250319 Addendum #2 - Project Schedule 3.14.25.pdf
PDF 225 KB Posted
- Attached to
- Material Testing and 3rd Party Inspections
- Solicitation number
- RFP_F-BSFD-0000000002
- Issued by
- Gallatin County, Montana
About this file
This document is a detailed project schedule for the Big Sky Fire Department's Fire Station No. 3 project, located in Big Sky, Montana. The comprehensive Gantt chart spans from March 2025 to November 2026, detailing a multi-phase construction timeline across numerous critical path activities. The project schedule encompasses administrative tasks, site preparation, geothermal work, structural framing, concrete phases, exterior and interior construction, mechanical and electrical rough-ins, and closeout activities. Key milestone dates include the GMP Contract Execution on 4/1/25, first day on site on 5/19/25, substantial completion on 10/26/26, and final building turnover on 11/25/26.
The schedule demonstrates a meticulously planned 20-month construction process with intricate dependencies between 233 distinct tasks. The project involves constructing a 10,273 square foot two-story fire station with multiple functional areas including three drive-through bays, sleeping quarters, offices, and support spaces. The schedule highlights specialized construction phases like geothermal well drilling, manifold installations, structural framing, exterior barriers, and interior finish work. The timeline incorporates considerations for winter delays, site preparation, utilities installation, and comprehensive mechanical, electrical, and plumbing rough-in and trim-out work, reflecting a holistic approach to fire station construction in a potentially challenging mountain environment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Duration Start Finish Predecessors Resource Names
1 Administrative 25 days Tue 4/1/25 Mon 5/5/25
2 GMP Contract Executed 0 days Tue 4/1/25 Tue 4/1/25
3 Request P&P Bond 1 day Tue 4/1/25 Tue 4/1/25 2
4 Subcontracts Issued 5 days Tue 4/1/25 Mon 4/7/25 2
5 Permit Delivered 0 days Mon 4/7/25 Mon 4/7/25 4
6 Submittal Assignment 20 days Tue 4/8/25 Mon 5/5/25 4
7 Long Lead Procurement 25 days Tue 5/6/25 Mon 6/9/25
8 Steel - Submit Shop Drawings and
Long Lead
25 days Tue 5/6/25 Mon 6/9/25 6
9 GLB Trusses - Submit Shop Drawings and Long Lead
20 days Tue 5/6/25 Mon 6/2/25 6
10 Mechanical - Submit Shop Drawings and Long Lead
25 days Tue 5/6/25 Mon 6/9/25 6
11 Electrical - Submit Shop Drawings and Long Lead
25 days Tue 5/6/25 Mon 6/9/25 6
12 Geothermal - Submit Shop Drawings and Long Lead
25 days Tue 5/6/25 Mon 6/9/25 6
13 Plumbing - Submit Shop Drawings and Long Lead
25 days Tue 5/6/25 Mon 6/9/25 6
14 Electrical - Submit Shop Drawings and Long Lead
25 days Tue 5/6/25 Mon 6/9/25 6
15 Detail, Fabricate, Deliver Steel 45 days Tue 6/10/25 Mon 8/11/258
16 LML Remaining Scope 57 days Mon 5/19/25Tue 8/5/25
17 1st Day On Site 0 days Mon 5/19/25Mon 5/19/25 Ridgeline Excavation
18 Snow Removal 2 days Mon 5/19/25Tue 5/20/25 17
19 Relocate Utillities 4 days Wed 5/21/25Mon 5/26/2518
