A_Statement of Work for Subcontract 7889840 (10.12.26).pdf

PDF 775 KB Posted

Attached to
Fire Alarm Control Panel Replacement Project (FACPR)
Solicitation number
2026-PTG-FACPR
Issued by

About this file

This is a Statement of Work for a Design-Build contract to replace fire alarm control panels at Lawrence Berkeley National Laboratory. The project (No. 109856) covers four buildings (2, 26, 33, and 76) and requires the subcontractor to serve as Engineer of Record and Responsible Design Professional, providing complete design, engineering, procurement, installation, and commissioning services. The existing Siemens System 3 Fire Alarm Control Panels, designed in the 1960s and deployed in the early 1990s, will be replaced with Siemens Desigo Systems hardware. Building-specific strategies include installing new panels in unused MXL cabinets in Buildings 2 and 26, performing interior hardware replacement in Building 33's existing MXL enclosure, and replacing the entire panel assembly in Building 76. Each approach requires new conduit pathways (ranging from three to five 2-inch rigid metal conduits) with specified conduit fill parameters and re-termination of existing field wiring.

The design schedule requires submittal of 50%, 75%, 95%, and 100% Final Design packages at 8, 12, 16, and 19 weeks respectively after notice to proceed, with LBNL allowing two weeks for review of each submittal. The subcontractor must comply with LBNL Construction Details and Design Requirements and Master Specifications, including comprehensive architectural details, structural seismic anchoring calculations per California Building Code, mechanical heat dissipation assessments, and electrical designs incorporating battery sizing (minimum 24 hours standby plus 15 minutes full alarm), voltage drop calculations, and NFPA 72 (2025 edition) compliance. All fire protection engineering drawings and specifications require formal review and approval from a California-licensed Professional Engineer in Fire Protection Engineering. Construction requires coordination of work across multiple active institutional facilities with specific notification requirements: two weeks advance notice for weekend work, one month for holiday work, and six months prior written notification to building occupants before scheduled panel cut-overs. The project involves hazardous materials management (asbestos and lead), requires a part-time onsite health and safety representative with minimum two years experience and 30-hour OSHA training, and mandates 10 business days for safety submittal reviews. LBNL will provide disposal services for non-asbestos and asbestos hazardous waste and testing/inspection services; the subcontractor is responsible for removing and disposing of decommissioned internal panel cards and legacy backup battery packs.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Project Name Fire Control Panel Replacement

Project Number 109856

Acquisition Type Design Build

Date 10/12/2026

Prepared by: Reviewed by:

Carlos Guerrero, Project Manager Projects and Infrastructure Modernization Division

Jenny Ledesma, Project Director Projects and Infrastructure Modernization Division

Statement of Work (SOW) for Design Build PIMD-TEMP-040 Rev.7: 02/06/2026 Page 1

Doc ID: 35cdc1bcca665aa9c150e81c9c5cb37aa99391ed

REVISION HISTORY*

(Revision history for this document did not start being documented until revision no. 6)

Rev No. Rev Date Sections Brief Descriptions of Revisions

6 09/23/2025 Sec. 2.2, 4.4, 4.10, 4.12

Sec 2.2: Weekend/Holiday Notifications Sec 4.4: Testing and Inspection turnaround requirements Sec 4.10: Off-site Soil Disposition Sec 4.12: Safety Submittals review turnaround requirements

7 02/06/2026 Sec. 3.2, 3.4.3, 3.4.7, 4.10

Sec 3.2: Performance Requirements Sec. 3.4.3: Minimum Required Div 1 Specs and Minimum Technical Specs Sec 3.4.7: Design Schedule Sec 4.10: Off-site Soil Disposition

