25-061-ITB_Terminal_2_&_3_Parking_Garage_Rehabilitation-Phase_3_-_Technical_Specifications.pdf
PDF 2 MB Posted
- Solicitation number
- 25-061-ITB
- Issued by
- Bell County, Kentucky
About this file
These are the technical specifications for the Cincinnati/Northern Kentucky International Airport's Terminal 2 & 3 Parking Garage Rehabilitation - Phase 3 project, prepared by the Kenton County Airport Board (KCAB). The project involves comprehensive rehabilitation of parking garage facilities, including concrete repairs, membrane installations, expansion joint replacements, metal surface treatments, and associated infrastructure improvements. A pre-bid meeting and site visit is scheduled for October 16, 2025, at 10:00 am in Erlanger, Kentucky. Bidder questions are due by October 27, 2025, with answers posted by October 30, 2025. The final bid submission deadline is November 6, 2025, at 2:00 pm, with no bids accepted after that time unless an addendum is issued.
The technical specifications detail extensive requirements for surface preparation, material specifications, installation procedures, and quality control across multiple divisions, including concrete repairs, metal work, roofing, waterproofing, expansion joints, and pavement markings. The project involves replacing and repairing various structural and surface elements with high-performance materials, including specialized concrete repair compounds, membrane systems, sealants, and coatings. The specifications emphasize strict adherence to manufacturer guidelines, compatibility testing, and comprehensive warranty requirements, with most warranties ranging from 2 to 5 years. The work is focused on maintaining the structural integrity, waterproofing, and aesthetic quality of the parking garage facilities while ensuring long-term durability and performance.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL SPECIFICATIONS
The Contractor shall at a minimum comply and meet all codes, as defined, at the time of construction.
TECHNICAL SPECIFICATION INDEX
PROJECT NOTES
DIVISION 01 - GENERAL REQUIREMENTS
015000 Temporary Facilities and Controls 015600 Barriers
DIVISION 02 - EXISTING CONDITIONS
024119 Selective Structure Demolition
DIVISION 03 - CONCRETE
030100 Concrete Repairs 033810 Post Tensioned Garage Cable Repairs
DIVISION 05 - METALS
055000 Miscellaneous Metals
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
061053 Miscellaneous Rough Carpentry
DIVISIONS 07 - THERMAL AND MOISTURE PROTECTION
070150 Membrane Reroofing Preparation 071800 Vehicular Traffic Membrane 071910 Penetrating Concrete Water Repellent/Corrosion Inhibitor 075416 Ketone Ethylene Ester Roofing 075600 Fluid Applied Roofing 079000 Expansion Joints 079200 Sealants
DIVISION 08 - OPENINGS
084413 Glazed Aluminum Storefront, Window, and Entrance Systems 087100 Door Hardware
DIVISION 09 - FINISHES
099100 High Performance Coatings
DIVISION 22 – DRAINS AND PIPING
221400 Drains and Piping
DIVISION 32 - SITE WORK
321723 Pavement Markings
PROJECT NOTES:
GENERAL NOTES
1. No work may proceed until the contract has been signed by KCAB including receipt and approval of the Contractor’s insurance.
2. The Contractor is responsible for obtaining and paying for all permits, including the Boone County Building Permit. Receipt of final permit close-out and occupancy must be received from Boone County prior to submitting payment for the final retainage application.
3. The Contractor is responsible for any damage to vehicle and persons as a result of construction. All claims associated with damage to vehicles or persons as a result of construction will be the Contractor’s responsibility. The Contractor shall take all means necessary to protect vehicles, pedestrians, and infrastructure during construction. KCAB can adjust the Contractor’s means to ensure protection of vehicles, pedestrians, and infrastructure at no cost to KCAB.
4. The Contractor shall be aware of other projects on the airport site that are under construction. The Contractor shall coordinate all construction activities so as not to interrupt other project construction activities.
5. The Contractor shall maintain access to all entrances, exits, stairs, elevators, walkways, and aisles within the garage at no cost to the Owner.
6. Any damages to plants, trees, landscaping, fence, utilities, restoration to site, etc., shall be replaced at no cost to the Owner.
7. All waste materials resulting from this project shall be legally disposed of off airport property.
8. The Contractor shall have utilities marked by calling Kentucky 811 (call before you dig at 1-800-752-6007). KCAB will request utility locate for utilities not covered by 811. In addition, notify KCAB at least two weeks prior to starting work for the location of KCAB owned utilities. Location of utilities is the Contractors responsibility. A 3rd party utility location Contractor may be required.
9. Location of existing FAA underground cables will be flagged one time by the local airway facilities sector officer personnel through coordination of the KCAB Project Manager.
These flags shall be protected and maintained by the Contractor at all times. If flags are lost or removed through the carelessness of the Contractor they will be flagged again at the Contractor’s expense. All underground cables shall be protected, and damages repaired immediately at no additional cost to the airport.
10. Before the Contractor begins any work or operations in the vicinity of subsurface structures, they shall carefully, by hand digging, locate such utility ducts, direct buried cables or structures, and conduct his operations so as to avoid any damage to them.
11. The Contractor shall be responsible for the safety, protection, maintenance, and final restoration of all surface and subsurface utilities, plus trees, plants, fence, landscaping, etc. (together with all parts and appurtenances thereof.) Utilities as referred to in this section, shall be understood to mean both public utilities and other privately-owned utilities.
12. The Contractor’s staging area(s) described in the Construction Notes represent the general proximity where the Contractor may stage. The exact limits may require minor modifications prior to beginning or during construction with the approval of the Owner.
The staging areas shall be restored to their original condition upon completion of the project at no cost to the Owner.