20 Pour Curbs - TBD 1 day Mon 8/4/25 Mon 8/4/25
21 Pave Drive - TBD 1 day Tue 8/5/25 Tue 8/5/25 20
22 R&R Taylor - NTP 0 days Mon 5/26/25Mon 5/26/2519
23 Mobilization / Excavation 134 days Tue 5/27/25 Fri 11/28/25
24 Overall Site Prep 25 days Tue 5/27/25 Mon 6/30/25
25 Snow Removal 2 days Tue 5/27/25 Wed 5/28/2519
26 Install BMPs 1 day Thu 5/29/25 Thu 5/29/25 25
27 Clear & Grub 3 days Fri 5/30/25 Tue 6/3/25 26
28 Cut to Subgrade 15 days Wed 6/4/25 Tue 6/24/25 27
29 Overex Hauloff 15 days Wed 6/4/25 Tue 6/24/25 28SS
30 Job Trailer Mobilization 3 days Wed 6/25/25Fri 6/27/25 29
31 Set up Site Fence 4 days Wed 6/25/25Mon 6/30/2529
32 Establish Laydown Area 4 days Wed 6/25/25Mon 6/30/2529
33 Living Quarters 58 days Wed 6/25/25Fri 9/12/25
34 Dig Footers - Living Quarters 3 days Wed 6/25/25Fri 6/27/25 28,29
35 Footer Drains - Living Quarters 3 days Wed 9/3/25 Fri 9/5/25 70
36 Backfill Foundation - Living Quarters5 days Mon 9/8/25 Fri 9/12/25 35
37 App Bay Prep 65 days Mon 6/30/25Fri 9/26/25
38 Stuctural Ex - App Bay 5 days Mon 6/30/25Fri 7/4/25 34
39 Sub Ex 3' - App Bay 2 days Mon 7/7/25 Tue 7/8/25 38
40 Excavate Geo Trench under App Bay2 days Wed 7/9/25 Thu 7/10/25 39
41 Install Manifold Sleeves & Backfill 1 day Fri 7/11/25 Fri 7/11/25 40
42 Place & Compact 3' - App Bay 2 days Mon 7/14/25Tue 7/15/25 41
43 Backfill - App Bay 2 days Thu 9/25/25 Fri 9/26/25 94
44 Civil/Utilities 23 days Mon 9/29/25Wed 10/29/25
45 Set Sand/Oil Separator 2 days Mon 9/29/25Tue 9/30/25 43
46 Water Line 6 days Wed 10/1/25Wed 10/8/2545
47 Sanitary Sewer 7 days Thu 10/9/25 Fri 10/17/25 46
48 Storm Drain 8 days Mon 10/20/25Wed 10/29/2547
49 Parking Structure Prep 22 days Thu 10/30/25Fri 11/28/25
50 Dig Footers - Parking Structure 2 days Thu 10/30/25Fri 10/31/25 48
51 Footer Drains 1 day Mon 11/3/25Mon 11/3/2550
52 Backfill Foundation - Parking Structure1 day Mon 11/24/25Mon 11/24/25105,56
53 Set Boulder Retaining Wall 5 days Mon 11/24/25Fri 11/28/25 52SS
54 Parking Lot Prep 6 days Tue 11/4/25 Tue 11/11/25
55 Place Pit Run - West 2 days Tue 11/4/25 Wed 11/5/2551
56 Place Pit Run - East 2 days Thu 11/6/25 Fri 11/7/25 55
57 Road Base 2 days Mon 11/10/25Tue 11/11/2556
58 Concrete 105 days Mon 6/30/25Fri 11/21/25 Allied Concrete
59 Living Quarters 81 days Mon 6/30/25Mon 10/20/25
60 Mat Slab - Elevator Pit 5 days Mon 6/30/25Fri 7/4/25
61 Form & Bar Footers 4 days Mon 6/30/25Thu 7/3/25 34
62 Pour Footers 1 day Fri 7/4/25 Fri 7/4/25 61
63 Footers - Living Quarters 7 days Mon 7/7/25 Tue 7/15/25
64 Form & Bar Footers 6 days Mon 7/7/25 Mon 7/14/2562
65 Pour Footers 1 day Tue 7/15/25 Tue 7/15/25 64
66 Walls - Living Quarters 35 days Wed 7/16/25Tue 9/2/25
67 Form & Bar Walls 32 days Wed 7/16/25Thu 8/28/25 65
68 Set Steel Base Plates 2 days Wed 8/27/25Thu 8/28/25 67FF Framer
69 Pour Walls 1 day Fri 8/29/25 Fri 8/29/25 67
70 Strip Forms & Cleanup 2 days Mon 9/1/25 Tue 9/2/25 69
71 Slab - Living Quarters 26 days Mon 9/15/25Mon 10/20/25
72 Underslab Utilities 12 days Mon 9/15/25Tue 9/30/25 36 Ridgeline Excavation