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 2

TABLE OF CONTENTS

1.0 Project Scope 5

1.1. Background 5

1.2. Project Objectives 5

1.3. Project Description 5

1.4. Applicable Codes and Standards 6

1.5. Alternates and Options 6

2.0 General Requirements 6

2.1. Definitions 6

2.2. Coordination of Work 8

2.3. Final Acceptance 8

3.0 Design 8

3.1. Existing Site Conditions 8

3.2. Design Requirements 8

3.3. Review Meetings 12

3.4. Design Deliverables 12

3.5. Construction Support 15

3.6. Commissioning 15

4.0 Construction 16

4.1. Staging/ Parking/ Traffic Control 16

4.2. Utility Deactivation 16

4.3. Government Furnished Equipment (GFE) 16

4.4. Services provided by LBNL 16

4.5. U.S. Government and/or University Property-Materials to be Removed 17

4.6. Environmental Protection 18

4.7. Hazardous Materials and Restricted Items 18

4.8. Construction Noise and Vibration Control 18

4.9. Building Characterization 19

4.10. Off-site Soil Disposition Quantities and Requirements 19

4.11. Waste Management 20

4.12. Safety 20

5.0 Reference Documents 21

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 3

5.1. Construction Details and Design Requirements (Version 0 – 9.30.24) 21

5.2. Applicable Technical Specifications 21

5.3. Design Deliverables Matrix (Version 2.0 – 06.30.26) 21

5.4. Fire Alarm Control Panel Replacement Conceptual Design Report 21

5.5. Fire Alarm As-Builts for Buildings 2, 26, 33, and 76 21

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 4

1.0 Project Scope

At the completion of the 95% Final Design documents, a revised proposal capturing changes to the scope via the design process will be allowed. If the revised proposal is validated with the 95% Final Design documents’ independent cost estimate, a modification accounting for the updated scope or differing site conditions will be awarded.

In case of a conflict between this statement of work (SOW) and the LBNL Permit Final Design package (drawings and specifications) for the project, the design package, which is a Subcontractor deliverable, takes precedence.

1.1. Background

Lawrence Berkeley National Laboratory (also referred to here as LBNL, or Berkeley Lab, or Laboratory) is a federally funded research and development center that is operated and managed by the Regents of the University of California (UC) (also referred to as “the University” or “UC”) for the United States Department of Energy (DOE) under a prime contract between UC and DOE. LBNL conducts unclassified research to carry out its mission of reaching a deeper understanding of our world and delivering science-based solutions to problems of national significance.

A 2016 FireSAFE report highlighted the approaching obsolescence of the fire and life safety infrastructure across the LBNL campus. The majority of the existing panels are Siemens System 3 Fire Alarm Control Panels (FACPs) designed in the 1960s and deployed across LBNL in the early 1990s. Support and original equipment manufacturer replacement parts for these panels were discontinued in the mid-2010s. To restore reliable operational safety and lay the foundation for a future site-wide transition to an intelligent, addressable field device framework, LBNL is executing a site-wide FACP replacement initiative. A Fire Alarm Control Panel Replacement Conceptual Design Report was prepared by Enercon in August 2024.

1.2. Project Objectives

The objective of this project is to replace the fire alarm control panels in buildings 2, 26, 33, and

76. The StarLink communication cabinets are to be relocated to follow panels as needed;

however, the fire alarm annunciation and notification devices and StarLink cabinets will not be replaced as a part of this project; they are to be addressed in a future project.

1.3. Project Description

The fire alarm replacements are anticipated to be executed across the Laboratory in phases over multiple fiscal years based on funding availability. This scope of work describes the buildings:

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 5

● Building 2

● Building 26

● Building 33

● Building 76

Under this turnkey contract, the Design-Build Subcontractor shall provide all professional design, engineering, procurement, installation, changeover, and commissioning services necessary to replace the fire alarm control panels and auxiliary battery systems. To ensure complete compatibility with the broad mix of existing peripheral devices, loops, and conventional circuits, the Siemens Desigo System has been specified as the campus standard hardware platform for this upgrade. The specific technical scope requirements tailored to each structure are detailed below:

Building 2:

● Existing Infrastructure: Three (3) existing legacy System 3 panels (FAP-01-002, FAP-01A-002, and FAP-01B-002) are recessed into the building corridor wall with concealed wiring. An unused, surface-mounted Siemens MXL cabinet is located nearby in Room 147. The building features approximately 120 functional input/output modules.

● Replacement Strategy ("Nearby MXL"): The Subcontractor shall install the new Siemens

Desigo FACP components directly inside the existing, unused MXL cabinet in Room 147.

The existing, recessed System 3 panel enclosures shall be gutted of their legacy internal cards and re-engineered to function cleanly as localized terminal junction boxes.

● Conduit & Wiring Pathways: The Subcontractor shall procure and install a minimum of five (5) new 2" Rigid Metal Conduits (RMC) with a maximum signal conduit fill parameter of 40% to safely extend existing signal circuits from the gutted System 3 enclosures out to the new FACP location. New signal conductors shall be pulled, labeled, and prepared ahead of time to facilitate an efficient cutover window.

Building 26:

● Existing Infrastructure: One (1) operational System 3 panel and one (1) unused MXL cabinet are Unistrut-mounted side by side on a concrete block wall within Room 021.

The structure contains approximately 22 active conventional input/output circuits.

● Replacement Strategy ("Nearby MXL"): The Subcontractor shall populate the adjacent, unused MXL cabinet structure to house the new Desigo FACP hardware. The vacant System 3 cabinet shall be stripped of its old interior components and fitted with high-density terminal strips to operate as a central junction box.

● Conduit & Wiring Pathways: The Subcontractor shall install three (3) new 2" RMC pathways (capped at 30% maximum expected conduit fill) between the old cabinet and

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 6 the new enclosure to house the extended field signaling lines.

