About this file

This file consists of Standard Specifications for Construction adopted by the City of Eugene, Oregon, effective March 12, 2026, incorporating the 2024 Oregon Standard Specifications for Construction and the City of Eugene Standard Drawings, along with Amendments #1 through #4. The specifications establish the technical requirements, standards, and procedures governing construction work performed for the City of Eugene. Key specifications address supplemental requirements including reference websites for quality assurance programs, traffic standards, and qualified products lists; updated abbreviations and definitions related to pedestrian accessibility; contractor responsibilities under the Occupational Accident Prevention Standards; Build America Buy America Act compliance requiring domestic sourcing of all construction materials and manufactured products permanently incorporated into projects obligated on or after October 1, 2025; workers' compensation and employer's liability insurance requirements; and progress payment procedures with multiple retainage options available to contractors.

The specifications detail strict compliance requirements for the Build America Buy America Act, including provisions for a public interest waiver applicable to non-compliant products not exceeding the lesser of $1,000,000 or 5 percent of total applicable project costs, or for projects with federal financial assistance below $500,000. Contractors must provide Certificates of Materials Origin for all applicable construction materials and manufactured products before incorporation into projects and retain manufacturers' certificates for three years after final payment. Retainage procedures offer contractors multiple options including cash retainage held by the Agency, interest-bearing accounts under ORS 279C.560(5), Surety bonds meeting requirements of ORS 701.435(4) and Oregon House Bill 4006 (2024), or approved bonds, securities, and other instruments in lieu of cash retainage. These specifications apply to the City of Eugene's ITB 20272017 Rental Car Sidewalk project with sealed bids due October 6, 2026, at 2:30 PM.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Standard Specifications – Updated 7/2026 Page 1

STANDARD SPECIFICATIONS AND STANDARD DRAWINGS

As of March 12, 2026 the 2024 Oregon Standard Specifications for Construction (Oregon Specifications) and the City of Eugene Standard Drawings, both as revised by Amendments #1, #2, #3 and #4, have been adopted as the Standard Specifications and Standard Drawings for the City of Eugene in accordance with City Code section 7.085. Amendments #1, #2, #3 and #4 are hereby made a part of the Standard Specifications and Standard Drawings of the City of Eugene as fully and completely as if it were set forth therein. The Standard Specifications, Standard Drawings and all Amendments may be examined on-line at https://www.eugene-or.gov/444.

SUPPLEMENTAL SPECIFICATIONS

The section, subsection and drawing numbers of the Supplemental Specifications correlate to the section and subsection numbers of the adopted Standard Specifications, which consist of the 2024 Oregon Standard Specifications and the General Conditions for Construction for the City of Eugene, and Standard Drawings.

00110.05(e) Reference to Websites

(ADD)

• American Traffic Safety Services Association (ATSSA) www.atssa.com

• City of Eugene Quality Assurance Program https://www.eugene-or.gov/444/Standard-Specifications-for-Construction

• City of Eugene Field Tested Materials Assurance Guide (FTMAG)

• City of Eugene Purchasing and City of Eugene Public Contracting Rules https://www.eugene-or.gov/108/Purchasing

• City of Eugene Standard Specifications for Construction

• City of Eugene Traffic Sign Manual https://www.eugene-or.gov/183/Traffic-Sign-Manual

• Equipment Watch https://equipmentwatch.com/

• ODOT Construction Section www.oregon.gov/odot/construction/pages/index.aspx

• ODOT Construction Section - Qualified Products List (QPL) www.oregon.gov/ODOT/Construction/Pages/Qualified-Products.aspx

• ODOT Estimating www.oregon.gov/ODOT/Business/Pages/Steel.aspx

• ODOT Traffic Control Plans Unit www.oregon.gov/ODOT/Engineering/Pages/Work-Zone.aspx

Standard Specifications – Updated 7/2026 Page 2

• ODOT Traffic Standards www.oregon.gov/ODOT/Engineering/Pages/Signals.aspx

• OregonBuys https://oregonbuys.gov/bso

• Oregon Legislative Counsel www.oregonlegislature.gov/lc

• Oregon Secretary of State: State Archives https://sos.oregon.gov/archives/Pages/default.aspx

00110.10 Abbreviations

(ADD) PCD – Pedestrian Channelizing Device

00110.20 Definitions

(ADD) Pedestrian Accessible Route - An area for the use of pedestrians to navigate along sidewalks, driveways, curb ramps, crossings, and pedestrian facilities.

