long Lead

25 days Tue 5/6/25 Mon 6/9/25 6

14 Electrical - Submit Shop Drawings and Long Lead

25 days Tue 5/6/25 Mon 6/9/25 6

15 Detail, Fabricate, Deliver Steel 45 days Tue 6/10/25 Mon 8/11/258

16 LML Remaining Scope 57 days Mon 5/19/25Tue 8/5/25

17 1st Day On Site 0 days Mon 5/19/25Mon 5/19/25 Ridgeline Excavation

18 Snow Removal 2 days Mon 5/19/25Tue 5/20/25 17

19 Relocate Utillities 4 days Wed 5/21/25Mon 5/26/2518

20 Pour Curbs - TBD 1 day Mon 8/4/25 Mon 8/4/25

21 Pave Drive - TBD 1 day Tue 8/5/25 Tue 8/5/25 20

22 R&R Taylor - NTP 0 days Mon 5/26/25Mon 5/26/2519

23 Mobilization / Excavation 134 days Tue 5/27/25 Fri 11/28/25

24 Overall Site Prep 25 days Tue 5/27/25 Mon 6/30/25

25 Snow Removal 2 days Tue 5/27/25 Wed 5/28/2519

26 Install BMPs 1 day Thu 5/29/25 Thu 5/29/25 25

27 Clear & Grub 3 days Fri 5/30/25 Tue 6/3/25 26

28 Cut to Subgrade 15 days Wed 6/4/25 Tue 6/24/25 27

29 Overex Hauloff 15 days Wed 6/4/25 Tue 6/24/25 28SS

30 Job Trailer Mobilization 3 days Wed 6/25/25Fri 6/27/25 29

31 Set up Site Fence 4 days Wed 6/25/25Mon 6/30/2529

32 Establish Laydown Area 4 days Wed 6/25/25Mon 6/30/2529

33 Living Quarters 58 days Wed 6/25/25Fri 9/12/25

34 Dig Footers - Living Quarters 3 days Wed 6/25/25Fri 6/27/25 28,29

35 Footer Drains - Living Quarters 3 days Wed 9/3/25 Fri 9/5/25 70

36 Backfill Foundation - Living Quarters5 days Mon 9/8/25 Fri 9/12/25 35

37 App Bay Prep 65 days Mon 6/30/25Fri 9/26/25

38 Stuctural Ex - App Bay 5 days Mon 6/30/25Fri 7/4/25 34

39 Sub Ex 3' - App Bay 2 days Mon 7/7/25 Tue 7/8/25 38

40 Excavate Geo Trench under App Bay2 days Wed 7/9/25 Thu 7/10/25 39

41 Install Manifold Sleeves & Backfill 1 day Fri 7/11/25 Fri 7/11/25 40

42 Place & Compact 3' - App Bay 2 days Mon 7/14/25Tue 7/15/25 41

43 Backfill - App Bay 2 days Thu 9/25/25 Fri 9/26/25 94

44 Civil/Utilities 23 days Mon 9/29/25Wed 10/29/25

45 Set Sand/Oil Separator 2 days Mon 9/29/25Tue 9/30/25 43

46 Water Line 6 days Wed 10/1/25Wed 10/8/2545

47 Sanitary Sewer 7 days Thu 10/9/25 Fri 10/17/25 46

48 Storm Drain 8 days Mon 10/20/25Wed 10/29/2547

49 Parking Structure Prep 22 days Thu 10/30/25Fri 11/28/25

50 Dig Footers - Parking Structure 2 days Thu 10/30/25Fri 10/31/25 48

51 Footer Drains 1 day Mon 11/3/25Mon 11/3/2550

52 Backfill Foundation - Parking Structure1 day Mon 11/24/25Mon 11/24/25105,56

53 Set Boulder Retaining Wall 5 days Mon 11/24/25Fri 11/28/25 52SS

54 Parking Lot Prep 6 days Tue 11/4/25 Tue 11/11/25

55 Place Pit Run - West 2 days Tue 11/4/25 Wed 11/5/2551

56 Place Pit Run - East 2 days Thu 11/6/25 Fri 11/7/25 55

57 Road Base 2 days Mon 11/10/25Tue 11/11/2556