Building 33:

● Existing Infrastructure: One (1) legacy, addressable Siemens MXL panel is actively in service within Room 103A, mounted securely to a Unistrut frame using spring-nut hardware. The system governs approximately 23 input/output circuits.

● Replacement Strategy ("Reuse MXL"): Because the existing MXL enclosure is fundamentally correctly positioned and structurally sound, the Subcontractor shall perform a turnkey interior hardware replacement. The old MXL interior chassis cards shall be completely demolished during a scheduled maintenance outage and replaced with a factory-supported Desigo inner-system upgrade/conversion kit (Siemens

FHA-MIQKIT).

● Conduit & Wiring Pathways: The existing structural signal conduits, pathways, and field wiring conductors shall be safely retained and re-terminated directly onto the new Desigo system cards inside the existing panel shell.

Building 76:

● Existing Infrastructure: One (1) operational legacy System 3 panel (FAP-01-076) protecting 44 conventional input/output zones is currently surface-mounted to a plywood backing wall in Room 123A.

● Replacement Strategy ("Replace Panel"): The Subcontractor shall completely demolish and remove the existing legacy System 3 cabinet assembly from the wall during a coordinated facility outage. A brand-new, modern Desigo enclosure and matching control panel configuration shall be structurally anchored in its exact physical footprint.

● Conduit & Wiring Pathways: The Subcontractor shall preserve, clean, and directly reuse the existing structural signal conduit entries and field wiring loops, re-terminating them systematically onto the new FACP interface modules.

Both design and construction services are part of this project. Work includes, but is not limited to: professional engineering services, general demolition and construction, electrical infrastructure work, control and communications networking, auxiliary utility safety systems integration, and the necessary removal.

The above is intended to summarize the general scope of the work, and it should not be assumed to be comprehensive.

1.4. Applicable Codes and Standards

The subcontractor shall complete construction in compliance with all applicable local and national codes as specified in the final LBNL permit drawings.

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 7

1.5. Alternates and Options

No alternates or options are included under this Subcontract.

2.0 General Requirements

2.1. Definitions

A. Architect/Engineer: The term "Architect/Engineer" is the person or firm designated as the Responsible Design Professional (RDP).

B. Having Jurisdiction (AHJ): The LBNL Fire Marshal, LBNL Building Code Official (BCO), or designated Environment, Health & Safety (EHS) officer.

C. Contractor Furnished Contractor Installed (CFCI): Materials and systems procured and fully implemented by the Subcontractor.

D. FACP / FACU: Fire Alarm Control Panel / Fire Alarm Control Unit.

E. Online Work: Turnkey installation, pathway routing, tracing, and panel assembly tasks performed by the Subcontractor ahead of the live system cutover, which remain invisible to facility occupants and keep the building fully protected.

F. Outage Work: Project phases executed during a tightly coordinated, scheduled building maintenance shutdown where the existing FACP is taken offline and temporary life-safety compensatory measures are put into active service.

Acronyms List:

The following list is to aid in review of SOW and may not be all inclusive

ABA / ADA Architectural Barriers Act / Americans with Disabilities Act

ACM Asbestos Containing Materials

BAA Buy American Act

BAAQMD Bay Area Air Quality Management District

BMP Best Management Practices

CCTV Closed Circuit Television

CFCI Contractor Furnished Contractor Installed

CPM Critical Path Method (schedule)

DOE U.S. Department of Energy

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 8

DOT U.S. Department of Transportation

DTSC California Department of Toxic Substances Control

EH&S LBNL Environment, Health & Safety Department

EMCS

Energy Management Control System (Building automation systems for HVAC and lighting)

EPA U.S. Department of Environmental Protection

ESG LBNL Environmental Services

EVMS Earned Value Management System

FSS Final Status Survey

GFI Government Furnished Information

HAZWOPER Hazardous Waste Operations and Emergency Response

HSA Historical Site Assessment

HWHF Hazardous Waste Handling Facility (Building 85)

IOR Inspector of Record

IWCP Integrated Work Control Program

JHA Job Hazard Analysis

JSA Job Safety Analysis

LBNL Lawrence Berkeley National Laboratory

LBP Lead Based Paint

LLW Low-Level (Radiological) Waste

LOTO Lock Out/Tag Out

OAC Owner, Architect, and Contractor

OFCI Owner furnished Contractor Installed

PCB Polychlorinated Biphenyl

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 9

PMP Project Management Plan

RDP Responsible Design Professional

SCADA Supervisory Control and Data Acquisition

SSSP Site Specific Safety Plan

UPS Uninterruptible Power Supply

2.2. Coordination of Work

The Subcontractor shall lead the coordination and scheduling of all work, including all lower-tier subcontractors, to ensure the proper execution of the project. All work must be performed in accordance with Section 010000, Coordination of Work.

