This document is a set of engineering and construction plans for the Pinellas County Public Works Department's FY2025-2026 Countywide Pavement Preservation Program, specifically focusing on Keene Road from East Bay Drive to Belleair Road. The project involves milling and resurfacing approximately 7.62 lane miles spanning 472,308 square yards, with a total estimated project cost of $1,110,216. The project includes comprehensive road restoration techniques such as milling existing asphalt pavement to a depth of 2 inches and applying a new Type SP 12.5 Structural Course (Traffic C) surface layer, also 2 inches deep. The design incorporates detailed plans for road markings, lane configurations, and maintaining proper road crown and drainage.

The project documentation includes extensive technical specifications for road reconstruction, including precise guidelines for milling, resurfacing, pavement marking, utility coordination, and traffic management. The plans detail core sampling results, typical road sections, and specific requirements for shoulder stabilization, inlet protection, and loop detector positioning. Eight core samples were taken to assess existing pavement and base conditions, with variations noted in top lift, middle lift, and bottom lift thicknesses. The project will involve carefully managing existing utilities, maintaining traffic flow, and ensuring proper surface elevation and drainage, with all work to be completed according to Pinellas County and Florida Department of Transportation standards.

View the file

Other files

Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PID 25-0070-006576A

FY2025-2026 COUNTYWIDE

PAVEMENT PRESERVATION PROGRAM

KEENE RD (E BAY DR - BELLEAIR RD)

FINANCIAL PID 004192A

STATE OF

No.

PR

O

FESSIONAL ENGIN

EE

R

JE

FFR

EY S. THOMPSON

FLORI'A

93254

MILLING

MILL EXISTING ASPHALT

PAVEMENT FOR DEPTH (2")

RESURFACING

TYPE SP 12.5 STRUCTURAL COURSE (TRAFFIC C) (2")

KEENE RD (EAST BAY DR - BELLEAIR RD)

STA. 51+38.65 TO STA. 55+95.60

TYPICAL SECTION

* 2% (OR AS DIRECTED BY THE ENGINEER)

STA. 55+95.60 TO STA. 129+77.90

TYPICAL SECTION

* 2% (OR AS DETERMINED BY THE ENGINEER)

KEENE RD (EAST BAY DR - BELLEAIR RD)

NOTES: SEE SHEET 11 FOR CORE LOCATION MAP

Feet

40200 10

Sheets and Views
1 Eng_Cover_SSM
2 GENERAL NOTES
3 ROAD TYPICAL SECTION
4 SH (50+00.00-56+20.00)
5 SH (62+40.00-68+60.00)
6 SH (74+80.00-81+00.00)
7 SH (87+20.00-93+40.00)
8 SH (99+60.00-105+80.00)
9 SH (112+00.00-118+20.00)
10 SH (124+40.00-130+60.00)
11 CORE LOCATION MAP
12 Typical Sections A_B
13 Typical Section C
14 LOOP DETAIL
2025-02-18T16:42:43-0500
Jeffrey S Thompson

File details come from the government source that posted it. Updated .