This presolicitation notice announces an upcoming solicitation for National Forest System Road 384 Improvements. The scope of work includes traffic control, erosion control, installing three aquatic organism passage culverts, replacing and installing road drainage culverts, screening and placing embankment material, installing two underdrain systems, placing riprap, mixing and placing aggregate surfacing, and asphalt paving. The location is on National Forest System Road 384 on the Boise National Forest in Idaho. The estimated start date is June 8, 2020, with a period of performance of 276 calendar days ending on October 8, 2021. The estimated value is between $1,000,000 to $5,000,000. A site visit is scheduled for April 29, 2020. The solicitation will be issued on or around April 15, 2020 and available on SAM.gov. The successful offeror must register in SAM and will be awarded a firm-fixed-price contract. The NAICS code is 237310 and the size standard is $39.5 million.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OFFEROR'S COPY
NOTE: Attached forms must be completed and submitted intact.
Solicitation No. RFP 12026120R0004 HELP PREVENT FOREST FIRES
IMPORTANT - NOTICE TO OFFEROR
1. This is a complete copy. Information and instructions for submission of proposals as well as contract provisions and specifications are contained in this OFFEROR REFERENCE COPY. This copy should be retained by offerors.
2. Note: An offer guarantee (Bid Bond) IS REQUIRED. Performance and Payment Bonds will be required of the successful offeror. (See Section I, FAR Clause 52.228-15.)
3. All questions regarding this solicitation must be in writing and addressed to the Contracting Officer email Tanya Spanfellner-tanya.spanfellner@usda.gov.
All questions must be received no later than 1630 MT on Friday April 24, 2020 to be considered prior to solicitation close date.
AT A MINIMUM PROVIDE THE FOLLOWING
1.SF-1442, Complete, date, and sign.
Provide DUNS NUMBER and email address. Block 14
2. Representations and Certifications Section K 52.204-8. You must complete Representations and Certifications via SAM, please only submit a response to Paragraph (b)(1) Pg. 32 and 35(as needed).
3.Provide information required Section L 452.215-71
4. Fill out the pricing schedule for all items Section B-Schedule of Items Pages 4-7, or similar providing same information. Place totals on Pages 2 bock 17 of SF-1442
5. Provide Liability insurance verification
6. Complete Determination of responsibility, Attach 9
7. Submit Bid Guarantee 52.228-1-20% of you bid
Proposals are due May 8, 2020 by 1630 MT Hand deliver or mail to Or Email:tanya.spanfellner@usda.gov USFS ATTN: Tanya Spanfellner 1249 S Vinnell Way, Ste. 200 Boise, ID 83709-1663
Issuing Office:
U.S. Department of Agriculture Forest Service SW Idaho/Nevada Acquisition Center
ATTN:TANYA SPANFELLNER
1249 S. Vinnell Way, Suite 200 Boise, ID 83709
Offers Are Solicited For:
NATIONAL FOREST SYSTEM ROAD 384
IMPROVEMENTS
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
994116
SW IDAHO-NEVADA ACQUISITION CENTER
ATTN
1249 S VINNELL WAY STE 200
BOISE ID 83709-1663
TANYA SPANFELLNER 208-373-4130
1x 03/30/2020
12026120R0004
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
National Forest System Road 384 Improvements
The estimated price range is between $1,000,000 and $5,000,000.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 276 calendar days and complete it within ________________ ________________ calendar days after receiving
52.211-10
05/08/2020
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
SW IDAHO-NEVADA ACQUISITION CENTER
ATTN
1249 S VINNELL WAY STE 200
BOISE ID 83709-1663
TANYA SPANFELLNER
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
DUNS No.:______________________________________
EMAIL Address:____________________________
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 47
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
12026120R0004
National Forest System Road 384 Improvements
Delivery: 05/01/2020
Delivery Location Code: 0261
SW IDAHO-NEVADA ACQUISITION CENTER
ATTN
1249 S VINNELL WAY STE 200
BOISE ID 83709-1663 US
0001 National Forest System Road 384 Improvements