(ADD) Pedestrian Channelizing Device - Devices used for channelizing pedestrians along a temporary pedestrian accessible route.

00150.50 (c) Contractor’s Responsibilities

(REVISE) In the tenth bullet change OAR 952-001-0090(6) to OAR 952-001-0090(7)

00160.20 (d) Build America Buy America Act Requirements – REPLACE this subsection, except for the subsection number and title, with the following:

(ADD) If federal highway funds are involved on the Project, the Contractor shall comply with the Build America Buy America Act and implementing regulations (Infrastructure Investment and Jobs Act (“IIJA”), Pub. L. No. 117-58, which includes the Build America, Buy America Act (“the Act”). Pub. L. No. 117-58, Sections 70901-70941).

The Build America Buy America Act requirements apply to construction materials and manufactured products permanently incorporated in the Project. All construction materials and manufactured products permanently incorporated in the Project must be produced in the United States.

Construction materials include an article, Material, or supply that is or consists primarily of only one of the following, with the standard for the material to be considered “produced in the United States’’:

• Non-ferrous metals - All manufacturing processes, from initial smelting or melting through final shaping, coating, and assembly, occurred in the United States.

• Plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables) - All manufacturing processes, from initial combination of constituent plastic or polymer-based inputs, or, where applicable, constituent composite materials, until the item is in its final form, occurred in the United States.

• Glass (including optic glass) - All manufacturing processes, from initial

Standard Specifications – Updated 7/2026 Page 3 batching and melting of raw materials through annealing, cooling, and cutting occurred in the Unites States.

• Fiber optic cable (including drop cable) - All manufacturing processes, from the initial ribboning (if applicable), through buffering, fiber stranding and jacketing, occurred in the United States. All manufacturing processes also include the standards for glass and optical fiber, but not for non-ferrous metals, plastic and polymer-based products, or any others.

• Optical fiber - All manufacturing processes, from the initial preform fabrication stage through the completion of the draw, occurred in the United States.

• Lumber - All manufacturing processes, from initial debarking through treatment and planing, occurred in the United States.

• Drywall - All manufacturing processes, from initial blending of mined or synthetic gypsum plaster and additives through cutting and drying of sandwiched panels, occurred in the United States.

• Engineered wood - All manufacturing processes from the initial combination of constituent materials until the wood product is in its final form, occurred in the United States.

The classification of an article, material, or supply as construction material is based on its status at the time it is brought to the work site for incorporation in the Project. In general, the work site is the location of the Project at which the construction materials will be incorporated.

FHWA issued a final rule on January 14, 2025 amending FHWA's Buy America regulation to terminate FHWA's general waiver for manufactured products and establish Buy America requirements for manufactured products with respect to Federal-aid highway projects.https://www.federalregister.gov/documents/2025/01/14/2024- 31350/buy-americarequirements-for-manufactured-products

Manufactured products assembled outside the Project Site are also subject to the Build America Buy America requirements. Manufactured products means articles, materials, or supplies that have been:

o Processed into a specific form and shape; or o Combined with other articles, materials, or supplies to create a product with different properties than the individual articles, materials, or supplies.

For manufactured products, the final assembly of the product shall occur within the

United States for projects obligated on or after October 1, 2025. For projects obligated after October 1, 2026, the cost of the components of the product that are mined, produced or manufactured in the United States shall be more than 55 percent of the total cost of all components of the product.

The USDOT issued a Public Interest Waiver for De Minimis Costs and Small Grants.

The final waiver can be viewed here:

https://www.federalregister.gov/documents/2023/08/16/2023-17602/waiver-of-buy-americarequirements-for-de-minimis-costs-and-small-grants and this waiver applies to Materials covered by the Build America Buy America Act.