73 Gravel Cushion 2 days Wed 10/1/25Thu 10/2/25 72 Ridgeline Excavation
74 Vapor Barrier & Rebar 7 days Fri 10/3/25 Mon 10/13/2573 Allied Concrete
75 Inspection Day 1 day Tue 10/14/25Tue 10/14/2574 R&R Taylor
76 Pour Slab 2 days Wed 10/15/25Thu 10/16/2575,36 Allied Concrete
77 Cure Time 2 days Fri 10/17/25 Mon 10/20/2576 Allied Concrete
78 Living Quarters - Concrete Complete0 days Mon 10/20/25Mon 10/20/2577
79 App Bay 93 days Wed 7/16/25Fri 11/21/25
80 Footers - App Bay 7 days Wed 7/16/25Thu 7/24/25
81 Form & Bar Footers 5 days Wed 7/16/25Tue 7/22/25 42
82 Pour Footers 1 day Wed 7/23/25Wed 7/23/2581
83 Strip Forms 1 day Thu 7/24/25 Thu 7/24/25 82
84 Walls - App Bay 45 days Thu 7/24/25 Wed 9/24/25
85 1st Lift 15 days Thu 7/24/25 Wed 8/13/25
86 Form & Bar Wall - 1st Lift 14 days Thu 7/24/25 Tue 8/12/25 82
87 Sleeve Forms for Drains 1 day Tue 8/12/25 Tue 8/12/25 86FF Ridgeline Excavation
88 Pour Wall - 1st Lift 1 day Wed 8/13/25Wed 8/13/2586
89 2nd Lift 15 days Thu 8/14/25 Wed 9/3/25
90 Form & Bar Wall - 2nd Lift 14 days Thu 8/14/25 Tue 9/2/25 88
91 Pour Wall - 2nd Lift 1 day Wed 9/3/25 Wed 9/3/25 90
92 3rd Lift 15 days Thu 9/4/25 Wed 9/24/25
93 Form & Bar Wall - 3rd Lift 14 days Thu 9/4/25 Tue 9/23/25 91
94 Pour Wall - 3rd Lift 1 day Wed 9/24/25Wed 9/24/2593
95 Slab - App Bay 16 days Mon 9/29/25Mon 10/20/25
96 Set Trench Drains 5 days Mon 9/29/25Fri 10/3/25 87,43 Williams
97 Underslab Utilites 5 days Mon 9/29/25Fri 10/3/25 96FF
98 Gravel Cushion 1 day Mon 10/6/25Mon 10/6/2596,97 Ridgeline Excavation
99 Vapor Barrier & Bar 8 days Tue 10/7/25 Thu 10/16/2598 Allied Concrete
100 Slab - 1st Pour 1 day Fri 10/17/25 Fri 10/17/25 99
101 Slab - 2nd Pour 1 day Mon 10/20/25Mon 10/20/25100
102 App Bay Concrete Complete 0 days Mon 10/20/25Mon 10/20/25101
103 Parking Structure 15 days Mon 11/3/25Fri 11/21/25
104 Footings 10 days Mon 11/3/25Fri 11/14/25 50
105 Site Walls 5 days Mon 11/17/25Fri 11/21/25 104
106 Site Stairs 7 days Mon 9/15/25Tue 9/23/25 36
107 Housekeeping Pads 5 days Tue 10/21/25Mon 10/27/2577,106
108 Geothermal 35 days Mon 6/30/25Fri 8/15/25
109 Mobilization 2 days Mon 6/30/25Tue 7/1/25
110 Drill West Wells 18 days Wed 7/2/25 Fri 7/25/25 109
111 Drill East Wells 15 days Mon 7/28/25Fri 8/15/25 110
112 Manifolding 32 days Mon 7/28/25Tue 9/9/25
113 West Bore Manifold Install 10 days Mon 7/28/25Fri 8/8/25 110
114 Sleeve Under App Bay 2 days Mon 8/11/25Tue 8/12/25 113
115 West Bore to Sleeve Connection 3 days Wed 8/13/25Fri 8/15/25 114
116 East Bore Manifold Install 10 days Mon 8/18/25Fri 8/29/25 115,111
117 Building Manifold Prep 7 days Mon 9/1/25 Tue 9/9/25 116
118 Manifold Underground Complete 0 days Tue 9/9/25 Tue 9/9/25 117
119 Exterior Foundation Work 7 days Mon 9/15/25Tue 9/23/25
120 Dampproofing 3 days Mon 9/15/25Wed 9/17/2536
121 Exterior Wall Insulation 4 days Thu 9/18/25 Tue 9/23/25 120
122 Framing - ROUGH 99 days Tue 10/21/25Fri 3/6/26
123 Assembly Scissor Truss in Shop 10 days Tue 10/28/25Mon 11/10/25124
124 Set Steel Columns & Beams 5 days Tue 10/21/25Mon 10/27/2578