13. The Contractor should field measure and verify all existing conditions and work areas prior to demolition and ordering materials to verify correct sizes.
14. All work items not specifically quantified in the bid are to be considered incidental to other pay items and will not be reimbursed on a unit cost bases or compensated by change order.
15. The Contractor shall follow FHWA Manual of Uniform Traffic Control Devices (MUTCD) (Current Edition) for signing and striping. All signs shall be new and meet retroreflectivity standards in MUTCD. The contractor shall maintain all signs in good condition, including cleaning or renewing surfaces as necessary to provide clear visibility and high retroreflectivity at all times. All signs will be of the largest size provided in the MUTCD. A small sign may be used if workspace requires with approval, or directed by
KCAB.
16. Signs shall not be attached to the garage.
CONSTRUCTION NOTES
1. The Contractor will be provided with 10 access cards for his/her employees and supervisors to gain access to the Terminal Parking Garage (T2 & T3). The Contractor shall be responsible for providing access and exit to all construction traffic.
2. Staging area will be provided at Level A at the north end of Terminal 2 Garage and Terminal 3 East Garage. The contractor may secure four parking spaces with fencing to create a staging area. Final location of each staging area must be approved by the Owner.
3. The Contractor shall not impede entering or exiting garage traffic unless specified in the plans.
4. The Contractor shall request a delivery address for deliveries prior to ordering.
5. The Contractor is required to attend weekly progress meetings.
6. The Contractor shall place traffic barrels along the perimeter of work area.
7. The Contractor shall x-ray concrete to locate post-tensioning tendons and rebar when drilling and cutting into concrete. Contractor shall not cut, chip, or drill into concrete in vicinity of post-tensioning tendons or rebar.
8. Any items disturbed from construction activities shall be replaced in kind, including striping and is incidental to bid items.
9. A parking spot wireless vehicle detection sensor exists in each parking spaces.
a. The contractor is responsible for protecting them from damage.
b. The contractor is responsible for providing a temporary cover over each sensor when the parking spot is closed for work and during the time it is reserved for closure.
CONSTRUCTION MAINTENANCE OF TRAFFIC PHASING NOTES
1. Contractor shall submit a Maintenance of Traffic Plan 7 calendar days prior to construction for review and approval. Maintenance of Traffic Plan submittals are required for construction at any new area or location.
2. Contractor shall have a dedicated flagger present when work impedes in driving and parking aisles or work performed over head of driving and parking aisles.
3. The Contractor shall provide flaggers or barriers to restrict vehicles and pedestrians from entering construction area. The Contractor is responsible for all maintenance of traffic equipment including orange construction fencing traffic barrels, signs, flagger, signs, etc. Use of caution tape not allowed unless approved by the Owner. At any time, the Contractor shall adjust maintenance of traffic method, including additional flaggers and traffic control equipment, as directed by the KCAB at no additional cost. Cones will not be allowed. Only barrels, or equivalent will be allowed.
4. At any time, the Contractor shall adjust maintenance of traffic method, including additional flaggers and traffic control equipment, as directed by the KCAB at no additional cost.
5. The Contractor may close drive lanes (flat bays of garage) and ramp lanes (sloped bays of garage between levels) assuming proper signage with turn-around to complete major work. The number of parking spaces closed must be below the total limit noted in section “Construction – Parking and Sequence”, based on the following restrictions.
a. A total of four (4) drive lane bays may be closed per level in all T3 Garages.
b. A total of one (1) ramp lanes bay may be closed per level in all T3 Garages. If a ramp lane bay is being closed on multiple levels, it must be the same bay.
c. Contractor is responsible for posting signage at these bays indicated the closure.
Sample minimum signage at each end of the bay is shown below.
CONSTRUCTION – PARKING AND SEQUENCE
1. The Contractor is responsible for all aspects of the construction area including the signage, notification, and reserving of parking spaces at no expense to the Owner. Delay claims will not be reimbursed for issues associated with vehicles parked in a construction area.
2. Contractor will submit to KCAB for approval of sign to be installed. The sign should include a notice that unauthorized vehicles will be towed at vehicles owner’s expense or operator’s expense if parked beginning at a specific date. The sign can be reusable as long as the date displayed is accurate. The sign cannot be attached to the garage with screws. The sign should be placed on a moveable sign base.
a. Sign and Moveable Base.
3. The Contractor shall post a no parking sign in each parking spot 16 calendar days prior to begin of construction. The Contractor shall notify KCAB on the 14th calendar day if a vehicle is parked in a spot needed for construction.
4. Once the no parking sign has been posted, it is the Contractor’s responsibility to reserve the parking spot with either additional signing, barrels, etc. It is the Contractor’s responsibility to reserve these spots once available. The Contractor shall continuously monitor these spots daily to reserve.
5. The Contractor shall have a dedicated employee monitoring the parking spots to reserve when available.
6. The Contractor shall develop a parking spot utilization report for tracking the parking spot occupancy. The report shall track the reservation of the parking spots and use of parking spots. The report will provide daily details of occupancy. The document will be coordinated with KCAB for the accurate count of spots occupied.
7. When the no parking signs are installed 16 calendar days prior to construction, the Contractor is responsible for taking pictures of the vehicles currently in the parking spot.
The pictures shall be part of the parking spot tracking form. The picture(s) shall include the license plate for the vehicle. These pictures will be used to track the initial parked vehicle. If the parked vehicle in the spot on the 14th calendar day is not the original or photographed vehicle, the Contractor will be charged the towing fee. If pictures are not provided of the initial parked car, the Contractor will be charged the towing fee. The Contractor is responsible for developing a procedure and forms to track the reservation of the parking spots.