Please fill out Schedule Of Items page 4-7 and return with package
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Bid Schedule for Edna Creek Culvert Replacement – Upper
Item No. Description Pay Unit
Estimated Quantity Unit Price Total Price
15101 Mobilization Lump Sum 1 $ $
15201 Construction Survey and Staking Lump Sum 1 $ $
15713 Soil Erosion and Pollution Control Lump Sum 1 $ $
20101 Clearing and Grubbing Lump Sum 1 $ $
20301 Removal of Existing Multiplate Culvert, Disposal Method A Lump Sum 1 $ $
20804 Structural Excavation and Backfill Lump Sum 1 $ $
25101* Placed Riprap, Class 3 (Commercial Source) Cubic Yard 21 $ $
27250* Geocell Abutment Stabilization, 6 Inch Depth Square Yard 67 $ $
30201* Aggregate Base Course (Government Furnished )
Cubic Yard 94 $ $
40301* Asphalt Concrete Pavement Type 1, 3/4 Inch Ton 46 $ $
553A01 Precast Concrete Members, Stem Wall W/ Footing LS 1 $ $
60302 12'-0" Span, 6' 3" rise, Structural Plate-Arch, 0.138" Thick, 6" x 2" Corrugations
Linear Foot 74 $ $
62201 Hydraulic Excavator with Thumb Hour 1 $ $
63501 Temporary Traffic Control Lump Sum 1 $ $
64801* Placed Streambed Simulation Rock, Bed Class 4 Cubic Yard 120 $ $
Total $
Note: * next to an Item Number above indicates that the quantity shown is a Contract Quantity per FP-14 Specification 109.02
Solicitation No.: 12026120R0004
Bid Schedule for Edna Creek Culvert Replacement – Lower
No. Description Pay Unit
Estimated Quantity Unit Price Total Price
15101 Mobilization Lump Sum 1 $ $
15201 Construction Survey and Staking Lump Sum 1 $ $
15713 Soil Erosion and Pollution Control Lump Sum 1 $ $
20101 Clearing and Grubbing Lump Sum 1 $ $
20301 Removal of Existing Multiplate Culvert, Disposal Method A Lump Sum 1 $ $
20804 Structural Excavation and Backfill Lump Sum 1 $ $
25101* Placed Riprap, Class 3(Commercial Source) Cubic Yard 27 $ $
27250* Geocell Abutment Stabilization, 6 Inch Depth Square Yard 83 $ $
553A01 Precast Concrete Members, Stem Wall with Footing Lump Sum 1 $ $
60302 12'-0" Span, 6' 3" rise, Structural Plate-Arch, 0.138" Thick, 6" x 2" Corrugations
Linear Foot 60 $ $
62201 Hydraulic Excavator with Thumb Hour 1 $ $
Yard 100 $ $
Note: * next to an Item Number above indicates that the quantity shown is a Contract Quantity per FP-14
Bid Schedule for Beaver Creek Culvert Replacement
No. Description Pay Unit
Estimated Quantity Unit Price Total Price
15101 Mobilization Lump Sum 1 $ $
15201 Construction Survey and Staking Lump Sum 1 $ $
15713 Soil Erosion and Pollution Control Lump Sum 1 $ $
20101 Clearing and Grubbing Lump Sum 1 $ $
20301 Removal of Existing Multiplate Culvert, Disposal Method A Lump Sum 1 $ $
20804 Structural Excavation and Backfill Lump Sum 1 $ $
25101* Placed Riprap, Class 3 (Commercial Source) Cubic Yard 25 $ $
27250* Geocell Abutment Stabilization, 6 Inch Depth Square Yard 105 $ $
553A01 Precast Concrete Members, Stem Wall with Footing Lump Sum 1 $ $
60302 20'-0" Span, 6' 4" rise, Structural Plate-Arch, 0.17" Thick, 6" x 2" Corrugations
Linear Foot 66 $ $
62201 Hydraulic Excavator with Thumb Hour 1 $ $
Yard 200 $ $
Note: * next to an Item Number above indicates that the quantity shown is a Contract Quantity per FP-14
Bid Schedule for NFSR 384 Road Improvements
No. Description Pay Unit
Estimated Quantity Unit Price Total Price
15101 Mobilization Lump Sum 1 $ $
20301 Removal of Culvert, Disposal Method A Each 36 $ $
20402 Roadway Excavation Mile 9.46 $ $
20415 Roadway Embankment, roller compaction Ton 8,400 $ $
25101* Placed Riprap, Class 3 (Commercial Source), including clearing and grubbing
Cubic Yard 779 $ $
30207* Minor Crushed Aggregate, roller compaction Cubic Yard 12,450 $ $
30232* Ditch Armor Cubic Yard 68 $ $
30321 Roadway Reconditioning Mile 2.27 $ $
30322 Roadbed Reconditioning, 6" Scarification Mile 4.86 $ $
30323 Ditch and Shoulder Reconditioning Mile 9.46 $ $
31101* Stabilized Aggregate Cubic Yard 12,450 $ $
60256A 18 inch corrugated steel pipe, 0.064 inch thickness
Linear Foot 1,772 $ $
60256B 24 inch corrugated steel pipe, 0.064 inch thickness
Linear Foot 56 $ $
60256C
36 inch corrugated steel pipe, 0.064 inch thickness. Includes: Saw Cut Asphalt, Excavation, Backfill, Sub base, compaction, and re- pave.