The public interest waiver is for manufactured products and construction materials for which:

o The total value of the non-compliant products (foreign or unknown origin) is no more than the lesser of $1,000,000 or 5% of total applicable costs for the project*; or o The total amount of Federal financial assistance applied to the project, Standard Specifications – Updated 7/2026 Page 4 through awards or subawards, is below $500,000.

*The “total value of the non-compliant products” includes construction materials and manufactured products only. The “total applicable costs” includes construction materials, iron and steel, and manufactured products. The value of materials are the actual cost of the materials, not the anticipated cost of materials. Furthermore, this bullet does not apply to iron and steel subject to the requirements of 23 U.S.C. 313. The de minimis threshold in 23 CFR 635.410(b)(4) continues to apply for steel and iron. (See 00160.20(a).)

Strict compliance with the Build America, Buy America domestic preferences is required, except to the extent the above public interest waiver applies. The Contractor shall not incorporate construction materials and manufactured products in excess of this amount into the Project. All foreign origin construction materials and manufactured products incorporated in the Project in excess of the amount indicated above shall be removed and replaced with domestic construction materials at the Contractor's expense.

The Contractor shall provide the Engineer with a Certificate of Materials Origin, on a form furnished by the Engineer, before incorporating any applicable construction materials and manufactured products into the Project. Unless a Certificate of Materials Origin has been provided to the Engineer, the products and Materials shall be considered of foreign origin.

The Contractor shall retain manufacturers' certificates verifying the origin of all applicable construction materials and manufactured products for 3 years after the date of final payment for the Project, and shall furnish copies to the Engineer upon request.

Iron and steel Materials and manufactured products that are predominately iron or steel are subject to 00160.20(a).

The Contractor shall include this provision in all subcontracts.

00170.61 Industrial Accident Protection:

(REPLACE) (a) Workers’ Compensation with

00170.61(a) Workers’ Compensation and Employer’s Liability - The Contractor shall provide workers' compensation and employer’s liability coverage for on-the-job injuries as required by 00170.70(e).

00195.50 Progress Payment and Retained Amounts

(REPLACE) (c) Forms of Retainage with

(c) Forms of Retainage - If the Agency withholds retainage, forms of acceptable retainage are specified below in Subsections (1) through (3). Unless the Contractor requests and the Agency accepts a form of retainage under Subsections (1)(b), (2) or (3), the Agency will use the "Cash Option " in (1)(a) of this Subsection. If the Agency incurs additional costs as a result of the Contractor's election to use a form of retainage other than Cash, Option (1)(a), the Agency may recover such costs from the Contractor by a reduction of the final payment.

(1) Cash Options - Retainage will be deducted from progress payments and held by the Agency using one of the following options until final payment is made

Standard Specifications – Updated 7/2026 Page 5 according to 00195.90, unless otherwise specified in the Contract.

(a) Except as otherwise provided, the Agency will hold the cash retainage withheld in a bank or other financial institution deemed appropriate by the Agency. Amounts retained will be included in the final payment made according to 00195.90, unless otherwise specified in the Contract.

(b) If the Contractor elects, the Agency will deposit the cash retainage withheld in an interest-bearing account, in a bank or other financial institution for the benefit of the Agency, as required by ORS 279C.560(5). Interest earned on the account shall accrue to the Contractor. Amounts retained and interest earned will be included in the final payment made according to 00195.90, unless otherwise specified in the Contract.

(2) Alternate A (Retainage Surety Bond) - The Contractor may submit a Surety bond in lieu of all or a portion of the retainage required under the Contract. The Agency will accept this Surety bond unless the Agency first finds in writing good cause for rejection based on unique project circumstances in accordance with ORS 279C.560(1)(c).