8. The Contractor is responsible for the construction area. The Contractor shall reserve adequate parking spaces to protect the construction area, vehicles, and persons.
9. The Contractor will phase work based on the utilization of 200 parking spots between the Notice to Proceed and Substantial Completion. The parking spot closure to account for the parking spot reservation time, construction, and curing time.
10. The Contractor will reserve the necessary parking spots on each level of the garage for work.
Cincinnati/Northern Kentucky International Airport Terminal 2 & 3 Garage Rehabilitation – Phase 3 September 2025
THP #24253.00
Temporary Facilities and Controls
015000 - 1
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 015000
TEMPORARY FACILITIES AND CONTROLS
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes
1. Administrative and procedural requirements for temporary services and facilities, including such items as temporary utility services, temporary construction and support facilities, and project security and protection.
1.2 OWNER OPERATION, MAINTENANCE OF OPERATION AND SAFETY
A. The structure is currently in use by the Owner. Areas of the structure outside the limits of a particular construction area shall remain functional throughout the construction period.
B. All construction operations shall be carefully coordinated with the Owner so as to minimize the overall inconvenience to the Owner, maintain the use of all means of egress at all specified times and to expedite job progress.
C. All fumes and dust arising from construction operations shall be controlled so as to not adversely affect persons/vehicles using the structure and all adjacent facilities.
D. The Contractor shall protect his Work and equipment from damage by the public and other entities occupying the structure during the construction period.
E. The Contractor shall take all necessary precautions for all Work Areas to prevent debris from falling and causing damage outside the work area, including damage to existing mechanical/electrical fixtures. The Contractor shall be held liable for all damage caused by excavation, patching, drilling, coring, cutting, sandblasting, dust and debris. The
Contractor shall be held liable for all damage to mechanical/electrical fixtures systems due to construction related activities. Contractor shall be responsible for all injury to people and property, including motor vehicles, caused by any construction related activity. The
Owner will endeavor to field complaints and forward same to Contractor. Contractor is responsible for contacting people or property owner and resolving complaints.
F. When Work is performed which may create a hazard to persons or property above, below or in the proximity of Work, affected areas shall be blocked or otherwise protected to eliminate the hazard.
G. Access to all emergency egress routes outside the limits of an individual construction area shall be continuously and safely maintained. Emergency egress routes shall not be impaired due to construction activities.
H. Coordinate Work Areas with the Owner to minimize interference with normal operations.
I. The Contractor shall comply with all Federal, State and Municipal laws, codes, ordinances
015000 - 2 and regulations applicable to the Work in this Contract and also with all requirements of the National Fire Protection Association, the National Electric Code, and the Occupational
Safety and Health Administration (OSHA). If the above laws, codes or ordinances conflict with this Specification, then the laws, codes or ordinances shall govern, except in such cases where the Specification exceeds them in quality of materials or labor, then the
Specifications shall be followed.
1.3 WORK AREAS
A. The Work is divided into sections termed Work Areas. Work outside the closed Work Area is not allowed, except work permitted by the Construction Documents or authorized by the
Owner.
B. The Construction limit lines are defined as the extent of the Work Areas designated on the
Drawings. Areas outside the construction limits may not be used by the Contractor for staging, storage of materials, or any other purpose, except as indicated in the Construction
Documents.
1.4 MATERIAL AND EQUIPMENT STORAGE AND DELIVERY
A. An area of the structure will be made available to the Contractor for material and equipment storage, staging and other facilities deemed necessary by the Contractor.
B. Deliveries shall not block entrance or exit to the facility by patrons or other services.
1.5 PROTECTION OF THE SURROUNDING AREA
A. All construction operations shall be conducted such as to protect the surrounding areas and adjacent buildings.
B. Fumes and dust shall also be controlled so as to prevent harmful or undesirable effects in the surrounding areas. All potential avenues for penetration of fumes or dust into occupied spaces adjacent to the work area must be located and sealed by the Contractor in a manner acceptable to the Owner prior to the start of the work in the affected area.
C. Areas below regions of construction activity may remain open for portions of that activity.
However, the Contractor is totally responsible for damage as a result of the Work.
1.6 PROTECTION OF EXISTING CONDITIONS
A. All portions of the existing structure, all utilities and all other building contents not part of the work damaged, moved or altered in any way during construction shall be replaced or repaired to the Owner’s satisfaction at the Contractor's expense.
B. Contractor and Owner shall conduct a preconstruction inspection of all finish materials and equipment located within the Work area to record in writing existing damaged finish materials and/or equipment not directly involved with this Contract. The Contractor shall be deemed responsible for damaged finish material and/or equipment not recorded during the preconstruction inspection. Contractor shall replace or repair to the Owner's satisfaction damaged finish material and/or equipment. It is the Contractor's responsibility to schedule and coordinate this preconstruction walk-through with the Owner.
015000 - 3
C. Accidental interruptions caused by the Contractor to services outside of the work area shall be reported to the Owner at once, and immediate, emergency efforts to restore the service shall be made at the expense of the Contractor.
D. When performing work adjacent to building and structures, protect buildings and structures from dirt, dust and debris.
E. Protect drain openings during construction from construction debris entering drainage system. Provide filter cloth over openings to prevent debris from entering pipes, but still allowing water to enter. Clean debris from drains as necessary to maintain water removal.
Remove drain protection during non-working hours and reinstall prior to commencing work.
1.7 TEMPORARY FACILITIES
A. The Contractor shall provide electric and water service required to perform the work.
B. The Contractor shall provide temporary toilet facilities for use by its employees and subcontractors. Locate in an area approved by the Owner. Use of Owner facilities is not allowed.