125 Frame Load Bearing Walls & Set Ledgers5 days Tue 10/28/25Mon 11/3/25124
126 Build CMU Walls 10 days Tue 10/21/25Mon 11/3/25124SS Kidrick Masonry
127 Floor Joist & Deck 12 days Tue 11/4/25 Wed 11/19/25125
128 Pour Concrete Topping Slab 3 days Thu 11/20/25Mon 11/24/25127
129 Infill Framing 15 days Tue 11/25/25Mon 12/15/25128
130 2nd Floor Walls 15 days Tue 12/16/25Mon 1/5/26 129
131 Set PE Trusses & Partial Sheathing 5 days Tue 1/6/26 Mon 1/12/26130
132 Set GLB Scissor Trusses & Perlins 14 days Tue 1/13/26 Fri 1/30/26 131
133 Set Metal Trusses - App Bay 5 days Mon 2/2/26 Fri 2/6/26 132
134 Roof Infill Framing 5 days Mon 2/2/26 Fri 2/6/26 132
135 Sheet Remainder of Roof 5 days Mon 2/9/26 Fri 2/13/26 134
136 Install Subfascia 10 days Mon 2/16/26Fri 2/27/26 135
137 Cover Window Openings 1 day Fri 2/27/26 Fri 2/27/26 136FF
138 Temp Heat Operational 0 days Fri 2/27/26 Fri 2/27/26 137
139 Drop Ceilings 5 days Mon 3/2/26 Fri 3/6/26 138
140 Exterior Barriers 47 days Thu 2/5/26 Fri 4/10/26
151 Winter Delay - Exterior Work Pause 57 days Tue 3/17/26 Wed 6/3/26 150
152 Exterior Finishes 97 days Thu 6/4/26 Fri 10/16/26
153 Masonry Prep - Lintel & Flashing 15 days Thu 6/4/26 Wed 6/24/26151
154 Deck Roof Dry-In 2 wks Thu 6/25/26 Wed 7/8/26 153
155 Stone Masonry 10 wks Thu 6/25/26 Wed 9/2/26 153
156 Wood Siding, Soffit & Fascia 10 wks Thu 7/9/26 Wed 9/16/26155SS+2 wks
157 Gutters 3 wks Thu 9/17/26 Wed 10/7/26156
158 Hand Rail 5 days Thu 9/17/26 Wed 9/23/26156
159 Deck Pavers 2 wks Thu 9/17/26 Wed 9/30/26156
160 Metal Siding @ Site Enclosures 2 wks Thu 10/1/26 Wed 10/14/26159
161 Set Flag Pole 2 days Thu 10/15/26Fri 10/16/26 160
162 Finish Civil Work 40 days Thu 7/23/26 Wed 9/16/26
163 Final Grade Touchup 5 days Thu 7/23/26 Wed 7/29/26155SS+4 wks
164 Pour Aprons & Set Bollards 2 wks Thu 7/30/26 Wed 8/12/26163
165 Pour Sidewalks 2 wks Thu 8/13/26 Wed 8/26/26164
166 Curb & Gutter 8 days Thu 8/27/26 Mon 9/7/26 165
167 Road Base 4 days Tue 9/8/26 Fri 9/11/26 166
168 Asphalt 3 days Mon 9/14/26Wed 9/16/26167
169 Landscape 35 days Tue 9/8/26 Mon 10/26/26
170 Rough-In Irrigation 10 days Tue 9/8/26 Mon 9/21/26166
171 Set Hardscapes 5 days Tue 9/22/26 Mon 9/28/26170
172 Fill Topsoil 10 days Tue 9/29/26 Mon 10/12/26171
173 Plantings 5 days Tue 10/13/26Mon 10/19/26172
174 Grass 5 days Tue 10/20/26Mon 10/26/26173
175 Interior Rough-In 65 days Mon 2/16/26Fri 5/15/26
176 Mechanical Rough-In 45 days Mon 2/16/26Fri 4/17/26 146
177 Electrical Rough-In 45 days Mon 2/16/26Fri 4/17/26 176SS
178 Plumbing Rough-In 45 days Mon 2/16/26Fri 4/17/26 176SS
179 Fire Suppression Rough-In 20 days Mon 2/16/26Fri 3/13/26 176SS
180 Low Voltage 20 days Mon 4/20/26Fri 5/15/26 177
181 Pull Wire 15 days Mon 4/20/26Fri 5/8/26 177
182 Set Door Frames 3 days Mon 2/16/26Wed 2/18/26176SS
183 Insulation 10 days Mon 4/27/26Fri 5/8/26 186SS+5 days
184 Finish Work 115 days Mon 4/6/26 Fri 9/11/26
185 Polish Concrete 10 days Mon 4/6/26 Mon 4/20/26186SF
186 Hang Sheetrock 15 days Mon 4/20/26Fri 5/8/26 176,177,178,179