Linear Foot 40 $ $
60502A Install Multi-Flow Underdrain System 70' by 18" Lump Sum 1 $ $
60502B Install Multi-Flow Underdrain System 140' by 18" Lump Sum 1 $ $
60710 Recondition Drainage Structure Each 2 $ $
Note: * next to an Item Number above indicates that the quantity shown is a Contract Quantity per FP-14
SECTION C - Description/specifications/Statement of Work Clauses SECTION E - Inspection and Acceptance Clauses SECTION F - Deliveries or Performance Clauses SECTION H - Special Contract Requirements Clauses SECTION I - Contract Clauses Clauses SECTION J - List of Documents, Exhibits, and Other Attachments List of Documents, Exhibits, and Other Attachments SECTION K - Representations, Certifications, and Other Statements of Offerors Clauses L - SECTION L - Instructions, Conditions, and Notices to Offerors or Respondents Clauses SECTION M - Evaluation Factors for Award Clauses
SECTION C - Description/specifications/Statement of Work
Clauses 452.211-72 Statement of Work/Specifications. (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
(End of Clause)
452.211-73 Attachments to Statements of Work/Specifications. (FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
(End of Clause)
Scope of Contract
The work shall consist of but is not limited to traffic control; soil erosion and sediment control; installation of 3 aquatic organism passage (AOP) culverts; replacement and installation of road drainage culverts; screening, hauling, weighing, and placement of embankment material on sections of the road to reestablish the road template; installation of 2 underdrain systems, placement of riprap to protect road fill slopes, pugmill mixing and placement of aggregate surfacing on the road, and asphalt paving.
The contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and shall perform all work required to complete the project as shown on the plans, shown on the manufacturer’s shop drawings, and as described in the Standard Specifications (FP-14) and Forest Service Supplemental Specifications (FSSS).
Project Location
The project site is located on the Idaho City Ranger District, Boise National Forest, Boise County, Idaho on National Forest System Road (NFSR) #384 in Township 7 North, Range 7 East Section 10. The project begins at the junction with Idaho State Highway 21 at milepost 56.7 and ends at Little Owl Summit. The project site can be reached from Boise, Idaho by taking Idaho State Highway northeast for approximately 57 miles to the junction of NFSR 384.
List of Specifications
The Standard Specifications for this project are contained within the “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” FP-14 U.S. Customary Units. Copies of this document are available on-line only at the Federal Highway Administration web site at http://www.wfl.fha.dot.gov/design/specs/fp14.htm in either Microsoft Word .doc or Adobe Acrobat .pdf format.
Supplemental Project Specifications included in full text in Section J of the contract amend, supplement, or replace the Standard Specifications.
Standard Specifications (FP-14) and Forest Service Supplemental Specifications (FSSS) contained in the following list are applicable to this contract. All specifications not included in the specification listing but referenced by listed specifications are applicable.