C. Job signs are not allowed unless authorized by the Owner.
D. The Contractor shall furnish temporary lighting or heat required so that work may proceed to meet the Contract schedule.
E. The Contractor shall arrange and establish a location satisfactory to the Owner where workmen may eat; provide a rubbish container, and clean and remove all debris at the end of each work day.
F. At all times when work is being performed, the Contractor's foreman shall be on-site. Both the foreman and the superintendent shall have a mobile phone or beeper with him/her at all times while on the job site. Provide the Owner with the telephone number.
G. A job site office/trailer is not required.
1.8 USE OF FACILITY
A. Contractor employees are not permitted to use Owner and tenant facilities except as previously noted. Failure to comply with this restriction can result in the dismissal of the offending employee from the construction site.
B. Elevators may not be used by the Contractor.
C. Except for materials being used during a work shift, store all materials in approved storage area.
1. Do not leave out tools, materials, and unattended packages in work areas or nearby due to Airport security protocols.
D. Materials being used for work shall be uniformly distributed throughout the work area so as to not overload or otherwise distress the supported structural system.
015000 - 4
1.9 TRAFFIC CONTROL
A. Refer to the Project Notes for traffic control and the procedure for closing parking spaces.
1.10 CLEANUP
A. Each Contractor or Subcontractor, upon completion of his division of the work, shall collect and remove all rubbish, surplus material, tools and scaffolding pertaining to his work, and shall keep the work area neat and orderly by periodic removal and cleanup. Crates and cartons in which materials or equipment are received shall be removed daily. Contractor shall leave each phase of the work broom-clean upon completion of that phase.
B. Each Contractor shall be responsible for daily collection and disposal of rubbish created by his materials, men and work. If this is not done, the Owner may direct that cleanup be done and the cost of same shall be deducted from the Contractor's contract.
C. Contractor shall clean surfaces of all lights, control panels, overhead piping, duct work, etc., after construction is complete, to the same level of cleanliness as surfaces were before construction.
D. Protect from damage during subsequent construction activities all new work and existing construction cleaned upon the completion of any one phase.
E. Contractor shall legally dispose of all debris (including concrete) off the site.
1.11 FIRE PROTECTION
A. It shall be the responsibility of the Contractor to take the proper precautions to prevent fires when welding or while other fire-hazardous work is being performed.
B. Gasoline and other flammable liquids shall be kept in approved safety cans at all times.
1.12 WATCHMEN
A. The services of a watchman will not be provided by the Owner.
B. The Contractor shall assume full responsibility for protection and safety of material and equipment stored at the job site both within and outside of the work areas or storage areas.
PART 2 PRODUCTS – NOT USED.
PART 3 EXECUTION – NOT USED.
END OF SECTION
Barriers
015600 - 1
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 015600
BARRIERS
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes
1. Dust barriers.
2. Barricades.
3. Miscellaneous barriers and efforts, including construction fencing, and signage.
B. Related Sections
1. Section 015000: Temporary Facilities and Controls.
2. Section 024119: Selective Structural Demolition.
3. Section 030100: Concrete Repairs.
4. Section 033810: Post-tension Garage Cable Repairs.
5. Section 055000: Miscellaneous Metals.
6. Section 061053: Miscellaneous Rough Carpentry.
7. Section 070150: Membrane Reroofing Preparation.
8. Section 071800: Vehicular Traffic Membrane.
9. Section 071910: Penetrating Concrete Water Repellent/Corrosion Inhibitor.
10. Section 075416: KEE Roofing.
11. Section 075600: Fluid-Applied Roofing.
12. Section 079000: Expansion Joints.
13. Section 079200: Sealants.
14. Section 081100: Metal Doors and Frames.
15. Section 084413: Glazed Aluminum Storefront, Window, and Entrance Systems.
16. Section 221400: Drains and Piping.
17. Section 321723: Pavement Markings.
1.2 SUBMITTALS
A. Submittals are not required unless Owner or Engineer raise questions or concerns regarding the quality or construction of barriers or enclosures. Potential submittals, if requested, could include the following:
015600 - 2
1. Fire-retardant treatment for dimensional lumber and plywood.
2. Fire-resistant visqueen sheeting.
3. Plastic Safety Fencing.
4. Enclosure construction details.
PART 2 PRODUCTS
2.1 MATERIALS
A. Lumber
1. Dimensional lumber
a. Minimum 2 x 4 dimensional lumber.
b. Fire-retardant treated (non-com) with treatment stamp visible.
2. Plywood
a. Minimum 1/2-inch thick.
b. Fire-retardant treated (non-com) with treatment stamp visible.
B. Visqueen Sheeting
1. Approved Products:
a. Griffolin fire-retardant type 55-FR.
b. Midco vinyl fire-resistant reinforced polyfilm.
C. High Visibility Safety Fencing
1. High density polyethylene material.
2. Diamond mesh with 1-1/2" openings.
3. Minimum 4 feet high.
4. Bright orange color.
5. Minimum 2200 lbs. break load capacity.
D. Chain Link Fencing with Mesh Screening.
1. Minimum 6’-0” feet tall.
2. Minimum 9 gauge galvanized with 2”x2” pattern configuration.
3. Fence to be panelized system, surface set with ballasted based.
4. Drilled posts are not permitted.
5. Provide green mesh screening at panels.
015600 - 3
PART 3 EXECUTIONS
3.1 GENERAL
A. Work shall not proceed until dust barriers, barricades, construction fencing, or partial or full height barriers or enclosures are in place and secure.
