218035 Bonifay ESP Addendum #1 .pdf

PDF 138 KB Posted

Attached to
Bonifay ESP
Solicitation number
ITB-00383
Issued by
Highlands County, Florida

About this file

This document is an addendum to an Invitation to Bid issued by the Florida Army National Guard Construction & Facility Management Office for Project 218035 - Bonifay ESP. The addendum modifies the original bidding documents and includes revisions to the civil site work, utility services, and other miscellaneous items as detailed in the attached narratives and revised plan sheets. Key clarifications and details include: the contractor's responsibility for termination of access control cabling and programming, the military unit's responsibility for relocating storage containers, and information on the removal and reinstallation of chain link fencing. The bid opening date is May 11, 2022 at 2:00 PM EST in St. Augustine.

The base bid for this project includes renovation of approximately 170,000 sf or 3.90 acres of the existing Bonifay National Guard Armory in Bonifay, Florida. The scope of work covers civil site work, utility services, paving, fencing, and other miscellaneous items as described in the project specifications and drawings. This project is funded by the State of Florida and will be awarded to a qualified contractor.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Army National Guard Construction & Facility Management Office

ISSUED ADDENDUM

Rev. 11/2018

Date April 27, 2022

Addendum Number 1

Project Number and Name 218035 - Bonifay ESP

Invitation to Bid Date April 5, 2022

Number of Attachments 4

Bid Opening Date and Time May 11, 2022 (2:00 PM EST – St. Augustine)

This addendum and the listed attachments forms a part of the contract documents and modifies the original bidding documents. Acknowledgement of this addendum in Exhibit 4 - Bid Proposal is required.

Concerns with this addendum should be addressed to:

ng.fl.flarng.list.cfmo-contracting@army.mil

Questions (Q) / Answers to Questions (A) / Clarifications (C) / Modifications (M)

M1. See attached Civil Addendum Narrative from Paul Davidson with Melvin Engineering dated April 27, 2022 and revised Plan Sheets regarding the full replacement of existing water and sewer lines.

Q1. Who will be responsible for the termination of the access controls cablings and programing for gate 14 and personnel gate?

A1. The Contractor See Specification Section 111200 and revised Plan Sheets.

Q2. Who is responsible for moving storage/containers?

A2. The military unit personnel will relocate storage containers and/or equipment within the limits of construction.

Q3. Provide mounting detail of gutter since metal roof extends out.

A3. See Sheet A502 - ROOM SIGNAGE AND GATE DETAILS, DAG Architects Revision #2 Addendum No. 1 dated 04/27/2022, DETAIL 4 - ROOF EDGE DETAIL mailto:ng.fl.flarng.list.cfmo-contracting@army.mil

Q4. Will chain link fence behind BLDG #6 need to be removed, reinstalled, and extended?

A4. See attached Civil Addendum Narrative from Paul Davidson with Melvin Engineering dated April 27, 2022 and revised Plan Sheets regarding the removal and installation of chain link fencing north of Building #6.

Attachment List

1. DAG Architects Addendum #1 dated April 27, 2022 (2 pages)

2. Melvin Engineering Civil Addendum Narrative dated April 27, 2022 (1 page)

3. Technical Specifications April 2022 Addendum No. 1

Specification Section 111200 (8 pages)

4. Revised Drawings (8 sheets)

a. Sheet G000 - Cover Sheet - Revision 1 dated 4/27/2022

b. Sheet C-1.1 - Demolition & Sedimentation/Erosion Control Plan Revision 1 dated 4/27/2022

c. Sheet C-2.0 - Site Geometry Plan - Revision 1 dated 4/27/2022

d. Sheet C-4.0 - Utility Plan - Revision 1 dated 4/27/2022

e. Sheet A502 - Room Signage & Gate Details - Revision 2 dated 4/27/2022

f. Sheet E0.1 - Legend and Notes - Revision 1 dated 4/27/2022

g. Sheet E1.1 - Site Plan - Electrical - Revision 1 dated 4/27/2022

h. Sheet E2.1 - Grounding Details - Revision 1 dated 4/27/2022

END OF ADDENDUM #1