FP-14 101 Terms, Format, and Definitions FSSS 101 Terms, Format, and Definitions FSSS 102 Bid, Award, and Execution of Contract FP-14 103 Scope of Work FSSS 103 Scope of Work FP-14 104 Control of Work FSSS 104 Control of Work FP-14 105 Control of Material FSSS 105 Control of Material
Solicitation No.: 12026120R0004 http://www.wfl.fha.dot.gov/design/specs/fp14.htm
FP-14 106 Acceptance of Work FSSS 106 Acceptance of Work FP-14 107 Legal Relations and Responsibility to the Public FSSS 107 Legal Relations and Responsibility to the Public FSSS 108 Prosecution and Progress FP-14 109 Measurement and Payment FSSS 109 Measurement and Payment FP-14 151 Mobilization FSSS 152 Construction Survey and Staking FP-14 153 Contractor Quality Control FSSS 153 Contractor Quality Control FSSS 154 Contractor Sampling and Testing FSSS 155 Schedules for Construction Contracts FSSS 156 Public Traffic FP-14 157 Soil Erosion Control FSSS 157 Soil Erosion Control FP-14 201 Clearing and Grubbing FSSS 201 Clearing and Grubbing FP-14 203 Removal of Structures and Obstructions FSSS 203 Removal of Structures and Obstructions FSSS 204 Excavation and Embankment FP-14 207 Earthwork Geosynthetics FP-14 208 Structure Excavation and Backfill for Selected Major Structures FSSS 208 Structure Excavation and Backfill for Selected Major Structures FP-14 209 Structure Excavation and Backfill FSSS 209 Structure Excavation and Backfill FP-14 251 Riprap FSSS 251 Riprap FSSS 272 Geocell Abutment Stabilization FP-14 302 Minor Crushed Aggregate FSSS 302 Minor Crushed Aggregate FSSS 303 Road Reconditioning FSSS 311 Stabilized Aggregate Surface Course FP-14 404 Minor Hot Asphalt Concrete FP-14 552 Structural Concrete FSSS 553A Precast Concrete Structures FP-14 554 Reinforcing Steel FP-14 602 Culverts and Drains FP-14 603 Structural Plate Structures FSSS 603 Structural Plate Structures FP-14 605 Underdrains, Sheet Drains, and Pavement edge Drains FP-14 607 Cleaning, Relaying, and Repairing Existing Drainage Structures FP-14 633 Permanent Traffic Control FP-14 635 Temporary Traffic Control FSSS 648 Stream Simulation FP-14 703 Aggregate FSSS 703 Aggregate FP-14 704 Soil FP-14 705 Rock FSSS 705 Rock FSSS 736 Geocell
NOTE: Bidders are cautioned to carefully review these Standard and Supplemental Project Specifications prior to submission of bids. All specifications in the “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” FP-14 U.S. Customary Units are binding on the parties signing the contract, including any that may be omitted above.
Technical Requirements Specific construction drawings and Supplemental Project Specifications are included in Section J. All items shown or noted on plans, which are not specifically bid items, are considered indirect payment items, per FP-14, Section 109.05(b). The cost of furnishing and installing all indirect payment items will not be paid for separately but shall be included in the unit price bid for other items unless noted otherwise.
Government Furnished Property
Crushed Aggregate and Caliche stockpile at Kempner Ranch, near Milepost 3 on Road 384.
Source for embankment material to be screened at Lamar waste site on Road 025M1.
SECTION E - INSPECTION AND ACCEPTANCE
CLAUSES INCORPORATED BY REFERENCE
52.246-12 Inspection of Construction (AUG 1996)
PART I - THE SCHEDULE
SECTION F - DELIVERIES OR PERFORMANCE
CLAUSES INCORPORATED BY REFERENCE
52.242-14 Suspension of Work (APR 1984)
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to
(a) commence work under this contract within 10 Days calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and
(c) complete the entire work ready for use not later than 276 days after notice to proceed received. The time stated for completion shall include final cleanup of the premises. Estimated start date June 8, 2020, and the entire project including final cleanup of the premises must be completed by October 8, 2021.
(End of clause)
Work Restrictions
Construction work on the Beaver Creek culvert replacement site must begin and be entirely completed between September 9, 2020 and October 2, 2020.
Construction work on the two Edna Creek culvert replacement sites must begin and be entirely completed between July 7, 2021 and September 2, 2021.
All instream work associated with the two Edna Creek culvert replacements must be completed prior to August 15th, 2021.
The last day in 2020 when work may take place on the project is October 9, 2020.
SECTION H - SPECIAL CONTRACT REQUIREMENTS
Clauses AGAR 452.237-74 Key Personnel (FEB 1988)
(a) The Contractor shall assign to this contract the following key personnel: Contracting Representative and Forman.
(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
Use of Premises
The Contractor shall comply with the regulations governing the operation of premises which are occupied and shall perform the contract in such a manner as not to interrupt or interfere with the conduct of Government business.
Conformity With Drawings and Specifications
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.
Barricades, Warning Signs, and Other Devices
The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.
