20262020_A2_Addendum 2.pdf

PDF 193 KB Posted

Attached to
RFP 20262020 Community Renewable Energy Project_Solar Electric and Battery Storage_Design Build
Solicitation number
S-KE0010-00016295
Issued by
Lane County, Oregon

About this file

This is Addendum No. 2 to Request for Proposals 20262020 issued by the City of Eugene, Oregon for the Community Renewable Energy Project (C.R.E.P) Solar Electric & Battery Storage Design-Build project. The addendum addresses clarifications regarding the service equipment installation at Building 10, confirming that no battery feasibility study has been conducted prior to proposal submission. The solicitation timeline has been extended by one week, with the last date to request clarifications or submit protests moved to April 14-15, 2026, and the proposal due date extended to April 22, 2026, at 3:00 PM. The non-mandatory pre-proposal meeting remains scheduled for March 26, 2026, at 1:00 PM, with the Notice of Intent to Award anticipated no later than May 15, 2026. All other specifications, terms, and conditions from the original RFP remain unchanged.

The project encompasses the design, procurement, and construction of a 120-kilowatt AC solar photovoltaic array and 440-kilowatt-hour usable energy battery storage system to be installed at the City of Eugene Public Works Maintenance Division and Parks & Open Space Division campus. The selected design-build contractor will be responsible for preliminary and detailed engineering, permitting, equipment procurement, construction management, system commissioning, and performance guarantees, with construction start required by September 21, 2026, and full system operation by January 25, 2028. The contract is funded entirely through a $1,000,000 State of Oregon Community Renewable Energy Project grant, with the contractor required to provide performance and payment bonds equal to the contract price and maintain $2,000,000 commercial general liability and professional liability coverage. The contractor must guarantee minimum annual energy output of 175,700 kilowatt-hours, BESS capacity of 440 kilowatt-hours with 85 percent round-trip efficiency, and 98 percent system availability annually. Evaluation criteria include firm and project team qualifications (30 points), project understanding and approach (30 points), proposed project cost (25 points), and project experience and references (15 points), with the contract term set for two years with renewal options for up to three additional one-year terms.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date: April 8, 2026 To: All Potential Proposers From: Michelle Hahn, Purchasing Analyst Subject: RFP 20262020 C.R.E.P Solar Electric & Battery Storage Design-Build

ADDENDUM NO. 2

The solicitation referenced above is amended as follows.

A. Answer questions received from potential Proposers.

1. Will the NEW Service equipment installed under Phase 3 at Building 10 have a dedicated

Solar POI (Main Breaker Section with dedicated Solar Breaker, or only lugs)?

Response: The service equipment for Phase 3 at Building 10 has already been installed.

We do not know if it has a dedicated solar breaker but are attaching the data we have available for the manufacturer’s specifications for the main distribution panel switchboard that was installed.

2. Has a battery feasibility study been conducted?

Response: No, a battery feasibility study has not been conducted.

B. Section IV. Anticipated Proposal Schedule has been amended to extend the proposal due date by one additional week. Revised dates are as follows.

Please note, this does NOT change any dates for the Project Schedule/Timeline.

ACTIVITY DATE

Request for Proposals issued .................................................................................... March 11, 2026

Non-Mandatory Pre-proposal Meeting ................................................ March 26, 2026 @ 1:00pm

Last date to request solicitation clarification or change…………………………April 7 14, 2026, by 4:00 PM

Last date to protest solicitation…………………...……...……………………………….April 8 15, 2026, by 4:00 PM

Proposals due no later than………...……....…...............………………………April 15 22, 2026, at 2:30 3:00 PM

Notice of Intent to Award……………………………..…………………………………...no later than May 15, 2026

All other specifications, terms and conditions remain unchanged.

ACTIVITY DATE