Access and Scheduling Notifications: The Subcontractor must manage site access and working hours to minimize impact on Laboratory operations:

● Weekend Work: A minimum of two (2) weeks advance notification is required for weekend work requests.

● Holiday Work: A minimum of one (1) month advance notification is required for holiday work requests.

● Winter Closure: LBNL is closed between Christmas and New Year's Day.

Interface with Others: The Subcontractor shall coordinate work with University personnel and other contractors operating in the area, making reasonable schedule adjustments as required.

Construction Limits: All operations, including material layout and personnel parking, must be confined to the immediate areas designated in the engineering drawings.

Maintenance Clearances: The Subcontractor must ensure that all new control unit equipment installations maintain absolute clear maintenance envelopes as required by the National Electrical Code (NEC), NFPA standards, and manufacturer recommendations.

Occupant Outage Advance Notice: The Subcontractor shall coordinate the baseline construction schedule with LBNL management to ensure building occupants receive written notification at least six (6) months prior to any scheduled panel cut-overs, commissioning, or system outages.

2.3. Final Acceptance

Subcontractor must comply with Final Acceptance per section 1.9, Division 010000 General

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 10

Requirements.

3.0 Design

The Subcontractor shall assume the role of Engineer of Record (EOR) and RDP for the project and provide updated PE stamped drawings. The updated construction documents must be submitted for review and approval by the LBNL Code Compliance Office (CCO) and relevant Authorities Having Jurisdiction (AHJs). The Subcontractor shall perform all design activities in strict accordance with LBNL Construction Details and Design Requirements (CDDR) and current LBNL Master Specifications

Subcontractor to perform design activities in accordance with LBNL Construction Details and Design Requirements.

3.1. Existing Site Conditions

The project site consists of separate, active institutional research and laboratory facilities across Buildings 2, 26, 33, and 76. Prior to the generation of the 75% Updated Final Design package, the Subcontractor shall conduct rigorous field walkdowns and verify configuration control against legacy records.

● Configuration Discrepancies: Historical campus records dating back to 1993 reveal that various modifications, device change-outs, and zone re-allocations may have occurred over the panels' 30-year operational history without systematic drawing updates. The Subcontractor shall field-verify existing circuit loads, trace field routing, and update as-built documents to re-establish rigorous configuration control before procurement.

● Interfacing Systems: The existing panels interface directly with localized emergency control functions, including Ventilation / Air Handling Unit (AHU) safety shutdowns, Variable Air Volume (VAV) controls, and automatic door-holder releases. The Subcontractor shall examine these interlocking control loops to ensure their functional preservation.

LBNL-provided records represent general baseline conditions. This data is included for informational purposes only, and while considered representative, it is not guaranteed to be comprehensive. The Subcontractor is responsible for verifying all physical site dimensions and circuit configurations.

Any LBNL provided data is included for the Subcontractor’s information only, and while it is considered to represent conditions existing on the project site anticipated at this time, it is not guaranteed to fully represent all conditions.

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 11

3.2. Design Requirements

The Subcontractor’s RDP is the responsible design professional with the design build team.

The Subcontractor’s RDP must comply with the Administrative and Design Requirements as detailed in Volume 1 of the CDDR (see hyperlink above).

Architectural

Provide comprehensive architectural details for wall framing, backing plates, cosmetic drywall replacement, fire-rated wall penetration draft-stopping, patching and painting required when existing panels are removed or converted. New plywood backing panels must be specified where surface-mounting new enclosures.

Any exemption to the CDDR requirements shall be approved by the LBNL Architect. The request for the exemption must be submitted prior to the submittal of Design to LBNL.

Structural

Provide seismic anchoring details, structural calculation sets, and lateral force calculations for all new FACP enclosures, auxiliary transponder cabinets, and secondary battery boxes. Design must comply with California Building Code (CBC) lateral force parameters

Structural work shall include all seismic and bracing design for mechanical & electrical equipment, piping, conduits and cable trays and other non-structural components designed or purchased by other engineering disciplines.

Any exemption to the CDDR requirements shall be approved by the LBNL Structural Engineer.

The request for the exemption must be submitted prior to the submittal of Design to LBNL.

Mechanical

Assess and design adequate heat dissipation and ventilation measures for any enclosed spaces where high-density secondary battery arrays or continuous-duty power modules are grouped together.

Equipment isolation, mechanical & electrical, must be provided to support Lock Out/Tag Out (LOTO) and commissioning of the system.

Any exemption to the CDDR requirements shall be approved by the LBNL Mechanical Engineer.

The request for the exemption must be submitted prior to the submittal of Design to LBNL.