Local Material Sources
(a) Designated Sources--Sources of local materials will be designated on the drawings. The Government assumes responsibility for the quality and quantity of material in the source. The Contractor shall determine the equipment and work required to produce the specified product.
The Contractor shall utilize all suitable material in the source. The designation of source will include the rights of the Contractor to use certain area(s) for plant site, stockpiles, and haul roads. Any Contractor royalty payment requirements will be stated below.
When materials are subject to weight measurement, the weight/volume relationship used for determination of designed quantities will be shown on the Drawings.
Should the designated source, due to causes beyond the control of the Contractor, contain insufficient suitable material, the Government will provide another source with an equitable adjustment in accordance with the Differing Site Conditions and Changes clauses.
(b) Contractor-Furnished Sources--When the material sources are not designated as provided above or the Contractor elects not to use designated sources, the Contractor shall be responsible for providing the specified product with no adjustment in contract price, unless weight/volume relationship differences between designated source material and Contractor-furnished source material result in financial disadvantage to the Government.
Quality testing shall be the responsibility of the Contractor. Test results shall be furnished to the Contracting Officer.
Samples, Tests, Cited Specifications
Reference made in the contract to specifications, standards, or test methods adopted by AASHTO, ASTM, GSA, or other recognized National technical associations, shall mean specifications, standards, or test methods (including interim or tentative issues) which are in effect on the date of the solicitation.
Weed-Free Equipment
In order to prevent the potential spread of noxious weeds into the project area, the Contractor shall be required to furnish the Contracting Officer with proof of weed-free equipment.
The following is considered proof of weed-free equipment:
The Contractor will be required to clean all construction equipment (equipment that operates off existing roads) prior to entry on the project area. This cleaning shall remove all dirt and plant parts and material that may carry noxious weed seeds into the project area. Only construction equipment inspected by the Contracting Officer will be allowed to operate within the project area. All subsequent move-ins of construction equipment shall be treated the same as the initial move-in.
Prior to initial move-in of all construction equipment, and all subsequent move-ins, the Contractor shall make equipment available for inspection at an agreed location.
Landscape Preservation
(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material, which falls outside of these limits, shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.
(b) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).
Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste water from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.
SPECIAL CONTRACT REQUIREMENTS
Traffic Control
NFSR #384 will generally remain open to public traffic throughout the project length. The road may only be closed to public traffic in accordance with the Forest Service Road Closure Restrictions.pdf in Appendix J.
The contractor must submit a Traffic Control Plan for approval that addresses the requirements of the Forest Service Road Closure Restrictions.pdf, the Traffic Control Plan for Edna Creek Culvert Replacement – Upper.pdf, and Sections 156 and 635 of the FP-14 Specifications and Forest Service Supplemental Specifications (FSSS).
Pumps and Drafting Water
All pumps used for drafting must be outfitted with a suction screen that has a maximum opening size of 3/32”;
follow the specific requirements for minimum screen dimensions in the Road 384 Project Special Requirements for AOP Sites.doc in Appendix J. Place portable pumps in secondary containment with enough capacity to hold the contents of the fuel tank. Draft water only at locations approved by the CO.
Erosion Control
Submit an Erosion Control and Sediment Control Plan which addresses the requirements of the Road 384 Projects Special Contract Requirements for AOP Sites.doc in Appendix J, the Contract Plans, and Section 157 of the FP-14 Specifications and Forest Service Supplemental Specifications (FSSS).
Special Contract Requirements for the Edna Creek and Beaver Creek Culvert Replacements
Site Preparation
• Install sediment barriers (e.g. silt fences, weed free straw bales, wattles, etc...) around excavated material stockpiles to minimize the potential for sediment delivery into stream channels and road ditches.
• Furnish a supply of surplus sediment barriers to be kept on hand, to respond to unanticipated events that have the potential to deliver sediment to stream channels. Minimum coverage length to supply for surplus barriers is 100 feet. i.e. 4 - 25 foot long straw wattles, or enough straw bales to cover 100 lineal feet when placed end to end.
• Obtain approval from C.O. for locations of staging areas, stockpile areas, fueling locations, and other locations where impacts might be anticipated.
Fish Avoidance
• Report the finding of a dead or injured bull trout/fish to the Forest Service immediately.
Dewatering
• Dewatered and completely bypass culvert sites prior to excavation.
• Stream diversion time is limited to a maximum of 14 days.
• Notify the Forest Service at least 72 hours in advance before diverting the stream.