B. Provide barricades to isolate areas directly under work areas for protection of persons or property.
C. Installation and removal of barricades or barriers shall not damage existing surfaces.
D. The use of anchors which penetrate the existing surface are prohibited, unless approved in advance by Engineer.
E. Remove all evidence of barriers installation upon removal.
F. Contractor is responsible for erection, maintaining, moving and removal of barricades, fencing and barriers from the job site.
3.2 BARRICADES
A. Where barricades are required for vehicular traffic control, provide orange construction fencing to divert traffic around work area. Support orange fencing to prevent sagging along entire length of barricade. Maximum spacing of orange fencing support is ten feet.
Construct and provide barricades that are permanent for the period when the barricade is required. Weight or otherwise secure the barricades to keep unauthorized personnel from moving them.
B. Where barricades are required to work areas and stair/elevator towers, provide chain link fencing with a mesh. Fully support base of fencing panels provide barricades that are permanent and fully secured for the period when the barricade is required.
C. Provide partial height or full height dust barriers where work performed is adjacent to pedestrian walkways, drive lanes or other public access areas.
D. Use of sawhorses, barrels and yellow caution tape are permitted only with advance approval by Owner.
Selective Structure Demolition
024119 - 1
DIVISION 02 – EXISTING CONDITIONS
SECTION 024119
SELECTIVE STRUCTURE DEMOLITION
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes
1. All labor, material, equipment, special tools, and services required to complete the work required for the project as indicated on the Drawings and in the Specifications, including but not limited to:
a. Demolition of selected portions of the structure as indicated in the Contract
Documents.
b. Demolition and removal from the job site of miscellaneous features as indicated in the Contract Drawings.
c. Removal from the job site and legal disposal of existing debris and accessories as shown on the Drawings.
d. Supply and maintenance of dumpsters to accommodate debris removals.
e. Maintenance of drains to accommodate storm water during demolition.
2. Materials Ownership
a. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain the Owner’s property, demolished materials shall become the Contractor’s property and shall be removed from the site with further disposition at the Contractor’s option.
b. Storage or sale of removed items or materials on-site will not be permitted.
1.2 REFERENCES AND REGULATORY REQUIREMENTS
A. Conform to applicable laws, ordinances, and the State Building Code for demolition of structures, safety of adjacent structures, dust control, runoff control, and disposal.
B. Comply with ANSI A10.6.
C. Comply with applicable requirements of NFPA Standard No. 241.75: Safeguarding
Building Construction & Demolition Operations.
D. Obtain required permits from authorities.
E. Do not close or obstruct roadways, sidewalks, and hydrants without permits.
F. Do not close or obstruct egress width to any entrance or exit.
G. Do not disable or disrupt fire or life safety systems without three days prior written notice to the Owner.
024119 - 2
H. Conform to applicable regulatory procedures when discovering hazardous or contaminated materials.
1.3 SUBMITTALS
A. Schedule of selective demolition activities indicating the following:
1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity.
2. Detailed sequence of selective demolition and removal work to ensure uninterrupted progress.
3. Coordination of Owner’s continuing occupancy.
B. Inventory: After demolition is complete, submit a list of items that have been removed and salvaged for Owner.
C. Pre-demolition Photographs or Videotape: Show existing conditions of adjoining construction and site improvements, including finish surfaces, which might be misconstrued as damage caused by demolition operations. This submittal should be delivered before Work begins.
1.4 QUALITY CONTROL
A. Demolition Firm Qualifications: An experienced firm that has specialized in demolition work similar in material and extent to that indicated for this Project. The firm shall have successfully performed at least three verifiable projects, similar to this project, within the last seven years.
B. Work in this Section shall be under the immediate control of a person (Contractor’s superintendent or other designated person) experienced in this type of work. The person identified with immediate control of the work shall have supervised three verifiable projects of similar magnitude and type. Supervising person shall be present during all operations.
C. Pre-Demolition Conference: Review methods and procedures related to selective demolition including, but not limited to, the following:
1. Inspect and discuss condition of construction to be selectively demolished.
2. Review and finalize selective demolition schedule; verify availability of all materials, demolition personnel, equipment, and facilities needed to maintain the schedule.
3. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations.
4. Review areas where existing construction is to remain and requires protection.
D. The Contractor shall comply with all Federal, State and Municipal laws, codes, ordinances and regulations applicable to the Work in this Contract and also with all requirements of the National Fire Protection Association, the National Electric Code, and
024119 - 3 the Occupational Safety and Health Administration (OSHA). If the above laws, codes or ordinances conflict with this Specification, then the laws, codes or ordinances shall govern, except in such cases where the Specification exceeds them in quality of materials or labor, then the Specifications shall be followed.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Store materials under cover and keep them dry and protected against damage from weather, direct sunlight, surface contamination, corrosion, construction traffic, and other causes.
1.6 PROJECT CONDITIONS
A. Contractor shall coordinate with the Owner for the required access and staging areas needed to accommodate demolition operations at grade areas.
B. The Owner will continue to occupy portions of the structure immediately beneath the selective demolition area. Conduct selective demolition so that the Owner’s operations will not be disrupted.
C. Demolition Efforts
1. The Contractor shall collect all debris generated by the demolition process and legally dispose of off the Owner’s property. Do not stockpile debris. Remove dumpsters containing debris upon filling to capacity or completion of the work.
2. No equipment exceeding 4,000 lbs. per axle, including transportation and removal equipment shall be allowed on a supported structural level.
3. The Owner assumes no responsibility for actual condition of features and components to be selectively demolished.
a. Conditions existing at time of inspection for bidding purpose will be maintained by the Owner as far as practical.
D. Utility Services
1. Maintain existing utilities required to remain, keep in service, and protect against damage during demolition operations.
2. Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by authorities having jurisdiction and the Owner. Provide temporary services during interruptions to existing utilities, as acceptable to the governing authorities and Owner.