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 12

Fire Protection

The fire alarm design must follow NFPA 72 (2025 edition) and California Fire Code requirements. RDP deliverables must include battery sizing calculations (specifying a minimum of 24 hours of standby operation followed by 15 minutes in full alarm state), voltage drop calculations for all notification loops, and a clear Input/Output Sequence of Operations Matrix.

RDP shall ensure that all existing StarLink communication cabinets are seamlessly linked to the new central supervising station interface.

Support commissioning and testing of the system to meet the LBNL Fire Department requirements.

Any exemption to the CDDR requirements shall be approved by the LBNL Fire Protection Engineer. The request for the exemption must be submitted prior to the submittal of Design to

LBNL.

All drawings, specifications, and scope modifications for fire detection, fire alarm, or mass voice notification systems shall require the review and approval of a qualified engineer. A qualified engineer is defined as a registered Professional Engineer (P.E.) in Fire Protection Engineering licensed in the State of California. System design elements may be developed by a NICET Level IV Fire Alarm Design professional; however, formal review, stamp, and written approval from a California-licensed Fire Protection Engineer (FPE) remain mandatory prior to submittal.

Electrical

Provide branch-circuit designs, panelboard power allocation metrics, and selective overcurrent protection coordination. All new FACPs shall be supplied from the identical matching source electrical panelboards currently feeding the legacy setups, unless code-clearance violations necessitate alternative routing. The design must incorporate dedicated 20A branch circuits, conductor sizing evaluations, and mandatory red on-breaker safety locks.

Electrical system design shall include voltage drop analysis;selection of equipment rating;

equipment layout in compliance with the code required clearances for operation and maintenance. Final design deliverables must comply with the documents as specified in this document.

Electrical system design includes the necessary electrical distribution components to support the FACP including panelboards, overcurrent protection devices, UPS systems, wiring for branching circuit, junction devices, wiring devices, conduit for control devices, and any other equipment requiring electrical power above 50VAC. Coordinate the interface with the laboratory’s infrastructure specifically regarding the fire alarm systems. Provide support for commissioning and testing of the system.

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 13

Electrical systems must be designed so that all FACP equipment and components operate within their capacities for the project electrical loads including future projected loads. The electrical studies shall include: the panelboard/circuits feeding the FACP’s Short Circuit Study and Equipment Evaluation, Protective Device Coordination, Arc Flash Evaluation, Power Factor Correction Capacitor Bank, Harmonics Analysis, and Electrical Grounding Analysis.

Any exemption to the CDDR requirements shall be approved by the LBNL Electrical Engineer.

The request for the exemption must be submitted prior to the submittal of Design to LBNL.

Communications/Information Technology (IT)

Subcontractor shall design all network communication for the replacement Fire Alarm Control Panels (FACPs) to interface with LBNL’s network. Replacement devices must utilize existing LBNL IT infrastructure, interfacing via single-mode fiber optic (OS2) or a copper RJ-45 connection from the existing media converter assemblies. Any new telecommunications infrastructure, pathways, cabling, media converters, or enclosures installed under this Subcontract must comply with LBNL Master Specification Division 27 (Telecommunications) and LBNL IT Construction Details and Design Requirements (CDDR). All network configurations must be submitted to LBNL IT for review, and any requested exemptions to Division 27 requirements must be formally approved in writing by LBNL IT.

Energy Management/Controls

The Subcontractor shall reestablish the input to the EMCS from the replacement FACP system in accordance with all applicable codes.

The Subcontractor shall provide a new input to the lighting control system from the replacement FACP. The specific type of input and communication protocol shall be determined by the type of lighting control system currently in operation within each building.

The Subcontractor shall support the commissioning and testing of the integration between the FACP, EMCS, and lighting controls, including functional testing across all modes of EMCS and lighting operation, to the satisfaction of LBNL Facilities Engineering.

Any exemption to the CDDR or the requirements listed in this section must be approved by the LBNL Controls Engineer. The request for such an exemption must be submitted prior to the formal submittal of the design to LBNL.

3.3. Review Meetings

All meetings must be documented by the Subcontractor and minutes distributed to the PM and the project team members within 48 hours of a meeting.

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 14

Meeting minutes will clearly describe every key item discussed and identify action items with responsible parties. A record of outstanding action items will be maintained in the meeting minutes and updated with each meeting.

Meetings shall be scheduled every two week(s) during the Final Design phase, and every 1 week during the Construction phase.

RDP must make periodic visits to the site during construction.

3.4. Design Deliverables

3.4.1. Basis of Design

Develop a Basis of Design (BOD). The BOD document records the major thought processes and assumptions behind design decisions made to meet the Owner’s Project Requirements.