187 Tape & Texture 20 days Mon 5/11/26Fri 6/5/26 183,186
188 Paint 25 days Mon 6/8/26 Fri 7/10/26 187,139
189 Interior Ceiling Soffit 15 days Mon 7/13/26Fri 7/31/26 188
190 MEP Trim Out 25 days Mon 7/13/26Fri 8/14/26 188
191 Fire Suppression Trim Out 10 days Mon 7/13/26Fri 7/24/26 188
192 Hang Doors 5 days Mon 7/13/26Fri 7/17/26 188
193 Set Interior Storefront 10 days Mon 7/13/26Fri 7/24/26 192SS
194 Tile 15 days Mon 6/15/26Fri 7/3/26 187FS+5 days
195 Casework 20 days Mon 7/13/26Fri 8/7/26 188
196 Seal Concrete 5 days Mon 8/10/26Fri 8/14/26 195
197 Flooring 15 days Mon 8/10/26Fri 8/28/26 195
198 Rubber Base 10 days Mon 8/31/26Fri 9/11/26 197,196,194
199 Set Drop Ceilings 10 days Mon 7/13/26Fri 7/24/26 188
200 Closeout Work 278 days Sun 11/2/25 Wed 11/25/26
201 Install Div 10 Specialties 20 days Mon 8/10/26Fri 9/4/26 195
202 Install Door Hardware 10 days Mon 7/20/26Fri 7/31/26 192
203 Door Thresholds 3 days Mon 8/3/26 Wed 8/5/26 202
204 MEP Test & Balance 5 days Mon 8/17/26Fri 8/21/26 190
205 Initial Punch 20 days Mon 8/24/26Fri 9/18/26 204
206 Generator Startup 5 days Mon 9/21/26Fri 9/25/26 205
207 Building Final & Fire Final 5 days Mon 9/28/26Fri 10/2/26 206
208 C.O./Final Routing Processing 20 days Mon 10/5/26Fri 10/30/26 207
209 Substantial Completion 0 days Mon 10/26/26Mon 10/26/26205,201,174,161,198,203
210 Final Punch 13 days Mon 11/2/26Wed 11/18/26208
211 Final Clean 5 days Thu 11/19/26Wed 11/25/26210
212 Building Turnover 0 days Wed 11/25/26Wed 11/25/26211
233 12 days Sun 11/2/25 Sun 11/16/25
Administrative
GMP Contract Executed 4/1
Request P&P Bond
Subcontracts Issued
Permit Delivered 4/7
Submittal Assignment
Long Lead Procurement
Steel - Submit Shop Drawings and Long Lead
GLB Trusses - Submit Shop Drawings and Long Lead
Mechanical - Submit Shop Drawings and Long Lead
Electrical - Submit Shop Drawings and Long Lead
Geothermal - Submit Shop Drawings and Long Lead
Plumbing - Submit Shop Drawings and Long Lead
Electrical - Submit Shop Drawings and Long Lead
Detail, Fabricate, Deliver Steel
LML Remaining Scope
1st Day On Site
Snow Removal
Relocate Utillities
R&R Taylor - NTP 5/26
Mobilization / Excavation
Overall Site Prep
Snow Removal
Install BMPs
Clear & Grub
Cut to Subgrade
Overex Hauloff
Job Trailer Mobilization
Set up Site Fence
Establish Laydown Area
Living Quarters
Dig Footers - Living Quarters
Footer Drains - Living Quarters
Backfill Foundation - Living Quarters
App Bay Prep
Stuctural Ex - App Bay
Sub Ex 3' - App Bay
Excavate Geo Trench under App Bay
Install Manifold Sleeves & Backfill
Place & Compact 3' - App Bay
Backfill - App Bay
Civil/Utilities
Set Sand/Oil Separator
Water Line
Sanitary Sewer
Storm Drain
Parking Structure Prep
Dig Footers - Parking Structure
Footer Drains
Backfill Foundation - Parking Structure
Set Boulder Retaining Wall
Parking Lot Prep
Place Pit Run - West
Place Pit Run - East
Road Base
Concrete
Living Quarters
Mat Slab - Elevator Pit
Form & Bar Footers
Pour Footers
Footers - Living Quarters
Form & Bar Footers
Pour Footers
Walls - Living Quarters