E. Damages: Promptly repair damages to adjacent construction, on or off site, caused by demolition operations at no cost to the Owner.
F. Hazardous Materials
1. Notify the Owner if asbestos-containing materials are encountered during demolition.
024119 - 4
PART 2 PRODUCTS – NOT USED
PART 3 EXECUTION
3.1 EXAMINATION
A. Examine areas intended for demolition and note conditions or defects that will adversely affect the execution and/or quality of the work.
B. Notify Owner in writing of any such conditions or defects. Do not begin work until unsatisfactory conditions are corrected. Failure to notify Owner prior to beginning work constitutes acceptance by Contractor of the surfaces and conditions under which the work is to be performed, and acceptance by Contractor for the performance of the work.
C. Inventory and record the condition of items to be removed and salvaged.
D. Engage a professional demolition engineer to perform an engineering survey of existing conditions of structure to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective demolition operations.
E. Verify that hazardous materials have been remedied before proceeding with selective demolition operations.
3.2 PREPARATION
A. Protection
1. Provide temporary protection during the course of the work to prevent water entry into the structure and walls and to maintain the structure in a weather tight condition.
Ensure that protection is in place and water tight before ending day's work.
2. Be prepared for unexpected weather changes so that temporary protection can be quickly installed.
3. Provide, erect, and maintain temporary barriers and security devices. Prevent spread of dust, odors, and noise to permit continued Owner’s occupancy.
4. Provide protection on existing surfaces and features to remain. Secure protection to prevent wind events from shifting or moving temporary protection. Securement methods shall not penetrate the surfaces or features. Protection shall define the path over which demolished material will be transported.
5. Conduct demolition operations and remove debris to ensure minimum interference with the interior of the structure, roads, streets, walks, adjacent structures, and utilities.
6. Conduct operations with minimum interference to public or private accesses.
Maintain protected egress and access at all times.
7. Protect existing landscaping materials, structures, and utilities which are not to be demolished.
024119 - 5
3.3 DEMOLITION REQUIREMENTS
A. Coordinate regular removal and replacement of filled dumpsters from the job site during off hours only, unless pre-approved by the Owner in advance.
B. Do not remove any part of the work that will leave the remaining work unstable, until adequate temporary bracing and shoring have been provided, or until permanent bracing or construction is in place. Cease operations immediately if adjacent structures appear to be in danger. Notify Owner and authority having jurisdiction. Do not resume operations until directed.
C. If deteriorated materials, not intended for removal, are encountered during demolition, stop all work in that area and notify the Owner immediately.
D. Demolish and remove existing construction to the extent required and as indicated. Use methods required to complete work within limitations of governing regulations and as follows:
1. Where required, neatly cut materials to be removed. Use cutting methods least likely to damage construction to remain or adjoining construction. To minimize disturbance of adjacent surfaces, use hand or small power tools designed for sawing or grinding, not hammering, and chopping. Temporarily cover openings to remain.
2. Remove temporary work.
E. Explosives: The use of explosives will not be permitted.
3.4 DISPOSAL OF DEMOLISHED MATERIALS
A. General: except for items to be salvaged, etc, remove demolished materials from project site and legally dispose of them in an EPA approved landfill.
1. Do not allow demolished materials to accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Separate recyclable demolished materials from other demolished materials to the maximum extent possible. Separate recyclable materials by type.
1. Provide containers or other storage method for controlling recyclable materials until they are removed from Project site.
2. Stockpile processed materials on site without intermixing with other materials. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
3. Stockpile materials away from demolition area. Do not store within the drip lines of remaining trees.
4. Store components off the ground and protect from the weather.
024119 - 6
5. Transport materials off Owner’s property and legally dispose of them.
C. Remove from site and legally dispose of debris, rubbish, and other materials resulting from demolition operations.
D. Burning of removed materials will not be permitted on the site.
3.5 PATCHING AND RESTORATION
A. Neatly patch and finish disturbed existing surfaces damaged by demolition.
B. Verify all patch locations, methods, and procedures with Engineer prior to beginning repairs.
3.6 STORM DRAINAGE MAINTENANCE
A. Maintain all drains during construction. Keep free and clear of debris to allow for proper drainage. Construction and construction barriers should not impede normal site drainage.
3.7 CLEANING
A. Clean adjacent floor and wall surfaces to remove dust, dirt, debris, sludge, etc., regardless of existing conditions prior to demolition.
Concrete Repairs
030100 - 1
DIVISION 03 – CONCRETE
SECTION 030100
CONCRETE REPAIRS
GENERAL
1.1 SUMMARY
A. Section Includes
1. All labor, material, equipment, special tools, and services required to complete the work required for the project as indicated on the Drawings and in the Specifications, including but not limited to:
a. Shallow floor repairs.
b. Concrete PT slab repairs.
c. Concrete slab overlay repairs.
d. Vertical surface repairs.
e. Overhead repairs.
f. Beam bottom repairs.
g. Expansion joint blockout repairs.
h. Curb repairs.
i. Miscellaneous repairs indicated on the Drawings.
B. Related Sections
1. Section 015600: Barriers.
2. Section 024119: Selective Structural Demolition.
C. Unit Prices
1. Unit prices are taken for the project bid quantities.
2. Final adjustment to the contract amount will depend on actual quantities of repair performed.
3. Repair quantities will be determined by measurements made jointly by the owner or its representative and the contractor. The contractor will record the measurements with both parties signing the record to attest to its accuracy.