The Owner’s Project Requirements are intended to capture “what” the owner needs and expects from a project. The Construction Documents detail “how” the Owner’s Project Requirements will be physically achieved. The BOD captures important information linking the “what” and “how”, by the Subcontractor’s RDP.

Content of the BOD document will vary from project to project and system to system, but in general should address the following:

• Specific codes, standards, and guidelines considered during design of the facility and designer interpretations of such requirements.

• Information regarding ambient conditions (climatic, geologic, structural, existing construction) used during design.

• Assumptions regarding usage of the facility.

• Expectations regarding system operation and maintenance.

• Performance criteria that the system was designed to meet – linked to the

Owner’s Project Requirements.

• Specific design methods, techniques, software used in design.

• A narrative statement of design – that verbally describes how the Subcontractor’s designer intends to meet the Owner’s Project Requirements.

• A narrative statement of operation – that verbally details how the facility is expected to operate under various situations (such as normal operation, extreme event, emergency).

The Subcontractor’s RDP shall identify in the BOD, specific Design Requirements that are delineated in the CDDR that are not satisfied by the design and shall provide the rationalization(s) why the design cannot meet the requirements.

3.4.2. Drawings

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 15

Prepare Drawings in accordance with the requirements in CDDR for the Final Design (50%, 75%, 95%, and 100%) deliverables. All drawing submittals and scope modifications for fire detection, fire alarm, or mass voice notification systems shall require formal review, stamp, and written approval from a registered Professional Engineer (P.E.) in Fire Protection Engineering licensed in the State of California prior to submittal. Drawing preparation by a NICET Level IV Fire Alarm Design professional is permitted, provided final California FPE approval and seal are secured.

3.4.3. Specifications

The Subcontractor must use the LBNL Master Specifications as the basis for the project specifications (also referred to as “Project Manual”) unless authorized otherwise by LBNL. The Federal Acquisition Regulations (FAR) 52.2254-9 Buy American-Construction Materials is applicable to LBNL construction subcontracts. When specifying products and materials in specifications, ensure specified items are compliant with the Buy American Act.

The following Division 01 Master Specifications are applicable:

● Division 01:

○ 000101 Project Manual Title Page

○ 000105 Certifications

○ 000110 Table of Contents

○ 000115 List of Drawings

○ 010000 General Requirements

○ 013500 Special Procedures

■ Attachment A: Supplement For Equipment Energization Plan

○ 013500A EEP-EVAP / MVAP

○ 013500B Inspection, Test and Hold Plan

○ 013523.11 Lateral Force Provisions

○ 013525 Electrical Energization Requirements

○ 013529 EHS Procedures

■ Attachment A: Subcontractor Injury Reporting Requirements

○ 014000 Subcontractor Quality Plan

○ 017429 Cutting and Patching

○ 017419 Construction and Demolition Waste Management

○ 017900 Demonstration and Training

○ 019113 General Commissioning Requirements

The following Division Technical Specifications are applicable:

○ 024119 Demolition (Air Gap)

○ 024119 Selective Structural Demolition

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 16

○ 054000 Cold-formed Metal Framing

○ 061000 Rough Carpentry

○ 078100 Applied Fireproofing

○ 078413 Penetration Fire Stopping

○ 079200 Joint Sealants

○ 092116 Non-Structural Metal Framing

○ 092900 Gypsum Board

○ 099123 Interior Painting

○ 104400 Fire Protection Specialties

○ 260500 Common Work Results

○ 260501 Inspections and Testing

○ 260519.11 600V Conductors / Cable

○ 260526 Secondary Grounding

○ 260533 Conduit

○ 260553 Identification

○ 260800 Commissioning

○ 262213 LV Transformers

○ 262816 Enclosed LV Circuit Breaker

○ 263100 Temporary Electrical Power Service

○ 263313 Batteries and Battery Chargers

○ 270500 Common Work Results for Communications

○ 270526 Grounding Bonding for Communications Systems

○ 270529 Hangers and Supports for Communication Systems

○ 270533 Conduits and Backboxes for Communications Systems

○ 270536 Cable Trays for Communications Systems

○ 270539 Surface Raceways for Communications Systems

○ 270553 Identification for Communications Systems

○ 271000 Structured Cabling, Basic Materials and Methods

○ 283176 Interior Fire Alarm and Mass Notification System

The Subcontractor’s RDP must compile a specification package including above specifications and others as applicable to the project per the requirements in the CDDR.

It is the responsibility of the Subcontractor’s RDP to include the current version of LBNL specifications. At the Final Design Review Set, the master specifications must be checked again by the RDP to make sure new revisions are incorporated in the project specifications as applicable.

3.4.4. Calculations

Battery calculations and voltage drop calculations are required.