58 Concrete 105 days Mon 6/30/25Fri 11/21/25 Allied Concrete

59 Living Quarters 81 days Mon 6/30/25Mon 10/20/25

60 Mat Slab - Elevator Pit 5 days Mon 6/30/25Fri 7/4/25

61 Form & Bar Footers 4 days Mon 6/30/25Thu 7/3/25 34

62 Pour Footers 1 day Fri 7/4/25 Fri 7/4/25 61

63 Footers - Living Quarters 7 days Mon 7/7/25 Tue 7/15/25

64 Form & Bar Footers 6 days Mon 7/7/25 Mon 7/14/2562

65 Pour Footers 1 day Tue 7/15/25 Tue 7/15/25 64

66 Walls - Living Quarters 35 days Wed 7/16/25Tue 9/2/25

67 Form & Bar Walls 32 days Wed 7/16/25Thu 8/28/25 65

68 Set Steel Base Plates 2 days Wed 8/27/25Thu 8/28/25 67FF Framer

69 Pour Walls 1 day Fri 8/29/25 Fri 8/29/25 67

70 Strip Forms & Cleanup 2 days Mon 9/1/25 Tue 9/2/25 69

71 Slab - Living Quarters 26 days Mon 9/15/25Mon 10/20/25

72 Underslab Utilities 12 days Mon 9/15/25Tue 9/30/25 36 Ridgeline Excavation

73 Gravel Cushion 2 days Wed 10/1/25Thu 10/2/25 72 Ridgeline Excavation

74 Vapor Barrier & Rebar 7 days Fri 10/3/25 Mon 10/13/2573 Allied Concrete

75 Inspection Day 1 day Tue 10/14/25Tue 10/14/2574 R&R Taylor

76 Pour Slab 2 days Wed 10/15/25Thu 10/16/2575,36 Allied Concrete

77 Cure Time 2 days Fri 10/17/25 Mon 10/20/2576 Allied Concrete

78 Living Quarters - Concrete Complete0 days Mon 10/20/25Mon 10/20/2577

79 App Bay 93 days Wed 7/16/25Fri 11/21/25

80 Footers - App Bay 7 days Wed 7/16/25Thu 7/24/25

81 Form & Bar Footers 5 days Wed 7/16/25Tue 7/22/25 42

82 Pour Footers 1 day Wed 7/23/25Wed 7/23/2581

83 Strip Forms 1 day Thu 7/24/25 Thu 7/24/25 82

84 Walls - App Bay 45 days Thu 7/24/25 Wed 9/24/25

85 1st Lift 15 days Thu 7/24/25 Wed 8/13/25

86 Form & Bar Wall - 1st Lift 14 days Thu 7/24/25 Tue 8/12/25 82

87 Sleeve Forms for Drains 1 day Tue 8/12/25 Tue 8/12/25 86FF Ridgeline Excavation

88 Pour Wall - 1st Lift 1 day Wed 8/13/25Wed 8/13/2586

89 2nd Lift 15 days Thu 8/14/25 Wed 9/3/25

90 Form & Bar Wall - 2nd Lift 14 days Thu 8/14/25 Tue 9/2/25 88

91 Pour Wall - 2nd Lift 1 day Wed 9/3/25 Wed 9/3/25 90

92 3rd Lift 15 days Thu 9/4/25 Wed 9/24/25

93 Form & Bar Wall - 3rd Lift 14 days Thu 9/4/25 Tue 9/23/25 91

94 Pour Wall - 3rd Lift 1 day Wed 9/24/25Wed 9/24/2593

95 Slab - App Bay 16 days Mon 9/29/25Mon 10/20/25

96 Set Trench Drains 5 days Mon 9/29/25Fri 10/3/25 87,43 Williams

97 Underslab Utilites 5 days Mon 9/29/25Fri 10/3/25 96FF

98 Gravel Cushion 1 day Mon 10/6/25Mon 10/6/2596,97 Ridgeline Excavation

99 Vapor Barrier & Bar 8 days Tue 10/7/25 Thu 10/16/2598 Allied Concrete

100 Slab - 1st Pour 1 day Fri 10/17/25 Fri 10/17/25 99

101 Slab - 2nd Pour 1 day Mon 10/20/25Mon 10/20/25100

102 App Bay Concrete Complete 0 days Mon 10/20/25Mon 10/20/25101