4. Refer to Project General Provisions Section for measurements and payment.
1.2 REFERENCES
A. American Concrete Institute (ACI)
1. ACI 301 - Specification for Structural Concrete for Buildings.
2. ACI 305R - Hot Weather Concreting.
030100 - 2
3. ACI 306R - Cold Weather Concreting.
4. ACI 318 - Building Code Requirements for Reinforced Concrete.
B. American Society for Testing and Materials (ASTM)
1. ASTM A185 - Specification for Steel Welded Wire, Fabric, Plain, for Concrete
Reinforcement.
2. ASTM A615 - Specification for Deformed and Plain-Billet Steel Bars for Concrete
Reinforcement.
3. ASTM A775 - Standard Specification for Epoxy-Coated Reinforcing Steel Bars.
4. ASTM C31 - Method of Making and Curing Concrete Specimens in the Fields.
5. ASTM C33 - Concrete Aggregates.
6. ASTM C39 - Test Method for Compressive Strength of Cylindrical Concrete
Specimens.
7. ASTM C94 - Specification for Ready-Mixed Concrete.
8. ASTM C143 - Standard Test Method for Slump of Portland Cement Concrete.
9. ASTM C150 - Specification for Portland Cement Concrete.
10. ASTM C260 - Specification for Air-entraining Admixtures for Concrete.
11. ASTM C494 - Specification for Chemical Admixtures for Concrete.
C. Structural Steel Painting Council (SSPC)
1. Surface Preparation Specification No. 6 (SP6) - Commercial Blast Cleaning.
D. American Association of State Highway and Transportation Officials (AASHTO)
1. AASHTO M182 - Specifications for Burlap Cloth Made from Jute or Kenaf.
E. Keep a copy of the referenced specifications cited in this section in the on-site field office.
1.3 SUBMITTALS
A. Submit literature for manufactured products, including manufacturer's specifications, test data and installation instructions.
B. Letter stating this Contractor and supplier are familiar with the referenced standards.
C. Submit shop drawings for review for all steel reinforcement in new curbs, topping slabs, and localized full slab replacement.
D. Submit mix designs and test results conforming to the requirements of Section 4 of ACI
301. Submit request for approval to use admixtures, if any. A complete mix design submittal must be furnished at least three weeks before the planned use of that mix. The
Contractor is cautioned to undertake mix design preparation and submittal procedures immediately after authorization to proceed with the project.
1. Submitted mix design shall address weather conditions which are expected to occur
030100 - 3 during the concrete repair phases. Concrete mixes shall not only be designed for average temperature and humidity conditions, but also for adverse conditions (hot and cold weather), as applicable to this project.
E. Provide the following in accordance with ACI 301
1. Mill test for cement.
2. Admixture certification.
3. Aggregate certification.
4. Procedure for adding water to ready-mix at site, including method of measuring water.
5. Method of adding admixtures.
6. Materials and methods for curing.
7. Ready-Mix delivery tickets.
8. Certificate of Conformance for concrete production facilities by NRMCA (National
Ready-Mix Contractors Association).
9. Field and laboratory tests that are the Contractor's responsibility.
F. The Owner's review of details and construction operations shall not relieve this Contractor of his responsibility for completing the work successfully in accordance with the Contract
Documents.
1.4 QUALITY ASSURANCE
A. The Contractor shall comply with all Federal, State and Municipal laws, codes, ordinances and regulations applicable to the Work in this Contract and also with all requirements of the National Fire Protection Association, the National Electric Code, and the Occupational
Safety and Health Administration (OSHA). If the above laws, codes or ordinances conflict with this Specification, then the laws, codes or ordinances shall govern, except in such cases where the Specification exceeds them in quality of materials or labor, then the
Specifications shall be followed.
B. Concrete that does not conform to the specified requirements, including bond to substrate, strength, finish and tolerances shall be subject to removal and replacement, including necessary preparatory work, at no additional cost to the Owner and without extension to the Contract Time.
C. Contractor shall be responsible for restoration of other components of the Work damaged during placement of concrete or damaged during removal of unsatisfactory concrete.
D. ACI 301, ACI 305R and ACI 306R are a part of the Contract Documents, are incorporated herein as fully as if here set forth and are referred to as General Concreting Requirements.
E. Chloride Ion Limitations: Maximum acid-soluble chloride ion concentration, in hardened concrete shall not exceed .10% by weight of cement.
F. Concrete testing and certification shall be as described in ACI 301, Chapter 16.
030100 - 4
1.5 WARRANTY
A. A warranty period of two (2) years shall be provided for concrete work performed under this Section against defects, as determined by the Owner, including but not limited to debonding, excessive cracking and surface scaling.
PRODUCTS
2.1 MATERIALS
A. General
1. Ready mixed materials used for concrete shall be furnished from the same source throughout the project unless otherwise approved by the Owner.
B. Cement
1. Use ASTM C150, Type I or Type II, or ASTM C595, Type IL cement unless noted otherwise. Air-entrained cement shall not be used. Air requirements shall be met by separate admixtures.
C. Admixtures
1. Air-entraining admixtures meeting the requirements of ASTM C260.
2. High range water reducer meeting the requirements of ASTM C494.
3. Calcium chloride, calcium nitrate and thiocyanates are not permitted. Admixtures containing more than 0.05% chloride ions are not permitted.