The Surety bond must be in substantially the form specified in ORS 701.435 (4) (Oregon House Bill 4006, 2024), and executed by a Surety bonding company that is authorized to transact Surety business in the State of Oregon and may not be a Surety obligation of an individual. The Surety bond and any proceeds of the Surety bond must be made subject to all claims and liens and in the same manner and priority specified for retainage under ORS 279C.550 to 279C.570 and ORS 279C.600 to 279C.625. Agency will reduce the cash retainage held by an amount equal to the value of the Surety bond and pay the amount of the reduction to Contractor according to ORS 279C.570. Any retainage withheld on Work performed by a Subcontractor will be released to the Contractor according to 00195.50(d).

When the Agency accepts a Surety bond in lieu of retainage from the Contractor, the Contractor shall accept Surety bonds from Subcontractors or Suppliers from which the Contractor has withheld retainage. At any time before final payment a Subcontractor may submit a Surety bond to the Contractor and request that the Contractor submit a Surety bond as described above for the portion of the Contractor’s retainage that pertains to the Subcontractor. The Surety bond the Subcontractor provides to the Contractor must meet the Agency requirements specified in the paragraph above. When a Contractor at a Subcontractor’s request obtains and submits a Surety bond under this subsection, the Contractor may withhold from payments to the Subcontractor an amount equivalent to the portion of the Contractor’s Surety bond premium for which the Subcontractor is responsible in accordance with ORS 279C.560 (Oregon House Bill 4006, 2024).

Within 30 Days after a Subcontractor’s request the Contractor shall provide a Surety bond as described above, and the Agency will accept the Surety bond unless:

• the Agency finds in writing good cause for rejection based on unique project circumstances in accordance with ORS 279C.560;

• a Surety bond is not commercially available;

• the Subcontractor refuses to pay to the Contractor the Subcontractor’s portion of the Surety bond premium; or

Standard Specifications – Updated 7/2026 Page 6

• the Subcontractor refuses to provide the Contractor with a Surety bond that meets the requirements of ORS 279C.560(1)(b).

Notwithstanding 00195.50(d), within 30 Days of receiving a Surety bond from Contractor at a Subcontractor’s or Supplier’s request, Agency will release to the Contractor the amount held as retainage that is equivalent to the amount the Contractor submitted as a Surety bond. Contractor shall, within 30 Days after receiving a Surety bond from a Subcontractor or Supplier, release to the Subcontractor or Supplier the amount the Contractor holds as retainage that is equivalent to the amount of the Surety bond submitted, in accordance with

ORS 279C.560(8).

(3) Alternate B (Bonds, Securities, and Other Instruments) - Contractor may deposit bonds, securities or other instruments with the Agency or in a bank or other financial institution, to be held by Agency instead of cash retainage for the benefit of the Agency, which the Agency will accept unless the Agency first finds in writing good cause for rejection based on unique project circumstances, in accordance with ORS 279C.560(1)(c).

If the Contractor deposits bonds, securities or other instruments, and Agency does not reject the bonds, securities or other instruments as permitted by ORS 279C.560(1)(c), the Agency will reduce the cash retainage by an amount equal to the value of the bonds, securities and other instruments. Interest or earnings on the bonds, securities and other instruments accrue to the Contractor.

Bonds, securities and other instruments deposited instead of cash retainage shall be of a character approved by the Director of the Oregon Department of Administrative Services, including, but not limited to:

• Bills, certificates, notes or bonds of the United States;

• Other obligations of the United States or agencies of the United States;

• Obligations of a corporation wholly owned by the federal government;

• Indebtedness of the Federal National Mortgage Association;

• General obligation bonds of the State of Oregon or a political subdivision of the

State of Oregon;

• Irrevocable letters of credit issued by an insured institution, as defined in ORS

706.008.

By: _________________________________ Doug Singer, P.E.

Interim City Engineer

Doug Singer (Jul 27, 2026 12:07:07 PDT) https://adobefreeuserschannel.na2.documents.adobe.com/verifier?tx=CBJCHBCAABAA_7cgQP55vQWpQ5Q8VEDQ8JCn0j-NBGCu

2026-07-27T19:07:09+0000
Certified by Adobe Acrobat Sign

File details come from the government source that posted it. Updated .