Attachment 6 - B2024 LPS Repair Questions and Answers.pdf

PDF 42 KB Posted

Attached to
Lightning Protection Systems Repair Building 2024 PSFB CO
Solicitation number
21CONSLPSSmith
Issued by

About this file

This document is a Questions and Answers (Q&A) file for a Lightning Protection Systems (LPS) Repair project for Building 2024. The file contains three key clarifications from potential bidders: 1) Specification for air terminals, which are specified as fiberglass, 2" X 21" – 3" in size, with a 25' #228 Class II Lightning Protection Conductor and 24" Blunt Tip air terminal, 2) Confirmation that LPI (Lightning Protection Inspector) certification can be submitted by a subcontractor, and 3) Verification that the required 5-years' experience can be provided in the narrative section of the proposal. The Q&A document is associated with a Department of the Air Force Space Command solicitation (Solicitation Number: 21CONSLPSSmith) for Lightning Protection Systems Repair.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B2024 LPS Repair Questions and Answers

Q: What size diameter and length do you want the new air terminals to be?

Q: What materials would you like the air terminals made from?

A: For mast air terminal, it shows the fiberglass 2” X 21” – 3” with 25’ #228 Class II Lightning Protection Conductor with 24” Blunt Tip air terminal.

Q: Can the LPI certification be submitted by a subcontractor?

A: Yes, the LPI certification needs to be submitted by a subcontractor.

Q: Can the 5-years’ experience be provided in the narrative or are you asking for past performance projects to be provided?

A: Yes, the 5-years’e experience can be provided in the narrative.