25_Milestone Payment Schedule_07152026.docx

DOCX document 33 KB Posted

Attached to
LTR Cromwell Maintenance & Storage Facility Modernization Project (LRMP Tranche 3) 20260715
Solicitation number
BPM057988
Issued by
Anne Arundel County, Maryland

About this file

This Milestone Payment Schedule is a required form for the Maryland Department of Transportation Maryland Transit Administration's LTR Cromwell Maintenance & Storage Facility Modernization Project (LRMP Tranche 3), Contract No. T-2443-0150. The Design-Build Contract encompasses the design and construction of improvements at the Cromwell Maintenance and Storage Facility located at 7390 Baltimore Annapolis Boulevard, Glen Burnie, Maryland, to accommodate the anticipated purchase and transition to new Low Floor Light Rail Vehicles (LFLRVs) and related transitioning, training, testing, commissioning, and maintenance activities. The project includes improvements to the existing main building, construction of a new annex building, and yard improvements. The milestone schedule outlines 13 key deliverables spanning design phases (Initial Design, Intermediate Design, IFC Documents), preconstruction activities, construction phases with substantial completion dates for each facility component, as-built documents, integration and testing, final acceptance, and retainage release. Bidders must establish milestone dates and associated pricing percentages of the total proposal price, with estimated completion dates sequenced in alignment with the proposed schedule in the Technical Proposal.

The Price column for construction activities must reflect retainage limits as specified in the contract requirements, with a separate milestone designated for retainage release. The form requires the bidder's authorized representative to sign and date the completed schedule. This milestone payment schedule must be completed in accordance with contract invoicing procedures outlined in NITO Section 3.4 and standard project requirements in Book 2, Section 7, which govern cost management and payment administration for the project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Maryland Department of Transportation Maryland Transit Administration

LTR Cromwell Maintenance & Storage Facility Modernization Project (LRMP Tranche 3)

Contract No. T-2443-0150

MILESTONE PAYMENT SCHEDULE

INSTRUCTIONS:

1. In completing this form, reference NITO, Section 3.4 – Invoicing, and Book 2- Standard Project Requirements, Section 7-Cost Management.

2. As applicable, insert additional rows for interim design, preconstruction and construction milestones.

3. The “Price” column, as it relates to construction activities, must reflect retainage limits set forth in NITO, Section 2.10.3 - Construction Contract Retainage. A separate milestone for “Retainage Release” will need to be completed.

4. The “Estimated Completion Date” column must outline the timing and sequencing of deliverables in alignment with the Proposed Schedule described in Appendix B- Technical Proposal Content.

REF.
MILESTONE
PRICE
% OF TOTAL PROPOSAL PRICE
ESTIMATED COMPLETION DATE
1
Initial Design
$
2
Intermediate Design
$
3
[Interim Design Milestone]
$
4
IFC Documents
$
5
[Interim Preconstruction Milestone]
$
6
[Interim Construction Milestone]
$
7
As-Built Documents
$
8
Integration and Testing
$
9
Substantial Completion Date – Existing Main Building
$
10
Substantial Completion Date – New Annex Building
$
11
Substantial Completion Date – Yard Improvements
$
12
Final Acceptance
$
13
Retainage Release
$

Name, Title of Authorized Representative

Signature

Bidder/Offeror Name

Date

T-2443-0150 Effective: 05/13/26 MPS 1 of 4