103 Parking Structure 15 days Mon 11/3/25Fri 11/21/25

104 Footings 10 days Mon 11/3/25Fri 11/14/25 50

105 Site Walls 5 days Mon 11/17/25Fri 11/21/25 104

106 Site Stairs 7 days Mon 9/15/25Tue 9/23/25 36

107 Housekeeping Pads 5 days Tue 10/21/25Mon 10/27/2577,106

108 Geothermal 35 days Mon 6/30/25Fri 8/15/25

109 Mobilization 2 days Mon 6/30/25Tue 7/1/25

110 Drill West Wells 18 days Wed 7/2/25 Fri 7/25/25 109

111 Drill East Wells 15 days Mon 7/28/25Fri 8/15/25 110

112 Manifolding 32 days Mon 7/28/25Tue 9/9/25

113 West Bore Manifold Install 10 days Mon 7/28/25Fri 8/8/25 110

114 Sleeve Under App Bay 2 days Mon 8/11/25Tue 8/12/25 113

115 West Bore to Sleeve Connection 3 days Wed 8/13/25Fri 8/15/25 114

116 East Bore Manifold Install 10 days Mon 8/18/25Fri 8/29/25 115,111

117 Building Manifold Prep 7 days Mon 9/1/25 Tue 9/9/25 116

118 Manifold Underground Complete 0 days Tue 9/9/25 Tue 9/9/25 117

119 Exterior Foundation Work 7 days Mon 9/15/25Tue 9/23/25

120 Dampproofing 3 days Mon 9/15/25Wed 9/17/2536

121 Exterior Wall Insulation 4 days Thu 9/18/25 Tue 9/23/25 120

122 Framing - ROUGH 99 days Tue 10/21/25Fri 3/6/26

123 Assembly Scissor Truss in Shop 10 days Tue 10/28/25Mon 11/10/25124

124 Set Steel Columns & Beams 5 days Tue 10/21/25Mon 10/27/2578

125 Frame Load Bearing Walls & Set Ledgers5 days Tue 10/28/25Mon 11/3/25124

126 Build CMU Walls 10 days Tue 10/21/25Mon 11/3/25124SS Kidrick Masonry

127 Floor Joist & Deck 12 days Tue 11/4/25 Wed 11/19/25125

128 Pour Concrete Topping Slab 3 days Thu 11/20/25Mon 11/24/25127

129 Infill Framing 15 days Tue 11/25/25Mon 12/15/25128

130 2nd Floor Walls 15 days Tue 12/16/25Mon 1/5/26 129

131 Set PE Trusses & Partial Sheathing 5 days Tue 1/6/26 Mon 1/12/26130

132 Set GLB Scissor Trusses & Perlins 14 days Tue 1/13/26 Fri 1/30/26 131

133 Set Metal Trusses - App Bay 5 days Mon 2/2/26 Fri 2/6/26 132

134 Roof Infill Framing 5 days Mon 2/2/26 Fri 2/6/26 132

135 Sheet Remainder of Roof 5 days Mon 2/9/26 Fri 2/13/26 134

136 Install Subfascia 10 days Mon 2/16/26Fri 2/27/26 135

137 Cover Window Openings 1 day Fri 2/27/26 Fri 2/27/26 136FF

138 Temp Heat Operational 0 days Fri 2/27/26 Fri 2/27/26 137

139 Drop Ceilings 5 days Mon 3/2/26 Fri 3/6/26 138

140 Exterior Barriers 47 days Thu 2/5/26 Fri 4/10/26

151 Winter Delay - Exterior Work Pause 57 days Tue 3/17/26 Wed 6/3/26 150

152 Exterior Finishes 97 days Thu 6/4/26 Fri 10/16/26

153 Masonry Prep - Lintel & Flashing 15 days Thu 6/4/26 Wed 6/24/26151

154 Deck Roof Dry-In 2 wks Thu 6/25/26 Wed 7/8/26 153

155 Stone Masonry 10 wks Thu 6/25/26 Wed 9/2/26 153

156 Wood Siding, Soffit & Fascia 10 wks Thu 7/9/26 Wed 9/16/26155SS+2 wks