4. Use approved admixtures in accordance with manufacturer's recommendations.
D. Fine and Coarse Aggregates
1. Meeting requirements of ASTM C-33.
E. Water
1. Mixing water shall be potable meeting requirements of ASTM C-94.
F. Pre-packed Concrete Materials
1. Horizontal Application: Typical Repair Areas (Patch Material Type A)
a. Plainitop 11 SCC by Mapei.
b. SikaEmaco 100 CI by Sika Corp.
c. Deck Mix AE by US Concrete Products
2. Vertical and Overhead Repair Areas: Trowel Grade (Patch Material Type B.1)
a. SikaEmaco 488Cl by Sika Corp.
b. SikaQuick VOH by Sika Corp.
c. SikaEmaco 425 Gel Patch by Sika Corp.
d. Planitop XS by Mapei
030100 - 5
e. US Thin Patch V/O by US Concrete Products
f. SikaEmaco 488Cl by Sika Corp.
g. SikaQuick VOH by Sika Corp.
3. Vertical and Overhead Repair Areas: Form-and-Pour (Patch Material Type B.2)
a. SikaQuick FNP by Sika Corp.
b. SikaEmaco440 by Sika Corp.
c. Planitop 15 by Mapei
d. Deck Mix FP by US Concrete Products
G. Bar Coating
1. Sikadur 32, Hi-Mod LPL by Sika Corp.
2. MasterEmaco ADH 326 by Sika Corp.
H. Bonding Agent (used for shallow floor patches if the patch is not deep enough for patch anchors; patch material must be placed while epoxy is still wet)
1. Sikadur 32, Hi-Mod LPL by Sika Corp.
I. Welded Wire Reinforcement
1. Conforming to ASTM A185.
2. All steel to be epoxy coated unless specifically noted otherwise on the drawings.
J. Reinforcing Steel
1. All reinforcing steel shall have a minimum Fy of 60 ksi.
2. All steel to be epoxy coated unless specifically noted otherwise on the drawings.
K. Curing Materials
1. 10 oz. burlap meeting the requirements of AASHTO M-182.
2. Visqueen: 6 mil polyethylene (white).
L. Curing Compound
1. VOCOMP-25 by W.R. Meadows.
2. MasterKure CC 1315WB by Sika Corp.
3. Liquid membrane forming curing compound shall conform to the requirements of
ASTM C1315, Type 1, Class A and have data from an independent laboratory indicating a maximum moisture loss of 0.40 grams per square cm. when applied at a coverage rate of 300 square feet per gallon.
M. Form Lumber
1. New fire-retardant material, grade and size to adequately form, support and brace concrete and to provide finishes that match adjacent surfaces.
030100 - 6
N. Epoxy Grout
1. Sikadur 32, Hi-Mod LPL epoxy mixed with silica sand.
O. Patch Anchors
1. Stainless steel mushroom head spikes by DeWalt.
2.2 MIXES
A. General
1. Ready Mix Producer, General Contractor, and those responsible for placing and finishing concrete shall review mix designs and agree on modifications to the proposed mixes listed below required to facilitate placing and achieve the desired results. No modifications reducing the cement content, increasing the chloride content or the W/C ratio will be acceptable. Both the General Contractor and Ready-Mix Producer are responsible for design and production of concrete mix.
B. Concrete Mix: (Patch Material Type C)
1. Strength at 28 days: 5000 psi.
2. Minimum Portland cement content: 565 lbs./C.Y.
3. Maximum percent of chloride by weight of cement: 0.10
4. Maximum water/(cement plus silica fume) ratio: 0.40
5. Percent of air entrainment (tested at point of placement): 5 to 7 percent
6. Maximum aggregate size: 3/8 inch
C. Slump
1. Produce the concrete to have a maximum slump of 4 inches as delivered to the site.
The maximum slump may not be exceeded except by the job site addition of High
Range Water Reducer (Superplasticizer).
2. When superplasticizer is used, the maximum superplasticized slump shall be 8".
Superplasticizer may not be added to a batch of concrete after initial slump adjustments are made and discharge has started.
3. Method of measuring and adding superplasticizers to the truck mixer at the site shall be approved by the Engineer.
4. Mix designs incorporating superplasticizer must be accompanied by test results from cylinders made from previous field test data in which the superplasticizer was added to a 6 c.y. (min.) batch in a truck mixer.
2.3 PRODUCTION OF CONCRETE
A. Furnish to the Project Superintendent 2 delivery tickets for each load of Ready-Mixed concrete. Tickets shall contain the following information:
1. Date.
030100 - 7
2. Producer and plant.
3. Job.
4. Contractor.
5. Truck No. and time dispatched.
6. Concrete designation and cement type.
7. Admixtures description and content.
8. Time discharge started and completed.
9. Amount of concrete in load.
10. Amount of water in mix at plant.
11. Amount of material(s) added at the site and authorized signature.
B. Site-mixed concrete is prohibited.
C. High Range Water Reducers (Superplasticizers) shall be premeasured and added at the site in accordance with the manufacturer's written instructions and specifications, using truck-mounted power injection equipment capable of rapidly and uniformly distributing the admixture to the concrete. Alternatively, the superplasticizer may be added manually to the back of the truck by a trained technician, if this procedure is confirmed by historical data to yield a uniform and acceptable product. Mix the concrete a minimum of six minutes after addition of the superplasticizer and before discharge.
D. Re-tempering with superplasticizer is prohibited.
E. When concrete arrives at the project with slump below that suitable for placing and below the slump specified, water may be added only if neither the maximum specified water/cement ratio nor the maximum slump is exceeded, provided that:
1. The approved mix design has allowed for on-site addition of water.
2. The amount of water added at the site is accurately measured to ± 1 gallons of the desired added amount.
3. That water addition is followed by 3 minutes of mixing at mixing speed prior to discharge.
4. Standard cylinder samples as required by these Specifications are taken after addition of water.
5. The person authorized to add water shall be mutually approved by Engineer, Contractor, and Ready-Mix Producer.
F. All concrete arriving at the site above the maximum slump will be…
This is the start of the file's text. The full file is on GovTribe.