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 17

3.4.5. Cost Estimate

Cost estimates are not required on this project. LBNL will prepare its own independent estimates.

3.4.6. Deliverables Matrix

The RDP shall submit documents for LBNL's review in accordance with the Construction Details & Design Requirements - Project Deliverables Matrix document.

3.4.7. Design Schedule

50% Final Design submittal 8 weeks after notice to proceed with final design.

75% Final Design submittal 12 weeks after notice to proceed with final design.

95% Final Design submittal 16 weeks after notice to proceed with final design.

100% Final Design submittal 19 weeks after notice to proceed with final design.

100% Design Reconciliation submittal 8 weeks after electrical product submittals approved – Refer to Spec Section 013525 Electrical Energization Requirements.

Record Drawings – As-builts submittal 4 weeks after receipt of Subcontractor field mark-up of As-builts.

The RDP should allow two weeks for LBNL review of design submittals.

3.5.Construction Support

The Subcontractor’s RDP will provide Construction Administration (CA) services including submittal review, Request for Information (RFI) responses, site-visits, RDP inspections, design clarifications, commissioning, As-Built Record Drawings, and project close out support.

As-Built Record Drawings: The Subcontractor shall maintain marked-up field drawings throughout construction and provide fully updated, PE-stamped As-Built Record Drawings upon work completion. Approval of final As-Builts—reflecting all field modifications, new equipment configurations, circuit routing, and panel terminations.

3.6.Commissioning

Testing and commissioning must include 100% of the Fire Alarm field devices and sequence of operations.

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 18

Rough-in construction and conduit/pathway routing may proceed concurrently across multiple buildings. However, system final commissioning, acceptance testing, and cut-overs must be executed sequentially on a single-building basis. A one-week (7 calendar days) operational buffer is required following the successful commissioning, acceptance testing, and cut-over of one building before initiating live bring-up and commissioning on the next facility.

4.0 Construction

4.1. Staging/ Parking/ Traffic Control

The Subcontractor shall discuss options with PM, CM, Parking Coordinator, and Building Manager and develop staging/laydown area as part of the drawings.

Work involves independent work sites across Buildings 2, 26, 33, and 76. All staging layouts must maintain clear, unobstructed envelopes for emergency vehicle access and stay inside designated construction limits. Staging and parking are strictly limited to the immediate perimeters of the active facilities.

See Division 01, 010000 section 1.5 for additional information on parking, site access, and traffic control.

4.2. Utility Deactivation

Applies to the project? Yes

The Design-Build Subcontractor shall coordinate with LBNL on the deactivation of all necessary building systems to facilitate safe interior construction and system cutovers. This includes the temporary deactivation/bypass of the fire alarm system and fire sprinkler monitoring loops.

Prior to re-energizing any circuit, the Subcontractor shall test all in-scope existing conductors and source circuit breakers targeted for reuse in accordance with NETA compliance criteria. Any breaker or conductor that fails NETA field testing must be replaced immediately by the Subcontractor.

No fire alarm system panel shall be left offline or unmonitored outside of actively managed, approved outage windows. During all active panel cut-overs, system deactivations, or outages, temporary compensatory life-safety measures in the form of a physical Fire Watch will be required per AHJ direction. Fire Watch personnel will be provided directly by LBNL; however, the Subcontractor remains responsible for coordinating outage schedules and timing with LBNL.

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 19

4.3. Government Furnished Equipment (GFE)

The Government will furnish the following materials for Subcontractor use or installation, as appropriate: None

4.4. Services provided by LBNL

LBNL-furnished Services. LBNL will perform the following services directly related to the Subcontractor work.

X Dispose of non-asbestos hazardous waste generated by the Subcontractor

Key locksets and cores

X Dispose of asbestos hazardous waste generated by the Subcontractor

Remove security access keypads, lock cores, and padlocks

Design and install telephone systems

Testing and Inspection*

*Testing and Inspection turnaround requirements:

● A minimum of 48 hours (two business days) advance notification is required for scheduling an inspection during normal business hours to assure adequate resource availability. A minimum of two weeks advance notification is required for scheduling an inspection on a weekend day. A minimum of one month of advance notification is required for scheduling an inspection on a holiday or during the December holiday shutdown.

● A minimum of 24 hours (one business day) advance notification is required for cancellation of an inspection.

● If required, coordinate testing minimum advance notification requirements with the Project Manager.

4.5. U.S. Government and/or University Property-Materials to be

Removed

No materials shall be removed from the site except Subcontractor's construction and demolition materials, soil spoils and other materials specifically listed herein.

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 20

Unless otherwise stated herein, U.S. Government or University property to be removed from the job shall remain with University jurisdiction. Such material shall be disposed of as directed by the LBNL Project Manager.