• Dewater slowly to allow the Forest Service time to capture and move stranded fish and other aquatic organisms.
• Utilize 3/32” maximum opening size fish screens for pump suction lines in accordance with the following NMFS fish screen criteria:
Total Screen Area (ft2) Dia. in Inches for 1 Foot Tall Cylindrical Screen
Intake Rate (gpm)
Perforated Sheet Metal Wire Mesh Perforated
Sheet Metal Wire Mesh
500 8.1 5.4 31 20 400 6.5 4.4 25 17 350 5.7 3.8 22 14 300 4.9 3.3 19 13 200 3.2 2.2 12 8 150 2.4 1.6 10 6 100 1.6 1.1 6 5 50 0.8 0.5 4 3
• Do NOT excavate material from stream channels or floodplains to construct stream diversion dams.
• Construct the stream diversion around the project site using non-erodible material, such as a pipe or plastic-lined channel to accommodate peak flows that may be expected during construction, including potential storm events.
• Pump turbid water to a temporary storage/treatment site, or into upland areas, to allow it to filter through vegetation prior to reentering the stream channel.
• Place portable pumps in secondary containment with a capacity large enough to hold the contents of the fuel tank.
• Stockpile material excavated from the diversion channel at a designated stockpile area for use in rehabilitating the excavated channel. Install sediment barriers (e.g. silt fences, weed free straw bales, wattles, etc...) around excavated material stockpiles to minimize the potential for sediment delivery into stream channels and road ditches.
Construction and Earthmoving Activities
• Conduct excavation with minimal impact to the active stream channel. Store excavated material in designated stockpile areas.
• Cross streams with equipment only at dewatered areas, on temporary bridges, or at designated temporary crossings.
• Store equipment in approved staging areas when not in use. Cease all operations in the event of local precipitation events or high flows, except efforts to minimize storm damage or excessive erosion.
• Provide certified weed free erosion control materials in order to prevent the spread of noxious weeds.
Pollution Control Measures
• Follow State and Federal regulations regarding spills: e.g., report any spills resulting in a detectable sheen on water to the EPA National Response Center (1-800-424- 8802).
• Report any spills over 25 gallons to the IDEQ (1-800-632-800), and initiate cleanup within 24 hours of the spill.
• Clean all equipment of external oil, grease, dirt and mud, and repair all leaks prior to arriving at the project site. Make equipment available for inspection by the C.O. and obtain approval from the C.O.
before unloading at the site.
• Correct any leaks or accumulations of grease before entering streams or areas that drain directly to streams or wetlands.
• Fuel and service all equipment, including chainsaws and other hand power tools in an approved staging area.
• Keep a spill containment kit containing oil-absorbing floating booms, or other equipment such as pads and absorbent peanuts, capable of containing hazardous oil spills from the largest piece of equipment used on site. Keep the spill containment kit available on-site during all phases of construction and place in a location that facilitates an immediate response to potential petroleum leakage.
Flow Reintroduction
• Pre-wash the newly constructed stream channel surface using pumps and nozzles prior to the reintroduction of streamflow. Continue washing until the C.O. approves the start of the re-water process.
Collect the turbid water in a sump and pump it to a temporary storage/treatment site, or into upland areas, to allow it to filter through vegetation prior to reentering the stream channel.
• Re-water stream channels slowly to prevent loss of surface water downstream as construction site streambed absorbs water and to minimize a sudden increase in turbidity.
Incidental Payment Items
The intent of the contract is to provide for the complete construction of the project described in the contract.
Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.
Invoice Processing Platform (IPP)
The Forest Service is utilizing the Invoice Processing Platform (IPP) for the electronic submission and tracking of contracts/purchase orders, invoices, and payment information. IPP is a secure Government-wide, Web-based invoice processing service. Visit http://www.ipp.gov to learn more.
Upon award of a contract, Contractors must register at https://www.ipp.gov/vendors/enrollment-vendors.htm.
Contractors shall submit all invoices electronically via IPP. Paper copies of invoices will no longer be accepted.
Solicitation No.: 12026120R0004 http://www.ipp.gov/ https://www.ipp.gov/vendors/enrollment-vendors.htm
Prework Conference
Prior to commencement of work, the Contracting Officer will arrange a meeting with the Contractor to discuss the contract terms and work performance requirements. Also at this meeting such things as work progress schedule and fire prevention and suppression plans shall be developed and established in writing.