Form & Bar Walls
Set Steel Base Plates
Pour Walls
Strip Forms & Cleanup
Slab - Living Quarters
Underslab Utilities
Gravel Cushion
Vapor Barrier & Rebar
Inspection Day
Pour Slab
Cure Time
Living Quarters - Concrete Complete 10/20
App Bay
Footers - App Bay
Form & Bar Footers
Pour Footers
Strip Forms
Walls - App Bay
1st Lift
Form & Bar Wall - 1st Lift
Sleeve Forms for Drains
Pour Wall - 1st Lift
2nd Lift
Form & Bar Wall - 2nd Lift
Pour Wall - 2nd Lift
3rd Lift
Form & Bar Wall - 3rd Lift
Pour Wall - 3rd Lift
Slab - App Bay
Set Trench Drains
Underslab Utilites
Gravel Cushion
Vapor Barrier & Bar
Slab - 1st Pour
Slab - 2nd Pour
App Bay Concrete Complete 10/20
Parking Structure
Footings
Site Walls
Site Stairs
Housekeeping Pads
Geothermal
Mobilization
Drill West Wells
Drill East Wells
Manifolding
West Bore Manifold Install
Sleeve Under App Bay
West Bore to Sleeve Connection
East Bore Manifold Install
Building Manifold Prep
Manifold Underground Complete 9/9
Exterior Foundation Work
Dampproofing
Exterior Wall Insulation
Framing - ROUGH
Assembly Scissor Truss in Shop
Set Steel Columns & Beams
Frame Load Bearing Walls & Set Ledgers
Build CMU Walls
Floor Joist & Deck
Pour Concrete Topping Slab
Infill Framing
2nd Floor Walls
Set PE Trusses & Partial Sheathing
Set GLB Scissor Trusses & Perlins
Set Metal Trusses - App Bay
Roof Infill Framing
Sheet Remainder of Roof
Install Subfascia
Cover Window Openings
Temp Heat Operational 2/27
Drop Ceilings
Exterior Barriers
Winter Delay - Exterior Work Pause
Exterior Finishes
Masonry Prep - Lintel & Flashing
Deck Roof Dry-In
Stone Masonry
Wood Siding, Soffit & Fascia
Gutters
Hand Rail
Deck Pavers
Metal Siding @ Site Enclosures
Set Flag Pole
Finish Civil Work
Final Grade Touchup
Pour Aprons & Set Bollards
Pour Sidewalks
Curb & Gutter
Road Base
Asphalt
Landscape
Rough-In Irrigation
Set Hardscapes
Fill Topsoil
Plantings
Grass
Interior Rough-In
Mechanical Rough-In
Electrical Rough-In
Plumbing Rough-In
Fire Suppression Rough-In
Low Voltage
Pull Wire
Set Door Frames
Insulation
Finish Work
Polish Concrete
Hang Sheetrock
Tape & Texture
Paint
Interior Ceiling Soffit
MEP Trim Out
Fire Suppression Trim Out
Hang Doors
Set Interior Storefront
Tile
Casework
Seal Concrete
Flooring
Rubber Base
Set Drop Ceilings
Closeout Work
Install Div 10 Specialties
Install Door Hardware
Door Thresholds
MEP Test & Balance
Initial Punch
Generator Startup
Building Final & Fire Final
C.O./Final Routing Processing
Substantial Completion 10/26
Final Punch
Final Clean
Building Turnover 11/25
24 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 4 9 14 19 24 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31
March 2025 April 2025 May 2025 June 2025 July 2025 August 2025 September 2025 October 2025 November 2025 December 2025 January 2026 February 2026 March 2026 April 2026 May 2026 June 2026 July 2026 August 2026 September 2026 October 2026 November 2026 December 2026 January 2027
Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress
Project: BSFD3 Schedule - Alt 1
Date: Fri 3/14/25