Only the following material shall be removed from the site and disposed of at the expense of the Subcontractor:

4.5.1. Decommissioned internal cards, legacy assemblies, transponder racks, and obsolete sheet-metal component shells from the panels in Buildings 2, 26, 33, and 76.

4.5.2. Existing legacy lead-acid or gel-cell backup battery packs disconnected during construction.

4.6. Hazardous Materials and Restricted Items

If suspect materials are encountered, work must stop to allow for those materials to be assessed accordingly.

The scope of the project involves work related to the following hazardous materials:

X Asbestos, see specification section 028200

X Lead, see specification section 028300

Contaminated material, see specification section 026113

PCB lighting ballast and universal waste, see specification section 028400

Radioactive Contaminated Areas, see specification section 025126

4.7. Waste Management

See requirements in specification section 017419, Construction and Demolition Waste Management.

4.8. Safety

For information regarding environmental, health, and safety requirements at LBNL please refer to the Subcontractor Construction Resource Page.

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 21

The Subcontractor must provide the following Health and Safety Representative when performing work on site:

Option A: Full-time Onsite Health and Safety Representative, with a minimum of ten (10) years construction health and safety experience and possesses one of the following certifications: a) CSP; or b) CIH. The person must also have the authority and responsibility to monitor and enforce the health and safety requirements of the project. The Option A Onsite Health and Safety Representative must be onsite during all hands on work and will have the ultimate responsibility and authority for monitoring the Environment, Health and Safety aspects of the work. This role shall not have any other duties assigned at any time during the project outside of the role of Onsite Health and Safety Representative or any safety specific duties that would diminish the ability to perform safety oversight for the entire project. For the purposes of this Safety Representative option, the term onsite, means at the specific project location at all times during hands on work.

Option B: A Full-time Onsite Health & Safety Representative with a minimum of five (5) years construction health and safety experience. The person must have a minimum of 30-Hour OSHA Outreach Training for Construction or a CHST Certification. Completions of OSHA Courses 500, 510, or 5109 are also acceptable. The Option B Onsite Health and Safety Representative must be onsite during all hands on work and will have the ultimate responsibility and authority for monitoring the Environment, Health and Safety aspects of the work.

This role shall not have any other duties assigned at any time during the project outside of the role of Onsite Health and Safety Representative or any safety specific duties that would diminish the ability to perform safety oversight for the entire project. For the purposes of this Safety Representative option, the term onsite, means at the specific project location at all times during hands on work.

X Option C: A Part-time Onsite Health & Safety Representative with a minimum of two years construction health and safety experience. The person must have a minimum of 30-Hour OSHA Outreach Training for Construction. Completions of OSHA Courses 500, 510, or 5109 are also acceptable. The Option C Onsite Health and Safety Representative must be onsite during all hands on work and will have the ultimate responsibility and authority for monitoring the Environment, Health and Safety aspects of the work. This role may have other duties assigned during the project. For the purposes of this Safety Representative option, the term onsite, means at the LBNL site at all times during hands on work.

See Specification section 013529 for more information. LBNL EHS requires 10 business days for safety submittals reviews. This includes SSSP, JHAs, Work Plan, Traffic Control Plans, PIMD-TEMP-040 Rev.7: 02/06/2026 Page 22

Certs, SDS, etc. This requirement applies to subsequent safety submittals throughout the life of the project, and not only to the original SSSP package.

5.0 Reference Documents

5.1.Construction Details and Design Requirements (rev 06.30.26)

5.2.Applicable Technical Specifications

5.3.Design Deliverables Matrix (Version 2.0 – 06.30.26)

5.4. Fire Alarm Control Panel Replacement Conceptual Design Report

5.5.Fire Alarm As-Builts for Buildings 2, 26, 33, and 76

PIMD-TEMP-040 Rev.7: 02/06/2026 Page 23

109856_Fire Control Panel Replacement Project SOW

109856_Fire_Contr..._SOW_20261012.pdf

35cdc1bcca665aa9c150e81c9c5cb37aa99391ed

MM / DD / YYYY

Signed

10 / 12 / 2026

22:20:47 UTC

Sent for signature to Jenny Ledesma (jledesma@lbl.gov) from cguerrero@lbl.gov

IP: 135.180.168.46

10 / 13 / 2026

15:39:19 UTC

Viewed by Jenny Ledesma (jledesma@lbl.gov)

IP: 131.243.99.71

10 / 13 / 2026

15:40:25 UTC

Signed by Jenny Ledesma (jledesma@lbl.gov)

IP: 131.243.99.71

The document has been completed.10 / 13 / 2026

15:40:25 UTC

2026-10-13T15:40:39+0000
San Francisco
Dropbox
Tamper Proofing

File details come from the government source that posted it. Updated .