Fire Control
(a) Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.
(b) Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or the Contractor’s employees, the Contractor when requested by the Contracting Officer shall place the employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.
Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area.
An equitable adjustment in contract time may be made for this period.
(c) Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to the Contractor’s operation under the contract.
(1) Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.
(2) Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:
One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.
One - shovel, round point #0 lady or equal.
One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.
One - water container (at least 1-gallon capacity), not required with stationary equipment.
(3) Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards;
(b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.
(4) Powersaws. For each powersaw used in connection with this contract, the following will be provided:
One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.
One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.
Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.
(5) Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.
(6) Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.
(7) Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site where all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.
(8) Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires.
Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.
(9) Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.
All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.
(10) Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.
(11) Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will usually be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.
When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:
(i) All high fire risk operations could be terminated at 1300 local time.
(ii) All burning could be stopped, including debris burning fires.
(iii) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.
(12) Pump and Trailer. The Contractor shall provide at a location satisfactory to the Contracting Officer, a serviceable truck or trailer, equipped with a fire fighting tanker unit to be kept ready for instant use for suppressing forest fires. The unit shall consist of a tank of not less than 100-gallon capacity upon which shall be mounted a live hose reel or live hose basket with 250 feet of at least ¾-inch I.D. heavy-duty rubber hose; a portable or power takeoff pump with discharge capacity of at least 10 gallons per minute at 150 P.S.I. pressure.
Gear type pumps shall be provided with a bypass or pressure relief valve so that the hose nozzle may be shut while the pump is operating. Each tanker unit shall have a hose nozzle of the shut-off type, adjustable for straight stream, spray or fog, at least 12 feet of 1-inch suction hose with an intake screen, and additional 250 feet of 3/4 – inch heavy-duty rubber hose or 1-inch cotton jacket rubber-lined or linen hose to be carried on the unit for use as needed. Tools, adapters, accessories and fuel necessary to operate the pump and truck or trailer shall be provided.
If a trailer is used, a serviceable vehicle with proper trailer tow hitch shall be located at a point satisfactory to the Contracting Officer. Where water is available, a supply sufficient for rapidly filling the water tank shall be provided at one or more accessible points along or adjacent to the main truck roads.
(13) Burning. Before starting any open burning, the Contractor shall comply with the following:
(i) Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.
(ii) Obtain a burning permit from the District Ranger.
(iii) Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.
(iv) Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion.
Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges.
Piles shall be patrolled during off-work hours to avoid wildfires.
(v) Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.
(vi) Under certain atmospheric conditions, smoke accumulations may become excessive and in these cases, the Regional Forester may, at his/her discretion, prohibit all open burning for definite periods within specific areas of the National Forest.
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEPT 2006) 52.203-7 Anti-Kickback Procedures (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of
Whistleblower Rights (APR 2014) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements. (JAN 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (OCT 2018) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements. (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (JUL 2016) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by
Kaspersky Lab and Other Covered Entities (Jul 2018) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters. (OCT 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records - Negotiation (OCT 2010) 52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.219-8 Utilization of Small Business Concerns (OCT 2018) 52.219-9 Small Business Subcontracting Plan (Aug 2018) 52.219-14 Limitations on Subcontracting (Jan 2017) 52.219-28 Post-Award Small Business Program Rerepresentation (JUL 2013) 52.222-3 Convict Labor (JUNE 2003) 52.222-4 Contract Work Hours and Safety Standards--Overtime Compensation (MAY 2018) 52.222-6 Construction Wage Rate Requirements (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (AUG 2018) 52.222-9 Apprentices and Trainees (JULY 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination--Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (SEPT 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015)
52.222-37 Employment Reports on Veterans (FEB 2016) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (MAR 2015) 52.222-54 Employment Eligibility Verification.(OCT 2015) 52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2015) 52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2017) 52.223-3 Hazardous Material Identification and Material Safety Data (JAN 1997) Alternate I (JULY 1995) 52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) 52.225-13 Restrictions on Certain Foreign Purchases (JUNE 2008) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance -- Work on a Government Installation (Jan 1997) 52.228-11 Pledges of Assets (AUG 2018) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds-Construction (OCT 2010) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer—System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) 52.233-1 Disputes (MAY 2014) Alternate I (DEC 1991) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-1 Performance of Work by the Contractor (Apr 1984) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
(APR 1984)
52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13…