157 Gutters 3 wks Thu 9/17/26 Wed 10/7/26156

158 Hand Rail 5 days Thu 9/17/26 Wed 9/23/26156

159 Deck Pavers 2 wks Thu 9/17/26 Wed 9/30/26156

160 Metal Siding @ Site Enclosures 2 wks Thu 10/1/26 Wed 10/14/26159

161 Set Flag Pole 2 days Thu 10/15/26Fri 10/16/26 160

162 Finish Civil Work 40 days Thu 7/23/26 Wed 9/16/26

163 Final Grade Touchup 5 days Thu 7/23/26 Wed 7/29/26155SS+4 wks

164 Pour Aprons & Set Bollards 2 wks Thu 7/30/26 Wed 8/12/26163

165 Pour Sidewalks 2 wks Thu 8/13/26 Wed 8/26/26164

166 Curb & Gutter 8 days Thu 8/27/26 Mon 9/7/26 165

167 Road Base 4 days Tue 9/8/26 Fri 9/11/26 166

168 Asphalt 3 days Mon 9/14/26Wed 9/16/26167

169 Landscape 35 days Tue 9/8/26 Mon 10/26/26

170 Rough-In Irrigation 10 days Tue 9/8/26 Mon 9/21/26166

171 Set Hardscapes 5 days Tue 9/22/26 Mon 9/28/26170

172 Fill Topsoil 10 days Tue 9/29/26 Mon 10/12/26171

173 Plantings 5 days Tue 10/13/26Mon 10/19/26172

174 Grass 5 days Tue 10/20/26Mon 10/26/26173

175 Interior Rough-In 65 days Mon 2/16/26Fri 5/15/26

176 Mechanical Rough-In 45 days Mon 2/16/26Fri 4/17/26 146

177 Electrical Rough-In 45 days Mon 2/16/26Fri 4/17/26 176SS

178 Plumbing Rough-In 45 days Mon 2/16/26Fri 4/17/26 176SS

179 Fire Suppression Rough-In 20 days Mon 2/16/26Fri 3/13/26 176SS

180 Low Voltage 20 days Mon 4/20/26Fri 5/15/26 177

181 Pull Wire 15 days Mon 4/20/26Fri 5/8/26 177

182 Set Door Frames 3 days Mon 2/16/26Wed 2/18/26176SS

183 Insulation 10 days Mon 4/27/26Fri 5/8/26 186SS+5 days

184 Finish Work 115 days Mon 4/6/26 Fri 9/11/26

185 Polish Concrete 10 days Mon 4/6/26 Mon 4/20/26186SF

186 Hang Sheetrock 15 days Mon 4/20/26Fri 5/8/26 176,177,178,179

187 Tape & Texture 20 days Mon 5/11/26Fri 6/5/26 183,186

188 Paint 25 days Mon 6/8/26 Fri 7/10/26 187,139

189 Interior Ceiling Soffit 15 days Mon 7/13/26Fri 7/31/26 188

190 MEP Trim Out 25 days Mon 7/13/26Fri 8/14/26 188

191 Fire Suppression Trim Out 10 days Mon 7/13/26Fri 7/24/26 188

192 Hang Doors 5 days Mon 7/13/26Fri 7/17/26 188

193 Set Interior Storefront 10 days Mon 7/13/26Fri 7/24/26 192SS

194 Tile 15 days Mon 6/15/26Fri 7/3/26 187FS+5 days

195 Casework 20 days Mon 7/13/26Fri 8/7/26 188

196 Seal Concrete 5 days Mon 8/10/26Fri 8/14/26 195

197 Flooring 15 days Mon 8/10/26Fri 8/28/26 195

198 Rubber Base 10 days Mon 8/31/26Fri 9/11/26 197,196,194

199 Set Drop Ceilings 10 days Mon 7/13/26Fri 7/24/26 188

200 Closeout Work 278 days Sun 11/2/25 Wed 11/25/26

201 Install Div 10 Specialties 20 days Mon 8/10/26Fri 9/4/26 195

202 Install Door Hardware 10 days Mon 7/20/26Fri 7/31/26 192

203 Door Thresholds 3 days Mon 8/3/26 Wed 8/5/26 202

204 MEP Test & Balance 5 days Mon 8/17/26Fri 8/21/26 190

205 Initial Punch 20 days Mon 8/24/26Fri 9/18/26 204

206 Generator Startup 5 days Mon 9/21/26Fri 9/25/26 205

207 Building Final & Fire Final 5 days Mon 9/28/26Fri 10/2/26 206

208 C.O./Final Routing Processing 20 days Mon 10/5/26Fri 10/30/26 207

209 Substantial Completion 0 days Mon 10/26/26Mon 10/26/26205,201,174,161,198,203

210 Final Punch 13 days Mon 11/2/26Wed 11/18/26208

211 Final Clean 5 days Thu 11/19/26Wed 11/25/26210

212 Building Turnover 0 days Wed 11/25/26Wed 11/25/26211

233 12 days Sun 11/2/25 Sun 11/16/25

Administrative

GMP Contract Executed 4/1

Request P&P Bond

Subcontracts Issued

Permit Delivered 4/7

Submittal Assignment

Long Lead Procurement

Steel - Submit Shop Drawings and Long Lead

GLB Trusses - Submit Shop Drawings and Long Lead

Mechanical - Submit Shop Drawings and Long Lead

Electrical - Submit Shop Drawings and Long Lead

Geothermal - Submit Shop Drawings and Long Lead

Plumbing - Submit Shop Drawings and Long Lead

Electrical - Submit Shop Drawings and Long Lead

Detail, Fabricate, Deliver Steel

LML Remaining Scope

1st Day On Site

Snow Removal

Relocate Utillities

R&R Taylor - NTP 5/26

Mobilization / Excavation

Overall Site Prep

Snow Removal

Install BMPs

Clear & Grub

Cut to Subgrade

Overex Hauloff

Job Trailer Mobilization

Set up Site Fence

Establish Laydown Area

Living Quarters

Dig Footers - Living Quarters

Footer Drains - Living Quarters

Backfill Foundation - Living Quarters

App Bay Prep

Stuctural Ex - App Bay

Sub Ex 3' - App Bay

Excavate Geo Trench under App Bay

Install Manifold Sleeves & Backfill

Place & Compact 3' - App Bay

Backfill - App Bay

Civil/Utilities

Set Sand/Oil Separator

Water Line

Sanitary Sewer

Storm Drain

Parking Structure Prep

Dig Footers - Parking Structure

Footer Drains

Backfill Foundation - Parking Structure

Set Boulder Retaining Wall

Parking Lot Prep

Place Pit Run - West

Place Pit Run - East

Road Base

Concrete

Living Quarters

Mat Slab - Elevator Pit

Form & Bar Footers

Pour Footers

Footers - Living Quarters

Form & Bar Footers

Pour Footers

Walls - Living Quarters

Form & Bar Walls

Set Steel Base Plates

Pour Walls

Strip Forms & Cleanup

Slab - Living Quarters

Underslab Utilities

Gravel Cushion

Vapor Barrier & Rebar

Inspection Day

Pour Slab

Cure Time

Living Quarters - Concrete Complete 10/20

App Bay

Footers - App Bay

Form & Bar Footers

Pour Footers

Strip Forms

Walls - App Bay

1st Lift

Form & Bar Wall - 1st Lift

Sleeve Forms for Drains

Pour Wall - 1st Lift

2nd Lift

Form & Bar Wall - 2nd Lift

Pour Wall - 2nd Lift

3rd Lift

Form & Bar Wall - 3rd Lift

Pour Wall - 3rd Lift

Slab - App Bay

Set Trench Drains

Underslab Utilites

Gravel Cushion

Vapor Barrier & Bar

Slab - 1st Pour

Slab - 2nd Pour

App Bay Concrete Complete 10/20

Parking Structure

Footings

Site Walls

Site Stairs

Housekeeping Pads

Geothermal

Mobilization

Drill West Wells

Drill East Wells

Manifolding

West Bore Manifold Install

Sleeve Under App Bay

West Bore to Sleeve Connection

East Bore Manifold Install

Building Manifold Prep

Manifold Underground Complete 9/9

Exterior Foundation Work

Dampproofing

Exterior Wall Insulation

Framing - ROUGH

Assembly Scissor Truss in Shop

Set Steel Columns & Beams

Frame Load Bearing Walls & Set Ledgers

Build CMU Walls

Floor Joist & Deck

Pour Concrete Topping Slab

Infill Framing

2nd Floor Walls

Set PE Trusses & Partial Sheathing

Set GLB Scissor Trusses & Perlins

Set Metal Trusses - App Bay

Roof Infill Framing

Sheet Remainder of Roof

Install Subfascia

Cover Window Openings

Temp Heat Operational 2/27

Drop Ceilings

Exterior Barriers

Winter Delay - Exterior Work Pause

Exterior Finishes

Masonry Prep - Lintel & Flashing

Deck Roof Dry-In

Stone Masonry

Wood Siding, Soffit & Fascia

Gutters

Hand Rail

Deck Pavers

Metal Siding @ Site Enclosures

Set Flag Pole

Finish Civil Work

Final Grade Touchup

Pour Aprons & Set Bollards

Pour Sidewalks

Curb & Gutter

Road Base

Asphalt

Landscape

Rough-In Irrigation

Set Hardscapes

Fill Topsoil

Plantings

Grass

Interior Rough-In

Mechanical Rough-In

Electrical Rough-In

Plumbing Rough-In

Fire Suppression Rough-In

Low Voltage

Pull Wire

Set Door Frames

Insulation

Finish Work

Polish Concrete

Hang Sheetrock

Tape & Texture

Paint

Interior Ceiling Soffit

MEP Trim Out

Fire Suppression Trim Out

Hang Doors

Set Interior Storefront

Tile

Casework

Seal Concrete

Flooring

Rubber Base

Set Drop Ceilings

Closeout Work

Install Div 10 Specialties

Install Door Hardware

Door Thresholds

MEP Test & Balance

Initial Punch

Generator Startup

Building Final & Fire Final

C.O./Final Routing Processing

Substantial Completion 10/26

Final Punch

Final Clean

Building Turnover 11/25

24 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 4 9 14 19 24 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31

March 2025 April 2025 May 2025 June 2025 July 2025 August 2025 September 2025 October 2025 November 2025 December 2025 January 2026 February 2026 March 2026 April 2026 May 2026 June 2026 July 2026 August 2026 September 2026 October 2026 November 2026 December 2026 January 2027

Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress

Project: BSFD3 Schedule - Alt 1

Date: Fri 3/14/25